Administrative Cost

I. DENR Permits
1.) Environmental Compliance Certificate (ECC) Application
a.) Programmatic Environmental Impact Assessment 15,000
b.) Environmental Impact Assessment 10,000
c.) Programmatic Environmental Performance Report and
Management Plan (PEPRMP) 10,000
d.) Initial Environmental Examination (IEE) Checklist 5,000
2.) Certificate of Non-Coverage (CNC)
(Exempted for Solar Energy)
Total 40,000
II. National Commission on Indigenous Peoples (NCIP) Permits
1.) Certificate of Non-Overlap/Certificate of Pre-condition
(Exempted since project site would not be undertaken within IP grounds)

III. DOE Administrative fees for RE Contracts


1.) Application fee (Solar) 11,600
2.) Processing fee (Solar) 6.50/has
Total 11,600
Other Fees
1.) Consultancy Fees 30,000
2.) Transportation Expenses 5,000
3.) Contingency Fees 10,000
Total 45,000
Grand Total 96,600

Renewable Energy Service (Operating) Contract (RE Contract)


I. Pre-Development Milestone Activity(ies) Milestone Period Milestone Cost
Stage 1. Initial modeling and annual energy 12 Months P500,000.00
- refers to the stage yield estimates (minimum financial
where the 2. Land/rights acquisition (if there is commitment)
preliminary land acquisition involved)
assessment and 3. Mandatory Activities
feasibility study up to 3.1 Public consultations
financial closing is 3.2 LGU Endorsements
done
- period of validity is
for three (3) years
II. Development Stage Milestone Activity Milestone Period Milestone Cost
- refers to the stage Electro-Mechanical Equipment (At Year 4 P95,000.000/MW
where the 80% Completion) (minimum financial
construction and commitment)
installation of
facilities up to
operation phase is
conducted