1 General Items
To Collection 1,050,000.00
11
Bill of Engineering Measurement and Evaluation ( BEME)
(₦:K)
1.04 Water for the work:
Include the Provisional sum of Two Hundred
and Fifty Thousand naira only for the provision
of clean portable water for the works. item item 250,000 250,000.00
1.05 Safety and Insurance
Include the Provisional sum of Five Hundred
Thousand naira only for all safety elements
required to protect personnel from injuries of
any sort including provision of workmen
insurance with a reputable insurance item
company. item 500,000 500,000.00
1.06 Medical
Include the Provisional Sum of Three Hundred
Thousand naira only for the provision of
medical facilities for workmen, including
retainer ship with a reputable clinic. item item 300,000 300,000.00
1.07 Progress Photographs
Include the Provisional Sum of Thirty
Thousand naira only for progress photographs
throughout the duration of the works. item item 30,000 30,000.00
To Collection 1,080,000.00
12
Bill of Engineering Measurement and Evaluation ( BEME)
(₦:K)
2.00 EARTHWORKS:
2.01 Clear site of all vegetation, debris, grasses and
2
grub up their roots. 22,000 m 100 2,200,000.00
2.02 Excavate to remove vegetable top soil average
300mm 6,000 m3 700 4,200,000.00
2.03 Excavate drainage trench average 300mm 1,200 m3 700 840,000.00
2.04 Backfill with sharp sand as embankment 18,000 m3 3,000 54,000,000.00
average 800mm
3.00 REINFORCEMENT
4.00 SAWN FORMWORK
4.01 Drainage channel 15,000 m2 1,500 22,500,000.00
To Collection 129,477,500.00
13
Bill of Engineering Measurement and Evaluation ( BEME)
(₦:K)
5.00 CONCRETEWORK:
5.01 Plain in‐situ concrete (1:2:4‐19mm aggregate)
for drainage 1,500 m3 40,000 60,000,000.00
5.02 Ditto culverts
90 m3 40,000 3,600,000.00
5.03 Ditto kerbs 360 m3 40,000 14,400,000.00
`
To Collection 237,000,000.00
14
Bill of Engineering Measurement and Evaluation ( BEME)
(₦:K)
Collections
Page 1
1,050,000.00
Page 2
1,080,000.00
Page 3 129,477,500.00
237,000,000.00
Page 4
SUBTOTAL 368,607,500.00
Add Vat 5% 18,430,375.00
`
18,430,375.00
Add 5% Contingency
TOTAL ESTIMATED COST 405,468,250.00
FOUR HUNDRED AND FIVE MILLION, FOUR HUNDRED AND SIXTY EIGHT THOUSAND, TWO HUNDRED AND
FIFTY NAIRA ONLY.
15
BIBLIOGRAPHY
Cobb, F. (2014), Structural engineer’s pocket book, 3rd ed, CRC Press Taylor &
Francis Group, London.
16