Beruflich Dokumente
Kultur Dokumente
Q
J=
Pe − Pwf
where J is the productivity index. Apparently J is not a constant in the
two-phase flow region.
Well IPR curves are usually constructed using reservoir inflow models,
which can be from either a theoretical basis or an empirical basis. It is
essential to validate these models with test points in field applications.
1- If Pwf > Pb
qo = J ∗ pe − Pwf , bbl/day
2- If Pwf < Pb
(Vogel’s method)
2
qo pwf pwf
= 1 − 0.2 − 0.8
qo(max ) p−
R p−
R
1
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
Jactual P−
R −P wf −ΔP S
Where : F. E = Jideal =
P−
R −P wf
The shape of the IPR curve depend on the bubble point pressure of the
reservoir and the static pressure of the well, where if the reservoir is
producing currently with a pressure above the bubble point, the relation
will be directly proportional and is represented with a straight line
starting from the static pressure until it reached the bubble point Pb
where it follows vogel’s correlation and is no more a straight line.
Q
J=
Pe − Pwf
Below the bubble point:
J ∗ Pb Pwf Pwf 2
Qo = Qob + ∗ (1 − 0.2 ∗ − 0.8 ∗ )
1.8 Pb Pb
Where
SAM Program
For vertical lift performance, multi flow correlations have a lot of
empirical equations and dimensionless groups, which are rather difficult
and complicated. Therefore, these correlations have been programmed
on computer. The present study utilizes that is known as system analysis
model program (SAM).
2
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
3
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
Well 2
4
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
Well 3
5
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
6
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
Well 1
7
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
Well 2
8
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
Well 3
9
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
10
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
1 3 1/2
2 4 1/2
3 3 1/2
11
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
Well 2
Ps = 660 psi Ps = 600 psi Ps = 550 psi Ps = 500 psi
Qtot Pwf Qtot Pwf Qtot Pwf Qtot Pwf
[bopd] [psig] [bopd] [psig] [bopd] [psig] [bopd] [psig]
0 660 0 600 0 550 0 500
27464 627 24967 570 22886 523 20806 475
53679 594 48799 540 44733 495 40666 450
78646 561 71496 510 65538 468 59580 425
102365 528 93059 480 85304 440 77549 400
124835 495 113486 450 104029 413 94572 375
146057 462 132779 420 121714 385 110649 350
166031 429 150937 390 138359 358 125781 325
184756 396 167960 360 153963 330 139967 300
202233 363 183848 330 168527 303 153207 275
218461 330 198601 300 182051 275 165501 250
233442 297 212220 270 194535 248 176850 225
247173 264 224703 240 205978 220 187253 200
259657 231 236052 210 216381 193 196710 175
270892 198 246265 180 225743 165 205221 150
280879 165 255344 150 234066 138 212787 125
289617 132 263288 120 241348 110 219407 100
297107 99 270098 90 247589 83 225081 75
303349 66 275772 60 252791 55 229810 50
308343 33 280311 30 256952 28 233593 25
312088 0 283716 0 260073 0 236430 0
12
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
Well 3
13
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
Well 1
14
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
Well 2
15
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
Well 3
Conculsion
It is obvious from charts that the wells are dead because there are not
interactions VLP and IPR
16
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
1-Open-hole completion:-
The pay zone is drilled after a casing has been
run in and cemented at top of the reservoir. It
is left as is and produces directly through the
uncased height of the borehole. This simple
solution can not solve any problems of
borehole stability, or selectivity of fluid or level
to be produced.
Open hole completions are used where there is only one zone which is either
very well consolidated or provided with open-hole gravel packing for sand
control. This is valid as long as there are — theoretically at least — no
interface problems.
17
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
Cased hole completions are mainly used when there are interface problems
and/or when there are several levels. As a result, they are not only much
more common, they are the most .
18
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
1- conventional completions :
This is a system whereby one or more production strings (tubing) are used for
safety and/or other reasons. The fundamental characteristic of the tubing is
that it is located completely inside the casing and that it is not cemented,
therefore easy to replace.
19
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
B -Multi-zone completion :
In the past, the technique of producing several levels together through (the
same tubing was used. It required only a minimum amount of equipment.
However, the subsequent reservoir
and production problems that were experienced have caused this practice to
become much less common.
