Beruflich Dokumente
Kultur Dokumente
IB-571- 1
TRACTION MOTOR TYPE TM 4907BZ
CONTENTS
INTRODUCTION 03
DESCRIPTION 03
CONSTRUCTION 03
DATA 05
MAINTENANCE SCHEDULE 11
ROUTINE MAITENANCE 12
MAINTENANCE TOOLS 20
GEAR CASE 74
GEAR WHEEL 74
BEARINGS 90
BRUSH GEAR 94
IB-571- 2
DESCRIPTION AND OPERATION 97
REMOVAL/INSTALLATION 101
SERVICING 101
ADJUSTING/CHECKING 102
DISASSEMBLY 103
CLEANING 105
CHECKING 105
REASSEMBLING 107
IB-571- 3
TACTION MOTOR-TYPE TM4907BZ
INTRODUCTION
DESCRIPTION
The Traction motor is a D.C. series wound, four pole, forced ventilated
machine arranged for axle mounting on roller bearings, and supported on
the opposite side by resilient suspension unit. Transverse movement is limited
by the flanges of the axle suspension bearings.
CONSTRUCTION
The armature core is built up from electrical quality varnished sheet steel
laminations assembled on the shaft with interference fit and consolidated
under pressure.
The armature is lap wound with 100% equalization. The armature coils
are Kapton covered. The armature and equalizer coil leads are TIG welded to
commutator risers. The armature coil are held down in the core slots by
Epoxy glass wedges, and the end windings are secured by Resi-I-glass
bands. The wound armature is finally Vacuum Pressure Impregnated with
insulation varnish.
There are four brush holders per motor, each carrying three split carbon
brushes, each brush holder is carried on two insulated support pins. Correct
brush pressure is provided by coil spring.
The axle suspension tube is made from cast steel, of one integral part, and
at the both ends tapered bearing housing are formed. The upper and lower
flanges of suspension tube are mounted to the magnet frame with bolts.
There TIMKEN make tapered roller bearings are used at both sides of tube,
and they are lubricated with grease.
The pinion which is shrunk on the armature shaft, drives the loco axle
IB-571- 4
through a spur gearwheel which is pressed onto the axle. The gearcase is of
welded sheet steel construction and is in two halves, which are bolted
together. The complete gearcase is supported on the motor frame. The joints
between the gearcase halves are baffled and grooved to carry felt sealing
rings so as to prevent ingress of dust and any other foreign material and escape of
the gear lubricant.
The motor is forced ventilated. Air enters the motor through a duct
system connected to an opening on the motor frame at the commutator
end. The cooling air then flows in two parallel paths, one under the
commutator through the armature core ducts, and the other along the
outside of the armature and between the field coils, and is discharged through
the openings provided at the pinion end of the frame.
IB-571- 5
MAINTENANCE DATA
RATING (continuous) at 45 Deg. C ambient
WEIGHTS (Approximate)
Machine complete with gears & 3664 Kg
gearcase
Armature 1165.5 kg
Gearcase 126 Kg
Pinion (18:74) 24 Kg
ARMATURE
Core diameter 489 mm
IB-571- 6
COMMUTATOR
Length of working face 187 mm
Diameter-New 423/424 mm
BRUSHGEAR
No of brush arms 4
Brush holders per arm 1
Brush per holder 3
Max. permissible brush to brush 0.5 mm box clearance
Clearance between brush-holder & 2.0 to 3.0 mm
commutator
CARBON BRUSH
Length 52 mm
Width 57.15 mm
ARMATURE BEARINGS
LUBRICATION
Quantities indicated for lubricants are approximate and for general guidance
only. The actual quantity of the lubricant and the interval between re-lubrication
should be determined from experience and duty. Relevant dipsticks should
invariably be used for checking levels of lubricants in the gearcase.
ARMATURE BEARINGS
Recommended Grease ESSO Andok B R or HP LITHON 3
GEARS
Recommended Lubricant Caltex Crater No.2 or Bharat
camex Compound FOR HP
Gear Tak 2.
Quantity of Lubricant in grease 5 Kgs at Max. Level 3 Kgs at
Min. Level
IB-571- 10
MAINTENANCE SCHEDULE
The efficient performance of electrical machines depends very largely on
periodical inspections during which incipient defects can be rectified.
Such attention reduces the cost of repairs and lengthens life of the
equipment.
After putting new or reconditioned machines into service for the first time,
the following checks should be carried out, during or at the end of first
week of operation.
Check that after the motor has been mounted backlash exists between
pinion and gear wheel. New gears are manufactured to have a nominal
backlash of 0.25 to 0.76 mm, as measured on the outer i.e. non relieved
end of the pinions.
Check that after a load run, temperatures of axle suspension bearing are
not excessive.
ROUTINE MAINTENANCE
MONTHLY:
Before removing commutator covers, brush off loose dust or dirt. Examine
the commutator and clean the outer vee-ring and the insulation over the
IB-571- 11
risers. The commutator should be of uniform colour, have a well -
polished surface and be free from bar marking or bar edge burning. For
commutator faults and their rectification see WORKSHOP
INSTRUCTION.
Remove any copper beads from the commutator surface with fine
carborundum cloth. Deposits from dirty or greasy hands should be
removed by a solvent.
Check that the brush springs sit correctly on the brushes and that the
springs are in good condition.
Check carbon brushes for wear/Fit new brushes in place of any which are
unlikely to last until the next inspection. See DATA for minimum length
and brush grade. Bed all new brushes to the curvature of the commutator.
Check brushes for freedom in the brush-holder and if sticking, clean both
the brush and the brush way in the holder. Do not soak the brush as the
solvent will eventually ooze out affecting the commutator and causing the
brush to jam in the holder.
Top up gearcase to the level of gear filler until. See DATA for Grade of
lubricant.
THREE MONTHLY
IB-571- 12
Take particular care to direct air under the commutator in order to remove
dirt lodged in the armature core ducts.
Check tightness of bolts securing axle suspension tube and gearcase. For
torque values with lubrication of the threads refer MACHINE DATA.
SIX MONTHLY
Check the Gearcase mounting bolt hole on magnet frame and replace the
bushes if wornout.
ANNUALLY
When motors are removed from bogies for wheel turning etc. clean pinion
and gearwheel and check for tooth wear.
Before fitting the gear cases, clean out old lubricant to avoid the
possibility of gears running subsequently in contaminated lubricant.
Dismantle the motor and clean the armature and field system. Dry out to
remove any detrimental moisture. After drying out, check the hot
insulation resistance of the armature and field and if greater that 1
Megohm apply a high voltage test as detailed under HIGH VOLTAGE
TEST.
