Tool Purpose Guide to follow a structured approach to complete a Six Sigma project
Task
Stage Task Tool Target Date Status Comments
no
14 Obtain tollgate 1 approval from Champion and Black Belt Structured Project Guide
WBH PI-II
1/33 Structured Project Guide (SPG) Version 1.0
Six Sigma Structured Guide
Six Sigma Project
Structured Project Guide
Project Name Reducing the Distance Piece Rejecton Rate after Grinding
Tool Purpose Guide to follow a structured approach to complete a Six Sigma project
Task
Stage Task Tool Target Date Status Comments
no
6 Obtain tollgate 2 approval from Champion and Black Belt Structured Project Guide
8 Obtain tollgate 3 approval from Champion and Black Belt Structured Project Guide
Prepare the appropriate control charts for variability Control Chart Control Chart templates are available on Beaumont University page on Inside
1
identification templates Beaumont
Tollgate 4 -
ANALYZE
4 Obtain tollgate 4 approval from Champion and Black Belt Structured Project Guide
WBH PI-II
2/33 Structured Project Guide (SPG) Version 1.0
Six Sigma Structured Guide
Six Sigma Project
Structured Project Guide
Project Name Reducing the Distance Piece Rejecton Rate after Grinding
Tool Purpose Guide to follow a structured approach to complete a Six Sigma project
Task
Stage Task Tool Target Date Status Comments
no
1 Identify all Possible causes through brain stroming Possible Cause List
Tollgate 5 - ANALYZE
5 Create KPIV control matrix to control root cause KPIV Control Matrix
7 Obtain tollgate 5 approval from Champion and Black Belt Structured Project Guide
2
difficulties & Contradicting factors etc., List
5 Obtain tollgate 6 approval from Champion and Black Belt Structured Project Guide
Tollgate 7 - IMPROVE
6 Obtain tollgate 7 approval from Champion and Black Belt Structured Project Guide
WBH PI-II
3/33 Structured Project Guide (SPG) Version 1.0
Six Sigma Structured Guide
Six Sigma Project
Structured Project Guide
Project Name Reducing the Distance Piece Rejecton Rate after Grinding
Tool Purpose Guide to follow a structured approach to complete a Six Sigma project
Task
Stage Task Tool Target Date Status Comments
no
Develop the Control System Matrix for the implemented
1 Control System Matrix
solutions Create this tool as per departmental requirements.
Tollgate 8 - CONTROL
8 Obtain tollgate 7 approval from Champion and Black Belt Structured Project Guide
3 Document the various tools used in the DMAIC cycle Final Report
WBH PI-II
4/33 Structured Project Guide (SPG) Version 1.0
Six Sigma Structured Guide
Project Summary
Project name
Tool to monitor the progress of the project and help facilitate when project is
Tool Purpose not progressing to plan
# of process # of steps % of
TOLLGATE # PI Stage Remarks
Steps Completed Completion
TG 1 Define 14 0 0%
TG 2 Define 6 0 0%
TG 3 Measure 8 0 0%
TG 4 Analyze 4 0 0%
TG 5 Analyze 7 0 0%
TG 6 Improve 5 0 0%
TG 7 Improve 6 0 0%
TG 8 Control 8 0 0%
TG 9 Close Project 5 0 0%
Overall Status 63 0 0%
WBH PI-II
5/33 Project Structured Guide (PSG) Version 1.0
Progress Monitoring Chart
Project Summary
TITLE
PROJECT OBJECTIVE
START DATE
END DATE
WBH PI-II
6/33 Structured Project Guide (SPG) Version 1.0
Project Summary
Project Attendance
Project name
Tool to monitor the attendance of team members at project
Tool Purpose meetings and mitigate any attendance issues.
Meeting Date
LEADER
FACILITATOR
WBH PI-II
7/33 Project Structured Guide (PSG) Version 1.0
Project Attendance
Project Charter
T
T
o
Application of the Quality Management System to design an all-in-one app called "My Health &
TITLE
Wealth" that will satisfy the customer's 'know all of what I eat' needs.
START DATE
END DATE
Business Case
In today's stressful world, people are more conscious of their health and money. Healthy eating has gain priority as there is less time to
exercise & as research suggest, healthy is 70% what we eat & rest exercise/meditation. Also in the present world of internet & on the
applications, people need a quick, dynamic & mobile solution to their problems of finding healthy food & saving money on groceries.
Thus, there is a need for "My Health & Wealth smartphone app". If we don't do it, a competitor would cash in on the scenario.
The customers' want to eat healthy, but there is little or vague information available on the food packages. Also, customers' are keen on
saving money buying best rocery at the cheapest price, but there is no common platform to compare & select the best product quality-
price combination.
The "My Health & wealth app" would be a one of its kind product, satisfying above mentioned customers' need.
Problem Statement
In the last three months it is observed that the wait time for a Q-Line is between 25 minutes to 30 min some times more with an
average of 30 min.Wait time is10 Minnutes more than the expected wait time,leading riders to choose other transportation systems
causing loss to the Q-Line System.
Project Objective
A new product development applying the 6Sigma & lean methodologies to get it right the first time. Also to build a high level QMS for
the production/Manufacturing of the app that would enable a house of quality for the newly developed app, converting the VOC into a
successful product - My Health & wealth App
Project Scope
Included Excluded
Data Collection for nutritional values of food
WBH PI-II
8/33 Structured Project Guide (SPG) Version 1.0
TG 1.4 - Project Charter
Project Charter
T
T
o
Resource Estimate
WBH PI-II
9/33 Structured Project Guide (SPG) Version 1.0
TG 1.4 - Project Charter
Project Charter
T
T
o
PI Project Approvals
LEADER
FACILITATOR
WBH PI-II
10/33 Structured Project Guide (SPG) Version 1.0
TG 1.4 - Project Charter
KPOV (Key Process Output Variable) Chart
Project Name
Create a document to record the Key Process Output variables whose performance needs to be
Tool Objective improved.
Unit of Frequency
KPOV - Description KPOV measure Baseline Target of report Remarks
Y
y1
y2
y3
CF1
CF2
CF3
BC1
BC2
BC3
WBH PI-II
11/33 Structured Project Guide (SPG) Version 1.0
TG 1.9 - KPOV Chart
SIPOC Chart
Project name
Tool Develop SIPOC process flow to determine KPOVs that need to be improved and KPIVs that need to
Objective be controlled.
Supplier Input Process Output Customer
Process Step 1
Process Step 2
Process Step 3
Process Step 4
Process Step 5
Process Step 6
Process Step 7
Process Step 8
WBH PI-II
12/33 Structured Project Guide (SPG) Version 1.0
TG 2.1 - SIPOC Chart
KPOV/KPIV Chart
Project
Name
Tool Create a list of KPOVs and associated KPIVs that would be utilized in the determination of controls for
Objective: KPIVs that would mitigate the cause and effect relationships that cause process failures.
Type
CC - Critical Key Process
Key Process Controllable
Sno. Input Process Output Output
Input Variables NC- Non critical
Noise Variables
SOP
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
WBH PI-II
13/33 Structured Project Guide (SPG) Version 1.0
TG 2.2 - KPOV KPIV Map
KPOV/KPIV Chart
Project
Name
Tool Create a list of KPOVs and associated KPIVs that would be utilized in the determination of controls for
Objective: KPIVs that would mitigate the cause and effect relationships that cause process failures.
Type
CC - Critical Key Process
Key Process Controllable
Sno. Input Process Output Output
Input Variables NC- Non critical
Noise Variables
SOP
#N/A
WBH PI-II
14/33 Structured Project Guide (SPG) Version 1.0
TG 2.2 - KPOV KPIV Map
Effort Vs. Elapsed Time Chart
Project Name
Determine if there are any opportunities for lean improvements - must be completed for turn around time/cycle time
Tool Objective improvement projects - contact project sponsor and Master Black Belt if there is a Lean opportunity.
Process Step 2
Process Step 3
Process Step 4
Process Step 5
Process Step 6
Process Step 7
Process Step 8
Process Total
Definitions
Elapsed Time Time to process including the waiting time before the process step
Effort Time Standard or design time for process step (no waiting time)
Compression Opportunity for lean improvements: +ve is opportunity for lean improvements, -ve is operating at or better than designed
factor cycle time
WBH PI-II
15/33 Structured Project Guide (SPG) Version 1.0
TG 2.3 - EffortElapsed Chart
PMC Chart
Project Name
Create a document to control what KPOV measures will be monitored through the lifecycle of the project and in steady state. The
Tool Objective control ducument will define the measurement plan.
Unit of Data
What data to Who will Data collection How will data Frequency
Output Measure collection Who will review Remarks
collect collect data Form be analyzed of review
(KPOV) frequency
WBH PI-II
16/33 Structured Project Guide (SPG) Version 1.0
TG 3.1 - PMC Chart
Baseline Sigma Chart
Project Name
Calculate the short-term "Baseline Sigma" of the process KPOV and determine the process
Tool Objective capability.
Example:
Situation: In a random audit, 500 lab sample test tubes are inspected. There are 3 opportunities for a sample test tube to
be in error (tube can be incorrectly labled with a wrong patients label, tube may contain the wrong patients sample, incorrect
tube may be used for the sample transport.) On inspection of the 500 sample test tubes, 38 errors were detected. Determine
the process short-term sigma.
Units sampled (Units) 500 500 lab test sample tubes were sampled
Opportunities for defects in a unit (Opportunities) 3 3 errors per lab sample test tube
WBH PI-II
17/33 Structured Project Guide (SPG) Version 1.0
TG 3.5 - Baseline Sigma Chart
Possible Causes List
Project Name
Tool Objective Brainstorm and organize possible causes that influence the KPIVs
List of possible causes
Category
Sno Cause Special vs Remarks
Common
10
11
12
WBH PI-II
18/33 Structured Project Guide (SPG) Version 1.0
TG 5.1 - Possible Cause List
Possible Causes List
Project Name
Tool Objective Brainstorm and organize possible causes that influence the KPIVs
List of possible causes
Category
Sno Cause Special vs Remarks
Common
13
WBH PI-II
19/33 Structured Project Guide (SPG) Version 1.0
TG 5.1 - Possible Cause List
Cause and Effect Diagram
Project Name
Tool Objective Organize brainstormed list of possible causes and drill down to root causes.
WBH PI-II
20/33 Structured Project Guide (SPG) Version 1.0
TG 5.2 - Cause Effect Diagram
KPIV Control Matrix
Project Name
Tool Objective Organize brainstormed list of possible causes and drill down to root causes.
x1
y1 x2
x3
x1
y2 x2
x3
x1
y3 x2
x3
x1
y4 x2
x3
x1
y5 x2
x3
WBH PI-II
21/33 Structured Project Guide (SPG) Version 1.0
TG 5.5 - KPIV Control Matrix
Solutions List
Project Name
Tool Objective Organize brainstormed list of possible solutions and analyze the
10
11
12
13
14
WBH PI-II
22/33 Structured Project Guide (SPG) Version 1.0
TG 6.1 - Solutions List
Action Plans
Project Name
Tool Objective To track project and / or implementation activities, assignments and tasks.
Status Legend:
A = Active
P = Pending
C = Complete
TBD = To be determined
WBH PI-II
23/33 Structured Project Guide (SPG) Version 1.0
TG 6.3 - Action Plans
Project Final Report
TITLE
PROJECT OBJECTIVE
START DATE
Actual END DATE
Improve
Analyze
Control
Define
WBH PI-II
24/33 Structured project Guide (SPG) Version 1.0
Project Final Report
Project Final Report
* Action Plan should be developed to identify and track action steps required to plan and implement
performance improvement solutions.
WBH PI-II
25/33 Structured project Guide (SPG) Version 1.0
Project Final Report
Project Final Report
Key Outcomes of Project
Project Comments
WBH PI-II
26/33 Structured project Guide (SPG) Version 1.0
Project Final Report
Six Sigma Project Tools
WBH PI-II
27/33 Structured Project Guide (SPG) Version 1.0
Inventory of Six Sigma Tools
Six Sigma Project Tools
WBH PI-II
28/33 Structured Project Guide (SPG) Version 1.0
Inventory of Six Sigma Tools
Inventory of tools in WBH PI-II Structured Project Guide
Task
Stage Task Comments Tool Responsible YB Training GB Training BB Training
no
Green Belt, Black
1 Identify the Project
Project Summary Belt
Green Belt, Black
2 Identify the Champion, Sponsors Project Summary Belt
Champion and Green Belt to identify team players and define Champion/Spons
3
Roles & Responsibilities
Project Summary ors
4 Develop "Draft Project Charter" & get reviewed by Black Belt Project Charter Green Belt
review/revise charter
6 Present Project Charter to PI-II project sponsors Presentation Template Green Belt
As Assigned -
11 Create Communication Matrix Communication Matrix team members
Create mock Dashboard, update responsibility and display Dashboard - Poster As Assigned -
12
the Dashboard at the Champion / Leader office Board team members
MOM taker -
13 Update MOM MOM team members
14 Obtain tollgate 1 approval from Champion and Black Belt Structured Project Guide Green Belt
As Assigned -
15 Develop Process Map – recommend “SIPOC” Chart SPIOC Chart
Tollgate 2 - DEFINE
team members
As Assigned -
16 Prepare the KPOV & KPIV Map KPOV KPIV Map team members
Develop the Effort/Elapsed time chart As Assigned -
17
(Mandatory for cycle time related projects)
Effort/Elapsed Time Chart
team members
As Assigned -
18 Finalize and update KPOV Chart KPOV Chart team members
As Assigned -
19 Update Communication Matrix, MOM and Dashboard Various
team members
20 Obtain tollgate 2 approval from Champion and Black Belt Structured Project Guide Green Belt
Task
Stage Task Comments Tool Responsible YB Training GB Training BB Training
no
Prepare the PMC (Process Measurement Chart) for the As Assigned -
21
KPOVs that need to be analyzed and monitored
PMC Chart team members
Tollgate 3 - MEASURE
28 Obtain tollgate 3 approval from Champion and Black Belt Structured Project Guide Green Belt
32 Obtain tollgate 4 approval from Champion and Black Belt Structured Project Guide Green Belt
33 Identify all Possible causes through brain stroming Possible Cause List Team
Tollgate 5 - ANALYZE
As Assigned -
34 Construct Cause & Effect Diagram Cause & Effect Diagramteam members
Priortize top 5 probable causes to perform Root Cause Historical data, As Assigned -
36
analysis observations or Voting team members
37 Create KPIV control matrix to control root cause KPIV Control Matrix Team
As Assigned -
38 Update Communication Matrix, MOM and Dashboard Activity
team members
39 Obtain tollgate 5 approval from Champion and Black Belt Structured Project Guide Green Belt
Task
Stage Task Comments Tool Responsible YB Training GB Training BB Training
no
As Assigned -
43 Update Communication Matrix, MOM and Dashboard Activity
team members
44 Obtain tollgate 6 approval from Champion and Black Belt Structured Project Guide Green Belt
As Assigned -
45 Calculate the new process sigma Activity
team members
Validate the Implemented solution - Confirm the effect of result
46 Activity Team
before & after implementation of solution
Tollgate 7 -
IMPROVE
50 Obtain tollgate 7 approval from Champion and Black Belt Structured Project Guide Green Belt
As Assigned -
57 Update Communication Matrix, MOM and Dashboard Activity
team members
Task
Stage Task Comments Tool Responsible YB Training GB Training BB Training
no
58 Obtain tollgate 7 approval from Champion and Black Belt Structured Project Guide Green Belt
Task
Stage Task Comments Tool Responsible YB Training GB Training BB Training
no
58 Document the roles played by the team players Final Report Green Belt
Project Closure
59 Document TGR & TGW (Things Gone Right / Things Gone Wrong) Final Report Green Belt
60 Document the various tools used in the DMAIC cycle Final Report Green Belt