DATED 4-03-2017
Pr pared By:
Raafat.Miller.Consulting
Prepared By
Table of Contents 1
2. Project Summary 4
2.1 Overall Project 4
2.2 Construction Buildings 4
3. Zones Key 5
4. Site Progress 6
4.1 Civil Works 6
4.2 Finishes Works 6
4.3 MEP Works 7
4.4 Building HN-02-B 8
4.5 Building HN-02-C 8
5. Trades Progress 9
5.1 Building HN-02-B 9
5.2 Building HN-02-C 9
` 6. Delayed Activities 10
6.1 Building HN-02-B 10
6.2 Building HN-02-C 14
7. Comparisons Report 18
8. Photos Progress 19
Report No. 62.xlsx
Budget
Report No. 62.xlsx
Total 14-Aug-16 08-May-17 -267 -69% -259 -67% -2% -1% 588 64
2- PROJECT SUMMARY
Report No. 62.xlsx
4- Overall Progress
5.2.1 HN-02-B
Civil 08-Aug-15 09-Dec-15 08-Aug-15 A 02-Mar-16 A 100% 100% 99.77% 0% -0.23% finished
Architecture 22-Nov-15 08-May-16 02-Dec-15 A 29-Aug-16 55.14% 7.44% 5.86% -48% -45% -97 149
MEP 17-Nov-15 21-May-16 10-Oct-15 A 20-Sep-16 62.29% 17.37% 17.37% -45% -40% -105 168
5.2.2 HN-02-C
Civil 02-Aug-15 05-Jan-16 02-Aug-15 A 17-Apr-16 100% 90.52% 89.02% -9% -11% -86 36
Architecture 09-Dec-15 19-May-16 24-Nov-15 A 31-Aug-16 41.07% 5.74% 4.91% -35% -28% -89 134
MEP 15-Nov-15 21-May-16 17-Oct-15 A 08-Sep-16 58.29% 8.34% 7.78% -50% -43% -95 158
A = Actual start date or Actual finish date Delay more than 10%
5.3.1 HN-02-B
Civil Backfilling & S.O.G 31/Oct/15 09/Dec/15 31/Oct/15 A 25/Feb/16 A 35 100% 100% - - - - - finished
Internal finishing 22/Nov/15 04/May/16 02/Dec/15 A 29/Aug/16 138 41.08% 9.11% 8.14% -31.97% -29.16%
Ground floor 13/Dec/15 04/May/16 11/Feb/16 A 15/Aug/16 120 40.97% 5.64% 3.38% -35.33% -30.14% -88 130 Delay in SOG
First floor 22/Nov/15 04/May/16 02/Dec/15 A 29/Aug/16 138 45.57% 22.06% 21.16% -23.51% -23.36% -100 142
Second floor 17/Dec/15 26/Apr/16 21/Dec/15 A 16/Aug/16 111 38.92% 7.35% 6.97% -31.57% -29.47% -94 138
Architecture
Roof floor 08/Dec/15 25/Apr/16 19/Dec/15 A 18/Aug/16 118 38.73% 0.65% 0.65% -38.08% -34.44% -97 140
Exnternal finishing 05/Jan/16 08/May/16 26/Jan/16 A 21/Aug/16 103 79.67% 4.52% 1.89% -75.15% -73.09%
Elevation 01 05/Jan/16 04/Apr/16 - - 76 80.00% 0.00% 0.00% -80.00% -79.91% -81 - not start
Elevation 02 23/Jan/16 27/Apr/16 26/Jan/16 A 28/Jul/16 82 78.64% 18.62% 9.93% -60.02% -47.57% -77 79
Elevation 03 05/Jan/16 17/Apr/16 09/Feb/16 A 16/Aug/16 87 94.69% 3.54% 2.36% -91.15% -89.71% -102 109
Elevation 04 05/Jan/16 08/May/16 09/Feb/16 A 21/Aug/16 103 71.83% 3.41% 0.00% -68.42% -68.64% -90 113
Ground floor 17/Nov/15 14/Apr/16 10/Oct/15 A 10/Aug/16 127 58.76% 27.14% 27.14% -31.62% -24.61% -99 133
First floor 23/Nov/15 12/Apr/16 01/Dec/15 A 18/Aug/16 120 75.22% 31.70% 31.70% -43.52% -38.83% -108 140
