Six Sigma Project

Structured Project Guide


Project Name Reducing the Distance Piece Rejecton Rate after Grinding

Tool Purpose Guide to follow a structured approach to complete a Six Sigma project

Task
Stage Task Tool Target Date Status Comments
no

1 Identify the Project


Project Summary

2 Identify the Champion, Sponsors


Project Summary
Champion and Green Belt to identify team players and
3
define Roles & Responsibilities Project Summary
Develop "Draft Project Charter" & get reviewed by Black
4
Belt
Project Charter

Explain Project Charter to all the team members and


TOLLGATE 1 - DEFINE

5 1st Project Meeting


review/revise charter

6 Present Project Charter to PI-II project sponsors Activity

7 Fine tune the Project Charter Project Charter

Obtain the Project Charter approval - Department Manager,


8
Department VP, Finance (??)
Project Charter

9 Create initial KPOV Chart KPOV Chart

Create shared folder for project documentation and assign


10
minutes of meeting (MOM) responsibilities
MOM

11 Create Communication Matrix Communication Matrix


.
Create mock Dashboard, update responsibility and display Dashboard - Poster
12
the Dashboard at the Champion / Leader office Board

13 Update MOM MOM

14 Obtain tollgate 1 approval from Champion and Black Belt Structured Project Guide

WBH PI-II
1/33 Structured Project Guide (SPG) Version 1.0
Six Sigma Structured Guide
Six Sigma Project
Structured Project Guide
Project Name Reducing the Distance Piece Rejecton Rate after Grinding

Tool Purpose Guide to follow a structured approach to complete a Six Sigma project

Task
Stage Task Tool Target Date Status Comments
no

1 Develop Process Map – recommend “SIPOC” Chart SPIOC Chart


Tollgate 2 - DEFINE

2 Prepare the KPOV & KPIV Map KPOV KPIV Map

Develop the Effort/Elapsed time chart Effort/Elapsed Time


3
(Mandatory for cycle time related projects) Chart

4 Finalize and update KPOV Chart KPOV Chart

5 Update Communication Matrix, MOM and Dashboard Various

6 Obtain tollgate 2 approval from Champion and Black Belt Structured Project Guide

Prepare the PMC (Process Measurement Chart) for the


1
KPOVs that need to be analyzed and monitored
PMC Chart
Tollgate 3 - MEASURE

Deveop the data collection templates as mentioned in PMC


2 Various templates
(Ensure the adequacy and appropriateness)

3 Collect data as per PMC in the templates developed Activity

Decide relevant charts to be prepared (based on data type)


4 Activity
for further analysis and launch periodic reports
Calculate "Baseline Sigma” to understand the current
5
process capability
Baseline Sigma Chart

Revisit Project Charter and update if required


6 Activity
Keep all versions of the charters for future references.

7 Update Communication Matrix, MOM and Dashboard Activity

8 Obtain tollgate 3 approval from Champion and Black Belt Structured Project Guide

Prepare the appropriate control charts for variability Control Chart Control Chart templates are available on Beaumont University page on Inside
1
identification templates Beaumont
Tollgate 4 -
ANALYZE

Perform Variability Analysis (Instability, Off target, Variation)


2 Activity
using control charts and Process Capability

3 Update Communication Matrix, MOM and Dashboard Activity

4 Obtain tollgate 4 approval from Champion and Black Belt Structured Project Guide

WBH PI-II
2/33 Structured Project Guide (SPG) Version 1.0
Six Sigma Structured Guide
Six Sigma Project
Structured Project Guide
Project Name Reducing the Distance Piece Rejecton Rate after Grinding

Tool Purpose Guide to follow a structured approach to complete a Six Sigma project

