Beruflich Dokumente
Kultur Dokumente
Thomas Overbye,
Re-engineering the Electric Grid, American Scientist, 2000, Vol. 88, Iss. 3.
Bulk Power Systems
Indian Power System : Among the Largest in the World
National Grid (UK)
PJM (USA) 68GW SO - UPS (Russia)
165GW 146 GW
RTE (France)
93GW
Tepco (Japan)
64GW
By 2027: ~575 GW
NEW
grid Thermal 65%
Hydro 21 %
South Nuclear 3%
grid
Renewable 11 %
Central Grid
MERGING
OF
MARKETS
North
East
West
Northeast
South
Installed Capacity: ~ 180 GW
Inter – Regional
Capacity:
Five Regional Grids 22 GW
By 2027: ~575 GW
Five Frequencies
Synchronous Links
Synchronous Grid:
Synchronous machines interconnected with
AC lines
Power Flow in AC lines - function of Voltage
phase Angle Difference (determined by the
relative rotor position in synchronous
machines)
Frequency throughout grid is the same
Asynchronous Links
Asynchronous Interconnects
HVDC links: Power flows not a function of
Phase Angle Difference
Frequencies of connected regions could
“happily” be different
Lack of Synchronism in AC ties
Not Acceptable !
Distance Relays trip
Uncontrolled
System Separation
Synchronous Links
(AC)
(PGEN1-PLOAD1) - (PGEN2-PLOAD2) = P1 + P2
(PGEN1-PLOAD1) - (PGEN2-PLOAD2) = P1 + P2
(1500 MW)
1. Rihand – Dadri
2. Chandrapur – Padge
1. Talcher – Kolar
1. Balia - Bhiwadi
BACK To BACK
1. Vindhyachal
1. Bhadravati
2. Gazuwaka
1. Sasaram
The Indian Grid
Major
Load
Centres
Cheap Thermal
31 State HQ
Nos. Level SLDC
Group of
51 District
Nos. Level SUB LDC
1649 Plant/Sub
Nos. Station RTU
Level
Dynamics in a Synchronous Grid
FL1 Fg1
FL3 Fg3 FL2 Fg2
Uncontrolled
Controlled separation
Islanding
(Mumbai)
Large Power Swing / Loss of Synchronism
Va
Ia
Vb
Ib
Vc
Ic
Courtesy:
Western Regional Power Committee, Mumbai
30th July 2012
2:33:11:9 hours
~02.34 hrs
MP antecedent trippings
overload
00.20 hrs
Hand tripped
00.10 hrs
overload
00.10 hrs
overload
2710 MW 1192 MW Bhutan
2650 MW 3123 MW
-33 MW
95 MW
-278 MW
2654 MW
DR of Bina-Gwalior
Normal
V1 ZL V2
V1 Z
I
Voltage at fault point is ~zero
V1 will be equal to Z
I
Relay setting to detects fault on this line V1 < ZL ; immediate trip
I
(Zone 1)
(Zone 1)
First Conclusion
The critical event leading to large angular
separation was Gwalior-Bina 400 kV trip
From DR, PMU, WAFMS : Tripping time is
established to be 2:33:11:9
Trip was NOT on fault.
Zone3 tripping (back-up protection)
“Load encroachment”
x
Event at RKL-JMSHDP-I (Rourkela end tripped)
DR time at Jamshedpur end was incorrect
Ckt-II trip
Zone-1 trippings at ~2:33:15, due to large angular
separation ---- NR becomes an island
Balia-Biharsharif
Balia-Patna
Grkpr-Muzzpr.
Zone -1 tripping (Gorakhpur-Muzaffarpur)
System separation at
this point.
13:00:13 hours
1170 MW 850 MW
2400 MW 2044 MW
-21 MW
150 MW
73 MW
1822 MW
894 MW
830 MW 900 MW
830 MW
Gwalior Bina
Event
System separation
31.07.2012
Bina-Gwalior-I
Gwal-Bina
Trippings at around ~13:00:15
Trippings at around ~13:00:18 – Large Swings: This is
the tipping point
WR system separation (PS trippings): Cut-Set are the
lines emanating from Rourkela
Separation Cut Set
Courtesy : POSOCO
Observations
Subsequent Over-voltage trippings in WR
GENERATOR
TRIPPING
In WR
Concluding Thoughts about the Blackout
Back to Basics
Technology: