CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.

193
C.A.NO.08/CIDCO/SE(Ulwe)/EE(Ulwe-II)/2010-11

Name of Work : Construction of 20.0 m. wide road in Sector – 16 under 12.5%


scheme around Shelghar Village at Ulwe Node, Navi Mumbai.

SCHEDULE “A”
BILL OF QUANTITIES
Part - I : Construction of Road
I. NO. DESCRIPTION QTY. RATE PER AMOUNT
1. Excavation for roadways in all 1400.00 99.70 Cum. 1,39,580.00
types of soil, soft murum,
hard murum, hard murum
with boulders, in all conditions
and nature, including clearing
and stripping of the area,
removal of vegetation, shrubs,
taking spot levels, excavating to
required depth, line, level and
slope, leveling, dressing and
consolidating the excavated
surface, dewatering by all
means upto any extent of water
accumulated from any source,
sorting out and stacking
serviceable and unserviceable
materials etc. complete
including conveying the
excavated material with all lifts
and upto a lead of 50 mtr. & its
spreading or stacking as
directed, etc. complete.
Note : All payments towards
the royalty, fees, taxes etc. shall
be borne by the contractor.

2. Excavation in soft rock for 1900.00 232.00 Cum. 4,40,800.00


general site grading below
ground level in all conditions
and nature, including clearing
CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.194
C.A.NO.08/CIDCO/SE(Ulwe)/EE(Ulwe-II)/2010-11

I. NO. DESCRIPTION QTY. RATE PER AMOUNT


and stripping of the area,
removal of vegetation, shrubs,
taking spot levels, excavating to
required depth, line, level and
slope, leveling and dressing and
consolidating the excavated
surface, dewatering by all
means upto any extent of water
accumulated from any source,
sorting out and stacking
serviceable and unserviceable
materials etc. complete
including conveying the
excavated material with all lifts
and upto a lead of 50 mtr & its
spreading or stacking as
directed, etc. complete.
Note : All payments towards
the royalty, fees, taxes etc. shall
be borne by the Contractor.

3. Excavation for roadway in 3900.00 553.00 Cum. 21,56,700.00


hard rock/ manjra rock by
wedging, chiseling or line
drilling including dressing,
sectioning to the required
grade, camber and side slopes
and conveying the excavated
material with all lifts and lead,
including boulders upto 5 cum
and stacking etc. complete.
Notes :
1) All payments towards the
royalty, fees, taxes etc. shall
be borne by the Contractor.
2) The excavated rock should
be Contractor’s Property.
CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.195
C.A.NO.08/CIDCO/SE(Ulwe)/EE(Ulwe-II)/2010-11

I. NO. DESCRIPTION QTY. RATE PER AMOUNT


4. Providing earthwork in 250.00 237.10 Cum. 59,275.00
embankment with approved
materials obtained from
Contractors own source
including all leads and lifts,
laying in layers of 20 to 30cms
in thickness, breaking clods,
dressing to the required lines,
curves, grades, and section
with watering and compacting
with vibratory power rollers
etc. complete.
Notes :
1. All payments towards the
royalty, fees, taxes etc. shall
be borne by the contractor.
2. The Environmental cess
shall be recovered at
Rs.1/m3 of gross volume
computed without
deductions as mentioned
for the monthly payments
or final payment.
3. P.D. Tests shall be carried
out @ one test comprising
of 3 specimens average
result per 1000 m2 area.
4. Compaction upto 95%
Modified P.D. and the
laboratory soil dry density
shall be not less than 1.6
g/cc. at optimum moisture
content.
5. The gross volume of the
embankment shall reduced
by 5% for monthly
payments and 1% for final
payment.
CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.196
C.A.NO.08/CIDCO/SE(Ulwe)/EE(Ulwe-II)/2010-11

I. NO. DESCRIPTION QTY. RATE PER AMOUNT


5. Providing earthwork in 900.00 237.45 Cum. 2,13,705.00
embankment with approved
materials obtained from
Contractors own source
including all leads and lifts,
laying in layers of 20 to 30cms
in thickness, breaking clods,
dressing to the required lines,
curves, grades, and section
with watering and compacting
with vibratory power rollers
etc. complete.
Notes :
1. All payments towards the
royalty, fees, taxes etc. shall
be borne by the contractor.
2. The Environmental cess
shall be recovered at
Rs.1/m3 of gross volume
computed without
deductions as mentioned for
the monthly payments or
final payment.
3. P.D. Tests shall be carried
out @ one test comprising
of 3 specimens average
result per 1000 m2 area.
4. Compaction upto 97%
Modified P.D. and the
laboratory soil dry density
shall be not less than 1.75
g/cc. at optimum moisture
content.
5. The gross volume of the
embankment shall reduced
by 5% for monthly
payments and 1% for final
payment.
CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.197
C.A.NO.08/CIDCO/SE(Ulwe)/EE(Ulwe-II)/2010-11

I. NO. DESCRIPTION QTY. RATE PER AMOUNT


6. Providing & laying granular
sub-base (GSB) as per clause
401 of M.O.R.T.&H (2001)
specifications of specified
grading (Table 400-1 or 400-2)
in specified thickness in layers.
The item to include premixing
the materials in plant,
transportation to site, spreading
in uniform layers with motor
grader on a prepared subgrade,
compacting with vibratory
rollers till 98% of the
maximum dry density (IS 2720
part-8) is achieved etc.
Complete. The rate includes
for tests on completion of each
GSB layer. The strength of
each GSB layer shall be
evaluated by conducting CBR
(IS 2720 Part 16 & 31) or Plate
load test using 750mm dia.
Plate, (IS 9214) for obtaining
equivalent CBR value @ one
test per 3000 m2 compacted
surface area as per the
Grading. The item includes for
all necessary material, labour,
diversions, taxes, royalty, cess
etc. complete.

a) For Grading-III of coarse- 270.00 758.80 Cum. 2,04,876.00


graded GSB material with
minimum CBR value of
20% to be obtained on top
of the compacted layer.
(Lower sub-base).
CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.198
C.A.NO.08/CIDCO/SE(Ulwe)/EE(Ulwe-II)/2010-11

I. NO. DESCRIPTION QTY. RATE PER AMOUNT


b) For Grading-II of coarse- 170.00 781.90 Cum. 1,32,923.00
graded GSB material with
minimum CBR value of
25% (As per IS 9214-1979)
to be obtained on top of the
compacted layer
(Intermediate sub-base)

c) For Grading-I of coarse- 130.00 801.10 Cum. 1,04,143.00


graded GSB material with
minimum CBR value of
30% (As per IS 9214-1979)
to be obtained on top of the
compacted layer. (Upper
sub-base)

7. Providing & laying granular 280.00 1,047.10 Cum. 2,93,188.00


base of wet mix macadam
(WMM) as per clause 406 of
M.O.R.T.&H (2001)
specifications of specified
grading (Table 400-11) in
specified thickness in layers.
The item to include premixing
the materials in plant,
transportation to site, spreading
in uniform layers with paver on
a prepared sub-base,
compacting with vibratory
rollers till 98% of the
maximum dry density (IS 2720
Part-8) is achieved etc
complete. The rate includes for
tests on completion of each
WMM layer. The strength of
each WMM layer shall be
evaluated by Plate load test
with 750 mm dia plate. (IS
CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.199
C.A.NO.08/CIDCO/SE(Ulwe)/EE(Ulwe-II)/2010-11

I. NO. DESCRIPTION QTY. RATE PER AMOUNT


9214) for obtaining equivalent
CBR value @ one test per
3000 m2 compacted surface
area as per the Grading. The
item includes for all necessary
material, labour, diversions,
taxes, royalty, cess etc.
complete.

8. Providing and applying low 1320.00 28.95 Sqm. 38,214.00


viscosity liquid bituminous
material such as bitumen
emulsion or cut back or road
tar complying to relevant
IRC/IS code of approved type
and grade by a self propelled
or towed bitumen pressure
sprayer as per clause No. 502
of Specifications for road and
bridge works (M.O.R.T.&
H.,2001). The item includes for
preparation of the base,
application of the prime coat,
curing, relevant tests for
quality control as enumerated
in table 900-4, diversion of
traffic, etc. complete. The rate
shall include for all labour,
materials, machinery,
transportation, taxes etc.
complete.
For low porosity surfaces
such as WMM/WBM at an
application rate of 0.6 to 0.9
kg/sqm. with kinematic
viscosity of primer at 60
degree ranges between 30-60
centistokes.
CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.200
C.A.NO.08/CIDCO/SE(Ulwe)/EE(Ulwe-II)/2010-11

I. NO. DESCRIPTION QTY. RATE PER AMOUNT


9. Providing and applying
bituminous tack coat @------
by manual/mechanical sprayer
including supplying all
materials, preparing the
existing surface, heating
bitumen and applying tack coat
evenly on the surface etc.
complete (using 60/70 grade
bitumen) the rate is inclusive
of all taxes.

a) @ 50kg/ 100 m2 over B.T. 3500.00 19.15 Sqm. 67,025.00


surface.
b) @ 100kg/100 m2 over 1320.00 35.25 Sqm. 46,530.00
WBM surface.

10. Providing and constructing 1320.00 168.60 Sqm. 2,22,552.00


Bituminous Bound Macadam
(BBM) surface 75 mm
thickness including supplying
all materials including metal,
bitumen etc. spreading 40 mm
hand broken trap metal 9 cum
per 100 m2 and 20 mm trap
metal at the rate of 1.5
cum/100 sqm., heating and
spreading bitumen (excluding
tack coat) at 250 kg./100 m2,
spreading 12 mm size key
aggregate at the rate of 1.8
cum/100 sqm and compaction
with vibratory roller complete.
Grade of bitumen shall be
60/70.
On WBM/WMM surface
including existing surface.
Excluding tack coat.
CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.201
C.A.NO.08/CIDCO/SE(Ulwe)/EE(Ulwe-II)/2010-11

I. NO. DESCRIPTION QTY. RATE PER AMOUNT


Note : Item also includes
cleaning the road surface with
wire brush/brooms and make it
free from dust and water before
applying/spreading tack coat.
The tack coat shall be paid
separately.

11. Providing & laying in situ dry 80.00 1,983.00 Cum. 1,58,640.00
lean cement concrete sub base
of trap metal of specified
gradation using mixing as per
approved mix design,
compacting with vibratory
roller of minimum 80 - 100
KN static weight to give
desired compacted density,
providing construction joints
and curing with liquid curing
compound & sprinkling water,
and covering with moist
Hessian or ponding of water
for seven days including all
labours, machinery with all
lifts & leads, bailling out water
manually & formwork etc
complete (using M-10
concrete)

12. Providing & laying in situ dry 80.00 2,335.00 Cum. 1,86,800.00
lean cement concrete sub base
of trap metal of specified
gradation using mixing as per
approved mix design,
compacting with vibratory
roller of minimum 80-100 KN
static weight to give desired
compacted density, providing
CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.202
C.A.NO.08/CIDCO/SE(Ulwe)/EE(Ulwe-II)/2010-11

I. NO. DESCRIPTION QTY. RATE PER AMOUNT


construction joints and curing
with liquid curing compound
& sprinkling water, and
covering with moist Hessian or
ponding of water for seven
days including all labours,
machinery with all lifts &
leads, bailing out water
manually & formwork etc
complete (using M-15
concrete)

13. Providing & laying crack 40.00 2,920.48 Cum. 1,16,819.20


relief layer of required
thickness with 20 to 30 %
interconnecting air voids with
binder content ranging 2.5% to
4% by weight of total mix.
Coarse and fine aggregate shall
confirm to clause 507.2.2,
507.2.3 of M.O.R.T. & H.
specifications and mineral
filler shall be as per clause
507.2.4. The job mix formula
and composition of crack relief
layer shall be as per the
particular specifications. The
binder to be used for those
work shall be PMB 40 (seal
oflex) of M/s Ooms Avenhorn.
the item also includes all
materials, labour required for
completion of the item
including laying by sensor
paver finisher, compacting
with power roller of 8 to 10
tonnes including
transportation, using PMB-40
manufactured by conversion of
CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.203
C.A.NO.08/CIDCO/SE(Ulwe)/EE(Ulwe-II)/2010-11

I. NO. DESCRIPTION QTY. RATE PER AMOUNT


60/70 grade bitumen with
modifier with SBS polymer
and stabilizers in appropriate
dose in manufacture's plant,
necessary test etc complete
(excluding tack coat). The rate
is inclusive of all types of
taxes.

14. Providing and laying hot mix 140.00 4,860.25 Cum. 6,80,435.00
hot laid Dense Graded
Bituminous Macadam
(DBM) of required thickness
with minimum 4.5% bitumen
by weight of total mix/
depending on job mix formula
& as per clause 507 of
MORTH (2001) specification
for road & bridges including
diversion of traffic, supply of
all materials, heating bitumen
and chips, mixing bitumen and
chips with necessary filler
material in batch type or
continuous type or drum mix
type hot mix plant, laying
dense bituminous macadam by
paver finisher including
compaction with vibratory
roller etc. complete (excluding
tack coat). The grade of
bitumen shall be 60/70. The
rate is inclusive of all types of
taxes.