Task
Stage Task Tool Target Date Status Comments
no

1 Identify all Possible causes through brain stroming Possible Cause List
Tollgate 5 - ANALYZE

Cause & Effect


2 Construct Cause & Effect Diagram
Diagram

3 Identify Probable causes Validate with staff

Priortize top 5 probable causes to perform Root Cause Historical data,


4
analysis observations or Voting

5 Create KPIV control matrix to control root cause KPIV Control Matrix

6 Update Communication Matrix, MOM and Dashboard Activity

7 Obtain tollgate 5 approval from Champion and Black Belt Structured Project Guide

Brainstorm and list down all Possible solutions for the


1
priortized root causes and KPIVs
Possible Solutions List
Tollgate 6 -

Prioritize the solution based on Cost, Implemention Priotitized Solutions


IMPROVE

2
difficulties & Contradicting factors etc., List

3 Develop action plan Action Plans

4 Update Communication Matrix, MOM and Dashboard Activity

5 Obtain tollgate 6 approval from Champion and Black Belt Structured Project Guide
Tollgate 7 - IMPROVE

1 Calculate the new process sigma Activity

Validate the Implemented solution - Confirm the effect of


2 Activity
result before & after implementation of solution
If the solution is "ineffective" then identify an alternative
3 Activity
solution and develop new action plan and re-validate

4 Compute Six Sigma Financial Score Card Activity

5 Update Communication Matrix, MOM and Dashboard Activity

6 Obtain tollgate 7 approval from Champion and Black Belt Structured Project Guide

WBH PI-II
3/33 Structured Project Guide (SPG) Version 1.0
Six Sigma Structured Guide
Six Sigma Project
Structured Project Guide
Project Name Reducing the Distance Piece Rejecton Rate after Grinding

Tool Purpose Guide to follow a structured approach to complete a Six Sigma project

Task
Stage Task Tool Target Date Status Comments
no
Develop the Control System Matrix for the implemented
1 Control System Matrix
solutions Create this tool as per departmental requirements.
Tollgate 8 - CONTROL

Integrate the estabilshed control and systems into SOP and


2 Activity
quality systems
Communicate the new control methods to all relevant
3 Activity
staff/departments

4 Provide training to the relevant staff/departments Activity

5 Set dashboard to monitor Big Y and contracdicting factors Activity

6 Develop standard format to publish periodical status report Activity

7 Update Communication Matrix, MOM and Dashboard Activity

8 Obtain tollgate 7 approval from Champion and Black Belt Structured Project Guide

1 Document the roles played by the team players Final Report


Project Closure

Document TGR & TGW (Things Gone Right / Things Gone


2
Wrong)
Final Report

3 Document the various tools used in the DMAIC cycle Final Report

4 Prepare project presentation for GB certification Final Report

Present to Champion and Black Belt and get approval for


5 Activity
project closure

WBH PI-II
4/33 Structured Project Guide (SPG) Version 1.0
Six Sigma Structured Guide
Project Summary
Project name
Tool to monitor the progress of the project and help facilitate when project is
Tool Purpose not progressing to plan

# of process # of steps % of
TOLLGATE # PI Stage Remarks
Steps Completed Completion

TG 1 Define 14 0 0%
TG 2 Define 6 0 0%
TG 3 Measure 8 0 0%
TG 4 Analyze 4 0 0%
TG 5 Analyze 7 0 0%
TG 6 Improve 5 0 0%
TG 7 Improve 6 0 0%
TG 8 Control 8 0 0%
TG 9 Close Project 5 0 0%
Overall Status 63 0 0%

WBH PI-II
5/33 Project Structured Guide (PSG) Version 1.0
Progress Monitoring Chart
Project Summary

TITLE

PROJECT OBJECTIVE

START DATE

END DATE

CHAMPION Department Head Dr Oduntan Olusala

LEADER Green Belt


FACILITATOR Black Belt
MEMBERS Yellow Belt

Department Function Name Role/Resp. on Team E-mail address Work Phone

WBH PI-II
6/33 Structured Project Guide (SPG) Version 1.0
Project Summary
Project Attendance
Project name
Tool to monitor the attendance of team members at project
Tool Purpose meetings and mitigate any attendance issues.

Name Role/Resp. on Team Meeting 1 Meeting 2 Meeting 3 Meeting 4

Meeting Date

LEADER

FACILITATOR

WBH PI-II
7/33 Project Structured Guide (PSG) Version 1.0
Project Attendance
Project Charter
T
T
o
Application of the Quality Management System to design an all-in-one app called "My Health &
TITLE
Wealth" that will satisfy the customer's 'know all of what I eat' needs.

