Beruflich Dokumente
Kultur Dokumente
In the
Moment Here are 60 tips for simplifying fully restrained
By Victor Shneur, P.E
M
Many buildings have moment connections for 6. As the engineer of record, request removing backing bars only
lateral frames and/or cantilevers. Even though they don’t encom- when required by the governing code or architectural reasons.
pass the majority of the connections, it is important to give moment (This is an expensive procedure.)
connections special attention since they require more work and
7. Do not fill weld access holes with weld material for cosmetic or cor-
may be a safety consideration during erection.
rosion-protection reasons. In addition to the cost, it creates undesir-
Here are a few (well, 60) suggestions for making moment con-
able triaxial stresses. Using mastic materials is preferable to welding.
nections easier to design, detail, fabricate, and erect, along with a
few recommendations for avoiding problems: 8. Avoid weak-axis moment connections at W-columns.
1. Moment connections for cantilevers require special attention 9. For moment frames, consider using partially restrained or flex-
from the erector. They always must be completed, including ible moment connections in lieu of fully restrained connections
moment connection for backing beams, before the cantilever is whenever possible.
released. Otherwise, adequate temporary support should be pro-
10. Carefully examine cantilever framing for reducing the number of
vided. Also, per OSHA requirements, a competent person should
members with moment connections. This is the best way to save
supervise cantilever erection.
money on moment connections. Potential increase in material
2. If moment connections are required for the lateral load resisting weight can be well justified by savings in labor and safer erection.
system, select an R of 3 or less whenever possible. When R > 3
11. When a direct-welded flange moment connection is made to a
the AISC Seismic Provisions must be applied, which has a signifi-
column web, extend connection plates at least ¾ in. beyond the
cant associated cost implication.
column flanges to:
3. When heavy rolled W-shapes are required at moment connec- ➜ avoid intersecting welds
tions with complete-joint-penetration (CJP) groove welds, don’t ➜ provide for strain elongation of the plates
forget about special requirements for the material covered in the ➜ provide adequate room for runout bars
AISC Specification, Section A3.1c.
12. When possible, consider using a deeper W-shape to reduce
4. When moment connections are flange forces and possibly eliminating stiffeners at columns. The
not designed by the EOR, provide increase in material weight is typically offset by eliminating stiff-
all end reactions, including vertical eners and using a less expensive/lighter moment connection (e.g.,
end reactions and moment envel- an extended end-plate connection in lieu of a directly welded
ops. The fabricator can then select connection if end moment allows).
the most efficient connections and
13. When moment connections are made to a column or beam web,
check columns for reinforcement.
use beams with the same depth on both sides of the web where
5. For non-domestic sections, possible.
consider using A913 steel to sub-
14. Don’t specify fully restrained moment connections to resist
stantially reduce preheat require-
moderate beam axial forces. Double-angle connections with
ments at welds (see Table 3.2 in
Victor Shneur is chief thicker angles for perpendicular framing and shear end plate
the AWS D1.1:2008) and pos-
engineer with LeJeune connections with thicker plates for skewed framing often can be
sible column reinforcement at
Steel Company in designed for combined shear and tension forces.
moment connections.
Minneapolis.