15. Providing and laying hot mix 90.00 5,589.80 Cum. 5,03,082.00
hot laid Asphaltic Concrete/
bituminous concrete (AC/
BC) with bitumen minimum
CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.204
C.A.NO.08/CIDCO/SE(Ulwe)/EE(Ulwe-II)/2010-11

I. NO. DESCRIPTION QTY. RATE PER AMOUNT


6.25% by weight of total mix
as per job mix formula as per
clause 509 of MORTH (2001)
specification for road &
bridges including supplying all
materials, heating bitumen and
chips with necessary filler
material mixing bitumen and
chips in hot mix plant laying
asphaltic concrete with sensor
paver finisher including
compaction with vibratory
roller etc. complete (excluding
tack coat). The grade of
bitumen shall be 60/70. The
rate is inclusive of all types of
taxes. The job mix formula
shall be conducted as per
frequency specified by
M.O.R.T. & H.

16. Disposal of surplus excavated 3200.00 66.80 Cum. 2,13,760.00


materials upto 2.0 km. lead
and all lifts including loading,
unloading, stacking and
spreading as directed by
Engineer etc. complete beyond
initial lead of 50 m.
Total of Part – I Rs. 59,79,047.20

Total Carried over to Summary of Schedule “A” on Sl.Pg.No.207

__________________ _____________________________
Signature of Tenderer Additional Chief Engineer (I&NT)
Date: Date:
CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.205
C.A.NO.08/CIDCO/SE(Ulwe)/EE(Ulwe-II)/2010-11

Name of Work : Construction of 20.0 m. wide road in Sector – 16 under 12.5%


scheme around Shelghar Village at Ulwe Node, Navi Mumbai.

SCHEDULE “A”
BILL OF QUANTITIES
Part - II : Construction of Kutcha Drain & P/L RCC Pipes
I. NO. DESCRIPTION QTY. RATE PER AMOUNT
1. Excavation for roadway in 870.00 553.00 Cum. 4,81,110.00
hard rock/ manjra rock by
wedging, chiseling or line
drilling including dressing,
sectioning to the required
grade, camber and side slopes
and conveying the excavated
material with all lifts and lead,
including boulders upto 5 cum
and stacking etc. complete.
Notes :
1) All payments towards the
royalty, fees, taxes etc.
shall be borne by the
Contractor.
2) The excavated rock should
be Contractor’s Property.

2. Providing and laying in situ 20.00 3,658.00 Cum. 73,160.00


cement concrete M-20 grade
using design mix with
minimum cement content as
per IS 456 with maximum
water cement ratio 0.45 using
maximum 25 mm size and
down trap metal for
foundation and bedding with
all labours, materials, plant &
equipments, shuttering form
work, staging, including
CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.206
C.A.NO.08/CIDCO/SE(Ulwe)/EE(Ulwe-II)/2010-11

I. NO. DESCRIPTION QTY. RATE PER AMOUNT


transporting, placing, vibrating
with mechanical vibrator,
finishing and curing etc.
complete.

3. Providing lowering, laying 75.00 2,698.00 Rmt. 2,02,350.00


and jointing RCC, S/S pipes
manufactured as per IS:458
(latest version) having ISI of
600 dia NP3 class with
rubber ring joints as directed
in proper grade including cost
of materials, rubber rings, all
taxes (central and local)
transportation, loading and
unloading and hydraulic
testing as per I.S. 458 (latest
version) including necessary
heavy dewatering by all
means up to any extent etc.
complete.
Note : The contractor has to
make his own arrangement for
testing the pipeline as per I.S.
standard.

Total of Part – II Rs. 7,56,620.00

Total Carried over to Summary of Schedule “A” on Sl.Pg.No.207

__________________ _____________________________
Signature of Tenderer Additional Chief Engineer (I&NT)
Date: Date:
CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.207
C.A.NO.08/CIDCO/SE(Ulwe)/EE(Ulwe-II)/2010-11

Name of Work : Construction of 20.0 m. wide road in Sector – 16 under 12.5%


scheme around Shelghar Village at Ulwe Node, Navi Mumbai.

SUMMARY OF SCHEDULE “A”


PART PARTICULARS TOTAL AMOUNT
NO. B/F FROM
SL.PG.NO.
Part-I Construction of Road 204 59,79,047.20
Part-II Construction of Kutcha Drain & P/L 206 7,56,620.00
RCC Pipes
A) Total of Schedule “A” Rs. 67,35,667.20
B) ADD/SUBSTRACT (+/-) _____% quoted by Rs.
the Contractor to reflect the total cost.
C) GRAND TOTAL (A) +/- (B) Rs.

__________________ _____________________________
Signature of Tenderer Additional Chief Engineer (I&NT)
Date: Date: