Beruflich Dokumente
Kultur Dokumente
Technical Report
Bovill Kaolin Project
Latah County, Idaho
Effective Date: April 20, 2014
Report Date: June 26, 2014
Reviewed by:
Bret Swanson, BEng Mining, MAusIMM, MMSAQP
Signed by QP(s):
Bart Stryhas, PhD, CPG
Harry Gatley, PE
David S. Hallman, PE
Manuel Rauhut, PE
Valerie Obie, BS Mining, RM-SME
SRK Consulting (U.S.), Inc.
NI 43-101 Technical Report – Bovill Kaolin Project Page i
Table of Contents
1 Summary ......................................................................................................................................1
1.1 Property Description and Ownership ........................................................................................................... 1
1.2 Geology and Mineralization ........................................................................................................................... 1
1.3 Status of Exploration, Development and Operations ................................................................................ 1
1.4 Mineral Processing and Metallurgical Testing ............................................................................................ 1
1.5 Mineral Resource Estimate ........................................................................................................................... 3
1.6 Mineral Reserve Estimate ............................................................................................................................. 5
1.7 Mining Methods ............................................................................................................................................... 5
1.8 Project Infrastructure ...................................................................................................................................... 6
1.9 Environmental Studies and Permitting ........................................................................................................ 6
1.10 Capital and Operating Costs ......................................................................................................................... 7
1.11 Economic Analysis ......................................................................................................................................... 7
1.11.1 Sensitivity Analysis ............................................................................................................................ 8
1.12 Conclusions and Recommendations ........................................................................................................... 8
2 Introduction.............................................................................................................................. 10
2.1 Terms of Reference and Purpose of the Report ...................................................................................... 10
2.2 Qualifications of Consultants (SRK) ........................................................................................................... 10
2.3 Details of Inspection ..................................................................................................................................... 11
2.4 Sources of Information ................................................................................................................................. 12
2.5 Effective Date ................................................................................................................................................ 12
2.6 Units of Measure ........................................................................................................................................... 12
3 Reliance on Other Experts ................................................................................................... 13
4 Property Description and Location ................................................................................... 14
4.1 Property Location.......................................................................................................................................... 14
4.2 Mineral Titles ................................................................................................................................................. 14
4.3 Royalties, Agreements and Encumbrances.............................................................................................. 16
4.4 Environmental Liabilities and Permitting ................................................................................................... 17
4.4.1 Environmental Liabilities ................................................................................................................. 17
4.4.2 Required Permits and Status ......................................................................................................... 17
4.5 Other Significant Factors and Risks........................................................................................................... 18
5 Accessibility, Climate, Local Resources, Infrastructure and Physiography .......... 19
5.1 Topography, Elevation and Vegetation ..................................................................................................... 19
5.2 Accessibility and Transportation to the Property ...................................................................................... 19
5.2.1 Proximity to Population Center and Transport............................................................................. 19
5.3 Climate and Length of Operating Season....................................................................................................... 20
List of Tables
Table 1.5.1: Measured and Indicated Mineral Resource Statement (as of April 20, 2014)* ................................. 4
Table 1.6.1: Mineral Reserve Statement, (as of June 14, 2014) .............................................................................. 5
Table 1.11.1: LoM Capital Cost Summary (US$000’s).................................................................................................... 7
Table 1.11.2: LoM Operating Cost Summary .............................................................................................................. 7
Table 1.12.1: Financial Model Results.......................................................................................................................... 8
Table 1.12.1.1: Project NPV Sensitivities (US$ millions) ........................................................................................... 8
Table 4.2.1: Mineral Leases ................................................................................................................................................ 15
Table 7.3.2.1: Average Quartz Composition Calculated from Electron Microprobe Analyses ........................... 28
Table 11.3.1: Clay Code Assignment ......................................................................................................................... 38
Table 13.2.1.1: Phase I Characterization Data ......................................................................................................... 58
(1)
Table 13.2.3.1: Primary Clay Pilot Plant Trials Compilation Recovery Data ..................................................... 68
Table 13.2.4.1: Grade vs. Hydrofluoric Acid Dosage ..................................................................................................... 71
Table 13.2.4.2: Grade vs. Collector Amine Dosage ....................................................................................................... 71
Table 13.2.4.3: Feldspar Middlings Evaluation.......................................................................................................... 71
Table 13.2.5.1: Quartz Products Evaluation .............................................................................................................. 72
Table 13.2.7.1: Quartz Products Evaluation .............................................................................................................. 74
Table 14.3.1: Capping and Compositing Results ...................................................................................................... 77
Table 14.5.1 Block Model Material Densities ............................................................................................................. 77
Table 14.6.1: Block Model Limits WBL and Middle Ridge Areas ............................................................................ 78
Table 14.6.2: Block Model Limits Kelly’ Hump Areas ............................................................................................... 78
Table 14.7.1 Percentage of Model Blocks in Clay Shell .......................................................................................... 80
Table 14.7.2 Resource Estimation Parameters......................................................................................................... 80
Table 14.8.1: Grade Estimation Performance Parameters ...................................................................................... 86
Table 14.8.2: Statistical Model Validation .................................................................................................................. 87
Table 14.8.3: Nearest Neighbor Model Validation .................................................................................................... 88
Table 14.10.1: Indicated Mineral Resource Statement, (as of 20 April 2014) ...................................................... 90
Table 15.1: Mineral Reserve Statement, (as of June 14, 2014) ............................................................................. 92
Table 16.1.1: Slope Angles from Geotechnical Report by STRATA (2012) .......................................................... 93
