Beruflich Dokumente
Kultur Dokumente
Introduction
All of you have had at least an introduction to earned value management in the project management
fundamentals course. Many of you may have had the opportunity to use earned value management in
your professional careers. In practice, most EVM analysis results are generated by scheduling software
or other applications. As a project manager, you must have a good handle on the concepts and be able
to verify the accuracy of EVM analysis results.
In this assignment, you will have an opportunity to brush up and expand upon your EVM knowledge and
skills by applying EVM concepts to a practical problem. THIS ASSIGNMENT REQUIRES A MANUAL
ANALYSIS - DO NOT USE MICROSOFT PROJECT.
Problem Background
Your project consists of seven activities with planned start and finish dates shown in the chart below:
Activity 7
Activity 6
Activity 5
Activity 4
Activity 3
Activity 2
Activity 1
1 3 5 7 9 11 13 15 17 19 21 23
Week
PMAN 650
Session 5 Individual Assignment (v3.1)
Earned Value Management
Activity budgets and earned value (EV) accrual rules from you project cost management plan are as
follows:
Assumptions
1. Assume a five-day work week with no holidays occurring during the work week.
2. For all activities (except activities 3 and 4), assume the expenditure rate is constant over the
duration of the activity, i.e., the amount planned to be spent each week is the same. See the
conceptual profile below.
Weekly Expenditures –
Constant Expenditure Rate Activities
Expenditure
Rate
1 2 3 4 5 6... and so on
Week
PMAN 650
Session 5 Individual Assignment (v3.1)
Earned Value Management
10000
8000
6000
4000
2000
0
1 2 3 4 5 6 7 8
PMAN 650
Session 5 Individual Assignment (v3.1)
Earned Value Management
The project sponsor wants you (the PM) to present a project cost and schedule performance assessment
using data through the end of week 8. You have collected the following information:
For activity 1, three equally-valued gates have been established and all gates are complete as of the end
of week 8.
For activity 3, five milestones have been established with the following values: (1) milestone 1 – 10%;
milestone - 20%; milestone 3 – 15%; milestone 4 -20%; milestone 5 – 35%. Four of the milestones are
complete as of the end of week 8.
For activity 4, four equally values gates (milestones) have been established. As of the end of week 8,
none of the gates have been reached but the activity owner estimates 30% of the work required to
reach the first gate has been accomplished.
Show all work. Round dollar values to the nearest dollar. Calculate all other
variables to three decimal places.
PMAN 650
Session 5 Individual Assignment (v3.1)
Earned Value Management
a. Calculate earned value measures for each activity and for the cumulative project as of
the end of week 8; fill in the table below:
Activity Planned Value (PV) Earned Value (EV) Actual Cost (AC)
Activity Five 0
Activity Six 0
Activity Seven 0
Entire Project
PMAN 650
Session 5 Individual Assignment (v3.1)
Earned Value Management
a. Calculate earned value performance parameters for each activity and for the cumulative
project as of the end of week 8; fill in the table below:
Activity One
Activity Two
Activity Three
Activity Four
Activity Five
Activity Six
Activity Seven
Entire Project