Sie sind auf Seite 1von 1

DAILY DRILLING REPORT

G.P.C DAILY DRILLING REPORT WELL : HH 83/1D


ATT.
EASTERN DESERT FIELD N AMER RIG HEADING : 206°
REPORT NO. 33 RIG ADMARINE-3 RKB-MSL 36 MT W. DEPTH 23 MT
SPUD IN DATE 22/2/2018 MID NIGHT DEPHT 1719 MT PROGRESS 14 MT. MORNING DEPTH 1719 MT.
DATE OF REPORT 27/3/2018 DATE OF OPER's 26/3/2018 OPERATION @ 6:00 AM CONT RIH W/ 12 1/4" DIRC DRLG ASSY.
NEXT 24 HRs OPERATION FORECAST:- CONT DRLG 12 1/4" HOLE W/ 12 1/4" DIRC ASSY .
CASING DATA 24" C.P THICKNESS 1" @ 115.5 MT & 13-3/8" ( 68# , K-55) @ 775 MT.
BIT DATA MUD DATA ENGINEERS DATA
BIT NO. 4 ( NEW ) MUD TYPE : OBM CO. MAN : ENG. MOHAMED HAMDY
SIZE 12-1/4" MUD WT. (ppg) 9.7 N.CO.MAN : ENG. YEHIA ZAKARIA
TYPE FC616 VISCOSITY 77 DRLG ENG : ENG. EHAB EID
S. / NO. 5278761 HTHP, ml/30 min. 8
NOZZLES 6X14/32" PV 29
PUMP ( G.P.M ) 640-660 YP 28
PRESS., PSI 2580-2700 LSYP 13 FLUID & BULK DATA
W.O.B ( KLB ) 10-30 GEL (10 SC / 10 MN ) 21/34 ITEM RCVD USED ON HAND
AVG. ROP ( M/Hr ) 1.9 ALKALINTY 4.2 DIESEL, LIT 0 36,729 213,159
R.P.M 130-145 CORREC. SOLID 18.56 CMT., SK's 0 0 2,440
T.ON BTM HRS 266 EMULSION STABILITY 1,225 BARITE, SK's 0 0 0
DEPTH IN (Mt) 775 EXCESS LIME , PPB 5.44 D. WATER, BBLS 0 0 1370
DEPTH Out (Mt) IN HOLE OIL/WATER RATIO 85/15
DRLD. ( MT ) 944 TOTAL HARDNESS mg/l
TORQUE, LB.FT 2500-8500 PH @ 120 ᴼf MUD COST DATA
T. BIT REV., K 2059 MBT,ppb DAILY MUD COST, $ : 9,632.50
WT BELOW JAR, KLBs : 25 CHLORIDES MG/L 254317 ACC. MUD COST, $ : 173,694.25
BHA LENGTH , MT : 302 JAR S.N 1762-5221 CENTRIFUGE PUMP OP
BHA WEIGHT , KLBs : 68 TOTAL JAR HRS 350

12 1/4" NEW PDC BIT (S.N:5278761, TYPE: FC616)+11 7/8" ATK STEERABLE STAB. + 9 1/2" MWD W/ 12 1/8" MOD STAB. + 9 1/2" BCPM + 9 1/2" SENSOR
BHA #4 : SUB + 9 1/2" X.OVER SUB + 12 1/8" STRING STAB.+ 8 1/4" FLOAT SUB + 3 X 8 1/4" DCs + 8" JAR ( S.N : 1762-5221 ) + 2 X 8 1/4" DCs + 8" X.OVER SUB + 24 X
5" HWDP + 5" DPs T/ SURFACE.
TIME
HRs OPERATIONS
FROM TO

H.P.J.S.M, RIH W/ 12 1/4" BHI DIRC. DRLG ASSY. ( 11 7/8" ATK STEERABLE STAB. , 9 1/2" MWD W/ 12 1/8" MOD
0:00 1:00 1:00 STAB. , 9 1/2" BCPM, , 9 1/2" SENSOR SUB, 9 1/2" X.OVER SUB, 12 1/8" STRING STAB., 8 1/4" FLOAT SUB) W/ 12 1/4"
R.R PDC BIT (S.N:5278761, TYPE: FC616) & TESTED ATK W/( F/R : 650 GPM , PRESS: 1350 -1500 PSI , OK).

CONT'D RIH W/ 12 1/4" BHI DIRC. DRLG ASSY. T/ BTM @ 1719 MT


1:00 8:30 7:30 >> M/U NEW 8" JAR ( S.N : 1762-5195 ) WHILE RIH.
>> WASHED DOWN LAST STAND

RESUMED CTRL DIRC. DRLG 12-1/4" HOLE W/ 12-1/4" BHI ATK DIRC DRLG ASSY. F/1719 MT T/ 1740 MT.
8:30 15:00 6:30 >> WASHED UP & REAMED DOWN TWICE EVERY STD.
>> SWEPT HOLE W/ 20 BBL H.V.P. EVERY STD.
>> AVG DOWNHOLE LOSSES: 4 BBLs/HR.

>> WIND SPEED @ 6:00 AM 28-30 KNTS.( N.W )


TOTAL HRs. 24:00

TIME
HRs OPERATIONS
FROM TO

TOTAL HRs. 6:00

MD INC. AZIM. TVD VS NORTH EAST DLS


LAST SURVEY
1698 16.62 298.42 1497.9 683.45 319.06 -604.41 2.1

FORMATION DEPTH ( MD ) DEPTH (TVD) LITHOLOGY


POST ZEIT SURFACE - 376 SURFACE - 375 SAND W/ L.ST, GYPSUM, ANHYDRITE
ZEIT 376 - 664 375 - 641 ANHYDRITE W/ SHALE STKS
S.GHARIB 664 - 943 641 - 862 ANHYDRITE W/ SHALE STKS
BELAYIM 943 - 1175 862 - 1044 SHALE, L.ST & ANHYDRITE
KAREEM 1175 - 1390 1044 - 1218 SHALE & ANHYDRITE W/ S.ST STRKS
RUDIES 1390 - 1646 1218 - 1449.5 SHALE W/ L.ST STRKS
THEBES 1646 - 1719 1449.5 - 1518 CHERTY L.S
1683
GAS READING:-
DEPTH , MT T.G, PPM C1 , PPM C2 , PPM C3 , PPM I C4 , PPM NC4 , PPM I C5 , PPM N C5 , PPM
986 - 1646 1200 - 3400 50 - 1590 NIL - 20 - - - - -
1646 - 1719 1900 - 4200 452 - 2533 8 - 43 NIL - 3 NIL - 2 NIL - 1 - -

MOHAMED HAMDY

G.P.C REPRESENTATIVE
MOHAMED HAMDY