Beruflich Dokumente
Kultur Dokumente
Keywords: Dynamic load, impact load, finite element modelling, structural rehabilitation, post-
tensioning, CFRP, powerhouse, emergency shutdown.
1 ANTECEDENTS
The every-five-year maintenance program executed in 1995 made evident the occurrence of
significant relative displacements between the first-stage and second-stage concretes, when some
problems during the re-installation of the safety valve to the scroll case were experimented in Unit 2.
From that moment on, the structure was instrumented and monitored, confirming the active nature of
both the related displacements and the cracking present in the second-stage concrete surrounding the
scroll case. Figure 2 presents a typical crack in Unit 2.
2/10
2 FIELD TESTING
With the main purpose of collecting as much information as possible related to the quality of the
second-stage concretes and to the probable corrosion processes in the reinforcing bars, extensive
non-destructive tests were executed. Those tests and their results are briefly described as follows:
Following, a detailed description of the methodology and main results from the analyses carried-
out for the vulnerability assessment of the Guadalupe IV Powerhouse are presented.
3/10
0.6
SEUDOACCELERATION (g)
0.5
0.4
0.3
0.2
0.1
0.0
0.010 0.015 0.020 0.025 0.030
PERIOD (sec)
The subsequent restart of the system after an emergency shutdown generates a pressure-
equilibrium process through the by-pass of the safety valve, inducing two significant dynamic
solicitations, namely:
• An impact load coming from the slip-type joint installed between the admission valve and the
scroll case. Because of the nature of this sort of joint, the total impact force is transmitted to
the second-stage concrete surrounding the scroll case, adjacent to the admission valve. The
instantaneous force, before considering the amplification factor associated to an impact force,
is about 12.000kN.
• A uniform radial-expansion pressure acting inside the scroll case and therefore pushing the
second-stage concrete through the pipe steel Considering that the mentioned concrete was
cast with the scroll case pressurised at 2,1MPa, and taking into account that the total water
column associated with the level difference to the water reservoir is 560m (generating a
pressure of 5,6MPa), it was concluded that an instantaneous excess pressure of 3,5MPa is
induced to the scroll case.
concrete of one of the units, and Figure 4(b) shows the shell elements representing the scroll case
and the draft tube embedded in the concrete. The shell elements were intended only to properly
define and visualise the complex geometry shape of the structure, without any structural implication.
Restraints, application of forces and obtained stresses on the model are related only to solid
elements.
• Influence of structure stiffness: Frequency analyses for different model restraint disposition
were carried out for the following cases: 1) fully fixed at the base, 2) fully fixed at the base and
the walls between levels 691,6 and 696, and 3) fully fixed at the base, the walls touching the
first-stage concrete and the sides in contact with other unit’s concrete. In Figure 5, the
obtained mass participation factor for each case is presented, for a constant modulus of
elasticity value of 26GPa.
45
40 Restraint Case 1
Restraint Case 2
35
Restraint Case 3
30
MASS %
25
20
15
10
5
0
0 0.01 0.02 0.03 0.04 0.05
PERIOD (sec.)
Besides, the effect of the modulus of elasticity of concrete on the frequency response was
analysed for two values considered as the possible minimum and maximum values,
5/10
Ec1=20GPa and Ec2=26GPa. Figure 6 shows the results of the analysis for the x and z
model directions (y is the vertical direction). The largest mass participation factor for both
modulus of elasticity were found in the x direction, corresponding to the second vibration
mode, and in the z direction corresponding to the third vibration mode.
30
Ec=20GPa - x dir
Third mode Ec=26GPa - x dir
25 Ec=20GPa - Z dir
Ec=26GPa - Z dir
20
Second mode
MASS %
15
10
0
0.000 0.005 0.010 0.015 0.020 0.025
PERIOD (sec)
Fig. 6. Effect of the modulus of elasticity of the concrete in the mass participation
It was concluded that there were no major differences between the behaviour of Cases 2 and
3, but significant between those cases and that observed for Case 1. However, Case 2 is the
one which represents in the most realistic way the restraint conditions of the second-stage
concrete inside the first-stage concrete of the main structure, being the model used for further
analyses in this study. From the point of view of the influence of the modulus of elasticity of
concrete, it was established that the model was not very sensitive to it for the values that were
used.
0.50
From shutdown record
0.45
From ambiance noise record
0.40
SEUDOACEELERATION (g)
0.35
0.30
0.25
0.20
0.15
0.10
0.05
0.00
0.010 PERIOD (sec.) 0.100
The load cases taken into account for the structural analysis, leading to the most critic
combination to be used in the vulnerability assessment, are present in Table 1:
Load Description
Figure 9 presents the principal stress distribution for longitudinal (a) and transversal (b) sections of
the unit.
The resulting principal stresses in the second-stage concrete, for a plant-view at the level of the
scroll case axis, are presented in Figure 10.
Fig. 10. Principal stresses - Plant at the level of the scroll case
Comparing the resulting stresses and the strength provided by the existing reinforcement steel, it
was concluded that the disposed bars upward the scroll case, according to the original design, are
insufficient to counteract the demand under the current solicitations. It was also evident that tensile
stresses present in some particular locations of the walls exceed the concrete tensile strength, and
then cracking at those locations must be expected. It is worth mentioning that, as an outstanding
result of this investigation, the locations in the structure at which cracking is expected and the cracking
orientation according to the results of the structural analysis, fit very well with the cracking patterns
observed in the real structure, implying an adequate loading definition and execution of the structural
analysis.
The initial hypothesis was confirmed. It was established that the progressive deterioration of the
second-stage concrete of the units is caused by repetitive emergency shutdown-restart cycles that
constantly act in the concrete through the admission valve and the scroll case due to the mechanical
behaviour of the slip joint.
According to the observed results, the repair strategy must counteract the acting stresses in the
upper part of the concrete surrounding the scroll case and the tensile stresses in the surface of the
walls. The structural solution must be relatively easy to implement generating an as-less-as-possible
interruption in the powerhouse operation service, and perfectly defined to prevent causing any
damage in the pipelines, instrumentation and other devices embedded in the concrete to be repaired.
8/10
In this way, it was decided to display a series of post-tensioning tendons to attend the stresses in the
internal concrete and carbon fibre reinforced polymer, CFRP mantles, to attend superficial stresses in
the walls and the floor at the safety valve level.
The structural model was used in the definition of tendon designation, by combining the effect of a
certain compressive force provided by the tendons with the current forces used in the previous
structural analysis. Different values of force provided by the tendons were combined, up to a
particular value for which the obtained stresses were less that the concrete tensile strength. For the
design of the CFRP, a tensile stress equal to 60% of the fibre ultimate strength (3.550MPa) was used.
The adopted solution consisted in the installation of 6 post-tensioning tendons of 8-0,6”, grade
270, according to the ASTM A416 norm, anchored to the non-weathered rock, as shown in Figure
11(a). Each tendon was tensioned to provide an ultimate effective force of 1.500kN, and were
displayed at the generator level as shown in Figure 11(b).
The 50-cm width CFRP was recommended to be placed in both the horizontal and vertical
directions, with a number of layers depending on the expected tensile stresses at a particular location.
In Figure 12, pictures illustrating the fibre placing on wall surfaces of Unit 2 are shown.
The sequence followed in the repairing works for each unit consisted in:
9/10
1. Injection and sealing of cracks in the second-stage concrete surrounding the scroll case and
the draft tube.
2. Drilling of ducts for tendon installation
3. Placing and post-tensioning of tendons
4. Grouting of ducts to protect tendons
5. Placing of CFRP mantles on the lateral walls
6. Placing of CFRP mantles on the floor, at level 696
7. Placing of a heavy duty mortar, for protection of the CFRP on the floor al level 696
The structural rehabilitation of the second-stage concrete of the three units of the Guadalupe IV
Powerhouse was undertook during the year 2000, taking advantage of the electro-mechanical
maintenance shutdowns of each unit, keeping the central continuously generating during the works.
The total area of CFRP used was around 720m2. Average length of the tendons ranged between 23
and 25m. Average total time for rehabilitation works in each unit were 30 days, and the total cost
associated with the rehabilitation process of the three units rounded US$350.000. Currently, the
powerhouse operates normally without any structural problem. Some noises and other minor
problems in the mechanical behaviour of the generator, that were usually reported, have been
prevented after the structural rehabilitation.
5 CONCLUSIONS
Studies intended to rehabilitate the second-stage concrete surrounding the scroll case and the
draft tube of each one of the three units of the Guadalupe IV Powerhouse were carried out. The
vulnerability assessment included a series of mechanical and structural analyses, non-destructive
testing and structural design. From those investigations, the following conclusions arose:
• The concrete in the non-cracked zone is homogeneous and has a good quality. The probable
concrete strength ranges from 26MPa to 30MPa. The extensive concrete cracking in
particular locations was not a result of corrosive processes, as determined after analyses of
corrosion electropotentials, measurement of chloride and moisture content and depth of
carbonation.
• Related to the estimation of diameters, spacing and coverings of reinforced bars, it was found
a very good concordance between construction plans and the actual condition of the structure.
Steel bars in the walls correspond to #6 bars displayed in both the horizontal and vertical
directions, spaced 0,30m. Measured coverings of reinforced bars indicate an adequate
protection of the steel from external aggressive agents.
• Although resonance phenomena between the structure and the exciting vibration generated
by shutdown-restart processes certainly exist, the fundamental reason that conducted to
cracking problems is the 12.000kN impact force that the concrete must absorb due to the
absence of a restricted-type joint between the admission valve and the scroll case, as well as
the increasing of the dynamic radial pressure (3,5MPa) into the scroll case. Both solicitations
are originated as a result of the unit restart operation.
• For the original design no previsions for changes in load regimes implying the frequency of
occurrence such as the one currently acting, were taken into account. Furthermore, twenty
years ago the effects on the surrounding concrete due to instantaneous increasing in the
scroll case internal pressure could not be calculated with the available tools. The present
study provided interesting information about the structural behaviour of this kind of massive
concrete structures subjected to different types of loads.
• The proposed and executed structural rehabilitation is considered the only viable solution to
recover the affected concrete of the powerhouse, according to its operation and generation
restrictions and the limiting space to undertake the works. The structural recovery was
successfully implemented in the year 2000, taking advantage of the periods for electro-
mechanical maintenance of the units.
10/10
ACKNOWLEDGEMENTS
The authors wish to express their acknowledgements to Empresas Públicas de Medellín and to
Integral S.A. for making the information used in the analysis of the Guadalupe IV Powerhouse
Structural Rehabilitation available for this paper.
REFERENCES
[1] Integral S.A.: Ultrasonic testing in the concrete surrounding the scroll cases and the draft
tubes in the Guadalupe IV Powerhouse, Medellín,1998.
[2] Integral S.A.: Vulnerability assessment for the Guadalupe IV Powerhouse, Medellín,1999.
[3] Neville, A.M.: Concrete Technology, Instituto Mexicano del Cemento y el Concreto, A.C.,
Mexico City,1977.
[4] Structural Research & Analysis Corp.: Cosmos/M Version 2.0, Santa Monica, 1998.