MEP
Second floor 17/Dec/15 14/Apr/16 10/Dec/15 A 07/Aug/16 101 73.77% 9.72% 9.72% -64.05% -58.66% -96 108
Roof floor 31/Dec/15 13/Apr/16 - - 88 70.37% 0.00% 0.00% -70.37% -67.48% -97 - not start
A = Actual start date or Actual finish date Delay more than 10% Not started Finished
5.3.2 HN-02-C
Part2 (axes 8-15) 02/Aug/15 05/Nov/15 02/Aug/15 A 20/Feb/16 A 73 100% 100% 100% - - - - finished
Backfilling & S.O.G 07/Nov/15 05/Jan/16 19/Dec/15 A 17/Apr/16 52 100% 65.47% 53.57% -34.53% -46.43%
Civil Part1 (axes 1-7) 01/Dec/15 05/Jan/16 16/Jan/16 A 17/Apr/16 31 100% 63.30% 45.51% -36.70% -54.49% -86 19 in-progress
Part2 (axes 8-15) 07/Nov/15 09/Dec/15 19/Dec/15 A 29/Mar/16 29 100% 68.16% 63.61% -31.84% -36.39% -92 1 in-progress
Superstructure 08/Aug/15 29/Oct/15 08/Aug/15 A 31/Mar/16 62 100% 90.16% 89.24% -9.84% -10.76%
Part1 (axes 1-7) 20/Oct/15 07/Dec/15 20/Oct/15 A 31/Mar/16 42 100% 83.26% 82.22% -16.74% -17.78% -97 5 in-progress
Part2 (axes 8-15) 16/Aug/15 07/Dec/15 16/Aug/15 A 28/Mar/16 88 100% 96.73% 95.92% -3.27% -4.08% -94 19 in-progress
Internal finishing 09/Dec/15 15/May/16 24/Nov/15 A 31/Aug/16 132 45.08% 7.64% 6.39% -37.44% -31.75%
Lower Ground floor 10/Dec/15 30/Apr/16 25/Nov/15 A 31/Aug/16 120 64.06% 10.70% 7.47% -53.36% -53.65% -104 129
Ground floor 09/Dec/15 30/Apr/16 24/Nov/15 A 11/Aug/16 121 49.11% 6.69% 6.69% -42.42% -30.07% -90 92
Part1 (axes 1-7) 14/Jan/16 30/Apr/16 - - 91 38.80% 0.00% 0.00% -38.80% -34.66% -87 - not start
Part2 (axes 8-15) 09/Dec/15 14/Apr/16 24/Nov/15 A 31/Jul/16 108 66.30% 18.21% 18.21% -48.09% -22.06% -90 77 in-progress
First floor 15/Dec/15 04/May/16 06/Dec/15 A 10/Aug/16 118 50.70% 14.42% 13.12% -36.28% -31.60% -84 116
Part1 (axes 1-7) 15/Dec/15 04/May/16 26/Jan/16 A 10/Aug/16 118 51.87% 10.15% 9.45% -41.72% -38.70% -84 116 in-progress
Architecture
Part2 (axes 8-15) 17/Dec/15 23/Apr/16 06/Dec/15 A 25/Jul/16 108 47.38% 26.56% 23.86% -20.82% -11.11% -78 68 in-progress
Second floor 02/Jan/16 04/May/16 13/Jan/16 A 17/Aug/16 103 31.52% 7.40% 4.71% -24.12% -21.03% -89 108
Part1 (axes 1-7) 17/Jan/16 03/May/16 25/Feb/16 A 15/Aug/16 90 27.97% 4.00% 0.40% -23.97% -20.73% -89 108 in-progress
Part2 (axes 8-15) 02/Jan/16 04/May/16 13/Jan/16 A 17/Aug/16 103 41.05% 16.54% 16.26% -24.51% -21.84% -89 95 in-progress
Roof floor 15/Dec/15 15/May/16 - - 127 38.07% 0.00% 0.00% -38.07% -34.12% -90 -
Part1 (axes 1-7) 29/Dec/15 14/May/16 - - 126 56.00% 0.00% 0.00% -56.00% -49.69% -90 - not start
Part2 (axes 8-15) 30/Dec/15 15/May/16 - - 127 22.82% 0.00% 0.00% -22.82% -20.87% -85 - not start