Table 16.2.2.1: Whittle™ Kelly’s Hump Block Model Import Parameters .............................................................. 95
Table 16.2.2.2: Whittle™ Middle Ridge Block Model Import Parameters.............................................................. 95
Table 16.2.2.3: Combined Recoveries for Kaolinite and Sand Minerals ............................................................... 96
Table 16.2.2.4: Combined Selling Prices for Kaolinite and Sand Minerals ........................................................... 96
Table 16.2.2.5: Whittle™ Economic Parameters ...................................................................................................... 97
Table 16.2.3.1: Whittle™ Economic Pits Middle Ridge ............................................................................................ 98
Table 16.2.3.2: Whittle™ Economic Pits Kelly’s Hump ............................................................................................ 99
Table 16.3.1.1: Pit Design Parameters ..................................................................................................................... 102
List of Figures
Figure 4.1.1: Location Map of the Bovill Kaolin Project ............................................................................................ 14
Figure 4.2.1: Land Management/Ownership Map ..................................................................................................... 16
Figure 7.1.1: Regional Geology ................................................................................................................................... 24
Figure 10.1.1: Drillhole Locations and Resource Areas ........................................................................................... 33
Figure 11.5.1: UOI vs. GMT Analyses for 2011,-325 Mesh Duplicates ................................................................. 39
Figure 11.5.2: UOI vs. CCL Analyses for 2011,-325 Mesh Duplicates .................................................................. 40
Figure 11.5.3: UOI vs. GMT Analyses for 2013, -325 Mesh Duplicates ................................................................ 41
Figure 11.5.4: UOI vs. Non Certified Reference Material for the -325 Mesh, 2013 Analyses ............................ 42
Figure 11.5.5: UOI vs. GMT Analyses for 2013, -325 Mesh Duplicates, with Bias Removed ............................ 43
Figure 11.5.6: UOI vs. Non Certified Reference Material for the -325 Mesh, 2013 Analyses with Bias
Removed........................................................................................................................................................... 44
Figure 13.1.1.1: Helmer-Bovill Clay Processing Plant Phase I Testing Block Flow Diagram ............................. 49
Figure 13.1.1.2: Helmer-Bovill Clay Processing Plant Phase II Testing Block Flow Diagram ............................ 51
Figure 13.2.3.1: SEM of 3" Hydrocyclone Overflow Showing Clays ...................................................................... 62
Figure 13.2.3.2: SEM of 3: Hydrocyclone Underflow Showing Feldspathic Sand Grit ........................................ 63
Figure 13.2.3.3: SEM of 0.5" Hydrocyclone 2nd Pass Overflow (Predominantly Halloysite).............................. 64
Figure 13.2.3.4: SEM of 0.5" Hydrocyclone 2nd Pass Underflow (Predominantly Kaolinite) ............................. 65
Figure 14.7.1: Drillhole Locations (Black Dots), Clay Shell >=10% (Blue), Clay Shell >1-<10% (Teal) ........... 79
Figure 14.7.2 WBL, East West Cross Section 1,904,800N Viewing North; Composite and Estimated Block
Grades, From Top to Bottom-Sand, Kaolinite, Halloysite and Waste ...................................................... 81
Figure 14.7.3 Middle Ridge, East West Cross Section 1,906490N Viewing North; Composite and Estimated
Block Grades, From Top to Bottom-Sand, Kaolinite, Halloysite and Waste ........................................... 82
Figure 14.7.4 Kelly’s Hump North, East West Cross Section 1,907,200N Viewing North; Composite and
Estimated Block Grades, From Top to Bottom-Sand, Kaolinite, Halloysite and Waste ........................ 83
Figure 14.7.5 Kelly’s Hump South, East West Cross Section 1,904,200N Viewing North; Composite and
Estimated Block Grades, From Top to Bottom-Sand, Kaolinite, Halloysite and Waste ........................ 84
Figure 16.2.3.1: Kelly’s Hump Results ...................................................................................................................... 100
Figure 16.2.3.2: Middle Ridge Results...................................................................................................................... 101
Figure 16.3.2.1: Kelly’s Hump Final Design ............................................................................................................. 103
Figure 16.3.2.2: Kelly South Final Design ................................................................................................................ 104
Figure 16.3.2.3: Middle Ridge Final Design ............................................................................................................. 105
Figure 16.3.2.4: WBL Final Design ........................................................................................................................... 106
Figure 16.3.3.1: Kelly’s Hump and Kelly South Pit Designs and Optimized Shells ............................................ 109
Figure 16.3.3.2: Middle Ridge and WBL Pit Designs and Optimized Shells ....................................................... 110
Figure 16.3.3.3: Cross Section (Designed pit versus Whittle™ shell) .................................................................. 111
Figure 16.3.4.1: Kelly’s Hump Waste Dump (Plan View) ........................................................................................... 112
Appendices
Appendix A: Certificates of Qualified Persons
1 Summary
This report on the Bovill Kaolin-Halloysite-Quartz-Potassium Feldspar Project (Bovill Kaolin Project)
was prepared as a National Instrument 43-101 (NI 43-101) Prefeasibility Technical Report for I-
Minerals Inc. (I-Minerals) by SRK Consulting (U.S.), Inc. (SRK), Tetra Tech Inc. (Tetra Tech), HDR
Engineering, Inc. (HDR) and Roberts & Schaefer Company, a KBR Company (R&S/KBR), collectively
the Consultants. A brief summary of the results of prefeasibility study are presented below.
Clay
Initial tests to determine the responsiveness of the clay to commercial processing technology were
completed by GMT with the following key results:
The clays have good brightness values with extensive processing methods;
SEM images from the crude and processed materials for each sample illustrated the range in
particle size and particle morphology of the minerals and showed the presence of the halloysite
with the kaolinite; and
The products produced from the crude samples concentrated the clay (halloysite and kaolinite)
to almost 100% and removed the majority of other mineral contaminants.
Based upon the metallurgical test work, a bulk crude ore sample was collected for pilot plant testing.
The primary focus of the pilot plant evaluations was to separate the clay from the feldspathic sand and
then concentrate the halloysite from the kaolin clay. Two tests were performed and reported in July
2008 and July 2010. Three additional smaller scale pilot plant testing followed up the July 2010 testing.
Key results from these tests included:
The 3 inch cyclone successfully split the grit fraction from the clay;
SEM’s illustrated excellent separation and concentration of the halloysite in the 2nd pass
overflow fraction using the 0.5 inch diameter cyclone;
A metakaolin product was successfully produced and provided for potential customer
development;
Total clay recovery should be in the range of 23%, halloysite 8%, and kaolinite 15%; and
Feldspathic sand fraction recovery should be in the range of 70%.
Additional metallurgical test work was performed in 2011 and 2012 on both a bulk crude ore sample
as well as composite core ore material to confirm qualitative and quantitative data from previous work,
produce additional material for product development, and investigate alternative separation processing
techniques. Key results from these test included:
The 0.5 inch cyclones could be successfully replaced with solid bowl decanter centrifuge
technology which would simplify processing requirements for the halloysite/kaolinite
separation;
Significant additional halloysite product was produced for product development; and
Recovery data for the composite core material mirrored that of previously run bulk samples,
both qualitatively and quantitatively, to confirm desired results.
The MRL at NCSU performed a series of pilot plant tests on K-spar tailings. The objective was to prove
the technical feasibility and developmental integration of processing techniques to produce commercial
grade K-spar and quartz products. The quartz material was subjected to further bench- scale testing
to produce varying degrees of quartz product quality. The MRL successfully achieved this objective
and the following key results were obtained:
The optimized feldspar circuit consistently produced quality K-spar product grades ranging
from 18.0% to 18.5% Al2O3 and 13.0% to 13.5% K2O;
K-spar yields from the feldspathic sand feed ranged from 17% to 20%;
The optimized quartz circuit, using varying degrees of flotation steps, resulted in the ability to
produce three grades of high quality quartz products. The three 50 x 200 mesh product grades
ranged from 355 to 280 ppm impurities; and
Quartz yields from the feldspathic sand feed ranged from approximately 24.5% for Quartz 1 to
13.6% for Quartz 3. The overall quartz yields will range from approximately 38% to 42% and
will be dependent on the quartz production matrix.
Table 1.5.1: Measured and Indicated Mineral Resource Statement (as of April 20, 2014)*
Tons Qtz & K-Spar Sand Kaolinite Halloysite Qtz & K-Spar Sand Tons Kaolinite Tons Halloysite Tons
Classification Location (M) (%) (%) (%) (000’s) (000’s) (000’s)
Kellys Hump 2.3 76.7 13.0 3.9 1,761 297 90
Measured Middle Ridge 1.0 74.8 12.0 5.9 745 120 58
All 3.3 76.1 12.7 4.5 2,505 417 148
Kellys Hump 3.8 72.2 18.0 2.8 2,721 680 107
Middle Ridge 2.9 77.0 12.4 3.0 2,208 355 86
Indicated
WBL Pit 1.3 75.0 15.8 1.7 973 204 22
All 7.9 74.4 15.6 2.7 5,902 1,239 215
Kellys Hump 6.1 73.9 16.1 3.2 4,482 978 196
Middle Ridge 3.9 76.4 12.3 3.7 2,952 474 144
M&I
WBL Pit 1.3 75.0 15.8 1.7 973 204 22
All 11.2 74.9 14.8 3.2 8,407 1,656 362
* Note that values presented here have been rounded to reflect the level of accuracy.
Source: SRK Consulting, 2014
Mineral Resources that are not mineral reserves do not have demonstrated economic viability. Mineral
resource estimates do not account for mineability, selectivity, mining loss and dilution. These mineral
resource estimates include mineral resources that are normally considered too speculative
geologically to have economic considerations applied to them that would enable them to be
categorized as mineral reserves. There is also no certainty that these inferred mineral resources will
be converted to Measured and Indicated categories through further drilling, or into mineral reserves,
once economic considerations are applied.
The proven and probable reserves are presented in the Table 1.6.1.
Table 1.6.1: Mineral Reserve Statement, (as of June 14, 2014)
Halloysite Kaolin Qtz & K-Spar Halloysite Kaolinite Qtz & K-Spar
Reserve Mt
Grade Grade Sand (%) Tons Tons Sand (t)
Kelly Hump
Proven 1.7 4.8% 13.5% 81.7% 82,000 229,000 1,389,000
Probable 1.0 6.0% 15.4% 78.6% 60,000 154,000 782,000
Kelly South
Proven 0 0 0 0 0 0 0
Probable 1.3 1.6% 23.2% 75.3% 20,000 296,000 959,000
Middle Ridge
Proven 0.7 6.9% 12.8% 80.3% 48,000 90,000 563,000
Probable 1.4 4.6% 13.1% 82.3% 66,000 187,000 1,179,000
WBL
Proven 0 0 0 0 0 0 0
Probable 0.8 2.4% 16.5% 81.1% 18,000 128,000 629,000
Source: SRK
Notes:
1. Some numbers may not add up as a function of rounding.
2. Reserves are based on 100% mine recovery and 0% dilution. This is due to the small equipment being utilized and the
selectivity of the material being mined. This will require further review as part of additional studies.
3. Halloysite processing recovery is 90%.
4. Kaolinite processing recovery is 90%.
5. Quartz and K-Spar processing recovery is 68%.
6. Variable selling prices were used depending on supply.
7. There is an overall strip ratio of 0.69:1 (waste: ore).
Each pit pushback design was divided into benches for creating a yearly mine schedule. The mining
is controlled by the required mix to the plant. To address the percentages of kaolinite, halloysite, and
sand were converted into product tonnages. Those tonnages of all the products were calculated for
each of the mining areas in order to get specific product tonnage (which replaces grade in this study)
for each subdivision.
Mining for both pits take place on the slopes of low hills at an approximate elevation of 3,000 ft. The
pit depth is limited by 75 ft. The pit design for each deposit was divided into several phases for
production scheduling with 40 ft wide ramps at an in-pit road grade of 10% or less.
The mining operations will be performed by a mining contractor, and will be open pit mining using a
hydraulic excavator and a wheel loader to load haul trucks for waste and ore haulage.
Power and natural gas will be brought into the facilities by a local utilities supplier, Avista Corp.
Although most of the water for the processing facility will be recycled, necessary make-up water will
be supplied from ground water wells and a reservoir north of the mining areas as described in Section
18.
A wetland and ordinary high water mark boundary delineation of the Project area was conducted in
the summer and fall 2012. The delineation focused on areas of potential land disturbance associated
with roads, processing facilities, quarries, and tailing storage facilities. The goal of the field study was
to map areas of wetlands and waters of the U.S., and then to provide this information to the project
design team so that disturbance of these areas could be avoided. As such, if there is no fill or
disturbance to wetlands and other waters of the U.S., no Clean Water Act Section 404 permit would
be required. A wetland delineation report will be submitted to the U.S. Army Corps of Engineers
(USACE) for a formal jurisdictional determination.
Operating costs are estimated on preliminary mine and process design criteria, engineering, as well
as budgetary quotes. LoM operating costs are shown in Table 1.11.2. Over the LoM, operating costs
will be about US$70.72/t of product.
Project financial results justify advancing and refining the prefeasibility engineering designs to
feasibility level during the next 12 to 18 months. SRK recommends that I-Minerals conduct additional
infill drilling within the areas supporting the first 10 years of mine life to increase the confidence of the
reserve to a proven classification. Additional elements of the recommended work program include
environmental permit application support, additional geotechnical studies, testwork, modeling, and
engineering designs for the tailings and waste storage; marketing studies; hydrogeologic modeling;
more comprehensive metallurgical testing; and more detailed evaluation of process equipment and
infrastructure. The recommended work programs are estimated to cost US$3 million.
2 Introduction
2.1 Terms of Reference and Purpose of the Report
This report was prepared as a National Instrument 43-101 (NI 43-101) Prefeasibility Technical Report
for I-Minerals Inc. (I-Minerals) by SRK Consulting (U.S.), Inc. (SRK), Tetra Tech Inc. (Tetra Tech),
HDR Engineering, Inc. (HDR) and Roberts & Schaefer Company, a KBR Company (R&S/KBR), or
collectively (the Consultants). The quality of information, conclusions, and estimates contained herein
is consistent with the level of effort involved in SRK’s services, based on: i) information available at the
time of preparation, ii) data supplied by outside sources, and iii) the assumptions, conditions, and
qualifications set forth in this report. This report is intended for use by I- Minerals subject to the terms
and conditions of its contract with SRK and relevant securities legislation. The contract permits I-
Minerals to file this report as a Technical Report with Canadian securities regulatory authorities
pursuant to NI 43-101, Standards of Disclosure for Mineral Projects. Except for the purposes legislated
under provincial securities law, any other uses of this report by any third party is at that party’s sole
risk. The responsibility for this disclosure remains with I- Minerals. The user of this document should
ensure that this is the most recent Technical Report for the property as it is not valid if a new Technical
Report has been issued.
This report provides mineral resource and mineral reserve estimates, and a classification of resources
and reserves in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum Standards
on Mineral Resources and Reserves: Definitions and Guidelines, November 27, 2010 (CIM).
Within this document, the term, “K-feldspar” refers collectively to the mineral members of the feldspar
group containing a high potassium content, namely orthoclase, microcline and sanidine. In commercial
terms, K2O is generally > 10%. The term “Na-feldspar” refers collectively to the mineral members of
the plagioclase feldspar group containing high sodium content, namely albite, oligoclase and andesine.
In commercial terms, Na2O is generally > 7%. The term “feldspar” refers collectively to a material
mixture of either K-feldspar and/or Na-feldspar in undetermined ratios. The term “kaolin” is generally
used as the name of a rock that is made up mostly or all of the clay minerals from the kaolinite group.
