1.1. OBJECTIVE:-

To construct Temporary Bench mark stations along the alignment staggered at an


interval of 2 Km (approx.)

1.2. PROCEDURE:-

METHODOLOGY OF CONSTRUCTION OF
Ref. No.
TEMPORARY BENCH MARKS

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1

The temporary bench marks will be marked on the steel piles driven into the
sea by GPS control method. The construction of temporary bench mark will
be done by following procedure. The procedure will mainly consist of following
steps
1. Mobilisation
2. Casted Pillers
3. Demarcation of Benchmark
METHODOLOGY OF CONSTRUCTION OF
Ref. No.
TEMPORARY BENCH MARKS

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1

Mobilisation
The location of the temporary benchmark shall be decided along the
alignment on an alignment Plan. Pile drilling equipments along with the
material and other instruments shall be mobilized on to the location with the
help of crane.
Casting of Pillers

METHODOLOGY OF CONSTRUCTION OF
Ref. No.
TEMPORARY BENCH MARKS

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1

A metal plate will be insert of the top of the Pillers to create a base for
temporary bench marking.
Temporary casting piller M15 Grade of concrete are used (appox.area
0.200*0.200*0.500 cum)
Demarcation of Benchmark
With the help of high resolution GPS/Total Station , and Auto level used for
Level transfer on Bench mark will be fixed on the top of the Benchmark, the
METHODOLOGY OF CONSTRUCTION OF
Ref. No.
TEMPORARY BENCH MARKS

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1

co-ordinates of this benchmark will be counter checked with respect to


permanent benchmark on land or other fixed benchmark station from more
than two locations. The final co-ordinates will be painted on the benchmark.

1.3. EQUIPMENTS:-

1. GPS
METHODOLOGY OF CONSTRUCTION OF
Ref. No.
TEMPORARY BENCH MARKS

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1

2. Total Station with accessories


3. Auto levels with accessories
4. Measuring tape

1.4. MATERIALS:-

1. Raw materials for Piller Casting


2. Steel Plate
METHODOLOGY OF CONSTRUCTION OF
Ref. No.
TEMPORARY BENCH MARKS

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1

3. Paint

1.5. SAFETY: -

Temporary Benchmark should be used for protection of Pillers.

1.6. SKETCH / DRAWINGS :-

Ref. No. METHODOLOGY OF CONSTRUCTION OF


TEMPORARY BENCH MARKS

CONSTRUCTION METHODOLOGY
Doc. No. Eastern Freeway
Rev .No
From Museum to Anik Junction