Exnternal finishing 02/Feb/16 19/May/16 24/Feb/16 A 20/Aug/16 91 33.22% 2.01% 2.01% -31.21% -20.66%
Elevation 01 02/Feb/16 19/May/16 24/Feb/16 A 09/Aug/16 91 43.64% 5.00% 4.80% -38.64% -26.13% -70 89 in-progress
Elevation 02 02/Feb/16 14/May/16 25/Feb/16 A 04/Aug/16 86 44.30% 5.00% 0.00% -39.30% -28.82% -70 84 in-progress
Elevation 03 14/Feb/16 17/May/16 01/Mar/16 A 20/Aug/16 79 10.00% 5.00% 0.00% -5.00% 0.00% -81 90 in-progress
Elevation 04 14/Feb/16 17/May/16 - - 79 5.00% 0.00% 0.00% -5.00% 0.00% -81 - not start
A = Actual start date or Actual finish date Delay more than 10% Not started Finished
BL1
Planned Actual Actual Actual
Duration Planned variance% variance% variance Remaining
Progress Progress Status Notes
(working Progress% this week last week per day Duration
BL Start BL Finish Start Finish this week% last week%
days)
Lower Ground floor 15/Nov/15 29/Mar/16 17/Oct/15 A 02/Aug/16 115 75.57% 10.98% 10.98% -64.59% -51.38% -106 123
Ground floor 23/Nov/15 14/Apr/16 29/Oct/15 A 02/Aug/16 122 58.10% 17.50% 17.50% -40.60% -36.92% -92 108
Part1 (axes 1-7) 10/Dec/15 14/Apr/16 05/Jan/16 A 02/Aug/16 107 49.61% 9.93% 9.93% -39.68% -35.51% -92 108 in-progress
Part2 (axes 8-15) 23/Nov/15 06/Apr/16 29/Oct/15 A 23/Jul/16 115 90.74% 46.61% 46.61% -44.13% -42.38% -90 95 in-progress
First floor 28/Nov/15 16/Apr/16 15/Nov/15 A 02/Aug/16 119 70.86% 10.69% 10.69% -60.17% -48.16% -91 109
Part1 (axes 1-7) 28/Nov/15 16/Apr/16 17/Jan/16 A 02/Aug/16 119 68.40% 5.16% 5.16% -63.24% -48.75% -91 109 in-progress
MEP Part2 (axes 8-15) 05/Dec/15 14/Apr/16 15/Nov/15 A 06/Jul/16 112 80.73% 32.97% 32.97% -47.76% -45.76% -69 81 in-progress
Second floor 08/Dec/15 16/Apr/16 09/Jan/16 A 07/Aug/16 110 67.71% 0.00% 0.00% -67.71% -59.44% -97 123
Part1 (axes 1-7) 08/Dec/15 13/Apr/16 01/Mar/16 A 07/Aug/16 108 63.04% 10.00% 0.00% -53.04% -53.44% -97 93 in-progress
Part2 (axes 8-15) 23/Dec/15 16/Apr/16 09/Jan/16 A 31/Jul/16 97 78.58% 10.00% 0.00% -68.58% -73.42% -88 123 in-progress
Roof floor 29/Dec/15 13/Apr/16 - - 90 37.22% 0.00% 0.00% -37.22% -32.47% -97 -
Part1 (axes 1-7) 29/Dec/15 03/Apr/16 - - 81 49.31% 0.00% 0.00% -49.31% -40.90% -97 - not start
Part2 (axes 8-15) 30/Dec/15 13/Apr/16 - - 89 21.68% 0.00% 0.00% -21.68% -21.63% -95 - not start
A = Actual start date or Actual finish date Delay more than 10% Not started Finished
6- Delayed activities
6.1 HN-02-B
Internal Finishing
Super Structure
SOG 100% 100% finished finished
Internal Finishing
Masonry 100% 50% -50% -70% 100% 100% finished finished 100% 100% finished finished 100% 50% -50% -85%
Plaster 100% 0% -100% -99% 100% 92% -8% -40% 100% 30% -70% -84% 100% 0% -100% -99%