“Kaolinite” and “halloysite” are two clay minerals in the kaolinite group and are hydrated
aluminosilicates with platelet morphology. “Halloysite” contains extra water that causes an imperfection
in its platelet, causing it to roll up, giving it a tube-like morphology.
None of the Consultants or any associates employed in the preparation of this report has any beneficial
interest in I-Minerals. The Consultants are not insiders, associates, or affiliates of I- Minerals. The
results of this Technical Report are not dependent upon any prior agreements concerning the
conclusions to be reached, nor are there any undisclosed understandings concerning
any future business dealings between I-Minerals and the Consultants. The Consultants are being paid
a fee for their work in accordance with normal professional consulting practice.
The following individuals, by virtue of their education, experience and professional association, are
considered Qualified Persons (QP) as defined in the NI 43-101 standard, for this report, and are
members in good standing of appropriate professional institutions. The QP’s are responsible for
specific sections as follows:
Bart Stryhas, PhD., CPG., SRK Associate Principal Consultant (Resource Geology), is the QP
responsible for Geology and Resource Sections 1.1 through 1.3, 1.5, 2 through 12 except for
4.4 and 5.5, 14, 23, 25.1, 25.2.1, 25.2.2, 26.1, 27 and 28.
Harry Gatley, P.E., R&S/KBR, is the QP responsible for Process and Metallurgy, Recovery
and Infrastructure Sections 1.4, 1.8, 5.5, 13, 17, 18 except 18.5, 21.1.2, 21.2.2, 25.2.4 and
26.5.
David S. Hallman, PE, Tetra Tech, is the QP responsible for Tailings Sections 18.5, 21.1.3,
25.2.5 and 26.4.
Manuel Rauhut, PE, HDR Engineering, is the QP responsible for Environmental and Permitting
Sections 1.9, 4.4, 20, 25.2.6 and 26.3;
Valerie Obie, BS Mining, RM-SME, SRK Principal Consultant (Mineral Economics), is the QP
responsible for Mining, Reserves and Economic Sections 1.6, 1.7, 1.10, 1.11, 1.12, 15, 16,
19, 21.1.1, 21.1.4, 21.2.1, 21.2.3, 22, 24, 25.2.3, 25.2.7, 26.2 and 26.6.
Dr. Bart Stryhas conducted site visits to the Project on May 12, 2010 and September 5, 2013. During
the 2010 inspection, Dr. Stryhas was met by Mr. Lamar Long, Project Manager of I-Minerals. Mr. Long
led a tour of the Project discussing the regional and local geology, inspection of the historic mining and
materials, explanation of the proposed mining and processing plan and reclamation plan. Dr. Stryhas
spent the afternoon in the field mapping.
On the 2013 inspection, Dr. Stryhas was met by I-Minerals staff including; Mr. Lamar Long, Project
Manager and Mr. Gary Nelson, Metallurgical Operations Manager. The morning was spent observing
diamond drilling procedures, sample chain of custody and geologic logging procedures. The afternoon
was spent at the University of Idaho’s custom clay testing facility in Moscow Idaho. Staff at the
laboratory provided detailed explanations of I-Mineral’s custom testing procedures, data transfer and
capture, SEM analysis and internal QA/QC procedures.
SRK Principal Consultant Valerie Obie and other report contributors have not visited the site.
Tetra Tech Inc. – Denver, Colorado (Tetra Tech)
Report contributor Ms. Jessica Spriet, PE, completed a site visit in May of 2011. She toured the site
with Mr. Lamar Long of I-Minerals and the previous QP for Tetra Tech, Mr. Justin Knudsen. Potential
tailings storage facility locations were visited and potential design issues were identified. Mr. Knudsen
has since left Tetra Tech and has been replaced by Mr. Dave Hallman as the QP. Mr. Hallman has not
visited the site.
Mr. Paul Slade (Project Manager) and Mr. Pete Gagestein (Sr. Mechanical Designer) of R&S/KBR
visited the Project site on October 6, 2010. They were met by Mr. Lamar Long and Mr. Gary Nelson of
I-Minerals. A tour was provided of the proposed processing plant site, tailings facility, mining areas,
and transload facility. In additional to obtaining a basic familiarization of the Project sites, a primary
focus of the visit was to investigate the proposed plant site topography for general layout design to be
used in future studies.
Mr. Laxmanarao Ravindra Nath, R&S/KBR Principal Process Engineer, visited the Minerals Research
Laboratory (MRL) at North Carolina State University in Asheville, NC on November 28, 2007. The
results from the MRL tests were the basis for the development of process and plant design criteria
used in the PEA.
Mr. Harry Gatley, P.E., has expertise in the review and verification of the process and layout design.
His previous experience with process design, water management, solids drying, and many other
industry phases led to his new assignment as the QP for R&S/KBR for this study.
Report contributor Michael Murray, PhD, HDR Vice President, visited the site on May 13, July 18, and
July 19, 2012, to assess general site setting and conditions including surface drainage patterns, soil
and vegetation conditions, wetlands, and wildlife habitat. Report contributor Christine L. Whittaker, LA.,
HDR Associate Vice President, visited the site July 18 and 19, and August 25 to 27, 2012, to conduct
wetland delineations and vegetation survey as well as to assess overall site conditions to support mine
permitting. HDR’s Manuel Rauhut and Diane Holloran have not visited the site.
The Consultants used their experience to determine if the information from previous reports was
suitable for inclusion in this Technical Report and adjusted information that required amending. The
QPs, Bart Stryhas, Ravi Nath, Dave Hallman, Christine Whittaker, and Valerie Obie, have examined
the data for the Project provided by I-Minerals, and have relied upon that basic data to support the
statements and opinions presented in this Technical Report. In the opinion of the QPs, the data is
present in sufficient detail, is credible and verifiable in the field, and is an accurate representation of
the Project.
This report includes technical information that requires subsequent calculations to derive sub-totals,
totals, and weighted averages. Such calculations inherently involve a degree of rounding and
consequently can introduce a margin of error. Where these rounding errors occur, they are not
considered to be material.
The authors have relied upon the work of others to describe the geology, exploration, land tenure and
land title in the state of Idaho, referring to Sections 4 – Property Description and Location and
4.2 – Mineral Titles and others. The information contained in these sections was obtained from “Report
on the Helmer-Bovill Feldspar, Quartz and Kaolin mineral Leases, Latah County, Idaho” prepared on
behalf of I-Minerals by James L Brown, PG.
Additionally, the authors have relied upon the independent market study by Charles River Associates
(CRA) dated December 2011 for Section 19 – Market Studies and Contracts. CRA is a leading global
consulting firm that offers economic, financial, and business management expertise to major law firms,
corporations, accounting firms, and governments around the world. Their marketing expertise is well
known in the business world.
The authors reviewed the December 2011 study, as mentioned above, against industry available data
and information, and found the results to be within industry standards and adequate for use in this
Technical Report at this level of study.
Prices for sand and clay products can vary dramatically depending upon the specifications and quality
each product produced. Due to the highly competitive nature of the industrial sand and clay industry,
contract prices are highly confidential and are not presented in public documents.
