Below is the IEE Checklist Report for Batching and Crushing Plant Projects.
For ECC applications, this IEE Checklist Report shall be submitted with:
Proof of Compatibility with the existing Land Use Plan
Proof of Authority over the Project Site
Accountability Statements of Proponent (see attached form) and the Preparer (if any,
following Annexes 2-22 of Revised Procedural Manual for DAO 2003-30)
Photographs or plates/vicinity map of the project site showing impact areas and affected areas
and communities
Duly Accomplished Project Environmental Monitoring & Audit Prioritization Scheme (PEMAPS)
Questionnaire (see Annex 2-7d of Revised Procedural Manual for DAO 2003-30)
(No other documents shall be required as pre-requisite to ECC applications per DENR MC 2010-14)
Read the questions carefully and write the required information on the spaces provided or
otherwise check () the appropriate boxes □ or parenthesis ( ). Use additional sheets if
necessary and indicate this in the appropriate space.
Misleading or erroneous answers are basis for legal actions and/or denial of ECC issuance.
Total Project/Building
Footprint Area ______________________________________________________
(Area actually utilized)
Project Proponent: ______________________________________________________
Office Address: ______________________________________________________
Contact Person: ______________________________________________________
Designation: ______________________________________________________
Contact Information
Telephone Number: _________________________________________
Fax Number: _________________________________________
Mobile Number: _________________________________________
E-mail Address: _________________________________________
I. PROJECT DESCRIPTION
1.1 PROJECT LOCATION AND AREA: Street Name, Barangay, and Municipality/City, Province
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
See attached vicinity map/s and photographs of the project site and site development/layout plan.
Geographic coordinates of the project area (Preferably use WGS 84 datum, otherwise specify datum
used).
Perimeter/Boundary points
Longitude Latitude
(based on OCT/TCT/etc)
9. Drainage system
Water Source
[ ] ground water [ ] well [ ] spring [ ] others: ____________________________
Energy/Water Efficiency
3
Water m /day
1.4 MANPOWER
a. Construction Phase
Manpower Expertise/Skills Total
Requirement
b. Operation Phase
Manpower Expertise/Skills Total
Requirement
Possible Environmental/ Baseline Environment Preventive/ Mitigating Measures Monitoring Parameters/ Cost of Mitigation/ Monitoring
Social Impacts Implementation and frequency
LAND
Consistency with land Current land use w/in 1km radius See attached proof of compatibility with
use (as per zoning ordinance): land use
Residential
Commercial/ Institutional
Industrial
Agricultural/ Recreational
Protected Areas
Others ___________________
Disturbance to wildlife Existing vegetation in the area: Compliance with conditions of DENR/LGU Annual inspection of area Cost integrated in the
due to vegetation Forestland SLUP, Tree Cutting Permit, ROW, PCA
Permit
replanted/ re-vegetated construction /operation cost
clearing
Marshland
Limit land clearing as much as possible
Grassland
Provide temporary fencing for vegetation
Mangrove that will be retained
Wetland Promote restoration of damaged or
Others, specify destroyed vegetation where possible (e.g.,
____________________ tree planting);
Possible Environmental/ Baseline Environment Preventive/ Mitigating Measures Monitoring Parameters/ Cost of Mitigation/ Monitoring
Social Impacts Implementation and frequency
Change in surface Slope: Provide erosion control and slope Regular inspection of slope Slope/ Erosion Control
landform/ topography/ flat (0-3%) protection measures protection measures in Cost: ___________
terrain/slope
gently sloping to rolling (3-18%) Designate a Spoils Storage Area, with erosion-prone areas Others, specify
topsoil set aside for later use and allow Regular inspection for new __________________
Soil Erosion steep (>18%) maximum re-use of spoils eroded areas near the site
Construction during dry season Others, specify:
Stabilization of embankment with grasses _______________________
or other soil cover
Others, specify
____________
Is the project site located in an area Compliance with the DENR Administrative
identified by Order No. 2003-30 and DENR
MGB/PAGASA/PHIVOLCS as Administrative Order No. 2000-28,
hazard prone? Implementing Guidelines on Engineering
Geological and Geo-hazard Assessment
Yes
(EGGA).
