Position Status of design (D=Design office F=Field Next action
CE/C Dy CE/C S.No. Location/Name of State TDC
work of GAD office) not possible
3 ROB at KM 10/23-25 near Amausi Rly. Stn. 1. Foundation and wall for pier RP1 and RP4 approved.
LKO-IV 3X33.004 DP UP APP F
(PSC)+1X46.029 (S)+1X26.070 (PSC)
(Skew 9°)
2. Foundation for RP2 is under proof checking and
feasibility signatures and yet to be submitted
Super str. - All referred.
LC 482- MB SRE
Soil report received & 0bservation sent. Reminder
4 CS UP APP ### sent on
PWD 26.09.2017
Loads- .Reply
letter sent for awaited.
want of load on F
(1X37.20 S) 31.10.2016.Reminder sent on 26.09.2017. Reply
( 43 degree skew )¯ awaited.
Super str.- one referred
GA plan approved on 16.02.2016. ROB (1-C & 418) Data awaited
Soil report received but given bearing capacity
does not match with the recommendation from
the field office.This has telephonically & by letter
dt.05.03.2017 & 02.11.2017.conveyed to field.
Reply awaited.
LC-1C
( 21.60 P+24.0 S + 21.60 P)
5(A) ( skew 8°) Sub str.- (Chourasia)
PWD loads- Letter send on 03.05/23.06 &
17.08.2016/05.03.2017 & 02.11.2017. reply F
awaited.
MB 418
5 (B) F
NW
PWDSoil report
loads- received.
Letter send on(Bearing capacity
03.05/23.06 &
received but it does not &
17.08.2016/05.03.2017 match with theReply
03.11.2017.
(1x 46.029 S ) recommendation from field office. This has
awaited.
telephonically & by letter dt. 05.03.2017 &
03.11.2017.conveyed to field.Reply awaited.
Super str. - To be designed
Sub str. (Smt.Rajshree) P1, P2 & CP1 Consultant
approved.P3 & CP2 pending due to design of design awaited
(42.70 consult. Design) Foundation will be
redesigned as pile foundation . Approval for
design of pile foundation obtained.Test pile
approved on 23.06.2017.Design of substr. awaited.
Loco Shed MB
6 (3X21.60 DP UP APP ### F
P+1X47.5 S) Pier cap;- P1,P2 & CP1 approved. P3 & CP2
pending as above.
Completed on 03.11.2017
Talara
JAT 9
1x 14.4 (RCC) DP HP APP
GAD Awaited. Approval of
GAD awaited
LC 26 (Khurja- Meerut) Super str. - (1X25.24) & (1X 37.240) - Already
1 X 25.240 + 1X 37.24 + 1X15.876 approved
10 steel compo. High stress CS UP U/APP 1X15.876 (Steel)- based on 18.00m high strength, F
(skew 0 degree) to be designed in house.
CSB
LC 79- Khairanthi
12
2X17.25 (P)+31.28 (S) CS HR APP ### Completed
Data awaited
GAD approved on 16.09.2016.
Substr.- (Sh.Khalique) Letter for net SBC sent on
LC11-MTC-KRJ 18.01.2017 & reminder on 26.09.2017. Reply
(1X25.00 P + awaited.
2x 48.920 S+
NDWCS 17
1X 25.00 P) CS UP APP ### PWD loads - Letter sent for want of load F
( 57.5 degree skew ) dt.18/01/2017 & reminder on 26.09.2017. Reply
awaited.
LC 48- Ichhapuri
26 19.08 (S)+37.28 (S) CS HR APP ### Completed
LC 23-A- Gurgaon
27 1X 55.0(fish belly) CS HR APP ### PWD loads - Letter issued to field Dy. on dt. F
18.01.2017. Reply awaited.