Check the armature for open and short circuits by a commutator bar-to-
bar test. For method see WORKSHOP INSTRUCTION.
Remove the brush-holder from the machine. Clean and inspect for brush
clearance in the holder-spring pressure and damage. Recondition as
IB-571- 13
necessary.
If the field coils and connections are in good condition and dry, paint the
interior of machine with suitable insulating varnish. If the field coils require
repair, remove and recondition individually, check the armature bearings
and bearing details of damage renewing as necessary.
Inspect the shaft for damage to pinion and bearing seatings and ensure
that it is straight.
Inspect the armature for loose bands, solder throwing etc. recondition as
required. If the commutatoris worn or damaged, skim the commutator and
undercut the micas.
Check the gear case mounting hole on magnet frame and replace the
metallic bushes if worn out.
Dynamically balance the armature, reassemble the machine and paint the
exterior of the machine. Run the machine on no load at about 1100 RPM
to ensure correct operation of the bearings. When installing the motor in
the bogie ensure that all bolts are tightened to the specified torque
values. Fill the gearcase with the correct lubricant to the maximum level
use dipsticks for Gear cases to be filled up to the filler unit level.
IB-571- 14
RECONDTIONING AND REPAIRS
Note: Refer also to WORKSHOP INSTRUCTION for reconditioning
and repair procedures.
ARMATURE
After removing the armature from the magnet frame, blow off loose dust
and dirt with clean, dry compressed air, if the armature is very dirty, clean
it.
Visually inspect the condition of the armature coils and bands. Check the
pinion and commutator end bands for looseness by tapping the band light
hammer and feeling for vibration.
Check the armature for open and short circuits by carrying out a
commutator bar-to-bar test.
Dry out the armature and check the hot insulation resistance. If this is
greater than 1 megohm apply a high voltage test, as detailed under HIGH
VOLTAGE TESTS in MACHINE DATA.
Wash and inspect the armature bearings. Inspect the bearing details for
damage. renewing as necessary. Inspect the shaft for damage to bearing
and pinion seatings. Ensure that the shaft is straight.
COMMUTATOR
If the commutator is damaged, grooved or shows flats and high bars,
resurface in a lathe. Turn the armature on its bearing seatings and
remove as little metal as possible. After turning undercut the micas to the
dimensions given in DATA, bevel the bar edges and clean out undercuts.
Do not resurface a commutator whose surface has a good polish and
colour and is free from grooving, signs of flats, high bars and bar marking.
Heat the sleeve to about 150 deg. Celsius in an oven having proper
exhaust ventilation and press it over the support pin. Ensure that it is
IB-571- 15
pushed solidly against the brush holder castings.
NOTE:-
MAGNET FRAMES
Clean and inspect the armature bores/faces. Check for any crack, dent,
damage repair them if required.
Check that the gear case mounting holes are not enlarged/oblong replace
the bushes if required.
Check the end shield mounting tapped holes on PE & CE side repair
them if required. Check the axle bore and face for dents, damages and
repair if required.
Traction motor has been provided with a flame ring which is supported on
the CE end shield with the help of 6 Nos. screws. The purpose of the
flame ring is to provide an arcing gap direct to earth & to protect the
commutator in the event of flashover.
PROCEDURE:
IB-571- 16
-Chip off the welding from flame ring screw heads
-Fully tighten the screws on to the flame ring after ensuring the
arcing gap to 25+2 /+0 mm between commutator and Flame ring
as shown in the Fig.o1. Steel washers may be used for maintaining
the arcing gap if required.
Lock the flame ring screw heads by tack welding at two places with CE
end shield as shown in Fig.01.
IB-571- 17
IB-571- 18
MAINTENANCE TOOLS
The following List gives the Maintenance Tools for traction Motor Type
TM4907BZ.
TOOLS
1. Spirit level, wooden blocks, wooden “V” blocks, chisel, light
hammer, Copper drift, oven, Screw Press.
2.
Spanners: Nos. 10,13,17,19,24,30,36,47 & 55.
NOTE:- Box Spanners with ratchet may be used to the extent possible.
Bearing Race
IB-571- 19
Extractor for PE outer Bearing Race 1405383
Spacer 1405979
Studs 1405982
IB-571- 20
IB-571- 21
IB-571- 22
IB-571- 23
IB-571- 24
IB-571- 25
IB-571- 26
IB-571- 27
IB-571- 28
IB-571- 29
IB-571- 30
IB-571- 31
IB-571- 32
IB-571- 33
IB-571- 34
IB-571- 35
IB-571- 36
IB-571- 37
IB-571- 38
IB-571- 39
IB-571- 40
IB-571- 41
IB-571- 42
IB-571- 43
IB-571- 44
IB-571- 45
IB-571- 46
IB-571- 47
DISMATLING & REASSEMBLING
DISMANTLING
The following list shows the tools which are required for dismantling
the traction motor. (See under MAINTENANCE TOOLS)
TOOLS
Spanners 13, 17, 19, 24, 30, 36, 46, 55.
Eyebolts M20, M24
Allen Keys 3 A/F, 5 A/F
Chisel, Spirit level, Wooden blocks, Screw press.
IB-571- 48
IB-571- 49
Before dismantling the motor refer to the section “Ball and Roller Bearings”
in the WORKSHOP INSTRUCTION for the precautions to be taken, to
avoid damage to the bearings. Also refer to the section “Hydraulic Tools” for
the correct use of such tools specified.
IB-571- 50
18. END SHIELD PE 41 BEARING HOUSING
IB-571- 51
REMOVING THE ARMATURE AND ARMATURE BEARINGS
1. Clean the motor externally.
5. Remove two of the P.E. endshield bolts 17 and insert two M24
eyebolts Using these eyebolts and lifting shackles 1405977 item
8 up-end the motor CE down onto wooden blocks. Using a spirit
level, set the machine axis truly vertical.
7. Check the retaining ring bolts for tightness and take up any
slackness which may have developed due to the armature
moving forward.
IB-571- 52
Fit the protecting sleeve 1405377 in the CE of the shaft. The
protecting sleeve permits trestle mounting of the armature,
provides a shaft extension for lowering the armature,
accommodates a lifting cap and protects the bearing inner race.
Lower the armature into a horizontal position on a wooden V-
block.
10. Remove the lifting cap and retaining ring. Using the extractor
1405382 remove the P.E. bearing retaining collar 21 Remove
screws 19 and insert three forcing screw 1405975 item 11 in the
bearing cap P.E. 20 and force it out of its fit. Insert eyebolt 1405979
item 4 into a forcing screw hole in the P.E. endshield 18 apply a
lifting sling and remove the endshield complete with the P.E.
bearing outer race.