20
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
Double-zone completions are the most common, but there can be three, four
and even more levels produced separately. However, this significantly
complicates the equipment that needs to be run into the well and especially
makes any workover operations much more complex.
• Parallel dual string completion with two tubing, one for each of the two
levels and two packers to isolate the levels from one another and protect the
annulus.
21
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
• Tubing-annulus completion with one single tubing and one packer, which is
located between the two levels that are to be produced, with one level
produced through the tubing and the other through the tubing-casing
annulus.
Dual-completion
22
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
2 - Tubingless completion :
A tubingless completion uses no tubing, but production flows through a
cemented pipe instead. This rather unusual type of completion, is mainly used
in certain regions and only under specific conditions.
Several levels with mediocre production can be produced in this way with a
minimum number of wells and downhole equipment, i.e. with a minimum
initial investment. This is true provided there are no safety or production
problems (artificial lift. Workover. etc.). This type of completion is mainly
encountered in the United States.
3-gravel-pack completion:
Many reservoirs contain sediments that are so poorly consolidated that sand
will be produced along with the reservoir fluids unless the production rate is
severely restricted. Sand production may erode the tubing or surface valves
and flow lines. In addition, sand could accumulate in downhole equipment
and create problems in wireline servicing. Gravel-packing was devised as a
means of eliminating sand production without greatly restricting production
rates. In a gravel-pack completion (as shown), sand with a grain size larger
than the average formation sand grain is placed between the formation and a
screen or slotted liner (Economides et al., 1994). More recently, high-
permeability fracturing (fracpacking) has been proven as a technique for sand
control.
23
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
1-Choke :
Constriction in the flow line useful in restricting flow and applying back
pressure on the well.
Principle:
The working principle of the choke is based on the critical flow rate achieved
when,
Pu ≥ Pd
Where,
Types of Choke:
1. Surface chokes:
Used in high energy well producing oil and gas from high pressure formation.
24
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
Design of chokes :
𝑎 . 𝐷𝑏 . 𝑃
𝑄=
𝑅𝑝 . 𝐶
Where,
P = THP, Psi
25
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
120
choke design
100
80
P,psi
60
40
20
0
1 3 5 7 9 11 13 15 17 19
Q,bpd
2) Christmass tree :
Assemblage of valves & fittings attached to control head in high pressure
wells producing large volume of oil and gas.
26
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
3) Packers :
a) Isolate the csg from corrosive fluids or high pressure.
Types of Packers
1) Cement packers
2) Packer pore receptacle
3) Production Packers:
a. Permanent Packers.
b. Permanent – Retrievable Packers.
c. Retrievable Packers:
i. Weight set Packers.
ii. Tension set Packers.
iii. Mechanical set packers.
iv. Hydraulic set Packers.
v. Hydraulic expansion seal
vi. Open hole inflatable Packers.
Design of Packer:
Determine type of Packer Force balance :
Where:
27
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
28
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
is normally applicable for low production rates. For high rate, using long
stroke units, high pumping speed and large plungers should be used .
In a jet pump, the nozzle converts the high pressure of the power fluid at
low pressure by changing its velocity. Well fluids are mixed in the pump
throat and the diffuser generates the discharge pressure (which is high
29
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
due to decrease in the fluid velocity) and the combined fluids are
produced back through the annulus.
component of the pressure difference from the bottom to the top of the
well. The purpose is to bring the fluids to the top at a desirable wellhead
pressure while keeping the bottom-hole pressure at a value, which that
is small enough to provide the desired production. However, this
pressure drawdown must not violate restrictions for sand control and
water or gas coning. Two other considerations must be considered for
the design. First, large amounts of gas injected into the well will affect
the separation facilities at the top. Second, there exist a limit (or
30
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
optimum) gas/liquid ratio above that the pressure difference in the well
will begin to increase because the reduction in the hydrostatic pressure
will be compensated by the increase in the friction pressure.
31
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
32
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
33
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
Design steps
34
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
E. Subtract the operating differential pressure, usually 100 psi, from the
pressure at the intersection found in D. The depth at which this pressure
occurs on the
flowing gradient line is the operating valve depth.