Screed 100% 0% -100% -61% 100% 100% finished finished 100% 51% -49% -49% 100% 0% -100% -19%
Marble 100% 0% -100% -84% 100% 55% -45% -50% 100% 4% -96% -95% Does not exist
Porcelain 17% 0% -17% -15% 30% 0% -30% -25% 33% 0% -33% -32%
G.B. Partitions 100% 0% -100% -100% 100% 85% -15% -25% 100% 0% -100% -63% Does not exist
External Finishing
External Finishing
Plaster 100% 0% -100% -100%
Marble 100% 0% -100% -100% 57% 75% 18% -5% 82% 15% -67% -61% 64% 20% -44% -53%
Steel Structure 100% 0% -100% -100% Does not exist Does not exist 100% 0% -100% -100%
Curtain Wall Aluminum 100% 0% -100% -100% 100% 0% -100% -100% 100% 0% -100% -100% 100% 0% -100% -100%
Curtain Wall Glass 100% 0% -100% -100% 100% 0% -100% -78% 100% 0% -100% -100% 100% 0% -100% -100%
Aluminum (windows&doors) 100% 0% -100% -100% 68% 0% -68% -30% 100% 0% -100% -100% 100% 0% -100% -100%
Aluminum Louver 100% 0% -100% -100% 100% 0% -100% -57% 100% 0% -100% -100% 100% 0% -100% -81%
Fire Fighting
Piping Installation 96% 80% -16% -18% 100% 90% -10% -18% 100% 40% -60% -63% 100% 0% -100% -100%
Sprinkler 30% 0% -30% -20% 48% 0% -48% -45% 33% 0% -33% -28% 100% 0% -100% -100%
Plumbing
Piping Installation 100% 73% -27% -27% 100% 67% -33% -33% 100% 0% -100% -100% 100% 0% -100% -100%
HVAC
Duct Installation 100% 96% -4% 0% 100% 89% -11% -11% 100% 23% -77% -77% 100% 0% -100% -81%
Fans Does not exist Does not exist 100% 0% -100% -100% 100% 0% -100% -100%
CHWP 94% 95% 1% 1% 100% 41% -59% -59% 100% 0% -100% -100% 100% 0% -100% -100%
Air Outlet 33% 0% -33% -22% 39% 0% -39% -33% 24% 0% -24% -12%
Electrical
Fire Alarm 79% 77% -2% -24% 80% 54% -26% -33% 100% 0% -100% -89% 75% 0% -75% -75%
Wirring Devices 5% 0% -5% - 13% 0% -13% -11% 12% 0% -12% - 20% 0% -20% -20%
Panels 100% 0% -100% -75% 100% 0% -100% -100% 100% 0% -100% -87% 100% 0% -100% -100%
Internal Finishing
Lower ground Ground floor First floor Second floor Roof floor
variance variance variance variance variance variance variance variance variance variance
Planned Planned Planned Planned Planned
Actual% this last Actual% this last Actual% this last Actual% this last Actual% this last
% % % % %
week% week% week% week% week% week% week% week% week% week%
Super Structure
Part1 (axes 1-7) Does not exist 100% 60% -40% -60% Does not exist Does not exist Does not exist
SOG
Part2 (axes 8-15) 100% 65% -35% -40% Does not exist Does not exist Does not exist Does not exist
Internal Finishing
Part1 (axes 1-7) Does not exist 100% 0% -100% -100% 100% 100% finished finished 100% 50% -50% -95% 100% 0% -100% -100%
Masonry Work
Part2 (axes 8-15) 100% 53% -47% -68% 100% 100% finished finished 100% 100% finished finished 100% 100% finished finished 100% 0% -100% -100%
Part1 (axes 1-7) Does not exist 100% 0% -100% -96% 100% 37% -63% -79% 100% 0% -100% -90% 100% 0% -100% -100%
Plaster Work
Part2 (axes 8-15) 100% 37% -63% -67% 100% 100% finished finished 100% 100% finished finished 100% 0% -100% -100% 100% 0% -100% -100%
Part1 (axes 1-7) Does not exist 52% 0% -52% -26% 100% 76% -24% -24% 99% 0% -99% -65% 100% 0% -100% -100%
Screed Work
Part2 (axes 8-15) 100% 0% -100% -100% 100% 35% -65% -65% 100% 100% finished finished 97% 73% -24% -7% 100% 0% -100% -100%
Part1 (axes 1-7) Does not exist 100% 0% -100% -100% Does not exist
Marble Work
Part2 (axes 8-15) 100% 0% -100% -100% 100% 70% -30% -10% 100% 50% -50% 9% 100% 0% -100% -100% Does not exist
Part1 (axes 1-7) Does not exist 34% 0% -34% -20% 51% 0% -51% -51% 22% 0% -22% - 97% 0% -97% -93%
Porcelain
Part2 (axes 8-15) 80% 0% -80% -79% 52% 0% -52% -7% 11% 0% -11% -11% 11% 0% -11% -11%
Part1 (axes 1-7) Does not exist 100% 0% -100% -52% 50% 0% -50% -36% Does not exist
G.B. Partitions
Part2 (axes 8-15) 100% 72% -28% -34% 100% 0% -100% -100% Does not exist
Part1 (axes 1-7) Does not exist 19% 0% -19% -11% 100% 0% -100% -96%
Ceiling (Gypsum
Board&Tiles)
Part2 (axes 8-15) 88% 0% -88% -44% 100% 0% -100% -70% 54% 0% -54% -22% 4% 0% -4% - 100% 0% -100% -
Part1 (axes 1-7) Does not exist 100% 0% -100% -44% 64% 0% -64% 64% 100% 0% -100% -
Epoxy Floor
Part2 (axes 8-15) 100% 0% -100% -73% Does not exist Does not exist Does not exist Does not exist
Part1 (axes 1-7) Does not exist 18% 0% -18% -10% 6% 0% -6% - 21% 0% -21% -
Painting
Part2 (axes 8-15) 67% 0% -67% -43% 51% 0% -51% -50% 13% 0% -13% - 5% 0% -5% -
External Finishing
External Finishing
Marble 42% 0% -42% -31% 74% 0% -74% -35%
Steel Structure 72% 25% -47% -35% Does not exist Does not exist Does not exist
Lower ground Ground floor First floor Second floor Roof floor
variance variance variance variance variance variance variance variance variance variance
Planned Planned Planned Planned Planned
Actual% this last Actual% this last Actual% this last Actual% this last Actual% this last
% % % % %
week% week% week% week% week% week% week% week% week% week%
Fire Fighting
Part1 (axes 1-7) Does not exist 81% 90% 9% 0% 100% 72% -28% -26% 100% 0% -100% -86% 100% 0% -100% -100%
Piping
Installation
Part2 (axes 8-15) 100% 95% -5% -21% 100% 90% -10% -10% 100% 90% -10% -10% 100% 0% -100% -100% 67% 0% -67% -67%
Part1 (axes 1-7) Does not exist 50% 0% -50% - 50% 0% -50% -
Fire Extingution
Part2 (axes 8-15) 100% 0% -100% -
Part1 (axes 1-7) Does not exist 9% 0% -9% - 43% 0% -43% -40% 21% 0% -21% -3% 56% 0% -56% -20%
Sprinkler
Part2 (axes 8-15) 67% 0% -67% 67% 50% 0% -50% -50% 50% 0% -50% -50% 28% 0% -28% -25%
Plumbing
Piping Part1 (axes 1-7) Does not exist 100% 0% -100% -100% 100% 4% -96% -96% 100% 0% -100% -100% 100% 0% -100% -100%
Installation
Part2 (axes 8-15) 100% 14% -86% -86% Does not exist Does not exist 100% 0% -100% -100% 100% 0% -100% -100%
HVAC
Part1 (axes 1-7) Does not exist 83% 77% -6% -27% 98% 0% -98% -94% 93% 0% -93% -86% 100% 0% -100% -100%
Duct Installation
Part2 (axes 8-15) 100% 65% -35% -35% 100% 95% -5% -5% 100% 83% -17% -52% 100% 0% -100% -100% 73% 0% -73% -73%
Part1 (axes 1-7) Does not exist Does not exist Does not exist Does not exist 100% 0% -100% -100%
Fans
Part2 (axes 8-15) 100% 0% -100% -100% Does not exist Does not exist Does not exist 100% 0% -100% -100%
Part1 (axes 1-7) Does not exist 100% 34% -66% -66% 100% 0% -100% -100% 100% 0% -100% -100% 100% 0% -100% -100%
CHWP
Part2 (axes 8-15) 100% 50% -50% -50% 100% 95% -5% -5% 100% 45% -55% -55% 100% 0% -100% -100% 100% 0% -100% -100%
Part1 (axes 1-7) Does not exist 5% 0% -5% - 44% 0% -44% -31% 13% 0% -13% -9%
Air Outlet
Part2 (axes 8-15) 66% 0% -66% -66% 65% 0% -65% -28% 40% 0% -40% -32% 28% 0% -28% -18%
Electrical
Part1 (axes 1-7) Does not exist 74% 0% -74% -59% 90% 0% -90% -70% 96% 0% -96% -86% 100% 0% -100% -97%
Fire Alarm
Part2 (axes 8-15) 100% 0% -100% -100% 100% 90% -10% -10% 82% 90% 8% 10% 100% 0% -100% -100% 66% 0% -66% -66%
Part1 (axes 1-7) Does not exist 85% 0% -85% - 100% 0% -100% -
Panels
Part2 (axes 8-15) 100% 0% -100% -100% Does not exist Does not exist Does not exist
Part1 (axes 1-7) Does not exist 37% 0% -37% -31% 10% 0% -10% - 72% 0% -72% -50%
Wirring Devices
Part2 (axes 8-15) 66% 0% -66% -62% 66% 0% -66% -66% 40% 0% -40% -40% 38% 0% -38% -28%
Work up to
(accumulative progress) (accumulative progress) (accumulative progress) (accumulative progress) (accumulative progress) (accumulative progress) (accumulative progress) (accumulative progress) (accumulative progress) Progress% up
to this period
up to 30‐6‐2016 up to 31‐7‐2016 up to 31‐8‐2016 up to 30‐9‐2016 up to 31‐10‐2016 up to 30‐11‐2016 up to 31‐12‐2016 up to 31‐1‐2017 up to 15‐2‐2017
Schedule % 42.87% 49.76% 53.77% 57.22% 63.88% 67.39% 68.80% 73.48% 74.44%
Progress 31.57%
variance ‐ 6.89% 4.01% 3.45% 6.66% 3.51% 1.41% 4.68% 0.96%
RME
Finish Date 14‐Jan‐17 08‐Jan‐17 06‐Feb‐17 31‐Jan‐17 21‐Feb‐17 20‐Mar‐17 18‐Apr‐17 09‐May‐17 24‐May‐17