Remove the P.E. bearing outer race from the endshield with
extractor 1405383. Clean and oil the inner bearing cap 30 inner
Race. flinger 29 and inner bearing sleeve 31.
Fit the protecting sleeve 1405384. If the bearing inner Race, flinger,
PE inner bearing cap. Inner bearing sleeve are damaged and are
to be replaced, remove inner bearing race P.E using 1405382.
Remove inner bearing cap and flinger using extractor 1404378.
Remove inner bearing sleeve P.E using extractor 1405378.
11. Using two M24 eyebolts screwed into the magnet frame at
P.E. endshield. Securing bolt holes turn the frame into a
horizontal position. Using three forcing screws 1405975
item 19 remove the C.E. endshield. Using a screw pressto
with draw the C.E bearing outer race from the endshield.
IB-571- 53
REMOVING THE FIELD COILS
1. Remove the insulation from the connection and unbraze these
using brazing tongs or a gas torch. If a gas torch is used, adjacent
insulation must be protected with wet asbestos paper.
2. After removal of the pole bolts, remove the pole and coil assembly.
If a main pole assembly is to be removed, the adjacent
compoles must be first removed.
3. Lift the coil and pole and coil assembly and recondition, if
necessary. The insulation and mechanical protection applied to
the coils are shown in the figure. After repair, treat the field
coils in silicone varnish and paint with insulating varnish.
REASSEMBLINGTHENEW/RECONDITIONED MAINFIELDCOIL&POLE
ASSEMBLY
1. On to the cleaned pole fit the main pole spring with the crests of the
corrugations adjacent to the pole tip. The open end of the spring
should, when the pole is finally assembled into the machine, be at
the pinion end of the machine.
3. Mount the pole and coil assembly in the frame, and fit new locking
washers on the pole bolts of the nose side , top & bottom poles,
The axle side pole is fitted with the reduced head bolts, which are
locked by tack welding the ends of the square steel bar, laid long
one of the bolts head flats to the Magnet frame. New main field coil
and pole assembly to be used where existing main field coil and
pole assembly is found in heavy damaged condition or magger
value is zero.
IB-571- 54
REASSEMBLING THE COMPOLE COILS
1. Clean the pole and check that the liner specified in DATA is fitted
to the back of the compole.
3. Using new locking washers under the pole bolt heads, mount the
frame and pull down the bolts.
RECONNECTING
Reconnect the coil as shown in fig. 03. All connections are made with
silver phos bearing alloy 0.25 mm thick using one piece only between
terminals and connections strips or brush gear leads. Flux is not required with
this alloy. It is strongly recommended that, if available, a brazing machine with a
pair of carbon brazing jaws to be used for brazing operations. Soak asbestos
paper in water and use it to protect the insulation adjacent to each
connection. Braze the connections using a current of approximately 2000
amperes.
Slip a piece of Silver phos bearing alloy, between the terminals and
clamp the connection with a screw clamp or vice grip pliers.
With the torch set to give a neutral flame, braze the connection
adding extra brazing alloy to fill the joints. Remove the clamps and
asbestos and blow out the inside of the frame with dry compressed air.
INSULATING STAPLES
Insulate the staples with two half lapped layers of 0.15 mm thick
varnished seamless Bias cut terylene tape, followed by one layer of 0.18
mm thick woven glass tape, wet treated in insulating enamel.
IB-571- 55
IB-571- 56
INSULATION OF BRAZED CONNECTIONS
a. BRAZING OF JOINTS
Existing and proposed method of placing the connection leads are
shown at fig. A & B.
b. INSULATION OF BRAZED JOINTS
The following insulation materials are used in brazed joints of field
connections for traction motor:-
4. INSULATE BRAZED
JOINTS
FOR JOINTS WITH CABLE A,AA & BRUSH GEAR LEAD WITH
COMPOLE COIL S1
IB-571- 57
9. FINAL TAPE ONE LAYER WOVEN GLASS 10 M.
1/2 LAPPED TAPE 25TKx25
IB-571- 58
IB-571- 59
INSULATION OF THE CABLE TERMINAL PLATE JOINT OF
POSITIVE BRUSH HOLDER LEAD
On the motors, flash over marks are observed on positive brush holder (3
‘O’ clock ) cable connector. Presently the terminal plate of the connector
is bare. Flashover, takes place between the +ve brush holder terminal
and the -ve terminal or between +ve terminal and ground. The flashover
cause erosion of the +ve bare terminal & amage to field coils.
MATERIALS:
a) Elastomer tape - 0.5 tk x 25 x 2.0 M
PROCEDURE:
2. Disconnect the positive brush holder lead from the brush holder (3
‘O’ clock).
3. Insulate the brush gear lead +ve terminal plate using the material
given at item 2.0 as follows :
IB-571- 60
TOOLS
Eye bolts M20, M24
REMOVING
1. Remove the pinion and bearing inner race using extractor 1405382
remove flinger 29 and inner Bearing Cap PE 30 using extractor
1405378 & remove inner bearing sleeve PE 31 using extractor
1405380 using extractor 1405376 remove CE, and sleeve and
bearing inner race. Remove inner bearing cap CE.2.
3. Mount the armature in a press, arrange to push the shaft from the
commutator end to pinion end. Between 200 to 350 tones will be
required to move the shaft. Immediately pressure is applied, check the
clamping stud nuts for tightness and retighten uniformly.
IB-571- 61
REFITTING
1. The armature core and commutator are located on the shaft by
means of keys. During the refitting operation, the keys, unless held
axially in the shaft keyways, could possibly cause difficulty by
riding up the run-outs of the keyways. To prevent this, fit the keys to
the shaft and, at about 25 mm from the commutator end of the
keys, drill through both keys in to the shaft to a depth of 15 to 17
mm from the top of the keys. Ream the holes 6 mm diameter
and fit 6 mm diameter steel pegs into the holes such that the top
of the pegs are flush or slightly below the top of the keys.
IB-571- 62
REASSEMBLING
The following list shows the tools which are required to reassemble the
traction motor. (See under MAINTENANCE TOOLS).
TOOLS
Spanners; 19,24,30, 36, 46, 55, Eyebolts; M20, M24, & Allen Keys;
3A/F, 5 A/F; light hammer, Copper drift, Oven, Spirit level, Wooden blocks,
Screw Press, Dial gauge, Feeler gauges.
Please refer “CE & PE Bearing grease Distribution” for the quantity of
grease to be filled in the armature bearings. See fig. 04 & 05.
Shrink the CE bearing inner race onto the shaft at 100 to 110
Deg. Celsius actual temperature. Fill the CE bearing cap inner 2
with grease as shown in fig.05.
