Corridor 1 (Phase 1)
14 June 2017
Location Jl. Kelapa Nias, Jakarta Utara – Jl. Boulevard Raya, Jakarta Utara – Jl. Velodrome, Jakarta Timur
Construction of LRT Jakarta’s Infrastructure and Procurement of Light Rail Vehicles (LRVs) to
facilitate a better public transportation system during the Asian Games 2018 with 6 elevated LRT
Description
stations and 1 depot for LRVs’ stabling + maintenance. During the initial stage, 8 articulated LRVs
or 4 train sets (1 train set = 2 LRVs) will be operated, with 10 minutes headway.
Collaboration Scheme LRT Project Team – PT Jakarta Propertindo – Pemprov DKI (Based on DKI Governor Decree)
Role: Company/Institution:
1. Oversight for LRT Jakarta Implementation 1. Dinas Perhubungan UP. Perkeretaapian
2. Feasibility Study Phase 1 Consultant Perkotaan DKI Jakarta
3. Preliminary Design Consultant 2. PT Mott MacDonald Indonesia
4. Tender Assistance Consultant 3. PT Mott MacDonald Indonesia
5. Construction Management and Supervision 4. PT Mott MacDonald Indonesia
Consultant 5. PT Mott MacDonald Indonesia
Partners 6. Operation Management Consultant 6. PT Mott MacDonald Indonesia
7. P101 Advance Work Contractor 7. PT Wijaya Karya (Persero) Tbk.
8. P102 Main Work (Civil, M/E, Archi and Railway 8. PT Wijaya Karya (Persero) Tbk.
System) Contractor 9. Hyundai Rotem Company
9. P103 Rolling Stock Supplier 10.Korea Rail Network Authority (KRNA)
10.Feasibility Study Phase 2 Consultant 11.LKPP
11.Procurement Advisory Committee 12.(under reviewing stage)
12.Operator for LRT Jakarta 13.(under reviewing stage)
13.Independent Verification & Validation
Project Details
Corridor 1 (Phase 1)
LRT Jakarta Station
LRT Jakarta Station
Lift
Pier
7,345
22.59%
7.000 Media Partners 21.50% 16.00% 15.66%
1,324
1,3 M Audiences
Plan Actual Plan Actual Plan Actual
*Construction
Jakarta merencanakan pembangunan
plan of LRT infrastruktur LRT mencapai 115,7 Km
up to 115,7 km
Major construction
Construction 15 Jan '17
LRT Appointment 22 Jun '16 Rolling stock Purchase Order (PO)
Asian Games 2018
1 Feb '17
11 Sep '15 Today 18 Aug '18
13 Aug '18
Plan : 23.25% Soft Operation
PM Consultant Tender
14 Sep - 2 Dec
Actual : 23.67% 1 May '18
Process 2.6 months Deviation: +0.42% Delivery of first Rolling
Feasibility Stock and
3 Dec - 29 Feb
Study 2.9 months Testing & Commissioning
Preliminary 1 Nov '17
1 Mar - 31 Jul
Design 5 months Establishment of PT LRT
P101: Tender 5 Apr - 20 Jun Jakarta and Recruitment for
2.5 months Operational HR
P101:
Implementation 20 Jun - 11 Dec
5.8 months
P102: Tender 16 Aug - 20 Dec
4.2 months
P102:
Implementation 23% 20 Dec - 21 Aug
20.1 months
P103: Tender 15 Dec - 1 Feb
1.5 months
P103: Implementation
(Rolling Stock Fabrication) 16% 1 Feb - 30 Oct
21 months
Pre-Operational Plan and Establishment of Infrastructure
1 Jun - 31 Oct
and Facility Enterprise 5 months
Operational
1 Nov - 13 Aug
Plan 9.5 months
LRT Jakarta Progress Update
Overall LRT Jakarta Corridor 1 (Phase 1) Progress S-Curve
Progress Summary :
Plan Progress : 23.25%
Actual Progress : 23.67%
Deviation : +0.42%
Jan-17
Jan-18
Nov-17
May-17
May-18
Jun-17
Jun-18
Dec-16
Apr-17
Apr-18
Jul-17
Aug-17
Dec-17
Jul-18
Aug-18
Sep-17
Oct-17
Feb-17
Mar-17
Feb-18
Mar-18
Sep-18
As of 26 May 2017
LRT Jakarta Project Schedule
Contract P102’s S-Curve
WEIGHT YEAR / MONTH
MAIN Plan
TOTAL UP TO
COST 2016 2017 2018
DESCRIPTION WEIGHT THIS
CENTRE DEC JAN FEB MAR APR MAY JUN JUL AGS SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG
(%) Actual PERIOD
NO. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
(%)
Plan 0.668 0.058 0.116 0.116 0.145 0.116 0.116 0.116 0.145 0.116 0.145 0.116 0.116 0.145 0.116 0.116 0.145 0.116 0.116 0.145 0.116 0.087
Preliminaries and
1 2.528
General Requirements 0.219 0.793 0.491 0.073 0.033 0.033
Actual 1.642
Plan 0.794 0.069 0.138 0.138 0.173 0.138 0.138 0.138 0.173
Design of Permanent
2 1.105
Works 0.097 0.156 0.039 0.048 0.039 0.039
Actual 0.418
Plan 4.151 0.563 0.924 1.257 1.407 1.688 2.462 2.251 2.814 1.970 1.688 1.759 1.126 0.844 0.704
3 Viaduct 21.458
0.011 0.599 2.524 1.210 1.396 0.649
Actual 6.388
Plan 0.795 0.108 0.202 0.216 0.270 0.324 0.472 0.431 0.539 0.378 0.324 0.337 0.216 0.162 0.135
4 Main Line Track Work 4.112
0.319 0.479
Actual 0.798
Plan 2.381 0.323 0.474 0.777 0.807 0.968 1.412 1.291 1.614 1.130 0.968 1.009 0.646 0.484 0.403
5 Main Line Station 12.307
0.228 0.468
Actual 0.696
Plan 0.791 0.107 0.201 0.215 0.268 0.322 0.469 0.429 0.536 0.375 0.322 0.335 0.215 0.161 0.134
6 Depot Track Work 4.089
0.317 0.476
Actual 0.793
Plan 0.222 0.030 0.056 0.060 0.075 0.090 0.132 0.120 0.150 0.105 0.090 0.094 0.060 0.045 0.038
7 Depot Station 1.146
Actual 0.000
Plan 6.002 0.814 0.871 2.283 2.034 2.441 3.560 3.255 4.069 2.848 2.441 2.543 1.628 1.221 1.017
8 Depot Area 31.026
0.967 1.974 4.598 4.313
Actual 11.853
Plan 0.566 0.077 0.144 0.153 0.192 0.230 0.336 0.307 0.384 0.268 0.230 0.240 0.153 0.115 0.096
9 Substations 2.924
Actual
Plan
0.000
Plan
0.000
0.000
Actual (%)
0.014 0.017 0.014
15.44
0.014 0.017
22.59
0.014 0.014 0.017 0.014 0.014 0.017 0.014 0.010
Testing and
11 0.190
Commissioning
Actual
Plan
0.000
0.000
Dev. (%) 1.44 1.09 0.351 0.281 0.281 0.351
12 Product Support 1.265
Actual 0.000
TOTAL 100.000 21.496 0.573 1.146 3.167 4.174 6.237 6.199 7.210 10.276 9.107 11.384 8.096 7.085 7.594 5.064 4.054 4.155 1.303 1.303 0.986 0.508 0.381
Cummulative Monthly Planned Progress 0.000 0.573 1.719 4.886 9.060 15.297 21.496 28.706 38.982 48.089 59.472 67.568 74.654 82.247 87.311 91.365 95.520 96.823 98.125 99.112 99.619 100.000
Monthly Actual Progress 22.587 0.963 2.501 4.021 3.305 6.295 5.502
Cummulative Monthly Actual Progress 0.000 0.963 3.464 7.485 10.790 17.085 22.587
Deviation 1.091 0.390 1.745 2.599 1.730 1.788 1.091
Plan 8.000 1.882 2.353 1.376 2.389 1.481 1.852 1.481 1.852 1.481 1.481 0.370
Initial and Final
2 18.000
Design Review 1.882 2.353 1.464 2.091
Actual 7.791
Procurement of
Plan 6.000 1.412 1.765 1.052 1.771 2.074 2.593 2.074 2.593 2.074 2.074 0.519
Major Equipment
3 20.000
/Materials and 1.412 1.765 0.876 1.841
Actual 5.893
Delivery to Factory
Plan 0.000 0.571 0.714 0.571 0.714 0.571 0.571 0.714 0.571 0.571 0.429
Manufacturing of 1st
4 6.000
LRV (incl. FAT)
Actual 0.000
Plan 0.000 0.643 1.500 2.357 4.249 3.399 3.399 4.034 2.328 1.470 0.621
Manufacturing of All
5 24.000
LRV (incl. FAT)
Actual 0.000
8
Delivery of All LRV on
Site
5.000
Plan 0.000
Plan (%) 11.73 16.00 20.13 2.000 3.000
Actual 0.000
Testing,
Commissioning and
Plan 0.000 Actual (%) 11.73 15.66 3.700 5.300 1.000
9 10.000
Acceptance of 1st to
Actual 0.000
4th LRV on Site
Testing,
Plan 0.000
Dev. (%) - (0.34) 3.000 5.000 2.000
Commissioning and
10 10.000
Acceptance of All LRV
Actual 0.000
on Site
TOTAL 100.000 16.000 0.000 3.910 4.887 2.932 4.271 4.127 5.159 4.127 5.802 5.627 6.484 5.852 3.970 3.970 4.463 5.328 6.770 8.321 7.000 5.000 2.000
Cummulative Monthly Planned Progress 0.000 0.000 3.910 8.796 11.729 16.000 20.127 25.286 29.413 35.214 40.841 47.325 53.177 57.148 61.118 65.581 70.909 77.679 86.000 93.000 98.000 100.000
Monthly Actual Progress 15.661 0.000 3.910 4.887 2.932 3.932
Cummulative Monthly Actual Progress 0.000 0.000 3.910 8.796 11.729 15.661
Deviation (0.339) 0.000 0.000 0.000 0.000 (0.339)
Note: 0.34% progress behind schedule, caused by several interface issues with P102 Progress as of May 26th 2017
Contractor that required a confirmation in Jakarta on 7 – 9 June 2017
LRT Jakarta Progress Photos
Construction works for Viaduct’s Foundation works for future Elevated LRT
16
foundation at Section 5A Station in front of Mal Kelapa Gading
LRT Jakarta Progress Photos
Segmental Box Girder Erection Ceremony at P68 Section 3 Segmental Box Girder Erection at P68 Section 3
Loading Test Segmental Box Girder at P68 Section 3 Launching Gantry at P68 Section 3
LRT Jakarta Progress Photos
Reinforcement Concrete works for Pier Head at P140 Reinforcement Concrete works for Pilecap at P153
Reinforcement Concrete works for Pilecap at RPSS Depot Reinforcement Concrete works for Ramp P12 Depot Area
THANK YOU