Beruflich Dokumente
Kultur Dokumente
Mario S, Pacaldo
BAC Chair
Island Garden City of Samal
Davao del Norte
Greetings.
This letter is made then to ask before your good office to again fully
reconsider our basis and relevant parameters for the issues involved
raised in our request for Reconsideration dated February 28, 2018.
Anent to the first ground, again and we reiterate the IRR OF R.A. NO.
6957, “AN ACT AUTHORIZING THE FINANCING, CONSTRUCTION,
OPERATION AND MAINTENANCE OF INFRASTRUCTURE PROJECTS BY
THE PRIVATE SECTOR AND FOR OTHER PURPOSES”, AS AMENDED BY
R.A. NO. 7718 which states therein that under the Build-transfer-and-
operate (BTO) scheme the contractual arrangement made by
Agency/LGU which contracts out the Construction of an
infrastructure facility to a private entity, the Contractor builds the
facility on a turnkey basis, assuming cost overruns, delays, and
specified performance risks.
Page 1 of 4
the performance guarantees undertaken by the contractor are
based only on certain assumptions with respect to the quality of raw
materials used and the operating conditions.
Considering that failure of our bid to yield the required volume under
the Bill of Quantities could be given a relax interpretation or to be
taken as minor defects which can be waived to match with the Turn
key basis approach considering that we do not or do attempt in any
manner to make the offer disadvantageous to the government.
Besides we are liable to our bid price and/or amount quoted on our
bid.
Anent to the second ground, which states that the Total Calculated
Bid Price when computed based in the required volume is
P155,793,638.50 which is beyond the Approved Budget for the
Contract of P149,999,997.12.
Again, we insist that the Bill of Quantities herein can only be faulty
because the Approved Budget Contract in itself is very deficient.
Under Sec. 1.3 of the IRR of the Build and Transfer Law (BT) which states
that the Project Proponent undertakes the financing and
Construction of a given infrastructure or development facility and
after its completion turns it over to the Agency or LGU concerned,
which shall pay the Project Proponent on an agreed schedule its total
investment expended on the project, plus a Reasonable Rate of
Return thereon.
Anent to the third ground, that the Request for Reconsideration was
submitted beyond the prescribed period of three (3) calendar days
upon receipt of written notice. We hope that stringent application of
Page 2 of 4
the rules should be disregarded in the interest of fairness under
justifiable causes and circumstances like in our case.
Your letter dated February 20, 2018 was delivered to us thru a courier
on February 23, 2018 which falls on a Friday.
Page 3 of 4
We are looking forward to getting your input on the matters brought
to your attention. We are hoping for a favorable response on our end.
Thanks for your extreme helpful attention to this matter.
Remegio G. Salanatin
Page 4 of 4