(accumulative value) (accumulative value) (accumulative value) (accumulative value) (accumulative value) (accumulative value) (accumulative value) (accumulative value) Progress% up to
IPC no.(011) 30‐6‐2016 IPC no.(012) 31‐7‐2016 IPC no.(013) 31‐8‐2016 IPC no.(014) 30‐9‐2016 IPC no.(015) 31‐10‐2016 IPC no.(016) 30‐11‐2016 IPC no.(017) 31‐12‐2016 IPC no.(018) 31‐1‐2017 this period
RME 53,818,312 58% 53,156,095 57% 53,622,867 58% 62,684,996 68% 63,883,282 69% 69,407,264 75% 71,486,172 77% 76,665,294 83%
Submitted by
RME OFOQ 18,179,819 33% 21,118,665 38% 25,065,706 45% 26,515,484 48% 27,479,986 50% 31,029,904 56% 35,595,755 64% 37,957,438 69%
SUM. 71,998,132 48.59% 74,274,761 50.12% 78,688,573 53.10% 89,200,480 60.19% 91,363,268 61.65% ########## 67.78% 107,081,927 72.26% 114,622,732 77.35%
44,076,109 47% 47,606,703 51% 52,638,277 57% 55,904,978 60% 61,503,560 66% 64,006,298 69% 69,267,880 75% 72,878,162 79%
Invoice RME variance variance variance variance variance variance variance variance
Payment ‐ ‐ 3,530,594 3.8% 5,031,574 5.4% 3,266,701 3.5% 5,598,582 6.0% 2,502,738 2.7% 5,261,582 5.7% 3,610,282 3.9%
Progress
15,223,210 28% 19,422,148 35% 22,524,222 41% 25,157,714 45% 26,510,148 48% 29,183,359 53% 32,002,893 58% 35,120,124 63%
(Gross) Certified by
OFOQ
RMC variance variance variance variance variance variance variance variance
‐ ‐ 4,198,938 7.6% 3,102,074 5.6% 2,633,492 4.8% 1,352,434 2.4% 2,673,211 4.8% 2,819,534 5.1% 3,117,231 5.6%
59,299,319 40.02% 67,028,851 45.23% 75,162,499 50.72% 81,062,692 54.70% 88,013,708 59.39% 93,189,657 62.89% 101,270,773 68.34% 107,998,286 72.88%
SUM. 32.86%
variance variance variance variance variance variance variance variance
‐ ‐ 7,729,532 5.2% 8,133,648 5.5% 5,900,193 4.0% 6,951,016 4.7% 5,175,949 3.5% 8,081,116 5.5% 6,727,513 4.5%
Report No. 62.xlsx
7- Progress Diagrams
Jul 2015 Aug 2015 Sep 2015 Oct 2015 Nov 2015 Dec 2015 Jan 2016 Feb 2016 Mar 2016 Apr 2016 May 2016
Planned Cash Flow Monthly (Gross) 0 4,930,131 5,733,545 10,520,368 11,526,673 13,576,510 17,410,256 31,213,318 34,118,293 18,428,976 728,816
MONTHLY CASH
FLOW Actual Cash Flow Monthly (Gross) 0 3,666,159 2,947,529 5,298,608 8,220,856 5,801,943 5,866,405
S‐CURVE
Cummulative Planned Value 0 4,930,131 10,663,676 21,184,043 32,710,716 46,287,226 63,697,482 94,910,800 129,029,094 147,458,069 148,186,886
S‐CURVE
160,000,000
140,000,000
120,000,000
100,000,000
80,000,000
60,000,000
40,000,000
20,000,000
0
Jul 2015 Aug 2015 Sep 2015 Oct 2015 Nov 2015 Dec 2015 Jan 2016 Feb 2016 Mar 2016 Apr 2016 May 2016
Cummulative Planned Value 0 4,930,131 10,663,676 21,184,043 32,710,716 46,287,226 63,697,482 94,910,800 129,029,094 147,458,069 148,186,886