IB-571- 63
PE BEARING GREASE DISTRIBUTION FOR
TM4907AZ FIG.-4
IB-571- 64
CE BEARING GREASE DISTRIBUTION FOR
TM4907AZ FIG.-5
IB-571- 65
2. With the identification marks facing towards the outside of
the machine, using screw press, press the CE bearing outer
race into the CE endshield. Force grease into the spaces
between the rollers, Roller faces, cage and out race track
at the back of the bearing position as shown.
Stick the gasket between the CE Bearing inner cap 2 and the
endshield with jointing compound. Insert two guiding studs
1405976 it.4 diametrically opposite in the magnet frame at
endshield securing bolt holes and assemble the endshield to the
magnet frame. Tighten bolts at specified torque.
Force grease into the spaces between the rollers, Roller faces, &
cage and outer race track at the back of PE. bearing as shown in
Fig.04 Arrange the bearing such that the identification marks
face towards the outside of the machine and press the bearing outer
race into the endshield by a screw press.
IB-571- 66
Force grease into the spaces between the rollers, Roller face, & cage
and outer race at the front of the PE bearing positions as shown in
Fig.04 (Fill grease in the outer bearing cap PE 20 as shown. Do not
assemble at this stage.)
5. Thoroughly clean the PE spacer 1405979 and slide onto the shaft
butting up against the PE bearing inner race. The PE spacer is used in
place of the PE bearing collar 21 to enable run out and diametrical
clearance checks to be made on the bearing after assembly of the
armature in the magnet frame.
6. Assemble the rotating ring and lifting plate 1405381 and apply the bolts
and screw up tightly to the retaining ring. Tighten the retaining ring
bolts.
7. Using two M24 eyebolts to the magnet frame at the tapped holes used
for the PE endshield, turn the frame on end, CE down. Set up on
blocks high enough to give access later to guide the shaft though the
CE bearing. Using a spirit level, set the machine axis truly vertical.
Screw two guiding studs 1405976 it. 4 into the frame to guide the PE
endshield during assembly.
8. Assemble the guide bush 1405375 to the commutator end of the shaft.
By means of the lifting cap on the Pinion End of the shaft, lift the
armature and lower into the magnet frame. Take care not to damage
the bearings. Insert and uniformly tighten the PE endshield bolts 17.
9. Using one of the lifting eyes cast on the motor frame and two M24
eyebolts in the tapped holes for the PE endshield bolts, turns the frame
into a horizontal position resting the PE on a wooden block
approximately 100 mm high.
12. Measuring the bearing run-out and radial clearances as follows, taking
care to prevent dirt getting into the grease and bearings.
(a) Attach a dial gauge with a magnetic base to the end of the armature
shaft. Arrange the spindle to bear against the bearing outer race-as
near the centre as possible but avoiding all identification marks.
(b) Rotate the armature slowly and read the run-out of the bearing outer
IB-571- 67
race making sure that the armature is kept forward (using the wooden
block under PE) so as to eliminate any end play.
If the run-out exceeds the above limits, check for burrs, dirt under the
fits of the endshield and magnet frame.
(c) Attach the dial indicator to the bearing outer race or a flat
portion of the endshield and arrange the spindle to bear
against the bearing inner race as near to the centre as
possible but avoiding all identification marks.
CE 0.013 mm PE 0.013 mm
Turn the shaft just sufficiently to roll the top roller on the feeler gauge.
Insert different feeler gauges until the clearance is established. Repeat
this for all rollers.
13. Assemble outer bearing cap PE 20 onto the endshield taking due care
to align the bottom grease outlet with the endshield outlet. Fit the
bearing retaining collar 21 by shrinking on at 90 to 100 deg. Celsius
above ambient temperature. When cold, tap the bearing collar with the
light hammer and copper drift to ensure that it is solidly butting against
the bearing inner race. Slowly tighten the bearing cap screw 19. check
and maintain a radial gap 0.25 mm minimum between collar and outer
bearing cap 20. Tighten screws at specified torques.
1 4 . Force grease into the spaces between the roller, roller faces, cage and
bearing outer race at the front of the CE bearing as shown in greasing
schedule.
Fit the CE bearing separate lip 9 and assemble the CE bearing locking
IB-571- 68
plate 6. Using a new locking washer under the 7 bolts. Tighten bolts at
specified torques. Lock the CE bearing locking plate bolts 7.
15. Smear the mating faces with suitable jointing compound and fit the CE
bearing outer cap 4 without putting grease inside it and tighten the
bolts 3 uniformly.
17. Replace the carbon brushes and check that they are properly bedded.
(a) Run the motor at a speed of 1100 rev/min. After the motor has been
running for a few minutes, check for noise. Run motor for at least one
hour for a correctly assembled bearing, the peak temperature rise
should not exceed 35 to 40 deg. Celsius during this run.
(b) Increase the speed to 1,700 rev/min. and run until the temperature of
the bearings has passed a peak value of 45 to 50 deg. Celsius above
ambient temperature and has fallen to a steady state of between 35 to
40 deg. Celsius above ambient temperature.
(c) Increase the speed to 2,231rev/min. for a short period to check for
bearing noise and vibration. In this case the peak temperature rise
above ambient should not exceed 60 deg. Celsius and the steady
temperature should be between 35 to 40 deg. Celsius above ambient
temperature.
19. Dismantle outer bearing cap CE 4 and fill the grease as shown in
greasing schedule reassemble the outer bearing cap CE 4, tighten the
bolts 3 at specified torque.
1. Lift the bottom half gearcase up around the gearwheel until the
felt seals around the motor shaft opening and the axle openings
rest on the bearing cap and gearwheel hub respectively.
2. Insert the two M36 mm mounting bolts, fitted with new lock
washers, and screw down to support the gear case, but do not
tighten.
3. Heat about 2.5 kgs. of gear lubricant to, about 85 deg. Celsius
and pour it over the pinion and gearwheel or alternatively paint
this lubricant onto the teeth.
4. Lower the top half gearcase over the gears until the felt seal rests
on the bearing cap as in note 1, above and insert and screw
down the M36 mm mounting bolt. Do not tighten bolt.
5. Fit Four M20 mm joint bolts and nuts, using new lock-washers,
and tighten. torque value, 20-22 Kg .M. In case one bolt of M30
is used tighten the bolt at 30 Kg M.
IB-571- 70
MATERIAL REQUIRED:-
1. Dia 80x60 mm long forged bars to IS2004 class 4, machined as per the
FIG.06.
PROCEDURE:
1. Remove the tack weld of the plain bush with the help of
chisel and remove the bush from the holes at two locations.
2. Clean the holes for welding deposit etc. and deburr the holes.
3. Press fit the bush fig.06 in the hole item 001 at top and item 002
at bottom maintaining the alignment of machined collar with the
frame step.
IB-571- 71
IB-571- 72
TRACTION MOTOR GEARS AND GEARCASE
GEARCASE
For the correct method of assembling, the gearcase and for the initial
application of lubricants to the gears. See ASSEMBLING THE GEARCASE
under MACHINE DISMANTLING AND REASSEMBLING.
See DATA for approved lubricants and quantities. The lubricant should
be heated to about 85 deg. Celsius to enable it to be poured. The gearcase
filler unit is in the bottom half of the gearcase and is accessible from the axle-side
of the motor.
During the first few weeks in service, check the level of lubricant every week
on several vehicles and, look generally for any sign of leakage. All checks
should be carried out with the gearcase warm after a run, but after allowing a
short period to settle the lubricant. Continue these weekly checks until the
lubricant level has fallen to the minimum permissible as batch of vehicles may
be used as a basis for the lubrication schedule, after allowing a safety margin to
ensure that the lubricant must last until the next examination. Thus, if the shortest
time interval two months specify topping up at months i n t e r v a l s .
If the gears are to re-enter service immediately clean thoroughly using xylol
or a similar solvent applied with a brush. Wipe with a cloth after wares. If the
gearwheel is likely to stand for a time, clean only ten to twelve teeth spaced
equally round the periphery, leaving lubricant on the remainder of the
gearwheel as protection. After examination, if the condition of these cleaned
teeth is satisfactory, recoat them with lubricant.
The teeth should be free from cracks and the flanks should have a
uniform, unscored polished appearance. The tooth profile should be
substantially the same as that of a new gear. If a gearwheel has chipped
broken or badly worn teeth, discard it and fit a new gearwheel.
Ensure that, as far as possible gearwheels are returned to service with the
pinions with which they were meshed originally.
IB-571- 73
Do not over fill the gear case which may flood the PE armature bearing
and cause premature bearing failure. Ensure that the gear case compound
is filled to the level of compound filling unit. Which is the maximum level.
Ensure also on no account, lubricant level goes below the minimum level.
Use dipstick 1405374 for maintaining minimum level.
PRECAUTIONS
Whenever a gear or pinion wears significantly there is “step” created near
the root of the tooth where the tip of the mating tooth runs out of engagement. If
the gear centre distance is exactly correct, this step will occur at the lowest point of
contact between the mating tooth. However the gear Centre distance cannot
be controlled exactly in service, due to axle bearing lining wear. As the gear centre
distance spreads, the teeth become further out of engagement this forms
“step” at varying depths.
If the same gearings are used there will be very severe tip leading of the tooth
and very poor profile at the root end of the tooth. This can cause severe noise,
vibration , and premature failure.
The step is to be dressed up with the help of small hand grinder,. Care
should be taken during the grinding operation not to under cut the tooth. Step
should be removed before checking the profile of the tooth by profile gauge
otherwise faulty readings will occur.
The gear wheel and pinion should be removed from service when
width at tooth tip or maximum wear per flank measures less or more
respectively than the following limits.
Min Tip Max. Wear per Min. Tip Max. wear per
width flank width flank
IB-571- 74
Dimension “K” shown in Fig No.08 is to be checked at the specified
number of teeth on 8 different sets of teeth. In case the coverage dimension is
found less than the service limit indicated in fig.08 gear or pinion should not
be used.
Feeler gauges of 0.05, 0.1, 0.15, 0.2, 0.25, 0.3 & 0.4 mm thickness
may be required for this purpose.
1. Be sure that the gear used as pattern is new. The gauge can only be as
accurate as the gear from which it is made. The gear should be thoroughly
cleaned before using as a pattern.
2. Make a “partial” mould as shown in Fig.07. The gear itself will complete the
mould.
3. Wax all surfaces which will receive the moulding compound with
silicone wax CP mould release. This material is made by the Chemical
Development Corporation, 54 Encicott St. Danvers, Mass U.S.A.
4. Lay the pinion or gear on a flat smooth waxed surface with the bore
vertical. If a table is not available, make a flat plate and clamp it to the side
of the gear or pinion.
NOTE:-
The pinions are made with tapered teeth-that is, the tooth is thicker
at the outboared (small bore) end than at the inboared (large bore) end.
Then pinion should be laid on the flat surface, with the outboared (small
bore) and face down. Thus the gauge will be moulded to fit the thicker
end of the tooth.
IB-571- 75
5. Place the partial mould in position against the tips of the teeth as
shown in sketch. Make sure that all surfaces that will contact the
moulding compound have been coated with wax as described
under sl.No.3 of the above. The partial mould and the pinion
should be clamped in position with “C” clamps to prevent anything
from disturbing their position during the hardening process.
IB-571- 76
IB-571- 77
LOCO PINION/ NO.OF NO. OF Dimension ‘K’ Service
GEAR TEETH TEETH
ON K
SERVICE
7. Pour the thoroughly mixed resin into the mould until full. Allow the mould
to set for several hours, preferably 12 hours or more.
8. Remove the parts of the mould the pattern pinion or gear the partial
mould, and the plate. If one was used. Care should be taken to slide the
plastic off the end of the gear teeth, so as not to disturb the profile surface of
the newly moulded gauge.
IB-571- 79
REMOVING AND FITTING PINIONS
The tapped hole in the shaft is sealed with a screwed plug to prevent
gear lubricant from entering and blocking the oil ways thus rendering the oil
injection difficult.
Using a solvent such as white spirit, remove all traces of gear lubricant
from the pinion, the shaft end, and the oil injection plug. Remove the plug
sealing the oil injection hole, using a large screw driver.
Remove any gear lubricant which may have found its way past the
plug.
Mount the pinion ejection safety plate 1405379 (item 1) onto the shaft,
allowing a gap of about 5 mm, for the removal of the pinion.
Assemble the S.K.F. pump and injector attachment tool no.1405981 fit
the high pressure pipe and fill the pump reservoir with clean oil. Fit the
reservoir to the pump. Do not fit the pump handle at this stage.
Open the pump relief valve and using the fingers, operate the pump
rapidly until air bubbles cease to be expelled with the oil. Close the relief
valve and again operate the pump handle socket with the fingers until the
system is full of oil and resistance to pumping is felt. Fit the pump handle
and continue pumping, raising the pressure gradually and pausing after
each stroke to let the pressure build up at the pinion seating. It will be
obvious when the pinion has ejected as a sharp crack will be heard as the
pinion hits the safety plate.
IB-571- 80
NOTE:-
The use of excessive pressure will cause the pinion to be ejected violently, it
may then rebound back of the special nut and reseat itself on the shaft, it
could also cause permanent distortion of the pinion bore. As the pressure is
built up and oil forces its way between the mating surfaces of the shaft and
pinion point is reached as at which oil will begin to seep out at the ends.
