Sie sind auf Seite 1von 2

Water Technologies & Solutions

case study

grass root Butadiene Unit passivation with


Butaclean* 4606
background passivation
Butadiene extractive distillation units are prone to For passivation, the Butaclean 4606 should be used in
polymer fouling. To minimize the fouling and to attain combination with Petroflo* 21Y21 according to the
multiple years runlength, passivation should be done following procedure:
prior to the plant start up. In case of a grass root • After decreasing and pickling the system was
plant, in most cases the whole system is degreased, kept under nitrogen (max 40 ppm O and
2

pickled and passivation. accordingly filled with boiler water containing 1%


During the construction phase, different kinds of Butaclean 4606.
chemicals are used and dust enters the system. • The passivation solution should be circulated and
Besides that, the metal surface is exposed to air and heated with steam injection up to >80 °C (max 90
becomes rusty which acts as a catalyst for °C).
polymerization. Prior to the unit start up, all present • Once starting the water circulation, the pH should
“contaminants” should be removed, so called be measured with adding Petroflo 21Y21 to
degreasing followed by a (acid) pickling to remove the elevate the pH to > 9 (max 9.5).
rusty layer with finally a passivation step.
• Coupons to be installed in the buffer tank in order
to follow up the passivation layer build up.
new challenge • Every 2 hours the residual Butaclean 4606 and pH
should be measured and corrective actions
A new European butadiene plant was built in 2014 and
should be taken, maintaining the required amount
prior to start up, the customer wanted to passivate the
of passivator (> 5000 ppm) and minimum the pH
whole unit (sphere, feed and return lines, extractive
(>9).
distillation and purification). Generally passivation
takes place with a Sodium Nitrite solution resulting in • Add Butaclean 4606 and Petroflo 21Y21 based on
a significant amount of highly contaminated toxic the analysis.
waste and difficult to process in a waste water plant. • Monitor the water circulation temperature
Because of the big volumes involved and the continuously (>80 °C) and check the coupons
difficulties with handling the waste water, SUEZ passivation layer every 2 hours.
proposed to passivate the plant with the non-toxic • Once the passivation reaction started, a
technology. By applying this new technology, a low significant drop from the residual Butaclean 4606
nitrogen free and environmental friendly technology takes place as well as a pH reduction will be
chemical, the contaminated solvent processing in the observed.
waste water unit was a key priority without
jeopardizing the passivation performance.

Find a contact near you by visiting www.suezwatertechnologies.com and clicking on “Contact Us.”
*Trademark of SUEZ; may be registered in one or more countries.
©2017 SUEZ. All rights reserved.

CS1513EN.docx Apr-15
• After 20 -24 hours, the water should be drain to Copper Sulphate Plating
the waste water plant (or basin in case of very
high volumes).
• Dry and inert the system / column with N .
2

• Determine the effectiveness from the applied


passivation with CuSO plating test.
4

monitoring
Every 2 hours, pH, temperature, and residuals were
monitored to confirm the good efficiency of the
procedure.

pH & Temperature
from left to right

1) CuSO - fresh coupon not passivated


4

2) New Coupon
3) CuSO from a passivated coupon
4

conclusions
The customer is extremely satisfied with the current
plant performance indicating the quality of the
passivation layer is outstanding, and the partnership
between SUEZ & the maintenance / cleaning company
we worked with.

residuals & temperature


EHS
EHS was a key priority for the customer and during
the 8 weeks on-site activities a 100 % compliance
score was achieved.

The unit is actually running with optimal conditions,


without any indication of polymer not popcorn
formation for more than 8 months.

Page 2 CS1513EN.docx