35
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
gas injection rate corrected for temperature at the valve. The corrected
gas rate is
𝐐𝐠𝐬𝐜 𝐓𝐯 + 𝟒𝟔𝟎
𝐐𝐥𝐠 =
𝟓𝟐𝟎
V. Determine the Required Dome Pressures for all the Valves.
A. Read the opening pressure (Po) at valve depth from the Po line.
B. Read the design tubing load (pt) at valve depth from the design
gradient line.
C. Calculate the closing or dome pressure (Pbt) at valve depth.
𝐏𝐛𝐭 = 𝐏𝐎 𝟏 − 𝐑 + 𝐏𝐭 𝐑
Where R = Ap/Ab
𝐏𝐛
𝐏𝐯𝐨 = 𝟏−𝐑
36
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
A. 𝛄𝐋 = 𝐖. 𝐂 ∗ 𝛄𝐰 + 𝟏 − 𝐖. 𝐂 ∗ 𝛄°
𝛄𝐋 = 𝟏. 𝟎𝟎𝟏𝟒
B. Determine the gas pressure at 6600 ft
C. Intersection is at 6300 ft
∆P = 130 psi
D. Operating valve depth = 6000 ft
II. Using the pressure traverse curves for 3.5 tubing and 1980 STB/day
establishes the required GLR above the operating valve as 870 scf/STB.
37
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
1 1650
2 2650
3 3500
4 4200
5 4750
6 5250
7 5650
8 6000
IV. A port size must be selected which will pass gas at a rate of 1.667
MMscfd with an upstream pressure of 1160 psig and a downstream
pressure of 1040 psig.
The temperature at the operating valve is Tv = 116 F
The corrected gas volume is: Qlg=1.846 MMSCF/day
From the choke capacity chart . a 24/64 orifice will pass gas at a rate
of1.9 MMscfd. Although a smaller port size will suffice, select the 0.375
in. port for possible changing conditions. From Table R =0 .345, (I - R) =
0.655 , Ab = 0.32 in. Use the same port size for all the valves.
38
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
39
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
40
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
Bs = Buoyancy factor
PT =Peak torque
Fc =frequency factor
41
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
API = 20
B oil = 1.18
W . C = 40 %
Ps = 1170
Gravity of oil
= 0.912
= 0.937
42
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
= 3947 ft
2- (L= 6494 ft) from figure 5.6 (well design book) it indicate use of
an API size (320) unit with (84 in ) stroke
An example of unit would meet these specifications is the
(LUFKIN C-320D -84 -30)
This unit has abeam load capacity of (30000 lb ) and maximum
counter balance effect (at the 84-in) stroke of 21645 lb
3- From table (5-11) the plunger size is (1 1/2 in ) the tubing size is
(2 1/2 in ) and rod size is (3/4 , 7/8 ) and 1 in. The plunger speed
(15.5 spm )
43
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
4- R1 = .664-(0.0894*AP)=.506
R2=.181+(.0416*AP)=.265
R3= .155 + (.0416*AP)= .228
5- L1= L*R1= 3286 FT
L2= L*R2= 1720 FT
L3=L*R3= 1408 FT
8- Q = KSpNEv
44
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
An API size (320) Unit has a rating of (320000 in-lb) And so the
peak torque is within allowable units
LN = D+(2.31 Pt /G)
= 4242.84 ft
Hydraulic Horsepower:
Hb =1.5 ( Hh + Hf )
= 30.6 hp
45
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
ESP DESIGN
NINE-STEP OVERVIEW
Centrilift has established a nine step procedure to help you design the
appropriate submersible pumping system for your particular well.