However, the QP for this Technical Report confirms that I-Minerals has, in fact, completed a market
study for its products which included preliminary negotiations to supply a series of clay and sand
products. The QP also confirms that the process facility is capable of producing these products.
The Project is located at geographical coordinates 46° 53’ 14.7” N. latitude and 116° 28’ 11.7” W
longitude (UTM NAD 27 Zone 11 N, coordinates 5,192,807 N and 440,392 W,) in Latah County, Idaho,
USA. (Figure 4.1.1).The property currently totals 5,140.64 ac in area. The mineral leases are not
contiguous, but are situated within three surveyed townships near the town of Bovill, Idaho.
properties primarily for profit through the production of timber, livestock grazing, and the extraction of
mineable materials.
The State of Idaho endowments lands fall in two categories referred to as Fee Simple (FS) and
Minerals Only (MO). The FS lands are where the State owns both mineral and surface rights. The MO
lands are where the State owns mineral rights but someone else owns surface rights. The majority of
the lands held by I-Minerals are FS. All mineral resources and mineral reserves described in this report
are located on FS lands. By way of its mineral leases, I Minerals has surface rights and legal access
to the Project provided it meets all permitting and bonding requirements administered by IDL. In the
State of Idaho, mineral leases are not required to be physically located in the field. The mineral leases
are currently described only on paper by the U.S. Public Land Survey Grid.
In 2002, I-Minerals acquired from Idaho Industrial Minerals (IIM), through its wholly owned subsidiary
Alchemy Kaolin Corporation, 16 State of Idaho mineral lease applications in Latah County, Idaho, to
cover deposits of feldspar, kaolin, and quartz located near Bovill, Idaho. In 2003, I-Minerals converted
these applications to ten mineral leases and subsequently obtained two more mineral leases. The
Project then consisted of 12 Idaho State mineral leases. Renewal applications for all 12 leases were
filed on April 27, 2012 with a US3,000 application fee. As part of the renewal process, the State
converted the 12 mineral leases into 10 revised mineral leases which were issued on February 28,
2013. Subsequently, during 2013 the State of Idaho granted one additional mineral lease to I-Minerals.
At this time, I-Minerals holds 11 mineral leases totaling 5,140.64 acres. All these are valid until 2023,
at which time; they can be renewed for an additional ten years. All leases are subject to rental fees of
US$1.00/acre/y and a production royalty of 5.0% based on gross proceeds. The production royalty is
prepaid at a rate of US500/lease for the first five years and increases to US1,000/lease for the second
five years of the lease. Details of the mineral leases are listed in Table 4.2.1 and shown in Figure
4.2.1.
The State of Idaho retains a 5% gross production royalty due upon commencement of any mineral
production.
I-Minerals submitted an original bond of US$750 to the IDL to cover environmental liabilities associated
with its exploration work. This bond has remained in place throughout the work programs but it was
refunded in December, 2012. On November 1, 2010, the State of Idaho changed its bonding program.
I-Minerals has been paying a reclamation bond of US100/lease per year since that time. All reclamation
bonding is current through October 31, 2014. The IDL has approved all reclamation conducted to date.
Exploration activities – I-Minerals has conducted exploration activities in accordance with Idaho
Administrative Procedure Act (IDAPA) 20.03.02.060 – Exploration Operations and Required
Reclamation. I-Minerals filed an original Notification of Exploration (NOE) to the IDL in 2000, which
was subsequently amended for surface exploration and drilling programs. Exploration disturbances
have been reclaimed and approved by IDL.
Mining activities – I-Minerals is permitted through an approved Mine Plan of Operations and
Reclamation Plan from IDL for the mining of approximately 10 acres of feldspathic sands from June
through October for up to 10 years (2012 through 2022). The feldspathic sands were deposited as
tailings from clay mining operations that occurred on or near the Company’s mineral leases between
1956 and 1974. These activities are conducted under aNPDES 2008 MSGP for Stormwater
Discharges Associated with Industrial Activities (Permit Number IDR05CU73). The stormwater permit
became effective on November 8, 2012.
A review of Project plans identified a range of environmental permits, review processes, and
authorizations needed for construction, operation, and closure. Development of the Project would
require approval of a Plan of Operations and Reclamation Plan by IDL (IDAPA 20.03.02), a NOI for
coverage under the federal NPDES General Permit for Stormwater Discharges from Construction
Activities, and a NOI for coverage under the NPDES MSGP for industrial activities (Sector J3: Chemcal
and Fertilizer Mineral Mining and Dressing/Clay, Ceramic, and Refractory Materials). In addition, a
state air quality permit for emission sources including dryer stacks and fugitive dust will be required.
Closure of the mine requires approval through IDL of a detailed mine site reclamation and tailings
closure plan. Also, monitoring of certain resources will likely be mandated through the state mine
permitting process as well as through the federal NDPES stormwater general permits.
The goal of Project design is to avoid fill in jurisdictional wetlands and other waters of the US, such
that no Clean Water Act Section 404 permit would be required. No federal lands or federal permits
(except for the stormwater general permits) are involved in the Project plans, and as such no National
Environmental Policy Act (NEPA) environmental review of the proposed Project is anticipated (other
than resource information required as part of the stormwater general permits).
A description of permitting requirements, risks, and other important factors are described in Section
20.
The Project area consists of low foothills and ridges alternating with relatively wide, flat basins.
Forested areas occupy the slopes and ridge tops which are managed primarily for timber production.
Conifer forest makes up approximately 50% of the overall Project area. Forest stands were observed
to be early seral, highly fragmented, and lacking in the ecological functions and values of older, more
contiguous forests. Grasslands occur in the basins alongside sinuous intermittent and perennial stream
channels. The Project area is currently permitted for livestock grazing. Most of the Project area has
been disturbed by previous mining, forestry and grazing activities and, as such, contain predominantly
disturbance oriented plant communities. Non-forested meadows or pasture areas are intensively
grazed resulting in a proliferation of non-native vegetation and soil compaction and erosion.
Surface waters primarily consist of small, meandering, intermittent stream channels that flow toward
the Potlatch River. These channels are typically located in the level “flats” between low hills or
ridgelines and dry up by mid or late summer. Most streams are hydrologically altered by high-density
road construction, historic mining, and cattle grazing. Grazing has also eliminated much of the woody
growth along most stream channels resulting in eroded channels and sedimentation. Other surface
waters include several old clay mining pits and small dams that have developed into water catchment
basins as well as emergent wetlands flanking the stream channels. Groundwater appears in scattered
locations as either springs or seepage discharge along streams or edges of wetlands. Native soils
predominate in the area.
Available records (February 1950 to February 1975) from the Clarkia Ranger Station weather station
indicate an average total snowfall ranging from 0.1 inch in October to 37.3 inches in January, with an
annual average of 100.9 inches. Average snow depth ranges from 1.0 inch in November to 23.0 inches
in February, with an annual average snow depth of 6.0 inches (WRCC, 2010).
Natural gas is available to the Project from a natural gas pipeline that extends from Moscow to Bovill
and is available to be utilized for this processing facility. Approximately two miles of pipeline would
need to be constructed.
Water needed for processing would come from new wells located at the process site. Groundwater
from drilled wells is typically used to serve domestic needs within the vicinity of the Project. Additional
water is also available in a small reservoir north of the Project. I-Minerals intends to apply for water
rights to this reservoir in the near future.
The region has a long history of clay production, forestry and farming. A labor force skilled in heavy
equipment operation, trucking, and general labor exists within the surrounding communities and rural
areas. Additional information about the local community is provided in Section 20.3.
There are several suitable locations for potential tailings storage, mining waste disposal, and potential
processing plants.
6 History
Section 6 summarizes the prior history of the Project.
During WWII, the clays in eastern Washington and northern Idaho were examined as a possible source
of alumina and a substitute for foreign bauxite ores. Domestic bauxite reserves were being depleted,
and the importation of foreign bauxites was handicapped by transportation difficulties (Hosterman, et
al., 1960). Both the USGS and USBM conducted extensive field studies that were followed by the
drilling of 650 holes that totaled about 20,252 ft. From this work, over 300 Mt of clay were identified in
this region with available alumina greater than 20%. About 90% of this tonnage was found in four
deposits in Latah County-Bovill, Olson, Canfield-Rogers and Benson deposits (Hosterman, et al.,
1960).
At the Bovill deposit, just west of the town of Bovill, 11 holes were drilled on approximately 1,000 ft
spacing in an 8,000 ft x 14,000 ft area. The average overburden in this area, which is about 900 ac in
3
size, is about 10 ft thick and the average thickness of the clay is 21 ft. Using a density of 2.15 g/cm
for clay in place, Hubbard (1956) calculated an indicated clay resource of over 57 Mt, where the clay
has available alumina averaging 21.8% and Fe2O3 4.0%. He also estimated an additional inferred clay
resource of 27 Mt for a 650 ac area, adjacent to the aforementioned area, with a clay layer thickness
of 20 ft, an available alumina of 20%, and Fe 2O3 of 4.0%. Both of these resource calculations are
unconfirmed and uncategorized in terms of NI 43-101.
USBM (1953-1963)
In 1953 the USBM continued their search for viable clay deposits. They also investigated the potential
of the contained silica sand for the glass industry. The USBM tested the Benson and Olsen clay
deposits between Troy and Deary, and then moved on to the Bovill deposits. Ninety-seven samples
were collected from 1,325 ft of drilling over an area covering 750 ft x 350 ft that is located
1.5 miles southwest of Bovill near State Highway 8 (Kelly, et al., 1963).
In 1956, A.P. Green Refractories Company purchased all the remaining assets of Troy Brick and Clay
and acquired a lease on Section 11, T.40N., R.1W., north of Helmer, from which they produced
refractory clay. They processed the clay by air flotation to produce two grades of refractory clay.
Production continued until the early 1990’s when Hammond Engineering purchased one pit from
A.P. Green. This pit produced transported clay for ceramic applications. Total production from the area
during this period is estimated to be 250,000 t. Erikson (1986) estimates that 10,000 t/y were produced
from 1956 to 1986.
J.R. Simplot Company (1956-1974)
In 1956, the J.R. Simplot Company (Simplot) of Boise, Idaho, acquired leases covering the Bovill
deposits. In a cooperative program, Simplot and USBM drilled 240 holes (99 of which were on 50 ft
centers) and conducted washing, pyrometric, mineralogical, and beneficiation tests (Kelly, et al., 1963).
By 1962, Simplot had built a clay plant, the Miclasil facility, for the production of paper fillers
and specialty ceramics (Hosterman and Prater, 1964). Production initially came from pits in the Bovill
deposit as defined by Kelly, et al. (1963), which are in transported clay of the Latah formation directly
south of the plant. Simplot shifted production to residual clay deposits in the granodiorite, as this source
proved more satisfactory for paper filler (Hosterman and Prater, 1964). The pits exploited by Simplot
for residual clays were the WBL north and south pits in Section 23, T41N, R1W and the Moose Creek
Clay Mine in Section 28, T41N, R1W in the Moose Meadows area, and the Stanford pit in Section 5,
T40N, R3W. Simplot operated their plant until 1974, when it was sub-leased to Clayburn Industries
of British Columbia (Rains, 1991). Reportedly, Clayburn operated the property only a few years,
calcining clay that was shipped to Canada and processed into super-duty and 70% alumina bricks. In
1994 the plant was dismantled and the property partially reclaimed.
Several Companies (1983-1986)
During the mid-1980’s a number of companies began exploration work in the Helmer-Bovill area to
identify clays suitable for use as paper fillers and coaters. The University of Indiana, Nord Resources,
Miles Industrial Mineral Research, and Cominco American conducted work on the Helmer-Bovill area
deposits. In 1985-1986, the Erikson- Nisbet Partnership formed a consortium of companies to develop
new processes for beneficiation of the clays, but the introduction of precipitated calcium carbonate
(PCC) fillers for paper reduced the demand for kaolin fillers.
During the Middle Proterozoic, the area was dominated by a large intra-cratonic basin that was
subsiding along syn-sedimentary faults. The basin sediments comprise the Belt which range in age
from about 1,470 to 1,400 Ma. The oldest units consist of the Lower Belt sequence, these are overlain
by the Middle Belt Carbonates and the youngest are the Missoula Group.
The Belt sediments are believed to have remained relatively stable until approximately 1,350 Ma when
portions of the basin were affected by compressional tectonics of the East Kootenay Orogeny. This
orogeny was followed by rifting of the basin during the late Proterozoic-early Paleozoic when large
portions of the sediments were transported away and the western margin of North America was
developed.
The next major tectonic event occurred during the Cretaceous Sevier Orogeny. Early compressional
tectonics dominated the area forming large-scale folds, reverse and thrust faults. During the late
Cretaceous, the Bitterroot Lobe of the Idaho Batholith was emplaced in the region. The intrusive rocks
described below were formed during this event.
The most recent, significant, geologic event was the deposition of the Columbia River Basalts (CRB).
The CRB consist of a large plateau flow sequence of Miocene age (6 to 17 Ma). The lavas are
distributed over an extensive area covering portions of Idaho, Oregon, and Washington. Minor
extensional block faulting has resulted in much of the present landscape. Figure 7.1.1 illustrates the
regional geology of the Project.
The Precambrian metasediments of the Belt series are the oldest rocks in the Bovill-Moscow area and
form the basement for the entire area (Tullis, 1944). The Belt series rocks crop out primarily in the
northern and eastern sections of the Property. They form a high-grade metamorphic facies
assemblage that includes gneiss, schist, and minor meta-quartzite, meta-argillite, and meta-siltite.
Thatuna Granodiorite
Granitoid intrusive rocks of Cretaceous age underlie a large portion of the Helmer-Bovill area and form
part of a body referred to by Tullis (1944) as the Thatuna batholith. He believed that this intrusive body
was separate from the Idaho batholith, owing to the distance between the two. However, Priebe and
Bush (1999) consider the Thatuna granodiorite to be a lobe of the Idaho batholith. Tullis (1944)
reported the Thatuna lithologies to consist predominantly of granodiorite with subordinate adamellite,
tonalite, and granite. The principal mineral constituents are quartz, plagioclase feldspar, K-feldspar,
and biotite with trace to minor amounts of muscovite, garnet, and
epidote. The batholith is medium- to coarse-grained granular, and porphyritic textures are common.
Erosion of the Thatuna batholith developed a mature topography where it is exposed in Latah County
(Kelly, et al., 1963).
Recent geological mapping done for the benefit of this Project, detailed in an internal company report
by Clark (2003a), identified a previously undescribed phase of the Thatuna batholith, referred to as the
Kmcp. The Kmcp is interpreted to be a border zone of the intrusion that occurs along the interface
between the main-stage, coarse-grained, and porphyritic Thatuna batholith and the Precambrian Belt
series roof rocks. Intrusion into cooler roof rocks resulted in a distinctive and texturally diverse unit
characterized by dominant granular medium-grained and subordinate coarse- grained and pegmatoid
textures, the lack of well-developed porphyritic textures and the presence of Precambrian xenolithic
paragneiss, paraschist and metasiltite blocks inherited from the roof rocks. Where unaltered, the Kmcp
intrusive rocks contain a primary assemblage of plagioclase, K-feldspar, quartz, biotite, and muscovite,
and are predominantly of granodioritic to granitic composition. The porphyritic main body of the
Thatuna batholith (Kg, Kgd) does not appear to crop out within the mapped part of the Helmer-Bovill
area.
According to Clark (2003a), the Kmcp derives its distinctive character from high-level interaction with
the Precambrian metasedimentary roof rocks. More rapid cooling in the contact zone produced a
dominant medium-grained, non-porphyritic, granodioritic unit in contrast to the coarser-grained,
porphyritic granodiorite lithology that characterizes the deeper main stage of the batholith (Kg, Kgd).
In the roof zone, hydrous mineral-bearing xenolithic blocks of the Precambrian Belt series
metasediments were entrained by the intruding magma and outgassed of their volatile component.
The outgassing contributes to the creation of pockets of hydrous granitic liquid proximal to the
Precambrian blocks. These pockets crystallized subsequently into coarse-grained to pegmatoid
granite pods that are distributed within the larger body of medium-grained granodiorite. Owing to the
physicochemical conditions of crystallization within the hydrous pods of granitic liquid, the resultant
solidified rocks show a stronger tendency toward higher proportions of K-feldspar relative to
plagioclase and higher K2O/Na2O ratios than does the dominant medium-grained granodiorite.
Weathered Thatuna Granitoid
The exposed Thatuna batholith was subjected to intense weathering in a tropical or near-tropical
climate during the Miocene epoch, while the Columbia River basalts were erupted and the Latah
formation sediments were deposited (Hosterman, et al., 1960). In response to the strong weathering,
much of the feldspar and at least some of the mica in the igneous body were altered to one or more
varieties of clay minerals. The depth limit of weathering may initially have been fairly consistent;
however, subsequent erosion has left a variable weathering profile with thickness roughly dependent
on topography. At present, the depth of weathering may exceed 100 ft along ridges and be less than
3 ft in some valleys.
The weathering profile of the Thatuna granodiorite is currently under study by I-Minerals, owing to its
importance in determining the range of mineral products that can potentially be produced from a given
area on the Property. Of particular importance is the weathering of the feldspar in the granitoids to
halloysitic to kaolinitic clays. It was the presence of kaolinitic clay deposits that provided the initial
impetus for economic mineral development in north Idaho. Plagioclase (Na-Ca bearing) feldspar is the
least stable phase in the weathering environment, and it alters to form clay well before K-feldspar and
muscovite (Murray, et al., 1978). K-feldspar and the micas (biotite and muscovite) are
relatively resistant to alteration during all but the most intense weathering. Quartz is impervious to
alteration throughout the weathering cycle. In the Helmer-Bovill area, pits that were mined for kaolin in
residual deposits contained mostly quartz, halloysite, kaolinite, and K-feldspar. The waste material is
primarily quartz and K-feldspar, with Na-feldspar (plagioclase) accounting for only a minor proportion
of the total feldspar. Na-feldspar made up less than 5% of the total feldspar in a tailings sample
examined by Clark (2003b). Residual clay deposits in the Helmer-Bovill area reflect this mineral
distribution and targeted commodities from strongly-weathered Thatuna granitoid are kaolin, quartz,
and K-feldspar.
The Potato Hill volcanic rocks were tentatively considered to be of Permian age by Tullis (1944), but
Bush, et al. (1999) interpreted field relationships to indicate an Eocene age. The silicic to intermediate
volcanic rocks include both lava flow and pyroclastic flow units, as well as hypabyssal intrusive rocks.
They form much of the rock along the western edge of the Helmer embayment at Potato Hill, and along
the southern edge of the Thatuna. Many of the pyroclastic flows contain abundant xenolithic clasts of
older granodiorite and Belt metasediments.
The individual flows are 3 to 50 ft thick and the complete sequence exceeds 900 ft in thickness. The
flow units generally contain 3% to 10% phenocrysts of feldspar and quartz distributed in an aphanitic
matrix of devitrified volcanic glass. Accessory minerals include magnetite, hornblende, apatite, and
zircon. Some lithic-rich pyroclastic flow units carry up to 20% fragments. The saprolitic weathering that
is well-developed in the older rocks has not appreciably affected the Potato Hill volcanics.
Swanson, et al. (1979) described the stratigraphy of the basaltic units and divided them into 14
members assigned to five formations. Two flow units are interpreted to have reached Latah County by
Swanson, et al. (1979), although Priebe and Bush (1999) have mapped at least five distinct flow units.
The First Normal member of the Grande Ronde formation, the Priest Rapids member of the Wanapum
formation, and the Onaway member of the Saddle Mountain formation (oldest to youngest,
respectively) are all Columbia River basalt flows mapped by Priebe and Bush (1999) in the Helmer-
Bovill area. The Grande Ronde formation flow occurs in the southern portion of the Helmer- Bovill area
and consists of fine-grained to very fine-grained aphyric basalt. The Priest Rapids flow is a medium to
course-grained basalt with microphenocrysts of plagioclase and olivine in a groundmass of
intergranular pyroxene, ilmenite, and devitrified glass. It crops out in increasing abundance to the
southwest toward Deary. Saddle Mountain basalts are found much further to the west. The importance
of the Columbia River basalts to the genesis of the Latah formation is that the episodic basaltic
extrusion dammed streams and formed lakes into which kaolin-rich sediments eroded from weathered
granitoid and Precambrian metasediments were deposited (Kirkham and Johnson, 1929).
Kirkham and Johnson (1929) described the Latah formation as lake bed sediments that, although local
in origin and distributed in disconnected basins, occur over an area 175 miles long and 75 miles wide
in eastern Washington and northern Idaho. Episodic flows of the Columbia River basalts blocked
streams and formed lakes that collected sediments eroded from surrounding rocks. In the Helmer-
Bovill area, a major basin termed the Helmer embayment (Hosterman, et al., 1960) occurs
2
over an area of approximately 25 to 30 mi . Latah formation sediments are termed the sediments of
Bovill (Tsb) by Bush, et al. (1999) and are described as clay, silt, sand and minor gravel deposits that
are laterally equivalent with and overlie flows of Columbia River basalts. The clays are white, yellow,
red and brown in color, kaolinite-rich, and range from a few feet to several tens of feet in thickness.
