Assemble Spice modules and Ensure safe work conditions. From plans, review preliminary layout.
mounting components for the job. Install roof anchors. This example on a south-facing roof
has 2 rows of 4 panels.
Lay out attachment points on roof: Install flashings and L Feet at all Attach plumb line to bottom row of L
65” from bottom to middle holes, attachment points, following feet, and tighten lag bolts.
65-3/4 from middle to top holes, instructions for flashings. Attach second plumb line to middle
36” ridge setback (if necessary), and Loosely tighten all lags so that the lags row of L feet, and adjust second row of
48” rafter spacing (typical). are in the center of each L Foot slot. L Feet so that spacing is 65” between
Drill pilot holes in rafters L Feet gap (extra ¼” spacing simplifies
installation of modules).
Loosely tighten lag bolts on middle row
of L Feet.
Install two (or three) T Bolts in lower Install third and subsequent modules in
Pre-assemble first two modules. slot and two (or three) T Bolts in upper bottom row
Install two E-W Splices in first module. slot of pre-assembled modules, with Tighten E-W Splices as modules are
Snap second module into first module. Hex nuts loosely attached to T Bolts. installed.
Push down hex bolt on top of E-W Install pre-assembled modules in L Use boxes to prop up and align
Splice to simplify snap connection. Feet. modules as they are installed.
Tighten E-W Splices between Do not tighten hex nuts at this time.
modules.
Copyright 2015, Spice Solar, Inc. Spice Solar Installation Tips – L-Foot Mounting System Page 1
Spice Solar, Inc. reserves the right to make changes without any prior notice. All rights reserved.
Verify east-west and vertical alignment Loosen lag bolts on L Feet on middle Install N-S Bracket on T Bolt and L
of modules on roof. row so that L Feet are flush with side Foot.
Adjust modules vertically on L Feet as of modules. Tighten Hex nut securing N-S Bracket.
needed. Tighten lag bolts securing L Feet to If necessary, remove bolt to reverse
Tighten bottom row hex nuts to L Feet. roof along middle row. bracket, then reinstall bolt.
Pre-assemble first two modules for Lower pre-assembled modules into top Install third and subsequent modules in
second row. row of L Feet. top row.
Tighten E-W Splices between Tighten N-S Brackets between Tighten E-W Splices and N-S Brackets
modules. modules. as modules are installed,
Install two (or three) T Bolts in top slot Adjust top row L Feet flush to side of
of pre-assembled modules. modules, and tighten lag bolts on L
Slide pre-assembled modules into Feet.
tabs on N-S Brackets installed in the Verify vertical alignment of top row of
middle row of attachments. modules, and tighten L Feet to side of
modules.
Torque Specifications:
E-W Splices and N-S Brackets: 7 ft-lbs
Hex nuts on T bolts: 25 ft-lbs
Ground lug bolt: 5 ft-lbs
Ground lug set screw: 2.5 ft-lbs