Beruflich Dokumente
Kultur Dokumente
Characteristics of different pipes for pumping main help to choose between pipe options for particular site.
The size of the main should be determined considering initial cost and capitalized O & M cost for different sizes as per method
given in Water Supply Manual. It is designed according to the following considerations:
Where flows are expected to substantially increase between 2026 and 2041 the option of laying a duplicate line at a
later stage will be investigated, and
Location
At places, where depth of sewer becomes too deep and it is difficult to lay sewer at such depths, sewage-pumping station is
required to lift the sewage to nearby manhole or to the STP, from where it will flow by gravity.
Screens and Overflow.
All SPS will be provided with coarse screens before the wet well with clear opening of 40-50 mm between the bars for the
manually cleaned type and 25 mm for the mechanical type. The screening units shall always be provided in duplicate. It is
also provided with a bye bass on the upstream side, to avoid overflow of the screen channel in case of sudden power failure.
Drainage facility shall also be provided in the individual screen channels to empty these channels for maintenance purposes.
Wet Well
The sewer line will discharge the sewage into a wet well. The capacity of wet well/sump should be such that deposition of
solids is avoided and sewage does not turn septic. The capacity should not be too low to require frequent on-off of pumping
sets. The capacity of the wet well is to be so kept that with any combination of inflow and pumping, the cycle of operation for
each pump will not be less than 5 minutes and the maximum detention time in the wet well will not exceed 30 minutes of
average flow. The high water level in sump well will not exceed invert level of lowest incoming pipe.
Types
The removal of contaminants from sewage is brought by a sequential combination of various physical unit operations and
chemical and biological unit processes. The physical unit operations include screening, grit removal and sedimentation. The
biological processes is broadly classified as i) suspended growth processes, both aerobic and anaerobic, including activated
sludge process, extended aeration, lagooning, nitrification, de-nitrification and anaerobic digestion and ii) attached growth
processes such as aerobic and anaerobic filter processes. The treatment plants are also called primary treatment if treatment
is limited to physical process, secondary treatment when treatment is up to biological treatment and tertiary treatment when
treatment goes beyond biological treatment to meet some further requirement of effluent quality.
Centralized or Decentralized
The treatment plants can be centralized or decentralized. In case of decentralized more number of smaller capacity plants are
constructed. This system decreases cost of sewerage system but increases initial and O & M cost of STPs.
Screening
Screen is a device with openings generally of uniform size for removing bigger suspended or floating matter in sewage and
are placed before SPS and STPs. Coarse screenings have opening of 75-100 mm for SPS and 50 mm for STPs. Medium
screens have opening of 20-50 mm and fine screens have openings less than 20 mm. Coarse screens are manually cleaned
but medium and fine screens are mechanically cleaned. Fine screens may be of the drum or disc or mat type. Quantity of
screenings is about 0.0015 cum/ml with screen size of 10 cm and 0.015 cum/ml in case of 2.5 cm.
Sedimentation
For primary sedimentation tanks, both, surface overflow rate and detention period (Hydraulic Residence Time) are important
design criteria as the solids to be settled are flocculent in nature and undergo flocculation. The major design parameters for
secondary settling tanks designed to remove bio-flocculated solids are solid loading rate or solid flux as well as surface over
flow rate. The overflow rates for settling tanks as per Manual. The smaller values in the range are applicable for plants less
than 5 MLD.
A. Primary Settling
B. Secondary Settling
Secondary Settling for trickling filter 15-25 40-50 70-120 190 2.5-3.5 1.5-2.0
Secondary Settling for extended aeration 15-Aug 25-35 25-120 170 3.5-4.5 1.5-2.0
Grit Removal
Grit consists of coarse particles of sand, ash and clinkers, egg shells, bone chips and many inert materials of inorganic in
nature. For STPs more than 10 MLD mechanical grit cleaning system should be provided. In case of manually cleaned grit
chambers at least two units should be provided and all mechanically cleaned units should be provided with a manually
cleaned unit to act as a bypass. The grit content is 0.05 to 0.15 cum/ml for domestic sewage. The minimum size of grit to be
removed is 0.2 mm although 0.15 mm is preferred where ash content is more. Detention period of 60 seconds can be
taken.The settling velocities and surface over flow rates for ideal grit chamber at 10 degree centigrade.
Settling velocities and Surface Overflow Rates for Ideal Grit Chambers
Sizing/Upflow-horizontal flow
Up flow tanks have been used for sewage sedimentation but horizontal flow types are more popular. Diameter of circular
tanks vary widely from 3 to 60 m although common range is 12 to 30 m. Rectangular tanks, maximum length and widths of
90 and 30 m with length to width ratio of 1.5 to 7.5 and length to depth ratios of 5 to 25 are recommended.
COD(mg/l) 250 -
5.5-9.0 5.5-9.0
pH
Sulphides (mg/l as S) 2 -
Total Chromium (mg/l as Cr) 2 -
Desirable 1,000
Land Requirement
Requirement of land for different processes of treatment is given below:
Copyright © 2009 National Capital Region Planning Board Legal Site Version 1.0 All Rights Reserved.