Beruflich Dokumente
Kultur Dokumente
-
WIDE AREA POWER QUALITY DECISION PROCESSES AND OPTIONS
FOR SENSITIVE USERS
-
G.A. Taylor Reyrolle Projects Ltd. (Rolls-Royce Industrial Power Group), U.K.
-
A.B. Burden Scottish Power plc., U.K.
ClRED 97,2-5 June 1997, Conference Publication No. 438,O IEE, 1997
2.30.2
figure 2 : Results of UK survey on causes of supply Option C therefore becomes the most probable
outage leading to production disruption. solution that the customer must resolve. Clearly the
debate must then centre on what devices are
The present UK regulatory standards ensure that all available, the level of immunity to power quality
users receive a common high standard of supply, disturbances required and the cost of installation and
related to their connection arrangement, and does not subsequent operation of such systems. The business
allow utilities to differentiate between customers. case for investment needs each option to be evaluated
For sensitive users, particularly in the industrial and carefully to determine the best solution.
commercial sectors, the following alternatives exist to
protect their production processes from supply Determining the Cost of Power Quality
disturbances :
In the survey referred to earlier, the authors
17% discovered that of those users who had suffered a loss
in production, 93% of the respondees were unaware
of the real cost to their companies of production loss
due to supply disruption. In an increasingly
competitive environment where achieving maximum
efficiency is paramount, such a lack of appreciation is
surprising. The true cost to a company consists of two
main components :
Actual cost incurred
a Potential losses
Cost of restoring production LR The user must calculate these two costs and attribute
[engineering time to reset/ start-up a risk weighting to both PE and P s . The user can
process, waste material] then use both totals, Lactual and Pactual to calculate
the cost of downtime from experience of the annual
Cost of recovering lost production LA supply disturbances. These numbers provide an
[additional shifts, overtime bonuses, encompassing model that will properly justify the
additional plant operating cost (heating, level of investment that can be made to provide a
electricity etc.)] solution. Figure 4 shows an example of how the two
components can contribute to the annual cost of
Hence the total actual cost of a single production downtime, when the probability of the potential
stoppage, Lactual, is losses is just once in every 4 years.
voltage. Thus for a system with a DVR rated to disrupted due to a power supply disturbance.
provide 50% support, a dip leaving only a 20%
retained voltage would be restored to 70% by the Those users who suffer minor disruption and whose
DVR. Because the DVR uses a high speed inverter critical processes are easily isolated are best protected
configuration it can provide a complex power quality by discrete equipment. For those with large loads
function (e.g. harmonic cancellation, phase (> 1MW total) whose production is wholly affected
balancing) that is more suited to complex loads. the decision process is not as straightforward. Plants
may have complex supplies, both at utilisation and
distribution voltages. In these cases the isolation of
all critical loads onto a common feeder is difficult to
achieve. The option may be to place discreet power
quality devices about the site, an option normally
2.30.5
figure 5a : Recorded voltage dip profile over a two year figure 5b :Effect of a 50% rated DVR, with 200ms
period at UK site. energy storage capability to protect supply.
taken with UPS solution routes. or shut-down during supply disturbances. The results
and discussion of the power quality survey presented
To highlight the problem of taking a distributed here suggests voltage dips are the prime cause of
solution path, the authors experience indicates that supply related downtime. Defining compatibility
industries investing in devices to protect process levels between supply and equipment is a difficult
control systems loads tend to progressively invest in process which is usually left to the user who
several units, as subsequent power quality events frequently lacks the information necessary to reach a
reveal the next weak link in the chain. This satisfactory decision. The utility does have a role to
programme means that downtime occurs each time a play in this determination by aiding customer
disturbance occurs incurring the type of losses understanding and supporting the decision process.
discussed earlier. A further net result of such an However the decision ultimately must be made by the
approach is that maintenance, reliability and the customer who must fully understand the true costs of
pollution that such distributed devices can create, downtime..
adds to the complexity of the facility management.
For large users, wide area protection of supplies, that,
Taking a wide area approach such as Custom Power in particular, decrease sensitivity to voltage dips may
means that large or whole sections of a users load can provide the simplest solution to large scale users,
be protected at the distribution voltage with a single while providing minimum impact on surrounding
device. The decision has then to be whether to distribution networks.
completely protect the system from both outages and
voltage dips, or whether to trade off the likelihood of Acknowledgements
one event being more disruptive to production than
the other. The evidence of the survey presented here The authors would like to thank Mr Neil Woodley of
suggests that voltage dips are more likely to cause Westinghouse Electric Corporation for additional
production downtime than any other electrical cause. information and support.