Beruflich Dokumente
Kultur Dokumente
1. State problem
Collegues 4. Develop options
2. Gather info 3. Identify stakeholders
Employers & Clients
Obligation as 5. Test options
Life long commitment Engineer
Public/Society
Reasoned judgement 6. Make choice of action
Ethical Decision
Expertise Oneself Making 7. Final choice, act & ask
Regulatory Requirements
No legal enforcement
Code of Ethics
Bring shame if breached
COE vs COC
Conversant with Code of Conducts
Honour pledge
Elements • Offer/acceptance: a party offer and the other • Failure to meet required standards
must accept the exact offer to form a contract • Duty of care owed by defendant to
• Legality: contract can’t be against public plaintiff
policy. • Damage reasonably foreseeable.
• Formalities: can be formed in writing and
orally.
Defences • No contract or contract expired • No breach of standards, limitation period
to the • No damages has expired.
claim • Damages not foreseeable. • No damages caused by the breach of
standards
• Damages not foreseeable
Damages • General: compensation for actual losses • General: compensation for non-monetary
award • Consequential: compensation that not loss or harm suffered
naturally flow from the breach (eg. economic • Special: compensation for direct,
harm) consequential and punitive losses.
• Punitive: awarded to punish certain (quantifiable)
behaviour (eg. Fraud) • Punitive: awarded to punish certain
behaviour (eg. Fraud)
Insurance
REGISTRATION
practise in the branch of
The study of moral issues and decisions confronting individuals Dont engineering he is not registered in
and organizations engaged in engineering Activities
endorse his PE Stamp and sign on
Engineering reports or plans not prepared by him
Engineer must not exploit the client Ethics
Issue of
Client places trust in the engineer ethics
Transparent with his work if requested
Engineer possess specialist knowledge and training Do
Take full responsibility for the checking of the work
COE for Young CONSULTANCY
Engineer
Dont accept work not within his competency
Re-engineer
Introduction Planning:
Establishment of framework for
Project Management: measuring, controlling and reporting a
Directing and coordinating humans, project resources and methods.
materials, and resources through the
life cycle of a project by modern Scheduling:
management techniques in achieving Converting outline plan of a project
pre-determined goals. (PMI) into a time-based graphical
Organizing and managing resources to representative based on resources and
deliver all works required to complete time constrain.
the project within defined scope. (BSI)
Purpose of planning:
Pre-defined objectives: -What
-Time -How
-Cost -Where
-Qualities -Whom
-When (lifecycle)
Characteristic of Eng. Projects:
-Specific goal
Purpose of Scheduling:
-Set of different activities
-Details breakdown of “when”
-Have a life cycle
-Ordering material and equipment
-Consume resources
-Study impact of productivity problem
-One time and temporary
-A communication platform
-Complex and Fragmented
-Contractual obligation
-Involve risk and uncertainty
Project life cycle: Type of Planning:
-Defining stage Pre-Project Pre-Design
-Planning stage By owners By owners or consultant
-Execution stage Feasibility studies To obtain optimum design
Project Manager:
-Planning (tactical and strategic)
-Leading (directing and motivating) Pre-construction task:
-Organizing (coordinating task) -Establish project team
-Controlling (corrective measures) -Review scope of work
-Identify potential risk
Approaches in PM: -Review cost estimation
-Initiation stage -Conduct value engineering
-Execution stage -Develop schedule
-Monitoring stage -Prepare cost plan
-Completion stage -Labor requirement
-Ordering material and equipment
-Select subcontractors
-Prepare safety program.
Procedure in scheduling: Terms:
-Establish objectives -Time now (date progess measured)
-Determine activities and sequence -Budget at Completion (BAC)
-Determine duration -Percentage Completed (PC Planned)
-Determine Logical relationship -Percentage Completed (PC Actual)
-Prepare “what if” scenarios -Earn value (EV)
-Draw logic network -Palnned value (PV)
-Identify critical path -Actual Cost (AC)
-Implement schedule
-Monitor and control “Traffic Light Status” project performance:
-Resource management -CPI green (1.00-0.95)
-CPI yellow (0.94-0.85)
Type of schedules: -CPI red (0.84-0.00)
-Bar chart (Gantt chart)
-Network/Precedence diagram example:
Control:
Measuring actual achievement
regarding the objectives when
compared to a baseline and taking
corrective measures if needed.
Tracking, monitoring and steering
project so objectives will be met.
Types of control:
-Time (schedule)
-Cost
Time control:
-Determining current status
-Determining any schedule changes
-Influencing the schedule changes
-Managing changes as they occur
Cost control:
-Influencing changes to the baseline
-Monitoring cost performance
-Keeping cost overruns in check.
-Informing stakeholders of changes.
-Reducing expected cost overruns
Handing Over:
-After practical completion
-Certificate of Practical Completion
-Defects Liability Period comance
-DLP guarantee period
-Outstanding or repairs work
-Handling Over Document signed.
Steps in RL:
-Determine critical path and floats.
-Identify key resources
-Histogram of resource demand
-Rescedule using floats
-Redraw resource profile