Sie sind auf Seite 1von 4

1995 381.

1 No Alat Referensi
1996 381.7 1 R-101 Towler
1997 386.5 2 V-101 Timmerhaus
1998 389.5 Chemical Engineering Plant Cost 3 V-102 Timmerhaus
1999 390.6700 4 T-101 Timmerhaus
2000 394.1 5 T-102 Timmerhaus
2001 394.3600 6 E-01 Towler
2002 395.6500 f(x) = 13.7610294118x - 27111.1889705879 7 E-02 Towler
R² = 0.8582212304
2003 402 8 E-03 Towler
2004 444.2400 9 E-04 Towler
2005 468.2300 10 E-05 Towler
2006 499.6 11 V-101 Timmerhaus
2007 525.4200 12 V-102 Timmerhaus
2008 575.4100 13 V-103 Timmerhaus
2009 521.9 14 V-104 Timmerhaus
2010 0
550.8 1994 15
1996 1998 2000 2002 2004 2006 2008 2010 2012 V-105 Timmerhaus
2011 585.7 16 V-106 Timmerhaus
17 V-107 Timmerhaus
18 P-01 Towler
19 P-02 Towler
20 P-03 Towler
21 P-04 Towler
22 P-05 Towler
23 P-06 Towler
24 P-07 Towler
25 P-08 Towler
26 P-09 Towler
27 P-10 Towler
28 P-11 Towler
29 P-12 Towler
30 P-13 Towler
31 P-14 Towler
32 P-15 Towler
33 P-16 Towler
34 CT-101 Towler
35 Generator Timmerhaus
36 Boiler Timmerhaus
37 Ion Exch Towler
Purch
tahun cost index index 2020 harga ref/unit harga 2020/unit Jumlah
2006 499.6 686.22 $ 109,546.784 $ 150,466.762 1
2002 395.6 686.22 $ 128,456.058 $ 222,823.853 1
2003 402 686.22 $ 133.506 $ 227.897 1
2006 499.6 686.22 $ 32,161.600 $ 44,175.206 1
2006 499.6 686.22 $ 46,178.500 $ 63,427.963 1
2006 499.6 686.22 $ 1,662.640 $ 2,283.701 1
2007 525.4 686.22 $ 3,497.219 $ 4,567.685 1
2006 499.6 686.22 $ 4,598.186 $ 6,315.787 1
2006 499.6 686.22 $ 5,321.529 $ 7,309.327 1
2006 499.6 686.22 $ 2,707.106 $ 3,718.315 1
2006 499.6 686.22 $ 142,478.000 $ 195,699.066 3
2006 499.6 686.22 $ 87,756.200 $ 120,536.548 4
2006 499.6 686.22 $ 155,675.000 $ 213,825.658 1
2006 499.6 686.22 $ 39,395.600 $ 54,111.386 4
2006 499.6 686.22 $ 1,139.610 $ 1,565.299 1
2006 499.6 686.22 $ 165,309.000 $ 227,058.331 3
2006 499.6 686.22 $ 25,755.000 $ 35,375.493 1
2006 499.6 686.22 $ 3,314.917 $ 4,553.167 2
2006 499.6 686.22 $ 3,327.906 $ 4,571.008 2
2006 499.6 686.22 $ 3,327.906 $ 4,571.008 2
2006 499.6 686.22 $ 3,348.763 $ 4,599.656 2
2006 499.6 686.22 $ 3,359.856 $ 4,614.893 2
2006 499.6 686.22 $ 3,354.307 $ 4,607.271 2
2006 499.6 686.22 $ 3,345.676 $ 4,595.416 2
2006 499.6 686.22 $ 3,355.286 $ 4,608.616 2
2006 499.6 686.22 $ 3,304.882 $ 4,539.384 2
2006 499.6 686.22 $ 3,304.882 $ 4,539.384 2
2006 499.6 686.22 $ 3,393.399 $ 4,660.965 2
2006 499.6 686.22 $ 3,335.545 $ 4,581.501 2
2006 499.6 686.22 $ 4,289.195 $ 5,891.376 2
2006 499.6 686.22 $ 3,720.762 $ 5,110.611 2
2006 499.6 686.22 $ 3,772.982 $ 5,182.337 2
2006 499.6 686.22 $ 3,307.493 $ 4,542.970 2
2006 499.6 686.22 $ 64,067.981 $ 87,999.860 1
2006 499.6 686.22 $ 87,166.421 $ 119,726.464 1
2006 499.6 686.22 $ 77.035 $ 105.811 1
2006 499.6 686.22 $ 18,485.817 $ 25,390.987 2
Purchased Equipment Cost (PEC)
total
$ 150,466.762 Purchased Equipment Cost (PEC)
$ 222,823.853 Equipment installation
$ 227.897 Piping
$ 44,175.206 Fluid 86%
$ 63,427.963 Instrumentation
$ 2,283.701 Extencive control 30%
$ 4,567.685 Electrical Auxilaries
$ 6,315.787 10 - 15 % PEC
$ 7,309.327 Insulation
$ 3,718.315 8% PEC
$ 587,097.197 Buidings
$ 482,146.193 30% PEC Outdoor contruction
$ 213,825.658 Land and Yard Improvement
$ 216,445.545 10 - 15% PEC
$ 1,565.299 Utilities
$ 681,174.992 Utilities average service : 40% PEC
$ 35,375.493 Physical Plant Cost (PPC)
$ 9,106.334 Engineering and Construction
$ 9,142.016 20% PPC
$ 9,142.016 Direct Plant Cost (DPC)
$ 9,199.312 Contractor fee
$ 9,229.785 10% DPC
$ 9,214.542 Contigency
$ 9,190.832 25% DPC
$ 9,217.231 Fixed Capital Investment (FCI)
$ 9,078.768
$ 9,078.768
$ 9,321.931
$ 9,163.001
$ 11,782.752
$ 10,221.222
$ 10,364.675
$ 9,085.940
$ 87,999.860
$ 119,726.464
$ 105.811
$ 50,781.975
$ 3,133,100.105
ment Cost (PEC) $ 3,133,100.105
43% $ 1,347,233.045
86% $ 2,694,466.090

30% $ 939,930.031

15% $ 469,965.016

8% $ 250,648.008

30% $ 939,930.031

11% $ 344,641.012

40% $ 1,253,240.042

$ 11,373,153.381
20% $ 2,274,630.676

$ 13,647,784.057
10% $ 1,364,778.406

25% $ 3,411,946.014

estment (FCI) $ 18,424,508.477