PROJECT: PROPOSED AMENDMENT TP APPROVED DP FOR PROPOSED 7 STOREY SHOP CUM OFFICE ON L.

15864 AT LIKAS, KOTA KINABALU, SABAH


WORK PROGRAMME IN 18 MONTHS

MONTH
Item Description Period 1 2 3 4 5 6 7 8 9 10 11
Start Finish 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2
1 PRELIMINARY
2 MOBILISATION 14 days
3 PILING WORKS 60 days

BUILDING WORKS
4 SUBSTRUCTURE 60 days
RC RAME 270 days
UPPER FLOOR & SUSPENDED SLAB 290 days
STAIRCASE STRUCTURE 150 days
ROOF 30 days
EXTERNAL & INTERNAL WALL 230 days
DOORS 120 days
WINDOWS 240 days
FLOOR FINISHES 150 days
WALL FINISHES 200 days
CEILING FINISHES 180 days
HANDRAILING 150 days
SANITARY AND WARES 45 days
EXTERNAL WORKS
ROAD & CARPARK 30 days
SURFACE WATER DRAINAGE 45 days
SOIL DRAINAGE 80 days
WATER RETICULATION SYSTEM 60 days
PRIME COST & PROVISIONAL SUMS
ELECTRICAL INSTALLATION 400 days
EXTRA LOW VOLTAGE 400 days
COLD WATER & SANITARY SERVICES 400 days
FIRE PROTECTION SERVICES 400 days
LIFT INSTALLATION 150days
AIRCOND SYSTEM 210 days
SWIMMING POOL SYSTEM 120 days
LANDSCAPING 60 days
GYM EQUIPMENT 60 days
DEMOBILISATION 14 days
TH
11 12 13 14 15 16 17 18 19
3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
PROJECT: PROPOSED MAIN BUILDING WORKS FOR MIXED DEVELOPMENT OF RESIDENTIAL (APARTMENT) & COMMERCIAL ON 0150, PL. 103, 0151 & 015 AT JALAN BUKIT PADANG, KOTA KINABALU, SABAH.
WORK PROGRAMME IN 30 MONTHS

MONTH
Item Description Schedule 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

Start Finish
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

PRELIMINARY 900 Days

MOBILISATION 30 Days

BUILDING WORKS

1 WORK BELOW LOWEST FLOOR FINISH 60 Days

LEVEL 2 (STRUCTURE) 30 Days

2 FRAME 390 Days

3 UPPER FLOOR 390 Days

4 ROOF CONSTRUCTION 75 Days

5 STAIRCASE CONSTRUCTION 270 Days

6 EXTERNAL WALLS 360 Days

7 INTERNAL WALLS 390 Days

8 DOORS 480 Days

9 EXTERNAL WALL FINISHES 300 Days

10 INTERNAL WALL FINISHES 405 Days

11 FLOOR FINISHES 405 Days

12 ROOF FINISHES 60 Days

13 CEILING FINISHES 405 Days

14 HANDRAILING 180 Days

14 SANITARY AND WARES 150 Days

15 PAINTING 315 Days

MACHANICAL WORK

1 COLD WATER & SANITARY PLUMBING SERVICES 795 Days

PRIME COST & PROVISIONAL SUMS

1 ELECTRICAL INSTALLATION 795 Days

2 EXTRA LOW VOLTAGE 795 Days

3 ALUMINIUM & GLAZING WORKS 615 Days

4 FIRE PROTECTION SERVICES 720 Days

5 LIFT INSTALLATION 180 Days

6 EXTERNAL WORKS 120 Days

7 PUMP HOUSE 120 Days

8 DROP OFF ENTRANCE ROOF 60 Days

TESTING & COMMISIONING 60 Days

SITE CLEARING 60 Days

DEMOBILISATION 75 Days