01. General
This work shall consists of all the concrete works relating to construction of culverts,
road side and lead away surface drains, catch pits, earth retaining structures, bridges and
other structures according to the road finished level.
2. Reference
.
3. Resources
3.1 Material
Step 2 – Excavation
Step 7– Concreting
Step 9 – Curing
Step 10 – Backfilling
3 of 6
MS/006
The design finishing levels and grade of the structural member shall be marked
using level pegs for base and level line on side shutter boards for walls
respectively. The line and grade of form work shall be checked immediately
prior to placing of concrete.
Step 7 Concreting
The constituent material shall be batched by volume for grade C 20 concrete at
the site of construction. A 400mm x 350mm x 250mm (0.035 m 3) measuring
box shall be used for batching of aggregate and sand. For mixing of concrete a
mixer with 125/250 Ltr capacity shall be used. Measurable water buckets shall
be used to measure the quantity of water to ensure the correct water/cement
ratio.
The concreting area shall be properly cleaned to remove all deleterious
materials. The concrete shall be uniformly and thoroughly mixed to the
required consistence prior to placing. Concrete would be pored in to the form
work in such a manner so as to avoid segregation and the displacement of
reinforcing bars and shall be spread in horizontal layers where practicable.
25mm or 40mm poker vibrator shall be applied for proper compaction.
Finally surface of the concrete shall be finished and smoothed to the required
level. Test cubes shall be cast in six numbers for every10 m 3 of concrete per
day. Two cubes shall be tested on 7 days and other four shall be tested on 28
days. Slump tests shall be carried out in randomly selected batches.
Step 9 Curing
Curing would be started just after the removal of formwork by covering all
exposed surfaces using wet gunny bags and preceded for minimum of 7 days.
Step 10 Backfilling
The method of structural backfilling is described in Method Statement for
“Excavation and Backfilling”
5 of 6
MS/006
6. Supervision
Position Responsibilities
Site Engineer Perform the concreting on the basis of method statement,
specifications and drawings.
Technical Officer All setting out works in accordance with Method Statement
and drawings
Supervisor Assist to Site Engineer/ Technical officer
Laboratory Assistant Casting of concrete cubes and slump tests.
7. Inspection
Site Engineer shall implement the Request for Inspection (RFI) and shall be kept
at site for the Engineer’s consent. When any of the Non-Confirmation is identified
by QAM or by the Engineer for the particular construction event, Site Engineer
shall perform to issue NCR through the QAM and he shall prepare for the
CAR/PAR
8. Traffic Control
All the traffic control arrangement at site will be in accordance with the site safety
manual.
9. Safety Provision