Cummulative Actual Value 0 3,666,159 6,613,688 11,912,296 20,133,152 25,935,095 31,801,500
Means That Value Less Than Minimum Amount of Interim Payment (90% of Approved Cash Flow)
Invoice under engineer reviews
34,118,293
MONTHLY CASH FLOW
Planned Cash Flow Monthly (Gross)
31,213,318
Actual Cash Flow Monthly (Gross)
18,428,976
17,410,256
13,576,510
11,526,673
10,520,368
71%
8,220,856
43% 34%
50%
5,801,943
5,866,405
5,733,545
5,298,608
4,930,131
74%
51%
3,666,159
2,947,529
728,816
0
0
Jul 2015 Aug 2015 Sep 2015 Oct 2015 Nov 2015 Dec 2015 Jan 2016 Feb 2016 Mar 2016 Apr 2016 May 2016
Planned Cash Flow Monthly (Gross) 0 4,930,131 5,733,545 10,520,368 11,526,673 13,576,510 17,410,256 31,213,318 34,118,293 18,428,976 728,816
Actual Cash Flow Monthly (Gross) 0 3,666,159 2,947,529 5,298,608 8,220,856 5,801,943 5,866,405
% Amount of Interim Payments%
7.2 Shop Draw ings Progress
120%
PROJECT SUMMARY
100%
80%
Planned % Complete Actual % Complete
Cumulative variance% till Cumulative variance% till
this month last month
variance %
this month 60%
Shop Drawing
Submit Approved Submit Approved Submit Approved Approved Approved 40%
Total 100% 100% 71% 67% -29% -33% -41% 8% 20%
0%
Submit Approved Submit Approved
Planned % Complete Actual % Complete
Total 100% 100% 71% 67%
120%
BUILDING SUMMARY
100%
80%
Planned % Complete Actual % Complete
Cumulative variance% till Cumulative variance% till variance %
60%
Shop Drawing this month last month this month
40%
Submit Approved Submit Approved Submit Approved Approved Approved
20%
HN-02-B 100% 100% 75% 71% -25% -29% -38% 9%
0%
Submit Approved Submit Approved
HN-02-C 100% 100% 68% 65% -32% -35% -44% 8%
Planned % Complete Actual % Complete
HN‐02‐B 100% 100% 75% 71%
HN‐02‐C 100% 100% 68% 65%
BUILDINGHN-02-B 120%
100%
Cumulative variance% till Cumulative variance% till variance %
Planned % Complete Actual % Complete 80%
Shop Drawing this month last month this month
Submit Approved Submit Approved Submit Approved Approved Approved
60%
Civil 100% 100% 100% 100% Finished
40%
Architecture 100% 100% 69% 66% -31% -34% -45% 10%
120%
100%
80%
60%
40%
20%
0%
Submit Approved Submit Approved
Planned % Complete Actual % Complete
Total 100% 100% 87% 85%
Architecture 100% 100% 80% 78%
Electric 100% 100% 89% 89%
Mechanical 100% 100% 94% 90%
7.4 Average Monthly Manpower
Jul 2015 Aug 2015 Sep 2015 Oct 2015 Nov 2015 Dec 2015 Jan 2016 Feb 2016 Mar 2016 Apr 2016 May 2016
Planned Labor (average) 0 122 50 101 101 215 562 690 479 245 13
Actual Labor (average) 0 The Contractor does not Provide Daily Reports Regularly.
Elevations: