Recently-Issued Rules and Guidelines

THE 2015 REVISED RULES AND


GUIDELINES ON TIME OF COMPLETION
By: Atty. Antonio M. Bernardo
Chief Executive Officer and Commissioner

SUBDIVISION AND HOUSING


DEVELOPERS ASSOCIATION (SHDA)
2016 1st Business Meeting
February 10, 2016
Metro Club, Makati City, Metro Manila
Recently-Issued Rules and Guidelines

B.R. No. 929 S. of 2015


M.C. No. 10, S. of 2015
(December 1, 2015)
(October 23,2015)
PURCHASE OF ASSET-BACKED SECURITIES
PROVISIONAL ACCREDITATION OF
ISSUED BY THE NHMFC AS MODE OF COMPLIANCE
SOCIALIZED HOUSING DEVELOPERS
WITH SECTION 18 OF REPUBLIC ACT NO. 7279

Dispenses with the requirement of 500


housing units built for accreditation

` Requires only the submission of


development permit and joint-venture
agreement between the main subdivision
and socialized housing developers
Recently-Issued Rules and Guidelines

B.R. No. 932 S. of 2015


B.R. No. 929 S. 28,
(January of 2015
2015)
(December 1, 2015)
SUSPENDING THE REQUIREMENT OF PRIOR
PURCHASE
APPROVALOF FOR
ASSET-BACKED SECURITIES
ADVERTISEMENTS TO BE
ISSUED BY THE NHMFC ASINMODE
PUBLISHED OF COMPLIANCE
PERIODICALS
WITH SECTION 18 OF REPUBLIC ACT NO. 7279

NHMFC will securitize and issue asset-


backed securities from existing buyers’ loans
with accredited socialized housing developers

` Purchase of the asset-backed securities by


developers of main subdivision project shall
be allowed as developers’ compliance with
Section 18 of UDHA
Recently-Issued Rules and Guidelines

B.R. No.No.
B.R. 933932
S. of
S. 2015
of 2015
(January 28, 28,
(January 2015)
2015)
DEVELOPERS’
SUSPENDING THE
PARTICIPATION
REQUIREMENT
IN LAND
OF PRIOR
DEVELOPMENT
APPROVAL
ANDFOR
HOUSING
ADVERTISEMENTS
CONSTRUCTION
TO BEIN
CMP PROJECTS
PUBLISHED
AS MODEINOF
PERIODICALS
COMPLIANCE WITH
SECTION 18 OF REPUBLIC ACT NO. 7279
Temporary suspension for a period of six
months of the requirement of prior approval
of project advertisements to be published
in newspapers, tabloids and magazines

` Suspension of prior approval does not exempt


any owner, developer, dealer, broker or
salesperson who may have caused the
dissemination of prohibited advertisements
from imposition of fines and penalties
Recently-Issued Rules and Guidelines

B.R. No. 933 S. of 2015


M.C.(January 28, 2015)
No. 1, Series of 2016
(February 1, 2015) PARTICIPATION IN LAND
DEVELOPERS’
DEVELOPMENT AND
DISPENSING HOUSING
WITH CONSTRUCTION
THE SUBMISSION OF IN
CMPUNDERTAKING
PROJECTS AS INMODE OF COMPLIANCE
POSTING CASH BONDWITH
SECTION 18 OF REPUBLIC ACT NO. 7279

Developers may participate in land


development and housing construction in
community mortgage program projects

` The cost of such participation shall be the


allowed as the developers’ compliance
with Section 18 of the UDHA
Rules and Guidelines
Recently-Issued Rules and Guidelines
Under Study and Consideration

M.C. No. 1, Series of 2016


(February 1, 2015)
DISPENSING WITH THE SUBMISSION OF
UNDERTAKING IN POSTING CASH BOND

Dealers, brokers and salespersons


registering or renewing their registration
may post cash bond in lieu of surety bond

` Submission of undertaking under oath as


required under M.C. No. 02-A, S. of 2015
is dispensed with to further expedite
registration and renewal process
Rules and Guidelines
Under Study and Consideration

NON-FORFEITURE OF PAYMENTS
(Section 23, PD 957)

Upon PERFORMANCE
notice, buyer may BOND
desist payment upon
failure of the owner/developer
(Section 6, PD 957) to develop the
project according to the approved plans and
within the period fixed by HLURB

In such a case, payments made by the


buyer shall not be forefeited in favor of
the owner or developer

Buyer may opt to be reimbursed the total


amount paid including amortization interests
but excluding delinquency interests, with
interest thereon at the legal rate
Rules and Guidelines
Under Study and Consideration

NON-FORFEITURE
REMOVAL OFOF PAYMENTS
THE
TEMPORARY LICENSE 957)
(Section 23, PD TO SELL
(Section 5, PD 957)
PERFORMANCE BOND
(Section 6, PD 957)

Current required bond is only 20% of


remaining cost of completion

Insufficient to complete the project in case


of non-development or abandonment
Rules and Guidelines
Under Study and Consideration

COMPLIANCE WITH BSP CIRCULAR


REMOVAL OF THE NO. 755 (2012)
Developers
TEMPORARYas Credit-Granting
LICENSE TO SELLEntities
(Section 5, PD 957)

Completion and delivery is delayed due to non-


development pending issuance of building permit

non-compliance by the developers with


the required escrow deposit

Non-submission of required sales reports

Building permit may be


denied by the local government
Rules and Guidelines
TIME OF COMPLETION
Under Study and Consideration

P.D. No. 957


COMPLIANCE WITH
Section 20.BSP
TimeCIRCULAR NO. 755 (2012)
of Completion
Developers as Credit-Granting Entities

Every owner
Real estateor developer
developers shall
who, construct
in the course of and
provide thebusiness,
their facilities, infrastructures
extend credit through and other forms
installment
of development,
or deferredincluding water
payment sale supply
shall and lighting
be deemed
facilities,aswhich
“Credit-Granting Entities”
are offered (CGEs)
and indicated in the
approved TIME OF COMPLETION
subdivision or condominium plans,
Registration of CGEs’ lending or financing
brochures, prospectus, printed matters, letters or
activity with the BSP to ensure compliance
in any form with
of advertisement, within
the Truth in Lending Act one (1) year
from the date of the issuance of license to sell for
the subdivision or condominium project or such other
Requirement and format of disclosure, including
period of time as of
manner may be fixed
computing of by the [Authority].
interest
TIME OF COMPLETION

Current Issues
P.D. No.and
957Concerns
MainSection
on Time
20. Time
Features of the
of Completion
of Completion
Revised Rules
BOARD RESOLUTION NO. 926
SERIES OF 2015
Every owner Nooruniformity
developer in fixing
shall the
construct and
REVISED
provide project’sRULES
IMPLEMENTING
the facilities, period of completion
AND REGULATIONS
infrastructures and other TO GOVERN
forms
THE TIME OF COMPLETION OF SUBDIVISION AND CONDOMINIUM
of development, including water supply and lighting
PROJECTS UNDER PRESIDENTIAL DECREE NO. 957, OTHERWISE
KNOWNfacilities,
AS “THE which
Extensions are of
SUBDIVISIONoffered
time
AND and indicated
granted as a in BUYERS’
CONDOMINIUM the
approved
PROTECTIVE subdivision
matter
DECREE” ofAND
course
ALLorOTHER
condominium
because of theplans,
PROJECTS REQUIRED
brochures, prospectus,
BY LAW TO practice
BE printed
of fixing
REGISTERED thematters,
WITH time
THE of letters
HOUSING ANDor
in any formLANDof advertisement,
completion within
on an annual
USE REGULATORY one (1) year
basis
BOARD
from the date of the issuance of license to sell for
Approved
the subdivision on Octoberproject
or condominium 1, 2015or such other
Developers invoke the grant of ETD
Published
period of against on
time as buyers January
may beto fixed 30, 2016
by the [Authority].
be exempt from
Effective on February 14, 2016
liabilities under Sec. 23 of P.D. No. 957
2015 Rules
2015and
Rules
Guidelines
and GuidelinesGeneral Rules
on Time TIME
on OF
ofTime ofCOMPLETION
Completion
Completion and Guidelines

Scope of Application
Main Features ofCIRCULAR
MEMORANDUM the Revised NO.Rules
02
SERIES OF 2016
Requirement to secure Certificate
Unbundling of the periods of completion
GUIDELINES ONof
forCompletion
BOARD for Land
land RESOLUTION
development Development
and
NO. completion
926, SERIES OF 2015 OR
(COCLD)
THE REVISED IMPLEMENTINGand of
and delivery optional
housing
RULES issuance
component
AND of
REGULATIONS TO
GOVERN THECertificate
TIME OF of CompletionOF
COMPLETION forSUBDIVISION
Housing AND
CONDOMINIUM PROJECTS Component
Period ofUNDER (COCHC)
completion for land DECREE NO.
PRESIDENTIAL
957, OTHERWISE KNOWN based
development AS “THE on SUBDIVISION
submitted AND
CONDOMINIUMAdditional
BUYERS’ period
program to complete
PROTECTIVE
of development the AND ALL
DECREE”
project
OTHER PROJECTS may only
REQUIRED BYbe granted
LAW TO BEinREGISTERED
meritorious
WITH THE HOUSING
Date of AND or exceptional
LAND
completion USE casesof BOARD
andREGULATORY
delivery
housingon
Effective unit purchased
February 15,based
2016 on
contract to sell or purchase agreement
2015 Rules and Guidelines General Rules
on Time of Completion and Guidelines

DutyScope of Application
To Complete
DefinitionThe Project
Within The Fixed Period of Completion
SUBDIVISION PROJECTS
Time of Completion
All subdivisions, including residential,
commercial, farmlot,
The period of and industrial
time fixed subdivisions
by the HLURB within
which the owner or developer shall develop and
CONDOMINIUM PROJECTS
complete the project, including the construction
and provision of facilities,
All condominiums, improvements
including and other
residential
forms of and
development,
commercial including water supply and
condominiums
electrical facility.
SIMILAR PROJECTS
Any other similar projects, including
cemeteries, memorial parks, and columbaria
2015 Rules and Guidelines General Rules
on Time of Completion and Guidelines

Duty To Complete The Project


Within The Fixed Period of Completion
Restrictive
Period
Grant
of Completion
of Additional Time
Based
To Develop
on Work
TheProgram
Project
Within one year from the date of the issuance
ofNothe
The license for
or the
work program
extension project
or program
additional or such
periodofofother
time period
may beof
development
time as
submitted
granted to may
for be fixed
approval
develop byby
and HLURB,
the owner
complete every owner
or project
the developer or
upon
unless
developer
application
such failureshall
for
orthe construct of and
project’s
inability provide
Certificate
the owner the
orof facilities,
Registration
developer to
andimprovements,
License
complete the infrastructures
to project
Sell (CR/LS)
is due shall and otherbe
primarily
to justifiable forms ofas
the basis
grounds
development,
forprovided
fixing the including
period
under water
theofnew supply
completion
rules and
theelectrical
andofguidelines.
project.
facilities, which are offered and indicated in the
approved project plans, brochures, prospectus,
printed matters, letters or any form of advertisement
2015 Rules and Guidelines General
Periods
Rules
of
on Time of Completion and
Completion
Guidelines

Unbundling of Periods of Completion


Monitoring
Restrictive Grant of Additional Time
To Develop The Project
Upon
Thereissuance
shall beofathe development
separate period ofpermit or CR/LS
completion
offor
No the project,
land
extension orthe
developmentHLURB, in the of
andperiod
additional house exercise of its
construction
time may be
visitorial
and
granted power,
delivery
to develop on its
in case
and of own initiative
residential
complete or upon
subdivision
the project unless
verified
such complaint,
projects
failure withmay
or inability ofmonitor
house and
the lot
owner the development
package
or developer to
completeand the
completion
project isofdue
a project and impose
to justifiable grounds as
appropriate
provided sanctions,
under the newfines
rulesand
andpenalties in
guidelines.
case of violation or non-compliance therewith
2015 Rules and Guidelines Periods of
on Time of Completion Completion

Period of Completion for Land Development


Unbundling of Periods of Completion
primarily based on the work program or
program of development submitted for approval
There
period shall be a separate
of completion period
to be fixed shallofconsider
completion
level of
for land development
development at the time ofand house construction
issuance of license to sell
and delivery in case of residential subdivision
projects with house and lot package
2015 Rules and Guidelines Periods of
on Time of Completion Completion

PeriodAllowances
of Completion
and for
Contingencies
Land Development
In the Work Program
primarily based on the work program or
program
The of development
work program submitted
or program for approval
of development shall
consider
period and provideto
of completion for
bea fixed
reasonable allowance
shall consider forof
level
possible delayat
development inthe
thetime
project development
of issuance due toto
of license work
sell
interruptions or temporary suspensions brought about by:

Period of Completion and Delivery


shortage of construction
inclement weather
Of Housing Components
supplies or materials
prolonged or repeated
Explicitly provided in the contract
other similarto sell
incidents
power failures
or any purchase agreement

In the absence of such provision, the


period of completion and delivery shall not
exceed one (1)-year from date of purchase
2015 Rules and Guidelines Periods of
on Time of Completion Completion

Allowances and Contingencies


Subdivision
In the
Amenities
Work Program
and Facilities

The work program or program of development shall


All subdivision amenities and facilities such as
consider and provide for a reasonable allowance for
clubhouse, playgrounds, sport facilities and other
possible delay in the project development due to work
infrastructures as may be included in the approved
interruptions or temporary suspensions brought about by:
project plans, brochures, prospects printed matters,
letters or any forms of advertisement shall be
developed and shortage
completed within of construction
the SUBMITTED and
inclement weather
supplies or materials
APPROVED period for the project’s land development.
prolonged or repeated
other similar incidents
power failures
2015 Rules and Guidelines Periods of
on Time of Completion Completion

Subdivision
Condominium
Amenities
Amenities
and Facilities

All subdivision amenities and facilities such as


All amenities and facilities included in the approved
clubhouse, playgrounds, sport facilities and other
plan or included or represented in brochures,
infrastructures as may be included in the approved
prospectus, printed matters, letters or any form of
project plans, brochures, prospects printed matters,
advertisement of the project shall all be completed in
letters or any forms of advertisement shall be
accordance with the work program or program of
developed and completed within the SUBMITTED and
development of the project
APPROVED period for the project’s land development.
2015 Rules and Guidelines Periods of
on Time of Completion Completion

Statement of the Date of Completion


Condominium Amenities
ON THE LICENSE TO SELL
TheAlldate of completion
amenities of theincluded
and facilities project, which shall
in the approved
include theor
plan month, dayor
included and year, shallin
represented bebrochures,
indicated
on the license to
prospectus, sell ofmatters,
printed the project.
letters or any form of
advertisement of the project shall all be completed in
accordance with the work program or program of
development of the project
2015 Rules and Guidelines Additional
Periods Time
of
on Time of Completion OfCompletion
Completion

Restrictive
Statement Grounds
of the Date for the Grant
of Completion
of Additional Time of Completion

ON THE LICENSE TO SELL


MANDATORY
The STATEMENT
date of completion of the project, which shall
ON THE
include theADVERTISEMENT
month, day and year, shall be indicated
on the
Such license
date to sell of the
of completion project.
of the project and date
of completion
HOUSE & and
LOT delivery
PACKAGE from date of purchase
of any housing
CONDITION unit,
IN THE if applicable,
LICENSE TO SELLis a mandatory
statement in any advertisement of the project
“The date of completion and delivery of the
housing component shall be explicitly provided in
the contract to sell or any purchase agreement”
“In the absence thereof, the period of completion
and delivery of the housing unit shall in no case
exceed one (1) year from the date of purchase”
2015 Rules and Guidelines Additional Time
on Time of Completion Of Completion

Restrictive Grounds for the Grant


of Additional Time of Completion

FORTUITOUS EVENTS
SUB-SOIL CONDITIONS
SUB-SOIL CONDITIONS
Existence of sub-soil condition[s];

FORTUITOUS
Discoverable only afterEVENTS
actual
excavation works in the project; and

Would necessarily require additional


LAWFUL ORDERS
excavation time
2015 Rules and Guidelines Additional Time
on Time of Completion Of Completion

Restrictive Grounds for the Grant


of Additional Time of Completion

LAWFUL ORDERS
FORTUITOUS EVENTS
1 Independent of the will of the owner or developer

2 Unforeseeable or unavoidable
Causes:
(i) Damage to the on-going project
that requires reconstruction; or
3 (ii) Delays which are directly
attributable to the event; and
Renders its completion within the original
approved period impossible in a normal manner

4 The owner or developer is free from any participation


or aggravation of the damage sustained by the project
2015 Rules and Guidelines Additional Time
on Time of Completion Of Completion

Restrictive
MEGAWORLD Grounds
GLOBUS for
ASIA, the Grant
INC., v. TANSECO
of Additional
G.R. Time
NO. 181206, of Completion
OCTOBER 9, 2009
LAWFUL ORDERS

Issuance of a lawful order of the court, government agency


or local government unit resulting to the temporary enjoinment
or stoppage of the construction or development of the project
AND PROVIDED
EXCEPT WHEN THE
FURTHER
ISSUANCE
THAT:
OF SUCH ORDER IS:

attributable
within SIXTYto any
(60) fault,
DAYS mistake,
from or or
receipt negligence
knowledge
1
3 on the part
thereof, of the owner
the owner or developer;
or developer or in writing,
shall have,
notified the RFO of such issuance
2 due to any dispute between the owner and developer
in the development and completion of the project
2015 Rules and Guidelines Additional Time
on Time of Completion Of Completion

New Procedure
MEGAWORLD for Application
GLOBUS ASIA, INC., v. TANSECO
and
G.R. Grant
NO. of Additional
181206, OCTOBERTime9, 2009
REQUIREMENTS
CRISISBond or Security
APPLICATION
THE ASIAN
Sworn
1The Courtapplication
cannot by the for
All applications
generalize owner
the or developer,
additional
1997 time financial
Asian
stating the
Additional grounds
ofperiod ofor
completion reasons
time shall
shall only with
be filed be granted
the upon
crisis to be unforeseeable and beyond the control of
posting
Proof ofofnotice
2a business a new
RFO tobond
whereall the
corporation. oror
lot security
project in accordance
or owners with
is registered
unit buyers
the existing rules and guidelines of the HLURB
3A real
Supporting pictures or
estate enterprise documents,
engaged in theif pre-selling
any
of condominium units is concededly a master in
In cases falling under Sub-Soil Conditions, a sworn
4 statementon
projections bycommodities and currency
a licensed engineer attesting movements,
to the
as existence
well as business risks. condition
of the sub-soil
Revised work program with computation of
5The fluctuating movement of the Philippine peso
the foreign
in the remaining cost of completion
exchange market is anduly signed
everyday
or sealed by
occurrence, a licensed
hence, not anengineer
instanceorof
architect
caso fortuito.
Megaworld’s excuse for its delay does not thus lie.
2015 Rules and Guidelines Additional Time
on Time of Completion Of Completion

New Procedure for Application


and Grant of Additional Time

PERIODS
REQUIREMENTS
TO APPLY

1 1Sworn
Underapplication
“Sub-Soil Conditions”,
by the owner within
or developer,
stating
sixty the
(60)grounds
days from
or reasons
discovery thereof
2 Under
Proof “Fortuitous
of notice to all Event”, within
lot or unit sixty
buyers or(60)
owners
days prior to the expiration of the approved
3 Supporting
original time pictures or documents,
of completion, provided if any
however
2 that if such occurrence shall fall within the last
Insixty
cases falling
(60) days under
of theSub-Soil
approvedConditions,
period of a sworn
4 statement by a licensed engineer attesting to the
completion, the application shall be filed within
existence
sixty (60)ofdays
the sub-soil
from thecondition
occurrence thereof
Revised work program
Under “Lawful Order”,with computation
within of
sixty (60) days from
5
3the remaining
receipt cost of completion
or knowledge of the orderduly
or signed
issuance
orlifting
sealed byenjoinment
the a licensed engineer
or stoppageor architect
of development
2015 Rules and Guidelines Additional Time
on Time of Completion Of Completion

New Procedure for Application


and Grant of Additional Time

PERIODS TO APPLY
Under TO
1 NOTICE “Sub-Soil
LOT OR Conditions”,
UNIT BUYERS within
sixty (60) days from discovery thereof
Any
Underowner or developer
“Fortuitous applying
Event”, within for additional
sixty (60)
time of completion shall notify all lot
days prior to the expiration of the approvedor unit buyers
or owners
original of of
time its completion,
intent to apply for additional
provided howevertime
2 to complete
that the development
if such occurrence of the
shall fall project.
within the last
sixty (60) days of the approved period of
completion, the application shall be filed within
sixty (60) days from the occurrence thereof
Under “Lawful Order”, within sixty (60) days from
3 receipt or knowledge of the order or issuance
lifting the enjoinment or stoppage of development
2015 Rules and Guidelines Additional Time
on Time of Completion Of Completion

New Procedure for Application


and Grant of Additional Time

EVALUATION AND GRANT


APPEAL
1 NOTICE TO LOTof
Upon receipt ORtheUNIT BUYERS the RFO shall:
application,
Any appeal from the decision of the application by the
RFOAny owner
shall or developer
be decided applying
by the for additional
Supervising Commissioner
verify the nature and extent of damage
time of completion shall notify all lot or unit buyersor
validate
or owners of the justification
its intent for
to apply forthe application
additional time
to complete thethe
ascertain development
additionalofperiod
the project.
of time
needed to complete the project and the
estimated remaining cost of completion
conduct an ocular inspection
of the project, If necessary

If the RFO finds justifiable reason to grant the


additional period of time, it shall proceed to grant
2 the application. Otherwise, it shall deny the same.
2015 Rules and Guidelines Additional Time
on Time of Completion Of Completion

New Procedure for Application


Fees
and Grant of Additional Time

B.R. NO. 912, S. OF 2013


2013 REVISED SCHEDULE OF FEES
APPEAL
Theappeal
Any fees provided
from thefor extension
decision or additional
of the time
application by to
the
develop
RFO shallapplicable
be decidedtoby
the different
the classifications
Supervising of
Commissioner
subdivision and condominium projects in the approved
Schedule of Fees of the HLURB, including Processing
Fee, Additional Fee, and Inspection Fee are adopted
2015 Rules and Guidelines Additional
Certificates
Time
on Time of Completion Of
of Completion

Issuance of Certificates
Fees
of Completion

B.R. NO. 912, S. OF 2013


2013 REVISED SCHEDULE OF FEES
The fees provided for extension or additional time to
develop applicable to the different classifications of
subdivision and condominium projects in the approved
Schedule of Fees of the HLURB, including Processing
Fee, Additional Fee, and Inspection Fee are adopted
2015 Rules and Guidelines Certificates
on Time of Completion of Completion

Issuance of Certificates
of Completion
CERTIFICATE
DUTY TO MAINTAIN
OFOF
CERTIFICATE COMPLETION
UNTIL
COMPLETION
FOR HOUSING
DONATION
FOR COMPONENT
OR TURNOVER
LAND DEVELOPMENT (COCHC)
(COCLD)
Upon
The completion
issuance,
Upon ofof
the
however,
completion thehousing
of component,
a COCLD
project’s shall not a
land
separate
relieve theCertificate
owner
Development, the of Completion
orowner
developer of theforobligation
or developer Housing
shall
Component
to maintain
apply (COCHC)
the roads,
for issuance may
of alsosidewalks,
alleys, be issued.
Certificate playgrounds,
of Completion
amenities, facilities, improvements,
for Land Development (COCLD) from infrastructures
the RFO
or other forms of developments represented or
If upon ocular
promised inspection
in brochures, the project is
advertisements found
and other
to have
sales been completed
propaganda in accordance
until proper donation orwithturnover
the approved time of completion, a COCLD
shall be issued in accordance with the existing
rules and guidelines of the HLURB.
2015 Rules and Guidelines Relief,
Certificates
Sanctions
on Time of Completion of
andCompletion
Penalties

Issuance of Certificates
Buyers’ Remedies in Case
of Completion
Of Non-Completion
CERTIFICATE OF COMPLETION
FOR HOUSING COMPONENT (COCHC)
Upon completion of the housing component, a
separate Certificate of Completion for Housing
Component (COCHC) may also be issued.
2015 Rules and Guidelines Relief, Sanctions
on Time of Completion and Penalties

Buyers’ Remedies in Case


Fines and Sanctions
Of Non-Completion

Buyers on - P 10,000 in accordance


P 1,000 Sec. 23 , P.D. 957
Installments
with HLURB’s Approved Schedule
of Fines and Penalties
Fully Paid Civil Code
Buyers [ Art. 1191 ]
Suspension of License to Sell
Other rights and remedies
provided for by other laws
CDO – Selling / Advertising /
Collecting Installments
2015 Rules and Guidelines Relief, Sanctions
on Time of Completion and Penalties

Fines and Sanctions


Repealing Clause

ExCom. Res. No. 01, S. of 2007 (Amending the


P 1,000 - P 10,000 in accordance
Delineation of Authority to Approve/Disapprove
with HLURB’s Approved Schedule
Applications for Extension of Time to Develop
of Fines and Penalties
Subdivision and Condominium Projects

Suspension
Applications of– License toField
Regional Sell
Office

CDO – Selling
Appeal – / Advertising
Supervising/
Collecting Installments
Commissioner
2015 Rules and Guidelines Relief, Sanctions
on Time of Completion and Penalties

Repealing Clause

ExCom. Res.Transitory Provision


No. 01, S. of 2007 (Amending the
Delineation of Authority to Approve/Disapprove
Applications
Within ninety (90)for Extension
days from the of Time to of
effectivity Develop
this Rules,
Subdivision
all on-going projectsand
withCondominium Projects
an original fixed or approved
period of completion or extension of time to develop that
is shorter than the period of
Applications completion
– Regional provided in the
Field
Office
originally submitted or revised work program or program
of development may apply for a final additional time to
Appealthe project
develop and complete – Supervising
based on their approved
or revised work program orCommissioner
program of development
2015 Rules and Guidelines Relief, Sanctions
on Time of Completion and Penalties

Transitory Provision

Within ninety (90) days from the effectivity of this Rules,


all on-going projects with an original fixed or approved
period of completion or extension of time to develop that
is shorter than the period of completion provided in the
originally submitted or revised work program or program
of development may apply for a final additional time to
develop and complete the project based on their approved
Thank you and visit us at
or revised work program or program of development

www.hlurb.gov.ph
09176273784
Thank you and visit us at
www.hlurb.gov.ph
09176273784