Each of the nine steps are explained in the sections that follow, including
gas calculations and variable speed operation. The nine steps are:
46
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
1.Well Data:
2-Production data:
Ps = 1400 psi
WC = 40 %
=112.3 SCF/STB
QL = 180 m3/day
=1132 STB/day
Qo =108 m3/day
47
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
w = 1.06
o = 0.933
g = 0.85
Rs@Pb = 35 m3/m3
4 - Power source:-
Current frequency = 50 HZ
Water cut is 40 %;
0.4*1.06=0.424
Oil is 60 %;
0.6*0.933= 0.5598
48
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
1.2048
𝑃𝑏 100.0125 × 𝜊𝐴𝑃𝐼
𝑅𝑠 = 𝛾𝑔 ×
18 100.00091 × 𝑇(𝜊𝐹 )
Rs = 148.5 scf/stb
2. Determine the Formation Volume Factor (Bo) using the Rs from above
and Standing's nomograph (see figure 3) or use Standing's equation as
follows:
Where:
𝛾𝑔 0.5
𝐹 = 𝑅𝑠 + 1.25 𝐓
𝛾𝑜
49
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
0.5
0.85
𝐹 = 148.5 + (1.25 ∗ 200)
0.933
𝐹 = 391.74
Therefore:
Bo = 1.136 bbl/stb
𝑇𝑀𝑃𝐹 = 𝐵𝑂𝑃𝐷 × 𝑆𝑝. 𝐺𝑟. 𝑂𝑖𝑙 + 𝐵𝑊𝑃𝐷 × 𝑆𝑝. 𝐺𝑟. 𝑊𝑎𝑡𝑒𝑟 × 62.4
× 5.615 + 𝐺𝑂𝑅 × 𝐵𝑂𝑃𝐷 × 𝑆𝑝. 𝐺𝑟. 𝐺𝑎𝑠 × 0.0752
𝑇𝑀𝑃𝐹
𝐶𝑜𝑚𝑝𝑜𝑠𝑖𝑡𝑒 𝑆𝑝. 𝐺𝑟. =
𝐵𝐹𝑃𝐷 × 5.615 × 62.4
50
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
𝑇𝐷𝐻 = 𝐻𝑑 + 𝐹𝑡 + 𝑃𝑑 + Pdepletion
Hd = 7026 ft.
Friction loss per 1,000 ft. of 2-7/8 tubing (new) is 5.7 ft. per 1,000 ft. of
depth at 1132 BPD (180 M3/D). Using the desired pump setting depth:
Ft = (5.7*7725)/1000 = 44 ft
51
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
TDH = Hd + Ft + Pd + Pdepletion
The head in feet (meters) for 100 stage at 180 m3/ day is 2170 ft. The
brake horsepower (BHP) per 100 stage is 30 hp
𝐻𝑒𝑎𝑑/𝑆𝑡𝑎𝑔𝑒 = 21.7
𝑇𝐷𝐻
𝑁𝑜. 𝑂𝑓 𝑆𝑡𝑎𝑔𝑒𝑠 =
𝐻𝑒𝑎𝑑 𝑆𝑡𝑎𝑔𝑒
52
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
Seal Section
It will be calculated using charts of total dynamic head versus HP
Using(appendix c)
Determination of total HP
Tot.HP= BHP+seal HP
=104.2 hp
Motor
Using table 2 , appendix 4F
Volt/Amp =(804/84)
Cable Type
Check to be sure the cable diameter plus tubing collar diameter is
smaller than the casing I.D. (see Engineering section ).
53
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
Cable Length
The pump setting depth is 7725 ft. With 100 ft. of cable for surface
connections, the total cable length should be 7825 ft.
Cable Bands
The pump and seal section are approximately 20 ft. (6 m) long. Twenty-
two inch (56 cm) bands will be required to clamp to the housing, with
bands spaced at 2 ft. (61 cm) intervals (10 bands).
Above the pump, banding of the tubing plus cable, the twenty- two
bands can also be used. The bands should be spaced at 15 ft. (4.5 m)
intervals. The setting depth of 6980 ft. would require 466 bands.
Motor Controller
The motor controller selection is based on its voltage, amperage,
and
54
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
𝐒𝐯 × 𝐌𝐨𝐭𝐨𝐫 𝐀𝐦𝐩𝐬 × 𝟏. 𝟕𝟑
𝐊𝐕𝐀 =
𝟏𝟎𝟎𝟎
KVA = 146
Transformer
The transformer selection is based on the available primary power
supply (12500volts), the secondary voltage requirement
(2400volts), and the KVA requirement (150 KVA). Chose 3, 50 KVA
single phase transformers as shown in your catalog.
Variable Frequency
The effects of varying frequency can be seen by preparing new head-
capacity curves for the desired frequencies, based on the pump's known
60 Hz performance curve data. The Electrospeed controller is commonly
used to generate any frequency between 30 and 90 Hz.
