Beruflich Dokumente
Kultur Dokumente
NO.
A. PHASE 1
I. MOBILIZATION (incl. Tempacil,Permits & etc.)
II. EARTHWORKS
a. Clearing & Grubbing
b. Top Soil Stripping
c. Site Grading Cut
d. Site Grading Engineered Fill
e. Hauling & Disposal
III. CONSTRUCTION OF UNDER GROUND DRAINAGE SYSTEM & OUTFALL
a. Excavation
b. Sand Bedding
c. Laying of RCP @ Road 1 to Road 5
d. Laying of RCP @ Road 6 to Road 10
e. Backfilling
IV. CONSTRUCTION OF COMBINED DRAINAGE INLET MANHOLE
a. 300mmØ x 300mmØ
b. 300mmØ x 375mmØ
c. 300mmØ x 450mmØ
d. 300mmØ x 600mmØ
e. 300mmØ x 750mmØ
f. 300mmØ x 900mmØ
V. CONSTRUCTION OF UNDERGROUND WATER DISTRIBUTION SYTEM
a. Laying of uPVC @ Road 1 to Road 5
b. Laying of uPVC @ Road 6 to Road 10
c. Installallation of Service Connection & accessories
VI. CONSTRUCTION OF ROAD PAVEMENT
a. Road Tracing
b. Sub Grade Preparation
c. Base Coarse Preparation
d. Pavement Concreting
1.'@ Road 1 to Road 5
2.'@ Road 6 to Road 10
VII. CONSTRUCTION OF CURVES & GUTTER
VIII. CONSTRUCTION OF SIDEWALK & PLANTERS
B. PHASE 2
IX. CONSTRUCTION OF UNDER GROUND DRAINGE SYSTEM & OUTFALL
a. Excavation
b. Sand Bedding
c. Laying of RCP @ Road 12 to Road 15
d. Laying of RCP @ Road 16 to Road 18
e. Backfilling
X. CONSTRUCTION OF COMBINED DRAINAGE INLET MANHOLE
a. 300mmØ x 300mmØ
b. 300mmØ x 375mmØ
c. 300mmØ x 450mmØ
d. 300mmØ x 600mmØ
e. 300mmØ x 750mmØ
f. 300mmØ x 900mmØ
XI. CONSTRUCTION OF UNDERGROUND WATER DISTRIBUTION SYTEM
a. Laying of uPVC @ Road 12 to Road 15
b. Laying of uPVC @ Road 16 to Road 18
c. Installallation of Service Connection & accessories
XII. CONSTRUCTION OF ROAD PAVEMENT
a. Road Tracing
b. Sub Grade Preparation
c. Base Coarse Preparation
d. Pavement Concreting
1.'@ Road 12 to Road 15
2.'@ Road 16 to Road 18
XIII. DEMOBILIZATION
TOTAL WEIGHTED %
ACT
Cummul
P
Cummulative P
PROJECT SCH
CONTRACT WT. %
2015
AMOUNT June July August September
1 2 3 4
331,200.00 0.583
209,898.00 0.369
102,465.00 0.180
41,124.00 0.072
46,644.00 0.082
36,328.50 0.064
475,453.13 0.836
475,453.13 0.836
637,635.90 1.122
287,150.40 0.505
47,058.00 0.083
840,644.94 1.479
840,644.94 1.479
122,047.20 0.215
220,800.00 0.388
139,932.00 0.246
68,310.00 0.120
27,416.00 0.048
31,096.00 0.055
24,219.00 0.043
316,968.75 0.558
316,968.75 0.558
122,047.20 0.215
136,537.20 0.240
415,090.20 0.730
2,074,485.00 3.650
0.000
2,827,940.76 4.975
2,827,940.76 4.975
342,125.00 0.602
56,838,500.00 100.000
ACTUAL PROGRESS % 0.602 0.446 2.674 3.452
Cummulative PROGRESS % 0.602 1.048 3.722 7.174
PLAN PROGRESS % 1.000 2.000 3.000 5.000
Cummulative PLAN PROGRESS % 1.000 3.000 6.000 11.000
PROJECT SCHEDULE
DURATION MONTH
2015
October November December January February March
5 6 7 8 9 10
0.418
0.090 0.090
0.137 0.137 0.137 0.137 0.137 0.137
0.547 0.547 0.547 0.547 0.547 0.547
0.706 0.706 0.706 0.706 0.706 0.706
0.706 0.706 0.706 0.706 0.706
0.738 0.738 0.738 0.738 0.738
0.515 0.515 0.515 0.515 0.515
0.345
0.101 0.101 0.101 0.101 0.101 0.101
1.423 1.423 1.423 1.423 1.423
0.099 0.099 0.099 0.099 0.099 0.099
0.715 0.715 0.715 0.715 0.715 0.715
0.277 0.277
0.277 0.277 0.277
0.036 0.036 0.036 0.036
0.041 0.041
0.032 0.032
0.418
0.418 0.418
0.561 0.561
0.137
0.547 0.547 0.547
0.706 0.706 0.706 0.706
0.706 0.706 0.706 0.706 0.706
0.738 0.738 0.738 0.738 0.738
0.515 0.515 0.515 0.515 0.515
0.279
0.279
100%
80%
70%
60%
50%
40%
30%
0.040
0.024
0.028
0.021 0.022 20%
0.279
0.279
0.215
10%
0.498
0.498 0.498
0.602 0%