Should the pinion not have been released by the time this pressure has
been reached and maintained for approximately five minutes, release the
pressure and leave for 10-15 minutes before repeating the attempt. Repeat
the pumping up to pressure pausing releasing and waiting at least five times
and if the pinion still refuses to move. It is permissible to change the oil in the
pump for one of a grade heavier, before following the above.
Refit the plug in the oil injection hole immediately after removal of the
pinion to prevent the ingress of foreign matter. Protect the pinion bore and
shaft tapered end from damage and corrosion.
If after repeating the bedding check several times, and light stoning still
fails to produce a satisfactory seating the shaft and pinion may be lightly
lapped using very fine emery paste.
Thoroughly clean the surface of the shaft including oil injection hole and
pinion using a solvent with degreasing properties such as white Spirit Wipe
dry using a clean dry cloth.
To establish the “cold” pinion position, pass the pinion onto the shaft,
and push it home without using excessive force. The desirable amount of
force, is such that the pinion seated thus, has sufficient Adhesion to allow it
to be used to rotate the armature. Mark a corresponding radial line on the
pinion and shaft end faces with chalk and measure with a depth micrometer
or vernier gauge the position of the pinion face in relation to the shaft end at
the chalk line and record this distance. The chalk line will facilitate the return
of the pinion to its original position, circumferentially in relation to the shaft.
IB-571- 82
APPLICATION OF R.C. COMPOUND:-
MATERIAL:
SOURCE OF SUPPLY:-
R C COMPOUND:
INDIAN REPRESENTATIVE :
The special compound has short shelf life of 3 months and starts to gel. It
is, therefore, recommended that the date of manufacture/expiry may be
checked before use of the special compound.
PROCEDURE :
Clean and degrease the Pinion bore and shaft taper. It is necessary to
check that 90 percent bedding is achieved between pinion and shaft before
application of special compound. Also ensure that bedding on the shaft portions
up to 15 mm length at both ends of the taper (major and minor dia) is 90
percent. This will also avoid oil leakage problem during extraction of the pinion.
See Fig. 09.
After checking pinion bedding on the shaft as above and marking of pinion
on shaft in cold condition as explained in Maintenance Manual, apply special
compound on the shaft and pinion bore as detailed below.
Clean the shaft and pinion bore with dry cloth. Stir the compound
thoroughly.
IB-571- 83
IB-571- 84
Apply a coat of compound with brush on the shaft and pinion bore.
Wipe clean the shaft and pinion bore with a dry lintless cloth or blotting
paper before the compound dries of its own to leave only a thin film on the
surface. Do not touch or allow any contamination of the treated surface.
Heat the pinion in an oven or induction heater and follow the pinion fitment
procedure as given in Maintenance Manual.
RECOMMENDATION :
Mount the pinion positioning gauge 1405387ontothe pinion, taking care
that there is 5.0 mm of clearance between the back of the setting tackle and the
pinion end bearing cap to allow for the advance of the pinion without fouling.
Adjust the setting screw, placing a gauge of the correct thickness between the
point of the screw and the shaft end.
Do not over tighten the setting screw against the gauge as this will give a
false position and the desired advance may not be achieved. Lock the setting
screw in position. Mark the position of Pinion on the shaft. Remove the pinion.
Heat the pinion (still with positioning tackle attached) in an oven providing
uniform heating. The oven should operate at a temperature approximately 20
deg. Celsius higher than that required for the pinion and must be constructed so
that the pinion is not in direct contact with the source of heat. Under no
circumstances must be oven temperature exceed 190 deg. Celsius.
When the pinion and positioning tackle have reached the required
temperature, quickly transfer them to a position conveniently near to the shaft,
and carefully wipe the mating surfaces on the shaft and pinion with a clean dry
cloth. Place the pinion over the shaft end 25 mm from its final position, with the
chalk marks coincidental. Quickly press the pinion as far onto the shaft as the
setting screw on the positioning gauge will allow. Hold the pinion in position until it
cools sufficiently to grip the shaft, and then remove the positioning tackle.
Check the advance of the pinion at the marked position using a depth
micrometer or vernier gauge. The advance must be between the limits
IB-571- 85
specified i.e. 2.25 to 2.45 mm. If the advance is not within these values,
remove the pinion by oil injection verifying the temperature to obtain the
correct, advance. If the advance is correct, allow the pinion to cool. After cooling
again check and record the final pinion advance which should remain within
the specified range.
If a suitable oven is not available, the pinion may be heated in an oil bath, but all
traces of oil must be removed from the pinion before fitting. In such case, R.C.
compound should not be applied on the shaft & pinion bore. This may effect
the bonding quality of the compound.
• Wipe clean the pinion faces & shaft with dry cloth.
• Apply thick layer of ‘M’ seal putty on both side faces of the pinion
at the mating points of pinion bore periphery and shaft, to seal the
same.
• If oil still leaks out through ‘M’ seal putty, repeat the process as
per clauses 1 to 6.
3. While applying extraction force, pour hot oil (200 deg. Celsius
approx), over the pinion.
4. If the pinion is not getting extracted, apply oil pressure
simultaneously by using Oil Injection. For this purpose, a small
metallic spacer may be used in between shaft end and ram of the
puller so as to enable fitting of oil injection plug into the shaft.
RECOMMENDATIONS:
The procedure of pulling and heating the pinion may be resorted to only
after oil injection with ‘M’ seal fails repeatedly.
IB-571- 87
PROCEDURE FOR ASSEMBLING OF DROP ROLLER CAGE
TYPE BEARING
INTRODUCTION :
Drop roller cage type bearings have also been successfully used on traction
motors. These bearing offer the following advantages:
- Larger shoulder diameter of the outer ring for easy mounting.
- Easier application of grease.
- Facilitating cleaning during inspections.
- Accurate examination of outer ring raceway possible.
It is pertinent to mention that these bearing have a cage which permits
the rollers to drop down towards the centre of the bearing. So, it is
necessary to use the bearing rollers guide to spread and guide the rollers up
over the inner race during the assembly of endshield on the shaft.
Considering the advantages of drop roller cage bearings, these have
been used o n a trial basis on traction motors like TM4907BZ.
IB-571- 88
IB-571- 89
IB-571- 90
PINION END :
Shrinkfit bearing sleeve (item 2) tight against the end plate at the
temperature of 115 degree Celsius (+20/-0 degree Celsius), if it has
been removed earlier. Shrink fit flinger (29) by heating at 90 to 100 Deg.
Celsius actual temperature.
Heat the bearing inner race (item 3) at the temperature of 110 degree
Celsius, and shrink it on to the shaft tight against the flinger.
Fill the pocket of endshield with 600 gms. of grease and smear 15 gms.
of grease on labyrinth of endshield, bearing sleeve & bearing inner race.
Fit inner bearing cap (30)and fill pocket of IBC with 600 gms. Grease.
Grease outer race track with 20 gms. of grease, assembly rollers in
outer race. Press the bearing outer race and rollers (item 5) tight against the
housing of endshield (item 4).
Force 50 gms. of grease into the spaces between the rollers, cage &
outer race track at the back of the bearing.
Now, install the bearing roller guide (fig. 10 item 1) on to the shaft as
shown in the sketch to facilitate assembly of drop roller bearing.
Slide the endshield with the bearing in position on the shaft through the
bearing roller guide.
Remove the bearing roller guide from shaft.
Fill 300 gms. of grease in outer bearing cap & smear 30 gms. of grease
on labyrinth of outer bearing cap.
Assemble outer bearing cap on the endshield.
Fit the bearing retaining collar (item 7) on to the shaft by shrinking at
the temperature of 115 deg. Celsius (+20/-0 degree Celsius). When cold,
tap the bearing collar with light hammer & copper drift to ensure that it is
solidly butted against the bearing inner race.
After assembly of outer bearing cap to the endshield, secure them with
suitable bolts & lock washers (item 8).
Tighten the bolts at specified torque.
COMMUTATOR END:
Locking typeroller bearing is used on commutator end.
IB-571- 91
BRUSHGEAR
1. Lift the brushes and insert clean presspaper between the brush-
holders and commutator.
3. Remove the clamp bolt and clamp plate securing the brush
holder to the frame. On the top brush holder the clamp bolt is
accessible through the top commutator opening on the axle side
brush-holder it is accessible through the bottom axle side
inspection opening and on the bottom and nose side brush-
holders the bolts accessible through the bottom nose side
inspection opening.
BRUSH HOLDERS:
1. Remove the brush holders from the magnet frame and
thoroughly clean them.
3. Check the clearance between a new carbon brush and the brush
box. If the clearance is excessive discard the brush holder. If the
brushes are sticking recondition as necessary.
IB-571- 92
PTFE INSPECTION.
1. Brush holder support pins have been covered with PTFE
(polytertra fluoroethylene) insulators to facilitate periodic cleaning.
Clean the PTFE surface by wiping a clean dry cloth. Do not
paint the insulators or wash in water.
2. For fitting new insulator remove the defective insulator and clean the
surface to the support pin with fine glass paper to remove any
carbon deposits and surface i r r e g u l a r i t i e s .
NOTE:
Extreme care should be taken when heating PTFE, since at about 200
deg. Celsius PTFE starts to release colourless and odourless gases which
are poisonous. Do not burn scrap PTFE insulator or pieces. Take
precaution to protect personnel in areas where PTFE dust may be
produced by grinding or machining operations.
PROCEDURE:
As and when the motor comes to Diesel loco shed for POH or for
repair.
IB-571- 93
- Lift the spring and rest it onto the resting pin.
- Cut the other end of copper shunt with scissors knife keeping its
terminal rivetted with the spring.
PRECAUTION
Copper shunt is not required in case the spring is replaced by new one.
IB-571- 94
MOTOR SUSPENSION UNIT
IB-571- 95
IB-571- 96
IB-571- 97
- BEARING INFORMATION
Axle suspension tube:-
Roller bearings: Non-gear wheel side Gear wheel side
Manufacturer: TIMKEN TIMKEN
FAULT FINDING
IB-571- 98
MOTOR SUSPENSION UNIT FOR TM4907BZ
(SEE FIG. 12 & 13)
ITEM DESCRIPTION
1. ABUTMENT PIECE.
2. END COVER (ROAD WHEEL END).
3. BEARING HOUSING.
4. ADJUSTMENT WASHER.
5. TAPERED ROLLER BEARING ASSEMBLY.
6. GREASE NIPPLE.
7. TUBE.
8. TAPERED ROLLER BEARING ASSEMBLY.
9. ENCLOSURE.
10. END COVER (GEAR WHEEL END).
11. SOCKET HD.CAP SCREW M10x30LG.
12. SOCKET HD.CAP SCREW M12x90 LG.
13. SOCKET HD.CAP SCREW M12x70 LG.
14. BOLT.
15. SPRING WASHER.
MAINTENANCE PRACTICES
1 REMOVAL / INSTALLATION.
2 SERVICING
IB-571- 99
Non-gear wheel side Gear wheel side
3 ADJUSTMENT/CHECKING
IB-571- 100
TORQUE VALUE TABLE
Insulating Torque value in kg-cm
Bolt size Standard Maximum
OVERHAUL PROCEDURES
1. DISASSEMBLY
- To withdrawal the abutment piece (1), use the special Tools No.
1405573.
- Remove all securing bolt (13) and cover (2) from end of
suspension tube (7).
IB-571- 101
4 Removal of Adjusting Washer (4)
- Insert the chisel into clearances of joints and draw out the
adjusting washers (4).
Road wheel end bearing inner race (cone) can be pulled out
with the suspension tube (7).
8 Pull out the bearing cup (8) from the suspension tube (7) by
bearing puller as shown in Tool No. 1405576.
9 Dismantle the bearing housing (3) from the suspension tube (7)
as a shown in Tool No. 1405577.
10 Pull out the bearing cup (5) from the bearing housing (3) as
shown in Tool No. 1405578
IB-571- 102
CLEANING:
Dry with compressed air. When handling the bearing after the final
washing, make sure hands are cleaned with such degreasing
agent as ethyl alcohol to prevent the bearing from getting rusty.
- WIPING.
CHECKING:
- Inspect visually appearances of the axle suspension tube, the
covers and so on for damages or rust or cracks.
- Measurement of dimensions
IB-571- 103
a. Inner diameter of installation portions for bearing
d. Abutment piece
IB-571- 104
e. Dimensions of mounting flanges of axle suspension tube Fig.
14.
SYMBOL DIMENSION
H = 35 + 0.1 mm + 0 mm
REASSEMBLING
1. GENERAL INFORMATION
IB-571- 105
(b) ASSEMBLY METHODS
If drivers are not available, mild steel bars can be used. Use
only mild steel, not hardened drifts or brass bars. The
hardened bars will damage the bearing and brass will chip
easily. On no account should a copper or brass-faced hammer
be used during assembly of bearing parts.
(c) STORAGE
If the wheel sets are stored outside, the tube should be turned
so that the open portion is on the lower side and wedged in
position. The assembly should be covered with waterproof
sheets for further protection and again, the machined surfaces
should be coated with a suitable rust preventative.