55
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
1.Well Data:
2-Production data:
Ps = 1000 psi
WC = 40 %
=112.3 SCF/STB
QL = 140 m3/day
= 880.5 STB/day
Qo = 84 m3/day
56
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
w = 1.07
o = 0.927
g = 0.85
Rs@Pb = 32 m3/m3
4 - Power source:-
Current frequency = 50 HZ
Water cut is 40 %;
0.4*1.07 = 0.428
Oil is 60 %;
0.6*0.927= 0.5562
57
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
1.2048
𝑃𝑏 100.0125 × 𝜊𝐴𝑃𝐼
𝑅𝑠 = 𝛾𝑔 ×
18 100.00091 × 𝑇(𝜊𝐹 )
Rs = 111.45 scf/stb
2. Determine the Formation Volume Factor (Bo) using the Rs from above
and Standing's nomograph (see figure 3) or use Standing's equation as
follows:
Where:
𝛾𝑔 0.5
𝐹 = 𝑅𝑠 + 1.25 𝐓
𝛾𝑜
0.5
0.85
𝐹 = 111.45 + 1.25 ∗ 200
0.927
𝐹 = 356.72
58
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
Therefore:
Bo = 1.119 bbl/stb
𝑇𝑀𝑃𝐹 = 𝐵𝑂𝑃𝐷 × 𝑆𝑝. 𝐺𝑟. 𝑂𝑖𝑙 + 𝐵𝑊𝑃𝐷 × 𝑆𝑝. 𝐺𝑟. 𝑊𝑎𝑡𝑒𝑟 × 62.4
× 5.615 + 𝐺𝑂𝑅 × 𝐵𝑂𝑃𝐷 × 𝑆𝑝. 𝐺𝑟. 𝐺𝑎𝑠 × 0.0752
𝑇𝑀𝑃𝐹
𝐶𝑜𝑚𝑝𝑜𝑠𝑖𝑡𝑒 𝑆𝑝. 𝐺𝑟. =
𝐵𝐹𝑃𝐷 × 5.615 × 62.4
𝑇𝐷𝐻 = 𝐻𝑑 + 𝐹𝑡 + 𝑃𝑑 + Pdepletion
59
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
Hd = 7040.6 ft.
Friction loss per 1,000 ft. of 2-7/8 tubing (new) is 5.7 ft. per 1,000 ft. of
depth at 880.5 BPD (140 M3/D). Using the desired pump setting depth:
Ft = (5.7*7602)/1000 = 43.3 ft
TDH = Hd + Ft + Pd + Pdepletion
60
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
The head in feet (meters) for 100 stage at 140 m3/ day is 1250 ft. The
brake horsepower (BHP) per 100 stage is 13 hp
𝐻𝑒𝑎𝑑/𝑆𝑡𝑎𝑔𝑒 = 12.5
𝑇𝐷𝐻
𝑁𝑜. 𝑂𝑓 𝑆𝑡𝑎𝑔𝑒𝑠 =
𝐻𝑒𝑎𝑑 𝑆𝑡𝑎𝑔𝑒
Seal Section
It will be calculated using charts of total dynamic head versus HP
Using(appendix c)
61
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
Determination of total HP
Tot.HP= BHP+seal HP
=79.4 hp
Motor
Using table 2 , appendix 4F
Volt/Amp =(987/44)
Cable Type
Check to be sure the cable diameter plus tubing collar diameter is
smaller than the casing I.D. (see Engineering section ).
Cable Length
The pump setting depth is 7602 ft. With 100 ft. of cable for surface
connections, the total cable length should be 7702 ft.
62
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
Cable Bands
The pump and seal section are approximately 20 ft. (6 m) long. Twenty-
two inch (56 cm) bands will be required to clamp to the housing, with
bands spaced at 2 ft. (61 cm) intervals (10 bands).
Above the pump, banding of the tubing plus cable, the twenty- two
bands can also be used. The bands should be spaced at 15 ft. (4.5 m)
intervals. The setting depth of 7052 ft. would require 470 bands.
Motor Controller
The motor controller selection is based on its voltage, amperage,
and
=1080 volt
63
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
𝐒𝐯 × 𝐌𝐨𝐭𝐨𝐫 𝐀𝐦𝐩𝐬 × 𝟏. 𝟕𝟑
𝐊𝐕𝐀 =
𝟏𝟎𝟎𝟎
KVA = 82.21
Transformer
The transformer selection is based on the available primary power
supply (12,470 volts), the secondary voltage requirement (1080
volts), and the KVA requirement (82.21 KVA). Chose 3 ,27.5 KVA
single phase transformers as shown in your catalog.
