Sie sind auf Seite 1von 5

Shoring Basics

Tips for shoring system design, bracing, erection, and removal

BY BOB RISSER

ne of the contractor’s

O many responsibilities is
the design and construc-
tion of shoring systems,
which support the formwork sys-
tem and construction loads. Im-
properly designed or constructed
shoring systems can be extremely
h a z a rd o u s, leading to damaged
concrete or even catastrophic fail-
ure. Qualified and experienced
formwork designers should devel-
op shoring plans and schedule
shore removal. Frequently the de-
signer is a professional engineer
who works for the contractor or Figure 2. Determination of l/d ratio for a 3x4 wood shore with different bracing
plans. Bracing may be required in both directions to adequately reduce the l/d
shoring manufacturer. When nec-
ratio below the maximum of 50. The larger ratio governs maximum load limits.
essary, the project engineer or ar-
chitect reviews these plans for
er vertical supports. Bearing loads or crushing of the
structural adequacy, especially for
ACI 347 (Ref. 1) recommends us- shore ends against joists, stringers,
complex multistory construction.
ing a minimum construction live or other supported hori zo n t a l
Designing Shores load of 50 pounds per square foot formwork also must be considered
The shoring system is a tempo- (psf) for shore load calculations (75 in the shoring system design. Ex-
rary structure designed to carry psf if motorized carts are used to cessive deflections from bearing
both vertical and horizontal loads transport concrete). The minimum loads could make it very difficult to
during construction. These loads design load for combined dead and meet strict tolerance requirements.
include the weight of the fresh con- live loads should be 100 psf, or 125 The allowable bearing stress at the
c re t e, forms, shores and other psf if motorized carts are used. The interface of lumber shores and hor-
falsework; construction and equip- weight of formwork and shores is izontal formwork may also govern
ment loads; and wind loads and typically assumed to be 10% of the the shore design rather than the ca-
other loads. Ho ri zontal shores, dead load of the slab. If unusually pacity of the shore itself. The size of
such as adjustable beams, trusses, heavy equipment or construction the loaded contact area between
or a combination of both, require material loads are anticipated, in- the shore and the supported form-
special design attention because clude these loads in the analysis for work will determine the maximum
they distribute greater loads to few- shoring requirements. allowable load. In some cases, the
Reference 2
bearing area may be considerably
less than the actual dimensions of
the shore (Figure 1). Ha rd w o o d
caps or metal bearing plates can
distribute end loads from timber
shores so full structural capacity of
the shore can be utilized.
Simplified design, typically sat-
isfactory for standard shoring sys-
tems, assumes that each shore or
Figure 1. Bearing area between the shore and the horizontal formwork may be scaffold leg supports an area which
less than the total end area of the shore. extends halfway to adjoining sup-
p o rt s. Wood shores are treated as many patented systems, the analy- ing in both vertical and horizontal
simple columns, with allowable sis of allowable loads becomes so planes where needed to provide
loads based on the slenderness ra- complex that only load tests will stability to individual shoring
tio l/d, where l is the unsupported provide sufficient accuracy. Follow members. Even though horizontal
length, in inches, and d is the net all manufacturer’s recommenda- lacing is used to decrease the l/d ra-
dimension of the wood face under tions for bracing, assembly, and tio, increasing the load capacity of
consideration, in inches. For wood construction. the individual shores, some diago-
shores, l/d must not exceed 50. nal bracing is desirable in all
Ho ri zontal bracing is often used Bracing Shores shoring systems to increase the sta-
to reduce the size of the l/d ratio. Adequate lateral bracing is ex- bility of the shores and resist lateral
When this is the only purpose of tremely important to stability and loads. Braced bays, bracing lines, or
horizontal bracing, it is more prop- safety in shoring construction, but bracing tied to completed walls are
erly called lacing. Figure 2 shows all too often it is treated carelessly three common schemes used to
how slenderness ratios are calculat- or even omitted entirely (Ref. 2). provide stability and lateral sup-
ed and adjusted by using lacing. Shoring systems must be designed port (Figure 3).
The allowable load for simple wood to carry all anticipated lateral Do not mix different types of
shores is based on the magnitude forces due to wind, cable tensions, shoring systems or individual
of the l/d ratio and the compressive inclined supports, concrete place- shores of different materials on the
strength of different lumber types. ment, and starting and stopping of same level. The different character-
Design round wood shores by as- equipment. ACI 347 (Ref. 1) recom- istics of each system can lead to
suming a square shore with the mends a minimum assumed hori- nonuniform deflections under the
same cross-sectional area. zontal load of 100 pounds per lin- imposed load, creating stresses in
For other shoring systems such ear foot of floor edge, or 2% of the the structure and shoring system
as steel tubes, adjustable shore s, total dead load on the form, for which they are not designed.
combinations of wood and steel, whichever is greater. Follow manufacturer recom-
and tubular steel scaffold-type Unless the shoring system has mendations for bracing patented
shoring, follow manufacturer rec- enough internal X-bracing to pro- shoring systems. Although bracing
ommendations on allow a b l e vide internal rigidity, the shoring may not be specifically recom-
loads. Load limits should be based and formwork system should mended by the manufacturer to in-
on actual load tests conducted on transfer all horizontal loads to the crease the system’s load-carrying
the products and devices under ground or to already-completed capacity, it may be needed to in-
s t a n d a rd i zed conditions. Fo r construction. Place diagonal brac- crease the safety and stability of the
entire formwork assembly.
TABLE 1. TYPICAL RANGE OF MAXIMUM ALLOWABLE BEARING PRESSURES
Mudsills for Shoring
The shoring system must be ca-
Type of Foundation Maximum Allowable Bearing
pable of carrying the concrete and
Material Pressure, lb. per sq. ft.
construction loads without exces-
Massive bedrock 200,000 sive deflections. If shores are sup-
Foliated or laminated rock 40,000-80,000 ported on soil, the load the soil can
including sound limestone, support must be known or conser-
schist, slate vatively estimated. Table 1 shows
typical allowable bearing pressures
Sedimentary rock including 20,000-50,000
for foundation materials. Because
shale and sandstone
new soils tests can be costly, some
Soft or broken rock 10,000-20,000 contractors choose to use larger
Hardpan 16,000-20,000 mudsills based on very conserva-
tive estimates of soil strength. One
Gravel soils 8,000-20,000 rough estimate of soil strength is
Sands 4,000-13,000 the “heel test.” An ave ra g e - s i ze d
man walking on compacted soil
Gravelly sands 6,000-16,000
without leaving heel marks indi-
Silt and clay soils, inorganic, 1,200-10,000 cates a soil-bearing strength of at
medium to stiff least 3,000 psf.
Soft and organic deposits Values below 500 psf are common Mudsills are typically used to dis-
tribute shore loads to the soil.
(Reference 2)
Where the soil’s bearing capacity is
low or uncertain (Figure 4), mudsills
(a) (b)
Figure 3. Braced bays (a) require no exterior guys or anchors. Bays marked with dashed X-lines have complete X-bracing
system on vertical lines in both directions as well as horizontal X-bracing. Distance between braced bays depends on such
factors as bay size, weight on form, form height, and live load. Center shores are tied with strut bracing.
Completed columns or walls (b) can be used for bracing. Dashed lines indicate one line of strut braces to columns cast
earlier. Solid lines represent X-bracing also tied into existing columns. Intermediate lines are needed if shores are spliced.

must be capable of evenly distribut- l i ve red materials to ensure proper • Metal shores are free of exces-
ing shore load over a large enough load-carrying capacity. sive corrosion which reduces
area to avoid unequal or excessive In addition to checking for the structural capacity
settlement. Do not place mudsills appropriate materials, check that: • All metal shore connections are
on frozen ground, recently placed • Single-post shore members are sound
backfill, or where rainwater will flow straight and true without twists • All locking devices, coupling
over the area. To determine the re- or bends pins, and pivoted cross-braces
quired area of the mudsill, divide
the total load on the shore by the al- TABLE 2. MINIMUM TIME SUPPORTS SHOULD REMAIN IN PLACE
lowable soil-bearing pressure. (If no concrete strength requirements are provided)
Even when care is taken to prop-
erly design the mudsill for the shore Less Than More Than
load, formwork is typically set Where Structural Structural Structural
slightly higher than specified to ac- Design Live Load is: Design Design
commodate a small amount of set- Dead Load Dead Load
tlement and reduce the size of final
Arch centers 14 Days 7 Days
adjustments with wedges and
jacks. If the soil is very poor or like- Joist, beam, or girder soffits
ly to become unstable during con- Under 10 ft. clear span between 7 Days 4 Days
struction, other techniques such as structural supports
t e m p o ra ry concrete sills, piles, or 10 to 20 ft. clear span between 14 Days 7 Days
soil stabilization may be re q u i re d structural supports
to support the shore loads.
Over 20 ft. clear span between 21 Days 14 Days
Erecting Shores structural supports
Before erecting the formwork
support system, check to see that One-way floor slabs
the appropriate shores are being Under 10 ft. clear span between 4 Days 3 Days
used. This is especially important structural supports
when using rented equipment.
10 to 20 ft. clear span between 7 Days 4 Days
Load ratings can vary considerably structural supports
based on bracing configurations
and assumptions of the extended Over 20 ft. clear span between 10 Days 7 Days
height of the shore post or scaffold- structural supports
type shoring system. One contrac- * Assumes 50° F ambient temperature around concrete.
tor matches serial numbers on (Reference 1)
equipment orders to those on de-
on prefabricated
shoring systems are
working
Follow the shoring
layout plan closely,
keeping a copy on the
jobsite at all times.
Changes made to the
layout or timing of
shore removal should
be approved by the
shoring designer, engi-
neer, or architect. Keep
extra shores or other
necessary accessories
Figure 4. Spread-type wood mudsills are recommended for fair and poor bearing or heavy loads.
on the jobsite for use in
an emergency. Plumb them during concrete placement. termine the earliest time to remove
all shore posts or scaffold legs to Adjustable shores and other shores and forms.
minimize lateral loads and signifi- patented devices usually contain a Concrete strength gain va ri e s
cant reductions in vertical load ca- jack or screw-type mechanism for widely depending on job condi-
pacity. making elevation adjustments. Fol- tions. ACI 347 recommends remov-
Multi-tier shoring with single- low manufacturer recommenda- ing supports from horizontal con-
post shores is considered danger- tions on maximum extension of crete beams and slabs only after the
ous and is not recommended by these shores, since load ratings are concrete has gained at least 70% of
ACI 347. Field constructed butt or usually based on these configura- its design strength, unless earlier
lap splices of timber shores are al- tions. Additional diagonal bracing support removal is approved by the
so not recommended by ACI unless may be required to extend the engineer-architect.
splices are made with approved shore further. If strength tests are used to deter-
fabricated hardware (Ref. 1). OSHA mine shore removal, be sure all
requires vertical alignment of the Removing Shores parties involved in the construction
spliced shores, splicing to pre ve n t Shores cannot be removed from understand:
misalignment, splices on each a slab or beam until concrete is • The tests to be used
shore face (three splices for round strong enough to hold its own • Appropriate handling and test-
shores), perpendicular bracing at weight. Reshores may be needed to ing procedures
the splice level, and diagonal brac- carry approved construction loads • Who will make concrete speci-
ing in two directions. after the shores are removed. Al- mens
Where slab forms are continuous though design, construction, and • How many specimens will be
across several supporting shores, safety aspects of the formwork are made and who will test them
concrete placed in one area can cause the contractor’s responsibility, the • The minimum required con-
uplift of the formwork in an adjacent required concrete strength and crete strength
area. Positively attach the shores to time period before shore removal Cure concrete specimens at the
deck forms to resist this uplift and to should be specified by the engi- jobsite under conditions no better
keep shores from falling out. neer-architect. than those the concrete in the
Vertical shores must bear firmly Removing shores and other con- structure are cured under to obtain
against the formwork they support crete formwork supports should not a conservative estimate of the in-
and be unable to tilt under con- produce excessive deflections, dis- place concrete strength. Se ve ra l
struction loads. Jacks or wedges al- tortions, or damage to the concrete. nondestructive testing techniques
low positive adjustment for form- Remove shores in a sequence that are also recommended by ACI 318
work settlement and final does not produce stresses in the (Ref. 3) for determining in-place
alignments prior to placing con- concrete for which it is not designed. concrete strength: penetration re-
c re t e. These devices also facilitate For typical slabs and beams, begin sistance, pullout strength, and ma-
stripping the forms after the con- shore removal in the middle of the turity measurement.
crete has attained sufficient bay or beam, working out toward If no strength requirements are
strength. Wedges can be used ei- supporting walls or columns. This provided by the engineer or local
ther at the top or the bottom of the ensures that the slab or beam will codes, refer to Table 2, which gives
shore post, but not in both areas. deflect and be loaded as designed. the minimum time shores should
After the wedges are in position, To maximize form reuse, a reli- remain in place. The table indicates
toenail them to the shore to secure able system needs to be used to de- the total number of days needed,
given an ambient temperature tractors find these traditional pending on rate of construction,
around the concrete of at least 50° schemes acceptable on most pro- many floors may need to be inter-
F. The times can be shortened as jects for safely distributing con- connected with shores and
approved by the engineer-architect crete and construction to older, reshores to safely carry the im-
if high-early-strength concrete is stronger floors. In some cases, posed load until the concrete
used to speed construction. If tem- howe ve r, these shoring and reaches design strength.
peratures below 50° F occur follow- reshoring plans will not safely carry In multistory construction, the
ing concrete placement, the engi- the constructions loads, and the most heavily loaded shores are
neer may decide to lengthen the contractor should use one or more those at ground level which carry
minimum requirements. of the following methods to ensure the load of all floors concreted be-
Contractors often use reshores to safe construction: fore first-level shores have been re-
maximize form reuse and limit sag • Increase the number of floors of moved. Depending on the con-
or creep in the new concrete. When shoring and reshoring struction sequence, loads on these
reshores are used, forms and • Use a longer cycle time for shores can be several times the
shores are removed after the con- each floor dead load of the slab itself.
crete has sufficient strength to car- • Either use a concrete mix or cre- Place shores in the same location
ry its own weight. After the beam or ate curing conditions that pro- on each floor to avoid developing
slab achieves its initial deflection, duce faster concrete strength gain reversed bending or punching
the reshores are placed under the Calculation of the loads imposed shear stresses the slab cannot carry.
concrete to carry additional con- on each floor during multistory If offset placement is needed, recal-
struction loads or prevent further construction can be complex. The culate the stresses to ensure that
creep deflections. shoring and reshoring plan should the slab has adequate re i n f o rc i n g
Place reshores as soon as possi- be approved by the project engi- in these areas to handle the re-
ble after the forms are stripped, but neer or architect. versed bending stresses that can
at least by the end of the day the This is particularly important for develop (Figure 5).
forms are removed. Reshores must construction of commercial office
be placed snugly without altering buildings or other structures de- References
the deflected shape of the concrete. signed for relatively low live loads. 1. ACI Committee 347, “Guide to
The engineer-architect should ap- If the ratio of the design live load to Formwork for Concrete,” (ACI 347R-
88), American Concrete Institute, De-
prove all reshoring plans. concrete dead load is low, the troit, 1988.
s t ru c t u re has very little reserve
Multistory Construction 2. M.K. Hurd, Formwork for Concrete,
strength to carry the imposed con- SP-4, fifth edition, American Concrete
In multistory work, the partially struction loads and weight of fresh Institute, 1989.
completed structure becomes part c o n c re t e. Often the construction 3. ACI Committee 318, “Building Code
of the shoring support. In planning live load and weight of new con- Requirements for Reinforced Con-
the shoring/reshoring system, the crete are greater than the live load crete,” (ACI 318-92), American Con-
designer uses information on the for which the slab is designed. De- crete Institute, 1992.
structural design loads, usually ob-
tained from the project drawings.
Multistory construction presents
special challenges for shoring pro-
c e d u re s, especially in terms of re-
moving the shores to maximize
form reuse. Se ve ral stories need to
be supported by shores and
reshores to handle the dead load of
the concrete and the construction
loads before the concrete gains full
design strength. Reshores are used
after the formwork is stripped to
distribute any further loads among
the older, stronger slabs.
Typical shoring and re s h o ri n g
schemes for multistory construc-
tion use a rule of thumb or local
custom: Contractors, for example, Figure 5. Improper positioning of shores from floor to floor can create bending
may build two stories of shoring for stresses for which the slab is not designed. Calculate for reversal stresses when
e ve ry one story of reshoring. Con- reshores do not match shores above. Be sure shores resist uplift and cannot fall.
PUBLICATION #C940856, Copyright © 1994, The Aberdeen Group, All rights reserved

Das könnte Ihnen auch gefallen