Sie sind auf Seite 1von 3

Summary

BP Berau Ltd of BP Plc (BP) is undertaking the expansion of Tangguh LNG facility in West Papua,
Indonesia.

The project involves the onshore expansion of Tangguh third LNG train with a capacity of 3.8 million
tonnes per annum (MTPA) bringing total plant capacity to 11.4MTPA.

It includes the construction of two offshore platforms, gas storage facility, gasification unit, subsea
pipelines, 13 new production wells, an expanded LNG loading facility, a new LNG jetty, bulk
offloading facility, the LNG and condensate loading jetty, pipelines and new wellhead platforms as
well as the redevelopment of the existing onshore Tangguh Brownfield site.and supporting
infrastructure, installation of compression equipment and gas metering facilities.

Onshore works will include an additional natural gas liquefaction train, an onshore receiving facility
(ORF), new LNG and condensate loading berth, additional Boil of Gas (BOG) recovery, utilities,
flares and other supporting infrastructures.

The scope of contract includes Bulk Offloading Facility (BOF)

Construction of the following:

1. Two finger piers (80m x 20m) and a 60m Ro-Ro quay wall;

2. Installation of sheet piles, tie-rods and waling beams, with 500m concrete capping beam;

3. Installation of Marine furniture (fenders, bollards, ladders);and

4. Installation of a floating pontoon with gangway and catwalks to the Passenger Terminal.

LNG & Condensate Loading Jetty 2

Design, supply, installation, construction, testing and commissioning of the following:

1. Abutment and shoreline rock protection;

2. Access trestle;

3. Loading Platform and Impounding basin (29m x 51m);

4. 6 Mooring and 4 Berthing Dolphins;

5. Oil Spill Response Facility and Tug Berths;

6. Impressed Current Cathodic Protection;

7. Marine equipment (ie. Fenders, Ladders, QRH, Navigation aids, BAS & EMS); and

8. Catwalks (2m wide) between dolphins/platform and 2 Access Gangway Towers.


On September 27, 2012, BP formally submitted the planning application to BPMigas, the upstream
oil and gas regulator of Indonesia.

In December 2012, BP received planning approval.

In August 2014, BP secured Integrated AMDAL environmental and social impact assessment
approval and also secured the environmental permit. However, BP has to secure government
approvals for project implementation.

On October 22, 2014, two consortia were awarded the front-end engineering and design (FEED)
contract.

The first consortium will work for the offshore FEED and consists of PT Tripatra Engineers and
Constructors, PT Tripatra Engineering, PT Chiyoda International Indonesia, PT Saipem Indonesia,
PT Suluh Ardhi Engineering and Chiyoda Corporation Consortium.

The second consortium will work for the onshore FEED and consists of PT Rekayasa Industri, JGC
Corporation, PT KBR Indonesia and PT JGC Indonesia Consortium.PT.

INPEX has been appointed as consultant for the project. On July 1, 2016, the final investment
decision (FID) was approved for the development of the project.

On July 27, 2016, contractors were appointed for onshore and offshore facilities.

Saipem has been awarded US$448 million engineering, procurement, construction and installation
(EPCI) contract under offshore facilities, consisting of two platforms and subsea pipelines. Saipem
will leverage its strong technological expertise in the design, fabrication and installation of a platform
and subsea pipelines. In accordance with the requirements of SKK Migas, Indonesia’s upstream oil
& gas regulator, Saipem will contribute to local content enhancement, including through its own
Karimun fabrication yard.

BP awarded a US$60 million pipeline construction contract to PT Aksia Pertiwi.

On August 3, 2016, BP signed a loan deal worth US$3,745 million with PT Bank Mandiri Tbk, PT.
Bank Negara Indonesia Tbk, and PT Bank Rakyat Indonesia.

On August 5, 2016, CSTS, a joint venture (JV) led by Tripatra with Chiyoda, Saipem, and Suluh
Ardhi Engineering awarded US$2,430 million engineering, procurement, construction (EPC) contract
for onshore LNG process train, utilities, offsite, an LNG jetty and associated infrastructure.

Clough has been selected to conduct mechanical engineering studies and provide basis of design,
and assistance during development, definition and procurement.

In September 2016, GE Oil & Gas awarded a contract to supply gas turbine-driven compressors and
two heat recovery steam generator to PT IMECO Inter Sarana a business partner of GE Oil & Gas
local in Indonesia,. It will be manufactured in Greenville, SC, USA, and Florence, Italy, It will be fully
digitally-enabled, including advanced sensors and monitoring capabilities to allow continuous
equipment care to safely maximize availability. The equipment will be export to the plant in mid-
2018.
In April 2017, McConnell Dowell was awarded the contract for the marine works, which includes the
construction of a Bulk Offloading Facility, the LNG and condensate loading jetty, pipelines and new
wellhead platforms as well as the redevelopment of the existing onshore Tangguh Brownfield site.

On September 25, 2017, ABB was appointed by the CSTS Joint Operation to supply prefabricated
electric substations for the project.

In October 2017, Suez, an Engie company, was appointed to supply waste water treatment system
to the project. The wastewater treatment system aims to treat 600,000 litres per day of effluents
produced by a new LNG process line.

Construction activities are underway with completion schedule by the third quarter of 2020.

Das könnte Ihnen auch gefallen