Variable Frequency
The effects of varying frequency can be seen by preparing new head-
capacity curves for the desired frequencies, based on the pump's known
60 Hz performance curve data.
Comment:
So The ESP seems to be the optimum artificial lift method
64
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
Well Test
Horner's Method
Under the following assumption, the pressure build - up survey can be made.
65
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
Steps of Calculation:
7.
Plot log ( tp +Δt)/Δt versus (PWS ) ( shut - in pressure ) the result is a
straight line.
The extrapolation of the above line until will cut the line or axis along
which log ( tp+ Δt)/Δt = 0 .
This gives (Ps).
Where,
Where,
Pc
P.R. 5.5
Ps Pwf
66
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
Where,
Ps
P.R. 1
Ps Pwf
Where:
S = ΔPs/0.87m
P P K
S 1.15 1hr i
log 3.23
C r 2
m o t w
Where:
67
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
ZONE NUKHUL
WELL AR 05
DATE 17/02/1959
AVG.Q 760bbl\day Tp 862.9894
CUM.OIL PROD. 27328bbl
NET PAY(H) 100ft
HOLE DIAMETER 7in
Calculations :
2747 0
68
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
build-up test
3500
3450
3400
3350 build-up test
3300
3250
3200
1 10 100 1000
PERMEABILITY (k )= 128.6085
SKIN (s )= 9
ZONE NUKHUL A
WELL SID 04
DATE 08/12/1959
AVG.Q 930bbl\day Tp 825.8065
CUM.OIL PROD. 32000bbl
NET PAY(H) 90ft
HOLE DIAMETER 7in
69
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
Calculations :
2737 0
PERMEABILITY (k )= 462.8
SKIN (s )= 42.1
70
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
Gas Engineering
Separator Components
1.Primary separation section :
For separating the bulk of the liquid from the well stream, it is desirable to
remove quickly liquid slugs and large droplets of liquid from the gas stream in
order to minimize turbulence and separate of liquid particles. This is
accomplished by the use of tangential inlet, which circulate the fluid.
71
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
Types of separator
1. Vertical Separator:
The well stream enters the separator through the tangential inlet, which
imparts a circular motion to the fluids. A Centrifugal and gravity force
provides efficient primary separation. A conical baffle separates the liquid
accumulation system from primary section to ensure a quiet liquid.
Surface releasing solution gas. The separated gas travels up ward through the
secondary separation section where the heavier entrained liquid particles
settle out. The gas flows through the mist extractor and particles accumulate
until sufficient weight to fall into the liquid accumulation section. Sediments
enter the separator and accumulate in the bottom and flushed out through
the drain connection.
2. Horizontal separator:
-Single tube: the well stream enters through the inlet and strikes an angle
baffle or dished deflector and strikes the side of the separator, producing
72
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
73
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
3. Spherical separator:
The incoming well stream is split by the inlet flow diverter and directed
tangentially against the wall of the separator. The liquid streams come
together after flowing 180o around the vessel wall and then fall into the
accumulation section to remain there until released. The gas stream is
travelling through the large diameter and loses particles due to its reduced
velocity. Then, the gas passes through mist extractor.
74
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
Stage separation
the final stage of vapor liquid separation because the final equilibrum flash
occurs in the tank.the propose of of stage separation is to reduce the
consecutively lower pressure. As shown in figure two stage separation
involves one separator and one storage tank. Three-stage separation Stage
separation is a process in which gasesous and liquid hydrocarbons are
separated into vapor and liquid phases by two or more equilibrim flashes at
requires two separators and a storage tank. Four-stage separation would
require three separators and a storage tank. The tank is always counted as
75
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
76
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin
Production Engineering
Ki= 1/P*(10)(a+cFi)
Where :
Fi = bi*(1/Tbi-1/T)
bi = Log(pci/14.7)/(1/Tbi-1/T)
for C7+
The API gravity for the separated oil can be calculated from the following
equation :
77
B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
Dri
llin
Production Engineering
Given Data :
78
Dri B.SC. PROJECT 2009 – ABU RUDEIS – SIDRI FIELD
llin