Weekly Progress Report

11

Welcomes You !

Jadcherla
Expressways Toll
Plaza Project
JEPL TOLL PLAZA– Project Progress:-
Progress Photographs: Admin Building Work Progress:-

Admin Building Basement Completed


Ground Floor Column Work in Progress :-

2
Progress Photographs: Box Culvert at Ch:54:080 :-

R.H.S :-Raft Casting Completion L.H.S :- -Raft Casting Completion


JEPL TOLL PLAZA–
Truck Lay Bay Progress Photographs:

blob:file:///95ff32c6-3488-4eab-a399-ac590b45d299

WMM Laying for 2 Lane on Site, for MC50 LHS & RHS:-
Road No. MC 50 ,MC40, MC30, Sub-grade & GSB Top Level Completed.
Total Area:-24000 Sqm. Completed Area For Subase:-17000 Sqm.
JEPL TOLL PLAZA–Drain & Tunnel
Tunnel Progress Photographs: L.H.S Side

Tunnel L.H.S 30m Length Completed.Back Filling in Progress

5
JEPL TOLL PLAZA–Drain & Tunnel
Tunnel Progress Photographs:R.H.S Side

Tunnel Side R.H.S Completed:-

6
Progress Photographs: Canopy Foundation :-
4 Nos Canopy Foundation Completed, Total Foundation-12 Nos.:-
Progress Photographs: Paver Block Manufacturing in
Progress:-

Paver Block Machine Erected at Site & 4 Lakh 30 Thousand pieces are
Casted, Average 10000 thousand casting per day:-
Total -12 Lakh required for Truck Lay bay Area
Grade:- M40
3 days Results :- 27 N/mm2
7 days Result :-32 N/mm2
28 days test Result :-42 N/mm2
Progress Photographs: Traffic & Security Aid Post :-
Traffic & Security Aid Post RCC Completed , PCC Work Completed:-
Progress Photographs: Medical Aid Post :-
Medical Aid Post R.C.C Completed, Soiling Work in Progress :-
Progress Photographs: Maintenance & Canteen building:-
Maintenance Building:- Footing Completed & Plinth Beam in Progress
Canteen Building:-Footing Completed & Plinth Beam in Progress
Progress Photographs: Way Side Amenities :-
Dhaba.:- Plinth Work in Progress, Anchoring for PEB in progress:-
Progress Photographs: Admin Area :-
Septic Tank Work , Brick work in progress:-
Progress Photographs: Electrical Work :-
Transformer Charged & Connected to Toll Plaza:-
Relocation of Existing Transformer in Progress:-
Road Work :-
L.H.S Road Work:-

L.H.S Side :-Subgrade Work in Progress


Cleaning & Grabbing Completed
Road Work :-
R.H.S Road Work:-

R.H.S Side :-Subgrade Completed, GSB Top Completed for 1700 Sqm :-
Guard Post Casting in Progress:-Total Quantity 600
Completed:-498 Casted Till Date, Daily 8 is been Casted

Kerb Casting Work in


Progress:-
JEPL TOLL PLAZA–Drain & Tunnel
Drain Progress Photographs:
Drain Work:-
Completion:- 470m !br0ken!!
Excavation:-560m

18
JEPL TOLL PLAZA– Project Plans and its Review

Thank You

19