No
Soil/Land contamination Existing soil type in the area: Implementation of the Ecological Solid Daily inspection of Cost integrated in the
due to improper solid sandy Waste Management Plan (ESWMP) waste/recycling bins for construction /operation cost
waste disposal
clay Set-up temporary fence around the segregation
construction area Daily inspection for presence
sandy-loam
Implement re-use and recycling of waste of mixed garbage in the
Others, specify materials facility
____________________
Implement proper segregation, collection Weekly inspection of waste
and disposal of domestic wastes in accumulated
designated areas Others, specify
Implement proper collection, labeling and ___________________________
_______
storage of hazardous waste
Provide receptacles / bins for solid wastes
Coordinate with the municipal / city waste
collectors
Possible Environmental/ Baseline Environment Preventive/ Mitigating Measures Monitoring Parameters/ Cost of Mitigation/ Monitoring
Social Impacts Implementation and frequency
Engage third party company for waste
collection
Others, specify: ________________
Impairment of Presence of visually significant Implement landscaping and other Regular inspection of Cost integrated in the
visual aesthetics landforms/landscape/structures? beautification measures landscaping and other construction/ operation cost
Devaluation of land Yes Provide adequate buffer beautification activities
values No Compensate adjacent property owners Regular monitoring of buffer
zones
Others, specify: ________________
Regularly monitor for
presence/absence of
complaints from adjacent
property owners
WATER
Specify nearest/receiving water Regular (ocular) inspection of Cost integrated in the
body: Provide ring canals around fuelling tanks/ water body for: construction/ operation cost
____________________________ motor pool/ maintenance areas Turbidity and/or silted
Distance to nearest/receiving water
Set-up proper and adequate sanitary condition
body:
facilities Floating wastes or debris
Increased siltation due 0 to less than 0.5 km
Strictly require the contractor and its
workers to observe proper waste disposal
to project activities
0.5 to 1 km and proper sanitation
Water quality
More than 1 km Strictly observe proper waste handling and
degradation disposal
Others, specify If nearest/receiving water body is Provision of wastewater treatment facility
_____________________ fresh water, specify classification: (e.g. septic tank, oil and water separator,
AA etc.)
A Set up silt trap/settling ponds to minimize
B downstream siltation
D
Possible Environmental/ Baseline Environment Preventive/ Mitigating Measures Monitoring Parameters/ Cost of Mitigation/ Monitoring
Social Impacts Implementation and frequency
Competition in water Size of population using receiving Implement rainwater harvesting and similar Cost integrated in the
use surface water: measures as an alternative source of water Regularly monitor for construction/ operation cost
Depletion of water ≤ 1,000 persons Observe water conservation measures;
presence/absence of
resources >1,000 and ≤ 5,000persons Others, specify
complaints
>5,000person ________________________
Regular coordination with
concerned agencies
Available/nearest water source. Regularly monitor for
occurrences of water
Deepwell shortages
Water district/LGU Others, specify:
Surface water ________________________
Others, specify:
______________________
Possible Environmental/ Baseline Environment Preventive/ Mitigating Measures Monitoring Parameters/ Cost of Mitigation/ Monitoring
Social Impacts Implementation and frequency
Increased occurrence Is the project site located in an area Use appropriate design for project facilities Regularly monitor for Cost integrated in the
identified by MGB/PAGASA as
of flooding
flood prone? Implement appropriate drainage system
presence/absence of
complaints
construction/ operation cost
AIR / NOISE
Air quality degradation Distance to nearest community: Properly operate and maintain all Regularly monitor for Cost integrated in the
0 to less than 0.5 km emission sources (e.g. vehicles, presence/absence of construction/ operation cost
0.5 to 1 km generator, etc) complaints
More than 1 km noise control device/s (e.g., mufflers, Regular monitoring of buffer
silencer, sound barriers, etc.) zones
Implement appropriate operating hours
Provide adequate buffer
Quarterly monitoring noise
(e.g. Perimeter planting of trees to serve as level
sound buffer and greenbelt)
Others, specify
_____________________________
PEOPLE
Displacement of Size of population of host barangay: Provide relocation/disturbance Presence/Absence of Cost integrated in the
residents in the project ≤ 1,000 persons compensation packages complaints construction/ operation cost
site and within its
>1,000 and ≤ 5,000persons Prioritize local residents for employment Regular coordination with
vicinity
Promptly pay local taxes and other LGU
Displacement of
>5,000person
financial obligations Others, specify
Indigenous People
Classification of host barangay: Regular coordination with LGU _________________
Enhanced employment
Urban Prior consultation & coordination to
and/or livelihood
opportunities Rural minimize disruption on daily domestic
activities & respect for IP rights and
Reduced employment
Available services within/near the cultural practices
and/or livelihood
opportunities
host barangay: Ensure participation of IPs in consultations
Impacts on community Regular coordination with LGU Regularly monitor for Cost integrated in the
health and safety Provide appropriate warning signs, lighting presence/absence of construction/ operation cost
Others, specify: and barricades, whenever practicable complaints
______________________ Observe proper housekeeping Regular coordination with
LGU
Provide on-site medical services for any
Regular submission of reports
emergency.
to concerned agency
Participate in public awareness programs
Others, specify
on health and safety
_________________
Implement appropriate safety programs for
both community and workers
Strictly comply with fire, safety and similar
regulatory requirements
Strictly comply with requirements of RA
6969
Others, specify
__________________________
III. ABANDONMENT /DECOMMISSIONING/REHABILITATION POLICIES AND GENERIC
GUIDELINES (if Applicable)
Provide description of the Abandonment activities, such as, dismantling and waste disposal.
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
Organization Chart:
This is to certify that all the information and commitments in this Initial Environmental
Examination (IEE) Checklist Report are accurate and complete to the best of my knowledge.
I hereby bind myself to answer any penalty that may be imposed arising from any
misrepresentation or failure to state material information in this IEE Checklist.
__________________________
NAME OF PROPONENT HEAD
(Position)
(Company Name)
SUBSCRIBED AND SWORN TO before me this _____ day of ____________ 201__, affiant
exhibiting his/her Community Tax Certificate No. ___________________ issued at
______________________ on __________________________.