What are the documents required for the application process for the Change of Tenancy (COT)?
Lisa says:
The process for the Change of Tenancy (COT) is by forwarding complete documents to TNB.
The required documents for Individuals and Company are:
For Individuals :
For Company :
You asked:
how to change electricity tariff from Tariff B to Tariff D when the business is expanding into manufacturing
Lisa says:
• Is it possible for customer to change tariff from general tariff (such as tariff E1) to a peak /off-peak tariff
(such as tariffs E2)?
• Electricity tariff is too high
• Is customized tariff customer subjected to changes during tariff review as approved by the government?
• What is the process for customers to apply for conversion to the industrial tariff rates?
You selected:
1/2
3/5/2018
What is the process for customers to apply for conversion to the industrial tariff rates?
Lisa says:
On-site verification is needed to confirm that a customer activity is coincides with the definition in TNB
tariff book. Site Visit Report with picture, the relevant supporting documents must be uploaded in the
BCRM record. Please refer to Tariff Verification checklist as in Circular PBK (PP) C14-2015.
To qualify for industrial rates:
- Charges for the use of lights and aircon office must not exceed 20% of the overall load on the premises
Relevant supporting documents (such as MIDA License/ PBT Manufacturer License etc)
Approval for change of tariff is at Branch Level
Consumer are required to sign a new supply contract.
Consumer need to sign the new contract.
Related Questions
You selected:
Lisa says:
The electricity tariff is determined by the government. However, through Imbalance Cost Pass Through (ICPT)
mechanism, changes (either an increase or reduction) of the uncontrollable fuel costs in the electricity tariff will
be reviewed every 6 months.
x • Is it possible for customer to change tariff from general tariff (such as tariff E1) to a peak /off-peak tariff
(such as tariffs E2)?
• Electricity tariff is too high
• Is customized tariff customer subjected to changes during tariff review as approved by the government?
• What is the process for customers to apply for conversion to the industrial tariff rates?