(a) Fit the gear wheel in the correct position on the axle.
(b) Check that the face of the gear wheel is square to the axle
within 0.05 mm on the face adjacent to the gear wheel end
bearing. This can be done by putting the axle in a lathe
between centre and checking run-out with a dial indicator. If the
face runs out more than the prescribed 0.05 mm, correct this
by machining. FIG.-15.
After fitting the gear wheel, check the dimension of part of dia
320 +0.113/+0.051 and correct with specified tolerance by
machining. Fig.-15
(c) The axle should now be placed in a vertical position with the
gear wheel at the bottom with the enclosure (Item 9) in position
making sure that all enclosure grooves are free from dirt and
swarf. FIG.-16.
IB-571- 106
(d) Clean thoroughly the suspension tube (7), making sure that
all holes are free from dirt and swarf and tighten the bolt (Item 11) to
the gear wheel. Apply “THREE BOND screw lock super No.1303” or
loctite ‘270’ to bolt (IT.11). It numbers referred to in Fig.-12 & 13.
(f) Place the two bearing cone assemblies in a tank of oil or dry
oven heated to 120 deg. Celsius (See General
information Section )
(g) Stand the tube on end, gear wheel end uppermost and fit
the gear wheel and cup M249710 into the tube Item 7.
The cup is a tight fit in the tube (7) and should be fitted
IB-571- 107
as follows:
IB-571- 108
FTG. - 18
FIG. - 19
* that the bearing cup in fitted squarely, top the cup driver near to
the cover edge and around its circumference units the bearing
cup is correctly seated against the abutment shoulder.
* Check that the cup is fully seated against its abutment shoulder
IB-571- 109
using a feeler gauge of 0.05 mm thickness. The gauge must
not enter between the faces of the cup and abutment of the
tube (fig 18).
(h) Fit cup M349510 into the Bearing Housing (It.3) in a similar
manner.
(i) Thread the end cover(It.10) over the axle and place in position.
(j) Remove cone assembly M249747 from the heater and enter
squarely over the axle and into position against the gearwheel face.
Oil bath temperature of 120 deg. Celsius must be strictly
maintained.
NOTE : Ensure that the back-face (broad-face) of the cone is
against the gearwheel bearing face. Use a clean assembly sleeve
to tap down the cone as it cools, ensuring that the cone is properly
seated. Remove the sleeve when the cone is fully cooled fig.-20.
Check that the cone assembly is a abutted against the gear wheel.
Then apply grease by hand and press that grease to fill the inner
spaces within the cage of bearing, and ensure adequate grease to
bottom roller ends, take into consideration that total amount of
grease in filling tube and pump up in 1250 grammes into gear
wheel end bearing on completion of total assembly.
FIG. - 20
IB-571- 110
(k) With suitable lifting tackle, thread the suspension tube (Gear wheel
and leading) over the axle and position on the cone assembly
engaging the cover,(IT.10) on the tube FIG.- 21.
(l) Fit the eight cover bolts (IT.12) and torque to 418 Kg. Cm. Rotate
the tube to ensure that bearing rollers are correctly seated against
the cone thrust rib and also to ensure that there is no fouling of the
cover (It.10) and gear wheel.
(m) Fit the bearing Housing (IT.3) with cup M349510 fitted, into the
tube and fit the split master spacer.(It. 10).
(n) Remove bearing cone assembly M349547 from the heater and fit in
the correct position on the axle. Follow immediately with the
assembly sleeve (FIG.-21) as used previously. Do not tap down,
but rotate the tube as the cone cools, allow to fully cool and remove
the assembly sleeve.
Then apply grease by hand and press the grease to fill the inner
space within the cage of bearing and around the thrust face (i.e.
top ends) of the rollers. Take into the consideration that total
amount of grease in filling tube and pump up to 600 grms in to non
gear wheel end bearing on completion of total assembly.
FIG. - 21
(o) Fit the cover (Item 2) and cover bolts (Item 13) and tighten to clamp
the cup holder master spacer, and cover and tube together. Check
that no gap exists between the faces by use of a 0.05 mm gauge.
(p) Place the abutment piece (IT.1) into position against the back face
IB-571- 111
of cone assembly.
(q) Remove cover bolts (it.13) and with draw the two halves of the split
master spacer.
(r) Fit non gear wheel on to the axle. The inner face of the wheel must
contact the outer face of the abutment piece (it.1). Any inward
movement of the abutment piece due to fitting the wheel should be
restricted to a maximum of 3mm. If movement exceeds this, the
wheel should be removed. The bearing cone and abutment piece
should be withdrawn and refitted according to the assembly
procedure (K to P inclusive).
FIG. - 22
IB-571- 112
FIG. - 23
(t) Check the lateral play in the assembly according to the instructions
given under Reference ‘u’. If the measured end play is above 0.25,
then a thicker adjustment washer will be required.
EXAMPLE:
End play required 0.15 to 0.25 Aim 0.2
IB-571- 113
Master spacer thickness 11.000 mm
Measured end play 0.275 mm
Required end play (Aim) 0.2 mm
Actual thickness end play is less than 0.05 then a thinner adjustment
washer is required.
EXAMPLE:
Master spacer thickness 11.00 mm
Measured end play 0.02 mm
Required end play (Aim) 0.2 mm
Actual thickness of adjustment washer - 11 + (0.02 - 0.2) = 10.82
u) The end play in the final assembly must be checked before the
wheel set is released for service. Fix a Dial Indicator on to the tube
with the stem contacting the wheel. Using levers, apply even loads
to move the tube in one direction and then the opposite direction.
Note the readings from the dial indicator which should be between
0.15 mm and 0.25 mm. Any measurement outside this tolerance
must be corrected by applying a narrower or wide adjustment
washer as required.
FIG. - 24
IB-571- 114
v) Grease nipples (Item 6) may be fitted if standard push-on grease
connectors are used for lubrication, but it is easier for the initial
filling to be by an adaptor screwed into the tapped holes with the
grease nipples fitted afterwards.
w) Pump grease into the Non-gear wheel end bearing housing until a
witness of grease is visible around the enclosure (approximately
600g).
x) Fill the gearwheel end bearing housing with approximately 1.25 kg
of grease.
The tube should be oscillated whilst filling with grease to ensure an
even distribution around the bearing.
The lubricant used should be a approved No. 3 consistency lithium
soap based grease.
The assembly procedure for the motor suspension unit is now
complete.
The final operation to complete the wheel set assembly is to fit the
gear end non gear wheel (Fig.-23) to gauge.
(y) Disassembly and withdrawal procedure
Item numbers referred are those on as per fig.12. Unless otherwise
stated.
IB-571- 116
IB-571- 117