Sie sind auf Seite 1von 12

product

Information on multi-boiler installations

Optimising multi-boiler plant


Weishaupt multi-boiler control system
Many multi-boiler installations are able to operate more
efficiently, particularly at partial load, if the boiler output
can be optimised to suit the heat demand. This is where
the Weishaupt multi-boiler control system can provide an
advanced and practical solution.

The principle
Weishaupt facilitates the modern, hydraulically optimised control
of multi-boiler installations by measuring and regulating boiler
flow rates. Variable-speed boiler pumps and modulating burners
combine with the innovative control concept to form the ideal
solution for multi-boiler plant.

The technology
Flow rate is measured in the consumer pipeline and at every
heat generator. Variable-speed pumps at every boiler provide a
balanced water flow rate and correct any deviations before they
have an effect on temperature. The ground-breaking properties
of this patented system enable an outstanding degree of control,
and the efficient and reliable operation of any size of plant.

The result
Measurable benefits compared to typical installations even with
condensing boilers and combined heat and power plant, both in
terms of control precision and energy consumption.

Products and efficiency technologies, such as


the Weishaupt multi-boiler control system, are
developed and tested at the Weishaupt Research
and Development Centre.

2
Responsive control of multi-boiler plant:
environmentally friendly and efficient

Bolier flow rates controlled by variable speed pumps Control / visualisation

Variable speed pumps control boiler Furthermore, balanced volume flow Gas demand peaks are levelled
flow rate rates prevent overheating of the boiler The demand peaks in the gas supply
When a reduction in load leads to a or flow-rate-linked instabilities (e.g. all that often occur with temperature-led
reduction of the circulation flow in the boilers on or all boilers off). controls are effectively reduced or
consumer circuit, the boiler pumps vary often even avoided.
their speed to adapt the rate of flow to All of the installed boiler capacity is
the heat exchanger. This reduces the available to the consumer Alternative heat generators can be
number of burner starts to a minimum. With the Weishaupt system, the water integrated
circuit and the control strategy are As well as boiler/burner sequencing
Therefore the Weishaupt system offers tailored to one another. with low and high-temperature hot-
the same benefits to heat generation as water plant, the Weishaupt system is
have for so long been available to heat The intelligent volume-flow-rate control also ideally suited to sequencing with
distribution: speed-controlled circulation sets the water flow rate so that a boiler alternative heat generators (e.g. bio-
pumps whose power consumption is can really transport its nominal capacity mass or CHP plant).
considerably reduced by varying volume to the consumer circuit. This supports
flow rate. the optimal utilisation of an ecologically The well-thought-out volume flow rate
advantageous lead boiler, e.g. biomass management system can ensure the
Condensing boilers with a low loss or combined heat and power; the next greatest possible utilisation of eco-
header operate without any loss of boiler in sequence is only started when logically advantageous heat generators
efficiency the lead boiler has reached full capacity. in both individual and sequenced
Across the whole of the control range, operation. This considerably increases
flow-rate control prevents a rise in the Disruptions during boiler switching the ecological and economical value
return temperature to the boiler circuit procedures are compensated for added.
at the low loss header. The Weishaupt immediately
system thus capitalises on all of the Outstanding control characteristics are Condensing boilers or DHW charging
control benefits of the low loss header, achieved because changes in flow rate systems can be incorporated parallel to
without impairing the efficiency of the caused by boiler switch-on or switch-off the low loss header without impairing
condensing technology or comparable procedures are detected and compen- their efficiency.
applications. sated for immediately, before they have
an effect on temperature.

4
The Weishaupt multi-boiler control system has been proving itself in numerous installations

5
The Weishaupt service package:
a one-stop solution

Bespoke control panels have been designed and built at the main works in Schwendi for more than 50 years

With more than 50 years’ experience As individual as a finger print Round-the-clock service
in the design and manufacture of The modular structure of the Weishaupt As well as supplying and assembling all
control panels, primarily for burner multi-boiler control system offers of the necessary components, the
and boiler controls, Weishaupt offers numerous options for meeting controls and software are tailored to
customers tailored, one-stop control customer-specific requirements. your individual requirements. Com-
solutions. The open bus communications system prehensive operator orientation/training
simplifies integration with existing takes place after commissioning.
Consultation building management systems. The
Good hydraulic design underlies optimal text and graphics of the user interface To ensure your equipment remains
operation characteristics. Alongside are individually tailored. problem-free in the future, Weishaupt
competent assistance, Weishaupt is provides round-the-clock service 365
also able to provide a comprehensive Forecasted energy savings days per year.
consultation service. The efficiency calculator MKR
developed by Weishaupt provides
On-site analysis of the current state reliable data on the potential energy
Before design comes the analysis of savings for a plant after conversion.
the situation on site. It is possible to
determine right at this initial stage That enables you to consider the
whether a conversion to the Weishaupt amortisation of the intended investment
system will be possible. and plan with a high degree of certainty.

6
The efficiency calculator:
Reliable projections of anticipated savings

Burner selection Plant schematic Pay-back calculations

The Weishaupt efficiency calculator can calculate the likely savings of the multi-boiler control system in advance

7
Some convincing examples:
making visible savings

Production plant in Wahlstedt (picture courtesy of Grundfos)

Deutsche Energie-Agentur GmbH Example installation: Grundfoss Results *


(DENA)’s Energy Efficiency Initiative An extensive energy analysis at the
has presented two Weishaupt production plant in Wahlstedt concluded • Reduction in fuel consumption:
projects as examples of efficient that a modernisation of the heating 1,806,000 kWh/year
energy utilisation by trade and system could realise potential energy
industry. These very impressive consumption and cost savings. As part • Reduction in electrical consumption:
examples demonstrate the potential of the modernisation, older burners 60,000 kWh/year
savings that can be made. were replaced by new models. A new
Weishaupt multi-boiler control system • Annual energy saving of 22 %
was also implemented, which ensures
that only those boilers needed to meet • Reduction in CO2 emissions:
demand are run. Now precisely the 479 t/year
required volume flow rate is transported,
so that the boilers are always operating • Investment: €265,000
at an optimal load point and with the
maximum possible efficiency. • Reduction in costs: €66,500 per year

• Return of investment: 25 %

* Full details can be found in DENA’s “Initiative


Energieeffizienz Industrie und Gewerbe” series
of publications.

8
Production plant in Rittershausen (picture courtesy of Rittal)

Example installation: Rittal Results *


The main source of heat in the factory • Installation of a multi-boiler control
are two boilers, each of which are fitted system and an efficient burner • Reduction in gas consumption:
with efficient burners. Both burners are 8,056,000 kWh/year
equipped with O2 trim and VSD. The • Installation of another burner, com-
combined output of the two boilers missioning of the biodiesel-fired CHP • Reduction in bio-oil consumption for
amounts to 4.76 MW. Heat is also plant. Conversion from thermal flue- heating: 6,720,000 kWh/year
provided by a biodiesel-fired CHP plant gas purification to catalytic flue-gas
rated at 420 kW, and two catalytic flue purification with heat recovery • Reduction in energy consumption
gas scrubbers. The main consumer of 1,337,000 kWh/year
the heat produced is the paint shop, • Installation of flue gas heat
whose pretreatment tanks have to be exchangers in the existing boilers • Saving of 9 %
kept at a constant temperature in
summer and in winter. In winter, heating • CO2 reduction 1,095 t/year
of the buildings consumes the largest
amount of energy. The following • Investment: €620,000
measures were taken in order to
optimise the plant: • Cost reduction: €270,670 per year

• Return of investment: 44 %

* Full details can be found in DENA’s “Initiative


Energieeffizienz Industrie und Gewerbe” series
of publications.

9
That’s reliability

Boiler production in Sennwald, Switzerland Neuberger building automation in Rothenburg Borehole drilling by BauGrund Süd

The Weishaupt Group has over 3,000 administrative headquarters, and home
employees and is a market leader for to the group’s own Research and
burners, condensing boilers, heat Development Institute.
pumps, solar energy, and building
automation. Heating systems are manufactured by
Weishaupt’s sister company Pyropac,
Since 2009 the business, which was which is located in the Swiss town of
founded in 1932, has been structured Sennwald.
as a holding for three companies
operating in the fields of energy Neuberger building automation, sited in
technology, energy extraction and Rothenburg ob der Tauber in Germany,
energy management. has been a group subsidiary since
1995.
The core division is Max Weishaupt
GmbH, which is located in the south- Bad Wurzach is home to the
west German town of Schwendi, and geothermal engineering company,
which is where all burners are BauGrund Süd, which has been part
manufactured. It is also the group’s of the Weishaupt Group since 2009.
Max Weishaupt GmbH
88475 Schwendi
Tel +49 7353 830,
Fax +49 7353 83358
www.weishaupt.de

Print No. 83150202, February 2013


Printed in Germany. All rights reserved.

Neachells Lane, Willenhall, WV13 3RG


Tel (01902) 609841,
Fax (01902) 633343

Weishaupt Service worldwide:


Germany: Leipzig Subsidiaries: Serbia Cyprus Lebanon Spain
Weishaupt worldwide: Augsburg Mannheim Belgium Slovakia Egypt Luxembourg Switzerland (W.)
The branch offices in Berlin Munich Bosnia Slovenia Estonia Macedonien Syria
Germany, and the various Bremen Münster Brazil South Africa Finland Malaysia Taiwan
subsidiary companies, Cologne Neuss Canada United Kingdom Greece Moldava Thailand
representatives and Dortmund Nuremberg Croatia USA India Morocco Turkey
agents abroad, provide Dresden Regensburg Czech Republic Representatives: Indonesia Netherlands Tunisia
local competence. Erfurt Reutlingen Denmark Bulgaria Iran New Zealand Ukraine
Frankfurt Rostock France China Irland Nigeria UAE
Freiburg Schwendi Hungary Lithuania Israel Norway Vietnam
Hamburg Siegen Italy Agencies: Japan Pakistan
Hanover Stuttgart Poland Algeria Jordan Philippines
Karlsruhe Trier Romania Australia Korea (South) Portugal
Kassel Wangen Sweden Austria Kuwait Russia
Koblenz Würzburg Switzerland (E.) Bangladesh Latvia Singapore

Das könnte Ihnen auch gefallen