START DATE

END DATE

LEADER Green Belt

Business Case
In today's stressful world, people are more conscious of their health and money. Healthy eating has gain priority as there is less time to
exercise & as research suggest, healthy is 70% what we eat & rest exercise/meditation. Also in the present world of internet & on the
applications, people need a quick, dynamic & mobile solution to their problems of finding healthy food & saving money on groceries.
Thus, there is a need for "My Health & Wealth smartphone app". If we don't do it, a competitor would cash in on the scenario.
The customers' want to eat healthy, but there is little or vague information available on the food packages. Also, customers' are keen on
saving money buying best rocery at the cheapest price, but there is no common platform to compare & select the best product quality-
price combination.
The "My Health & wealth app" would be a one of its kind product, satisfying above mentioned customers' need.

Problem Statement
In the last three months it is observed that the wait time for a Q-Line is between 25 minutes to 30 min some times more with an
average of 30 min.Wait time is10 Minnutes more than the expected wait time,leading riders to choose other transportation systems
causing loss to the Q-Line System.

Project Objective
A new product development applying the 6Sigma & lean methodologies to get it right the first time. Also to build a high level QMS for
the production/Manufacturing of the app that would enable a house of quality for the newly developed app, converting the VOC into a
successful product - My Health & wealth App

Project Scope
Included Excluded
Data Collection for nutritional values of food

Data Collection on food related allergies & health risks

Data collection on food/groceries' prices in supermarts

WBH PI-II
8/33 Structured Project Guide (SPG) Version 1.0
TG 1.4 - Project Charter
Project Charter
T
T
o

Project Schedule (High Level) Suggested Timeframe


START DATE Phase Target Small Project Large project
END DATE Define 2 weeks 1 month

Duration Days Measure 1 week 2 weeks

Analyze 2 weeks 1 month

Improve 2 weeks 1 month

Control 1 week 2 weeks

Resource Estimate

Description Type of resource Cost of resource ($)

Total Expenses $0.00


Expected Benefits of Performance Improvement
Description Type of benefit Value of Benefit ($)

Total Benefits $0.00

WBH PI-II
9/33 Structured Project Guide (SPG) Version 1.0
TG 1.4 - Project Charter
Project Charter
T
T
o

Associated Company/Department Objectives

Departments Involved in Problem/Issue

PI Project Approvals

Approver Date Approved Approver Comments

CHAMPION Dr Oduntan Olusala

LEADER

FACILITATOR

WBH PI-II
10/33 Structured Project Guide (SPG) Version 1.0
TG 1.4 - Project Charter
KPOV (Key Process Output Variable) Chart

Project Name
Create a document to record the Key Process Output variables whose performance needs to be
Tool Objective improved.
Unit of Frequency
KPOV - Description KPOV measure Baseline Target of report Remarks

Y
y1
y2
y3
CF1
CF2
CF3
BC1
BC2
BC3

Instructions for KPOV Chart

Y The project objective


Sub objectives of the project / Contributors to Y. This will be required when:
– the Y is large
ys – Not easy to monitor
Ex:- if “Y” is productivity improvement of the overall process, then the small “ys” will be the productivity
of the sub processes.
Contradicting Factor – Factors that should not get adversely affected while achieving the project
CF objective.
Ex:- While improving productivity, quality should not deteriorate.
Boundary Condition – They are the assumed levels of influencing factors, usually not controllable by
BC the Project team.
Ex:- While improving throughput, volumes are assumed to be at certain levels.

WBH PI-II
11/33 Structured Project Guide (SPG) Version 1.0
TG 1.9 - KPOV Chart
SIPOC Chart
Project name
Tool Develop SIPOC process flow to determine KPOVs that need to be improved and KPIVs that need to
Objective be controlled.
Supplier Input Process Output Customer

Process Step 1

Process Step 2

Process Step 3

Process Step 4

Process Step 5

Process Step 6

Process Step 7

Process Step 8

WBH PI-II
12/33 Structured Project Guide (SPG) Version 1.0
TG 2.1 - SIPOC Chart
KPOV/KPIV Chart
Project
Name
Tool Create a list of KPOVs and associated KPIVs that would be utilized in the determination of controls for
Objective: KPIVs that would mitigate the cause and effect relationships that cause process failures.

List of KPOVs and KPIVs

Type
CC - Critical Key Process
Key Process Controllable
Sno. Input Process Output Output
Input Variables NC- Non critical
Noise Variables
SOP

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

WBH PI-II
13/33 Structured Project Guide (SPG) Version 1.0
TG 2.2 - KPOV KPIV Map
KPOV/KPIV Chart
Project
Name
Tool Create a list of KPOVs and associated KPIVs that would be utilized in the determination of controls for
Objective: KPIVs that would mitigate the cause and effect relationships that cause process failures.

List of KPOVs and KPIVs

Type
CC - Critical Key Process
Key Process Controllable
Sno. Input Process Output Output
Input Variables NC- Non critical
Noise Variables
SOP

#N/A

WBH PI-II
14/33 Structured Project Guide (SPG) Version 1.0
TG 2.2 - KPOV KPIV Map
Effort Vs. Elapsed Time Chart
Project Name
Determine if there are any opportunities for lean improvements - must be completed for turn around time/cycle time
Tool Objective improvement projects - contact project sponsor and Master Black Belt if there is a Lean opportunity.

Prepare SPG Tool

Process Step 2

Process Step 3

Process Step 4

Process Step 5

Process Step 6

Process Step 7

Process Step 8
Process Total

Elapsed Time In hours 0.0


Cumulative Time In hours 0 0 0 0 0 0 0 0
Effort Time In hours 0.0
Cumulative Time In hours 0 0 0 0 0 0 0 0

Availability of process steps or compression


### ### ### ### ### ### ### ###
factor

Total process compression factor:


Opportunity for improvement Effort / Elapse ###

Definitions
Elapsed Time Time to process including the waiting time before the process step
Effort Time Standard or design time for process step (no waiting time)
Compression Opportunity for lean improvements: +ve is opportunity for lean improvements, -ve is operating at or better than designed
factor cycle time

WBH PI-II
15/33 Structured Project Guide (SPG) Version 1.0
TG 2.3 - EffortElapsed Chart
PMC Chart
Project Name

Create a document to control what KPOV measures will be monitored through the lifecycle of the project and in steady state. The
Tool Objective control ducument will define the measurement plan.

Unit of Data
What data to Who will Data collection How will data Frequency
Output Measure collection Who will review Remarks
collect collect data Form be analyzed of review
(KPOV) frequency

WBH PI-II
16/33 Structured Project Guide (SPG) Version 1.0
TG 3.1 - PMC Chart
Baseline Sigma Chart

Project Name

Calculate the short-term "Baseline Sigma" of the process KPOV and determine the process
Tool Objective capability.

Example:

Situation: In a random audit, 500 lab sample test tubes are inspected. There are 3 opportunities for a sample test tube to
be in error (tube can be incorrectly labled with a wrong patients label, tube may contain the wrong patients sample, incorrect
tube may be used for the sample transport.) On inspection of the 500 sample test tubes, 38 errors were detected. Determine
the process short-term sigma.

Measurement description Value Example

Units sampled (Units) 500 500 lab test sample tubes were sampled

Opportunities for defects in a unit (Opportunities) 3 3 errors per lab sample test tube

Total opportunity for defects (Total Opportunities) 1500 500 * 3 = 1500

38 errors (12 tubes with wrong label, 16 tubes


Total count of defects in sampled items (Defects) 38 with wrong sample, 10 incorrect tubes used)

DPO (Defects Per Opportunities) 0.025333 38 / 1500 = 0.0253

DPMO (Defects Per Million Opportunities) 25333.33 DPO * 1000000 = 25333

Process Sigma (6s) 3.46 3.4579

Note: Do not delete/change formulas in the fields Do not


change
that are shaded in orange. formula

WBH PI-II
17/33 Structured Project Guide (SPG) Version 1.0
TG 3.5 - Baseline Sigma Chart
Possible Causes List
Project Name

Tool Objective Brainstorm and organize possible causes that influence the KPIVs
List of possible causes

Category
Sno Cause Special vs Remarks
Common

10

11

12

WBH PI-II
18/33 Structured Project Guide (SPG) Version 1.0
TG 5.1 - Possible Cause List
Possible Causes List
Project Name

Tool Objective Brainstorm and organize possible causes that influence the KPIVs
List of possible causes

Category
Sno Cause Special vs Remarks
Common

13

WBH PI-II
19/33 Structured Project Guide (SPG) Version 1.0
TG 5.1 - Possible Cause List
Cause and Effect Diagram
Project Name

Tool Objective Organize brainstormed list of possible causes and drill down to root causes.

WBH PI-II
20/33 Structured Project Guide (SPG) Version 1.0
TG 5.2 - Cause Effect Diagram
KPIV Control Matrix
Project Name

Tool Objective Organize brainstormed list of possible causes and drill down to root causes.

Output Details - y factors Input Details - x factors

Sub Objectives (small ys) Identified Xs Control Knob Details


Big Y Current
Target Current Data Control
(Objective) status # Description Target # Input(s) KPIV(s) Level 1 Level 2
status type type

x1

y1 x2

x3

x1

y2 x2

x3

x1

y3 x2

x3

x1

y4 x2

x3

x1

y5 x2

x3

WBH PI-II
21/33 Structured Project Guide (SPG) Version 1.0
TG 5.5 - KPIV Control Matrix
Solutions List
Project Name

Tool Objective Organize brainstormed list of possible solutions and analyze the

List of possible solutions

Sno Solutions Positive Impacts Negative Impacts Remarks/Priotity


1

10

11

12

13

14

WBH PI-II
22/33 Structured Project Guide (SPG) Version 1.0
TG 6.1 - Solutions List
Action Plans
Project Name

Tool Objective To track project and / or implementation activities, assignments and tasks.

No. Activity/Task Assigned To Start Date End Date Notes Status


1

Status Legend:
A = Active
P = Pending
C = Complete
TBD = To be determined

WBH PI-II
23/33 Structured Project Guide (SPG) Version 1.0
TG 6.3 - Action Plans
Project Final Report
TITLE

PROJECT OBJECTIVE

START DATE
Actual END DATE

Tools and Statistical Methods Used


Identify processes or tools used to indicate how you logically progressed through the steps of the model. All supporting
documentation (charts, graphs, etc) should be attached to proposal/summary or readily available. Use Benchmarking Sources
form, if needed, to track benchmarking.

Used During Which Step of Process?


1. Plan 2. Do 3. Check 4. Act
Measure

Improve
Analyze

Control
Define

Identify Tool or Method


Used Tool Purpose

Examples of Tools Which May Be Used:


• Brainstorming • Value Added/ • Pareto Chart
• Benchmarking Non-Value • Nominal Group Technique
• Flowcharting • Cause & Effect • Action (Work) Plan *
• Workflow Analysis • Control Chart • Gantt Chart
• Histogram

WBH PI-II
24/33 Structured project Guide (SPG) Version 1.0
Project Final Report
Project Final Report
* Action Plan should be developed to identify and track action steps required to plan and implement
performance improvement solutions.

WBH PI-II
25/33 Structured project Guide (SPG) Version 1.0
Project Final Report
Project Final Report
Key Outcomes of Project

Was Project Goal Achieved?

Planned Future Action & Follow-Up

Things gone right/Things gone wrong

Project Comments

WBH PI-II
26/33 Structured project Guide (SPG) Version 1.0
Project Final Report
Six Sigma Project Tools

Phase of DMAIC in which tool is


most commonly used

Tool Define Measure Analyze Improve Control Comments


Activity Network Diagram (AND)/GANTT a
Affinity Diagram a
Brainstorming a a
Business case a
Cause & Effect Diagram a
Charter a
Commitment scale a
Communication plan a a
Consensus a
Control Charts a a a a
CTQ (Critical to Quality) Tree a
Data Collection Forms a a a a
Check Sheet a a a a
Concentration Diagram a a
Data Collection Plan a a a
Data Types a
DOE (Design of Experiments) a
Full factorial
Reduced (fractional factorial)
Screening designs
Plackett-Burnham designs
More than two levels
Flow diagrams/Flowchart a a a a a
Focused problem statement a
FMEA (Failure Mode Effect Analysis) a a
Frequency plots a a a a
Gage R&R/MSA a
Histograms a a a
Hypothesis tests a
t-test
paired t-test
ANOVA
Chi-square
Interrelationship Digraph (ID) a
Involvement Matrix a
Kano model a
Matrix Diagram a
Measurement Systems Analysis (MSA) a
Operational Definitions a
Planning tools a
GANTT chart a
Planning grid
Pareto charts a a a

WBH PI-II
27/33 Structured Project Guide (SPG) Version 1.0
Inventory of Six Sigma Tools
Six Sigma Project Tools

Phase of DMAIC in which tool is


most commonly used

Tool Define Measure Analyze Improve Control Comments


Pilot Test/PDCA a
Prioritization matrix a a
Process capability a a
Process management chart a
Process sigma a a
Quality Control Chart a
Regression a
Rolled Throughput Yield (RTY)/First pass a
Run Chart a a
Sampling a a a a
Scatter plots/Scatter Diagrams a
SIPOC a
Six Sigma Storyboard a
Stakeholder analysis a a
Standardization a
Stratification a a a a
Stratified frequency plots a
Taguchi Loss Function a
Time Series Plots (Run Charts) a a
Tollgate review a a a a a
Tree diagram a
VOC (Voice of the Customer) a
Y = f(X) a a a a a

WBH PI-II
28/33 Structured Project Guide (SPG) Version 1.0
Inventory of Six Sigma Tools
Inventory of tools in WBH PI-II Structured Project Guide

Task
Stage Task Comments Tool Responsible YB Training GB Training BB Training
no
Green Belt, Black
1 Identify the Project
Project Summary Belt
Green Belt, Black
2 Identify the Champion, Sponsors Project Summary Belt
Champion and Green Belt to identify team players and define Champion/Spons
3
Roles & Responsibilities
Project Summary ors

4 Develop "Draft Project Charter" & get reviewed by Black Belt Project Charter Green Belt

Explain Project Charter to all the team members and


5 1st Project Meeting Green Belt
TOLLGATE 1 - DEFINE

review/revise charter

6 Present Project Charter to PI-II project sponsors Presentation Template Green Belt

7 Fine tune the Project Charter Project Charter Green Belt

Obtain the Project Charter approval - Department Manager,


8
Department VP, Finance (??)
Project Charter Green Belt

9 Create initial KPOV Chart KPOV Chart Green Belt

Create shared folder for project documentation and assign


10
minutes of meeting (MOM) responsibilities
MOM Green Belt

As Assigned -
11 Create Communication Matrix Communication Matrix team members

Create mock Dashboard, update responsibility and display Dashboard - Poster As Assigned -
12
the Dashboard at the Champion / Leader office Board team members
MOM taker -
13 Update MOM MOM team members

14 Obtain tollgate 1 approval from Champion and Black Belt Structured Project Guide Green Belt

As Assigned -
15 Develop Process Map – recommend “SIPOC” Chart SPIOC Chart
Tollgate 2 - DEFINE

team members
As Assigned -
16 Prepare the KPOV & KPIV Map KPOV KPIV Map team members
Develop the Effort/Elapsed time chart As Assigned -
17
(Mandatory for cycle time related projects)
Effort/Elapsed Time Chart
team members
As Assigned -
18 Finalize and update KPOV Chart KPOV Chart team members
As Assigned -
19 Update Communication Matrix, MOM and Dashboard Various
team members

20 Obtain tollgate 2 approval from Champion and Black Belt Structured Project Guide Green Belt

WBH PI-II Project Structured Guide (PSG)


29/33
Inventory of Tools Version: 1.0
Inventory of tools in WBH PI-II Structured Project Guide

Task
Stage Task Comments Tool Responsible YB Training GB Training BB Training
no
Prepare the PMC (Process Measurement Chart) for the As Assigned -
21
KPOVs that need to be analyzed and monitored
PMC Chart team members
Tollgate 3 - MEASURE

Deveop the data collection templates as mentioned in PMC


22 Various templates Team
(Ensure the adequacy and appropriateness)

23 Collect data as per PMC in the templates developed Activity Team

Decide relevant charts to be prepared (based on data type)


24 Activity Team
for further analysis and launch periodic reports
Calculate "Baseline Sigma” to understand the current As Assigned -
25
process capability
Baseline Sigma Chart team members

Revisit Project Charter and update if required As Assigned -


26 Activity
Keep all versions of the charters for future references. team members
As Assigned -
27 Update Communication Matrix, MOM and Dashboard Activity
team members

28 Obtain tollgate 3 approval from Champion and Black Belt Structured Project Guide Green Belt

Prepare the appropriate control charts for variability As Assigned -


29
identification
Control Chart templatesteam members
Tollgate 4 -
ANALYZE

Perform Variability Analysis (Instability, Off target, Variation) As Assigned -


30 Activity
using control charts and Process Capability team members
As Assigned -
31 Update Communication Matrix, MOM and Dashboard Activity
team members

32 Obtain tollgate 4 approval from Champion and Black Belt Structured Project Guide Green Belt

33 Identify all Possible causes through brain stroming Possible Cause List Team
Tollgate 5 - ANALYZE

As Assigned -
34 Construct Cause & Effect Diagram Cause & Effect Diagramteam members

35 Identify Probable causes Validate with staff Team

Priortize top 5 probable causes to perform Root Cause Historical data, As Assigned -
36
analysis observations or Voting team members

37 Create KPIV control matrix to control root cause KPIV Control Matrix Team

As Assigned -
38 Update Communication Matrix, MOM and Dashboard Activity
team members

39 Obtain tollgate 5 approval from Champion and Black Belt Structured Project Guide Green Belt

WBH PI-II Project Structured Guide (PSG)


30/33
Inventory of Tools Version: 1.0
Inventory of tools in WBH PI-II Structured Project Guide

Task
Stage Task Comments Tool Responsible YB Training GB Training BB Training
no

Brainstorm and list down all Possible solutions for the


40
priortized root causes and KPIVs
Possible Solutions List Team
Tollgate 6 -
IMPROVE

Prioritize the solution based on Cost, Implemention


41
difficulties & Contradicting factors etc.,
Priotitized Solutions ListTeam

42 Develop action plan Action Plans Team

As Assigned -
43 Update Communication Matrix, MOM and Dashboard Activity
team members

44 Obtain tollgate 6 approval from Champion and Black Belt Structured Project Guide Green Belt

As Assigned -
45 Calculate the new process sigma Activity
team members
Validate the Implemented solution - Confirm the effect of result
46 Activity Team
before & after implementation of solution
Tollgate 7 -
IMPROVE

If the solution is "ineffective" then identify an alternative


47 Activity Team
solution and develop new action plan and re-validate
GB, BB &
48 Compute Six Sigma Financial Score Card Activity
Champion
As Assigned -
49 Update Communication Matrix, MOM and Dashboard Activity
team members

50 Obtain tollgate 7 approval from Champion and Black Belt Structured Project Guide Green Belt

Develop the Control System Matrix for the implemented


51
solutions
Control System Matrix Team
Tollgate 8 - CONTROL

Integrate the estabilshed control and systems into SOP and


52 Activity TBD
quality systems
Communicate the new control methods to all relevant
53 Activity TBD
staff/departments

54 Provide training to the relevant staff/departments Activity TBD

55 Set dashboard to monitor Big Y and contracdicting factors Activity Team

56 Develop standard format to publish periodical status report Activity Team

As Assigned -
57 Update Communication Matrix, MOM and Dashboard Activity
team members

WBH PI-II Project Structured Guide (PSG)


31/33
Inventory of Tools Version: 1.0
Tollgate 8 - CONT
Inventory of tools in WBH PI-II Structured Project Guide

Task
Stage Task Comments Tool Responsible YB Training GB Training BB Training
no
58 Obtain tollgate 7 approval from Champion and Black Belt Structured Project Guide Green Belt

WBH PI-II Project Structured Guide (PSG)


32/33
Inventory of Tools Version: 1.0
Inventory of tools in WBH PI-II Structured Project Guide

Task
Stage Task Comments Tool Responsible YB Training GB Training BB Training
no

58 Document the roles played by the team players Final Report Green Belt
Project Closure

59 Document TGR & TGW (Things Gone Right / Things Gone Wrong) Final Report Green Belt

60 Document the various tools used in the DMAIC cycle Final Report Green Belt

61 Prepare project presentation for GB certification Final Report Green Belt

Present to Champion and Black Belt and get approval for


62 Activity Team
project closure

WBH PI-II Project Structured Guide (PSG)


33/33
Inventory of Tools Version: 1.0