Sie sind auf Seite 1von 1

Air Conditioning Unit Area Breakdown

Item Building Location Floor Level Area Ceiling Height Volume No. of Unit Capacity (hp) Total Hp kW Amp

1.00 Building 1 Packing Office Ground 35.10 5.00 175.50 1.00 2.50 2.50 5.00 20.00
2.00 Building 3 PED Office Ground 83.60 5.00 418.00 2.00 3.00 6.00 6.00 30.00
3.00 Building 3 QA/QC Office Ground 81.30 5.00 406.50 2.00 3.00 6.00 6.00 30.00
4.00 Building 3 Engg Office Ground 53.00 5.00 265.00 2.00 3.00 6.00 6.00 30.00
5.00 Building D Delivery Office Ground 34.20 5.00 171.00 1.00 3.00 3.00 6.00 30.00
6.00 Building D Wire Cut Office Ground 15.00 5.00 75.00 1.00 1.50 1.50 3.06 20.00
7.00 Building D Production Office Ground 45.00 5.00 225.00 1.00 3.00 3.00 6.00 30.00
8.00 Building A Packing Office Ground 28.00 5.00 140.00 1.00 2.50 2.50 5.00 20.00
9.00 Building A Warehouse & Delivery Office Ground 24.10 5.00 120.50 1.00 2.50 2.50 5.00 20.00
10.00 Building 2 Billing Office Ground 25.80 2.80 72.24 1.00 3.00 3.00 6.00 30.00
11.00 Building 2 Delivery Office Ground 24.00 2.80 67.20 1.00 3.00 3.00 6.00 30.00
12.00 Building 2 Warehouse Office Ground 26.30 2.80 73.64 1.00 3.00 3.00 6.00 30.00
13.00 Building 2 Clinic Ground 39.30 2.80 110.04 1.00 3.00 3.00 6.00 30.00
14.00 Building 2 Maintenance Office Ground 14.00 2.80 39.20 1.00 1.50 1.50 3.06 20.00
15.00 Building 2 HR Department Ground 73.00 2.80 204.40 2.00 3.00 6.00 6.00 30.00
16.00 Building 2 Conference / Show Room Ground 68.40 2.80 191.52 3.00 3.00 9.00 6.00 30.00
17.00 Building 2 Lobby/lounge Ground 84.20 3.80 319.96 2.00 3.00 6.00 6.00 30.00
18.00 Building 2 SVP Sales & Mktg Office Ground 28.80 2.80 80.64 1.00 2.50 2.50 5.00 20.00
19.00 Building 2 Sales & Mktg Office Ground 60.50 2.80 169.40 2.00 3.00 6.00 6.00 30.00
20.00 Building 2 Meeting Room 1 Ground 12.50 2.80 35.00 1.00 1.50 1.50 3.06 20.00
21.00 Building 2 Meeting Room 2 Ground 12.50 2.80 35.00 1.00 1.50 1.50 3.06 20.00
22.00 Building 2 Meeting Room 3 Ground 12.00 2.80 33.60 1.00 1.50 1.50 3.06 20.00
23.00 Building 2 Auditorium Ground 250.00 3.80 950.00 5.00 6.00 30.00 14.00 40.00
24.00 Building D MIPPC Main Office Second 224.00 2.80 627.20 8.00 3.00 24.00 6.00 30.00
25.00 Building D SVP Operations Office Second 29.70 2.80 83.16 1.00 3.00 3.00 6.00 30.00
26.00 Building D MIPPC Meeting Room Second 25.00 2.80 70.00 1.00 3.00 3.00 6.00 30.00
27.00 Building D MIPPC Meeting Room Second 10.00 2.80 28.00 1.00 1.00 1.00 2.54 15.00
28.00 Buillding 1 Meeting Room Second 17.00 3.10 52.70 1.00 3.00 3.00 6.00 30.00
29.00 Buillding 1 Meeting Room Second 17.00 3.10 52.70 1.00 3.00 3.00 6.00 30.00
30.00 Buillding 1 Planning & Production Office Second 160.00 3.10 496.00 6.00 2.50 15.00 5.00 20.00
31.00 Buillding 1 Meeting Room Second 20.50 3.10 63.55 1.00 2.50 2.50 5.00 20.00
32.00 Buillding 1 SVP Operations Office Second 12.70 3.10 39.37 1.00 2.50 2.50 5.00 20.00
33.00 Buillding 2 Chairman's Office Second 49.60 2.80 138.88 2.00 2.50 5.00 5.00 20.00
34.00 Buillding 2 Board Room Second 80.00 2.80 224.00 3.00 3.00 9.00 6.00 30.00
35.00 Buillding 2 Executive Office Second 35.60 2.80 99.68 2.00 2.50 5.00 5.00 20.00
36.00 Buillding 2 IT Office Second 50.00 2.80 140.00 2.00 2.50 5.00 5.00 20.00
37.00 Buillding 2 Server Room Second 11.82 2.80 33.10 2.00 2.50 5.00 5.00 20.00
38.00 Buillding 2 Meeting Office Second 19.00 2.80 53.20 1.00 2.50 2.50 5.00 20.00
39.00 Buillding 2 SVP Finance Second 39.80 2.80 111.44 1.00 3.00 3.00 6.00 30.00
40.00 Buillding 2 Finance Office Second 226.00 2.80 632.80 8.00 3.00 24.00 6.00 30.00
41.00 Buillding 2 Hallway Ground 70.94 3.80 269.57 2.00 2.50 5.00 5.00 20.00
42.00 Buillding 2 Hallway Second 82.04 2.80 229.71 2.00 2.50 5.00 5.00 20.00
43.00 Buillding 2 Kitchen Second 24.30 2.80 68.04 1.00 2.50 2.50 5.00 20.00
44.00 Buillding 2 Executive Lounge Second 54.50 2.80 152.60 1.00 2.50 2.50 5.00 20.00

83.00 241.00