Stepping Stone Method

>>> This is a one of the methods used to determine optimality of


an initial basic feasible solution (i.e. Northwest Corner Rule, Least
Cost or Vogel’s Approximation)

>>> The method is derived from the analogy of crossing a pond


using stepping stones. This means that the entire transportation
table is assumed to be a pond and the occupied cells are the
stones needed to make certain movements within the pond.
Optimum Solution:
Stepping-Stone Method
Transportation Table
DESTINATIONS

1 2 3 4 SUPPLY

4 6 8 8
A 40
10 30

SOURCES 6 8 6 7
B 60
50 10

5 7 6 8
C 50
10 40

DEMAND 20 30 50 50 150

Z = 4x10+6x30+6x50+7x10+5x10+8x40 = 960
Optimum Solution:
Stepping-Stone Method
1. Starting at an unused/empty cell, trace a closed path or loop back
to the original cell via cells that are currently being used and/or
occupied.
Note: A closed path or loop is a sequence of cells in the
transportation table such that the first cell is unused/empty
and all the other cells are used/occupied with the following
conditions:
a. Each pair of consecutive used/occupied cells lies in either the
same row or column
b. No three consecutive used/occupied cells lie in the same row
or column
c. The first and last cells of a sequence lies in the same row or
column
d. No cell appears more than once in a sequence (i.e. no
duplication)
e. Only horizontal and vertical moves allowed and can only
change directions at used/occupied cells
Optimum Solution:
Stepping-Stone Method
Example: At Cell A3, A3->B3->B4->C4->C1->A1->A3

DESTINATIONS

1 2 3 4 SUPPLY

4 6 8 8
A 40
10 30
SOURCES
6 8 6 7
B 60
50 10

5 7 6 8
C 50
10 40

DEMAND 20 30 50 50 150
Optimum Solution:
Stepping-Stone Method
Example: At Cell A4, A4->C4->C1->A1->A4

DESTINATIONS

1 2 3 4 SUPPLY

4 6 8 8
A 40
10 30
SOURCES

6 8 6 7
B 60
50 10

5 7 6 8
C 50
10 40

DEMAND 20 30 50 50 150
Optimum Solution:
Stepping-Stone Method
Example: At Cell B1, B1->B4->C4->C1->B1

DESTINATIONS

1 2 3 4 SUPPLY

4 6 8 8
A 40
SOURCES 10 30

6 8 6 7
B 60
50 10

5 7 6 8
C 50
10 40

DEMAND 20 30 50 50 150
Optimum Solution:
Stepping-Stone Method
Example: At Cell B2, B2->B4->C4->C1->A1->A2->B2

DESTINATIONS

1 2 3 4 SUPPLY

4 6 8 8
A 40
10 30
SOURCES
6 8 6 7
B 60
50 10

5 7 6 8
C 50
10 40

DEMAND 20 30 50 50 150
Optimum Solution:
Stepping-Stone Method
Example: At Cell C2, C2->C1->A1->A2->C2

DESTINATIONS

1 2 3 4 SUPPLY

4 6 8 8
A 40
10 30
SOURCES
6 8 6 7
B 60
50 10

5 7 6 8
C 50
10 40

DEMAND 20 30 50 50 150
Optimum Solution:
Stepping-Stone Method
Example: At Cell C3, C3->B3->B4->C4->C3

DESTINATIONS

1 2 3 4 SUPPLY

4 6 8 8
A 40
10 30
SOURCES
6 8 6 7
B 60
50 10

5 7 6 8
C 50
10 40

DEMAND 20 30 50 50 150
Optimum Solution:
Stepping-Stone Method
2. For every traced path or loop, begin with a plus (+) sign at the
starting unused cell and alternately place a minus (-) and plus (+)
sign at each used cell
Example: At Cell A3, A3->B3->B4->C4->C1->A1->A3

DESTINATIONS

1 2 3 4 SUPPLY
-
A
4 6 8 + 8
40
10 30

6 8 6 - 7
SOURCES B 60

+
50 10

5 7 6 8
+

C - 50
10 40

DEMAND 20 30 50 50 150
Optimum Solution:
Stepping-Stone Method
3. Calculate an Improvement Index by first adding the unit-cost
figures found in each cell containing a plus sign and subtracting
the unit costs in each square containing a minus sign.
Example: At Cell A3, A3->B3->B4->C4->C1->A1->A3
DESTINATIONS

1 2 3 4 SUPPLY
-
A
-4
4 6 88 + 8
40
10 30

6 8 -6
6 - +7
7
SOURCES B 60

+
50 10

+5
5 7 6 -8
8
+

C
10 40
- 50

DEMAND 20 30 50 50 150
IA3 = =2
Optimum Solution:
Stepping-Stone Method

Iteration #1 - Computing for the Improvement Index:


At A3, A3->B3->B4->C4->C1->A1; IA3 = +8-6+7-8+5-4 = 2
At A4, A4->C4->C1->A1; IA4 = +8-8+5-4 = 1
At B1, B1->B4->C4->C1; IB1 = +6-7-8-5 = 2
At B2, B2->B4->C4->C1->A1->A2; IB2 = +8-7+8-5+4-6 = 2
At C2, Loop C2->C1->A1->A2; IC2 = +7-5+4-6 = 0
At C3, C3->B3->B4->C4; IC3 = +6-6+7-8 = -1

4. If all indices calculated are greater than or equal to zero, then,


an optimal solution had been reached. If not, select the
path/loop that has the most negative value and use this to
further improve the solution.
Note: Should there be two or more “most” negative values,
select arbitrarily.
Optimum Solution:
Stepping-Stone Method
Example: At Cell C3, C3->B3->B4->C4 IC3 = +6-6+7-8 = -1

DESTINATIONS

1 2 3 4 SUPPLY

4 6 8 8
A 40
10 30
SOURCES

B
6 8 6 - 7
+ 60
50 10

+
C
5

10
7 6 8

40
- 50

DEMAND 20 30 50 50 150
Optimum Solution:
Stepping-Stone Method
To further improve the current solution, select the “smallest” number found
in the path/loop C3->B3->B4->C4 containing minus(-) signs. This number is
added to all cells on the closed path/loop with plus(+) signs and subtracted
from all cells on the path assigned with minus(-) signs.

DESTINATIONS

1 2 3 4 SUPPLY

4 6 8 8
A 40
10 30
SOURCES

B
6 8 6 -
5050- 40
7

10 10
+
+ 40
60

+
C
5

10
7 6

40
8
-
4040- 40
50

DEMAND 20 30 50 50 150
Optimum Solution:
Stepping-Stone Method
5. Then, we have a new basic feasible solution…
DESTINATIONS

1 2 3 4 SUPPLY

4 6 8 8
A 40
10 30
SOURCES
6 8 6 7
B 60
10 50

5 7 6 8
C 50
10 40

DEMAND 20 30 50 50 150

…and repeat steps 1 though 4 to calculate an Improvement Index for


all unused squares in order to test whether an optimal solution has
been reached.
Optimum Solution:
Stepping-Stone Method

Iteration #2 - Computing for the Improvement Index:


At A3, A3->C3->C1->A1; IA3 = +8-6+5-4 = 3
At A4, A4->B4->B3->C3->C1->A1; IA4 = +8-7+6-6+5-4 = 2
At B1, B1->B3->C3->C1; IB1 = +6-6+6-5 = 1
At B2, B2->B3->C3->C1->A1->A2; IB2 = +8-6+6-5+4-6 = 1
At C2, C2->C1->A1->A2; IC2 = +7-5+4-6 = 0
At C4, C3->B3->B4; IC3 = +8-6+6-7 = 1

Since the results of all indices calculated are greater than or equal to
zero, then, an optimal solution had been reached.
Optimum Solution:
Stepping-Stone Method
…and computing the objective function Z:

DESTINATIONS

1 2 3 4 SUPPLY

4 6 8 8
A 40
10 30

SOURCES 6 8 6 7
B 60
10 50

5 7 6 8
C 50
10 40

DEMAND 20 30 50 50 150

Z = 4x10+6x30+6x10+7x50+5x10+6x40 = 920
Optimum Solution:
Stepping-Stone Method
However, in checking the calculation in Iteration #2, there is an
improvement index equal to zero. This means that there is an
ALTERNATE optimum solution:

In Iteration #2 :
At A3, A3->C3->C1->A1; IA3 = +8-6+5-4 = 3
At A4, A4->B4->B3->C3->C1->A1; IA4 = +8-7+6-6+5-4 = 2
At B1, B1->B3->C3->C1; IB1 = +6-6+6-5 = 1
At B2, B2->B3->C3->C1->A1->A2; IB2 = +8-6+6-5+4-6 = 1
At C2, C2->C1->A1->A2; IC2 = +7-5+4-6 = 0
At C4, C3->B3->B4; IC3 = +8-6+6-7 = 1
Optimum Solution:
Stepping-Stone Method
To calculate for the alternate optimum solution, again select the “smallest”
number found in this path/loop containing minus(-) signs. This number is
added to all cells on the closed path/loop with plus(+) signs and subtracted
from all cells on the path assigned with minus(-) signs.

Hence, at C2->C1->A1->A2, DESTINATIONS

1 2 3 4 SUPPLY

A
4
+
1010
+ 10
6

3030- 10
- 8 8
40

SOURCES
6 8 6 7
B 60
10 50

C
5
-
1010- 10
7

10
+ 6

40
8
50

DEMAND 20 30 50 50 150
Optimum Solution:
Stepping-Stone Method
Then the alternate optimum solution with objective function Z:

DESTINATIONS

1 2 3 4 SUPPLY

4 6 8 8
A 40
20 20

SOURCES 6 8 6 7
B 60
10 50

5 7 6 8
C 50
10 40

DEMAND 20 30 50 50 150

Z = 4x20+6x20+6x10+7x50+7x10+6x40 = 920
Optimum Solution:
Stepping-Stone Method
DEGENERACY
When the number of empty/occupied cells in any solution (either
initial or later) of the transportation table is not equal to the number
of rows plus the number of columns minus 1 (i.e. m+n-1) the
solution is called DEGENERATE
Example: m + n -1 = 3 + 4 -1 = 6
DESTINATIONS

1 2 3 4 SUPPLY
4 6 8 8
A 40
SOURCES
20 20
6 8 6 7
B 60
10 50
5 7 6 8
C 50
50
DEMAND 20 30 50 50 150
Optimum Solution:
Stepping-Stone Method
DEGENERACY
To handle degenerate problems, artificially create an occupied cell by
placing a zero (representing a fake shipment) in one of the unused
cells. Treating this cell as if it were occupied, it must be chosen in such
a position as to allow all stepping-stone paths to be traced. Then, all
stepping-stone paths can be closed and improvement indices
computed.
Example: DESTINATIONS

1 2 3 4 SUPPLY
4 6 8 8
A 40
20 20
SOURCES
6 8 6 7
B 60
10 50 0
5 7 6 8
C 50
50
DEMAND 20 30 50 50 150
Optimum Solution:
Stepping-Stone Method

QUESTIONS?
DIOS MABALOS PO!
Cam on !
Shukriya !
ありがとうございます!
Thank you!
Merci!
Gracias!
Obrigado!
謝謝!

Das könnte Ihnen auch gefallen