Palouse Formation
The Palouse Formation comprises mixed loess and flood plain sediments of Pleistocene age. It ranges
in thickness from 3 to 35 ft in thickness and averages 10 ft thick in the Helmer embayment. The
unconsolidated layers also include volcanic ash from the eruption of various Cascade Range
volcanoes.
The primary Na-feldspar deposits are hosted within granitic border phases of the Thatuna granodiorite.
These deposits are described in detail in a previous I-Minerals report (SRK, 2010).
The transported clay deposits are hosted primarily within the Latah formation. This formation was
deposited primarily in shallow lakes dammed by Columbia River Basalts. Extensive weathering of
feldspathic source terrains constitutes the provenance of these clays.
The K-feldspar-quartz tailing deposits are the result of previous mining and washing of the residual
deposits. Here, the majority if the clay has been removed and the tailings are composed primarily of
K-feldspar and quartz. These deposits are described in detail in a previous I-Minerals report (SRK,
2012b).
The residual deposits are derived from saprolitic weathering of the Thatuna granodiorite-granitic
phases. In general, the Na-feldspar alters to kaolinite and halloysite. These clays are accompanied by
residual K-feldspar and quartz. These deposits are described in detail in a previous I-Minerals report
(SRK, 2012a) and are the subject of this report.
The information in the following sections has been cited with minor modifications from “The report on
the Helmer-Bovill feldspar, quartz, and kaolin mineral leases, Latah County, Idaho” on behalf of I-
Minerals Vancouver, B.C. by James L. Browne, PG March 13, 2006. These citations are intended to
inform the reader of the general geologic setting as it pertains to the four deposit types described
above.
7.3.1 Feldspars
Tullis (1944) described the main lithologies in the Thatuna Batholith as consisting primarily of
granodiorite with subordinate adamellite and tonalite and minor granite. Total feldspar content in these
intrusive rocks is reported by Tullis (1944) to range between 47.4% and 80.6%, with an average of
about 62.7% total feldspar. By definition (Streckeisen, 1976), granodiorite contains an abundance of
plagioclase feldspar in excess of 65% of the total feldspar. Thus, the unweathered Thatuna represents
a source carrying a high total feldspar abundance, of which a significant proportion is Na-bearing
feldspar (sodic plagioclase).
Clark (2003a) collected many samples of Thatuna batholithic rocks from the Moose Meadows portion
of the Helmer-Bovill area during his mapping program in 2002 and from core drilled during the 2000-
2001 diamond-drilling program. Results from the petrographic work indicate that intrusive lithologies
range from granodiorite to quartz monzonite (one sample) to granite, with granodioritic rocks being the
most common. Estimated total feldspar abundances for these samples range from 60% to 82% and
average about 71.5%. Following the petrographic and cathodoluminescence work, electron
microprobe analyses of feldspars and quartz from representative samples were undertaken in order
to quantify feldspar compositions and determine potential product quality in terms of alkali abundances
and suitably low Fe2O3 contents (Clark 2003a, 2003b). Petrographic analyses of the Kmcp samples
show that contained feldspars rarely have inclusions of Fe-bearing minerals (biotite, muscovite, or
FeOx; Clark, 2003a, b).
In the strongly weathered Thatuna Batholith rocks plagioclase shows nearly complete alteration to a
kaolin mineral, but much of the K-feldspar survives alteration. This is illustrated by sample IK81,
collected from the Stanford Pit, about 11 miles WSW of the Moose Meadows area. Plagioclase was
not identified by the X-Ray Diffraction (XRD) analysis. These results correspond well with the
mineralogy of the material in the tailings impoundment adjacent to the pit. The tailings contain essential
quartz and K-feldspar, some clay/mica, and only minor amounts of plagioclase.
7.3.2 Quartz
Petrographic examination of 21 granitoid samples from the Moose Meadows area led Clark (2003a) to
conclude that quartz in Thatuna batholithic rocks is relatively free of Fe-bearing mica or oxide
inclusions. The average quartz composition calculated from electron microprobe analyses of quartz in
drill core, surface outcrop, and processed quartz product samples from the Moose Meadows area
granitoid (Clark, 2003b) is given in Table 7.3.2.1, along with two analyses of MRL quartz products from
Moose Meadows granitoid (WBL pit and an interval from drillhole MC-22) and one of a commercial
mid-western U.S. glass sand:
Table 7.3.2.1: Average Quartz Composition Calculated from Electron Microprobe Analyses
Product SiO2 (%) Al2O3 (%) Fe2O3 (%) CaO (%) Na2O (%) K2O (%)
Avg. quartz analysis >99.9 0.004 0.003 0.004 0.009 0.007
MRL-P quartz prod 99.8 0.15 <0.01 <0.01 <0.05 0.08
MC-22 quartz prod 99.7 0.19 <0.01 <0.01 0.08 0.05
Mid-west glass sand 99.5 0.15 0.09 0.01 0.01 0.04
Source: Clark, 2003b
The analytical values for the trace elements in the quartz are very near or below detection limits for
the electron microprobe and indicate that quartz from the Moose Meadows area is essentially free of
impurities. This data suggests that the area has excellent potential to produce a glass-grade product
that might be processed further into feed stocks for the high purity quartz market.
platelets, whereas halloysite forms tubes and spheroids. Although halloysite also has a plate-like
crystal form, imperfections in its crystal lattice cause the crystal to “roll up” into the tubular forms. There
are two varieties of halloysite, the four-water variety and the two-water variety. The two-water variety
is a dehydrated version of the four-water halloysite and is almost impossible to distinguish from poorly
crystallized kaolinite. Both varieties of tubular halloysite and poorly crystallized kaolinite exhibit poor
viscosity, and their use is limited to fillers and ceramics. Well-crystallized kaolinite generally exhibits
good viscosity properties and is suitable for high quality ceramics and paper coaters.
Most of the mineralogical work (Kelly, et al., 1963; Yuan, 1994; GMT, 2005) completed on the Helmer
embayment clays indicates that the transported, sedimentary kaolins consist predominantly of
kaolinite, but have a significant halloysite component. Yuan (1994) sampled clays from both the
A.P. Green Refractories Company (A.P. Green) pit near Helmer and Simplot's Miclasil pits near Bovill.
The main producing clay bed in the A.P. Green pit is 10 ft thick and includes several thin (1 to 6 in)
interlayers of white to yellow tonsteins. The clay fraction in the main clay bed contains variable
proportions of kaolinite and halloysite. Kaolinite abundance in the clay fraction ranges between 42 and
100%, while halloysite abundance ranges from 58 to 0%, respectively. Ginn Mineral Technology, Inc.
(GMT) recognized only minor halloysite in a bulk sample from the same pit (GMT, 2005). The tonstein
interlayers are generally all halloysite, the spheroidal halloysites that Yuan (1994) found to have low
viscosities. Historically, Simplot mined sedimentary clay from their Miclasil pits west of Bovill for paper
filler, but later switched production to residual clay pits. A.P. Green mined sedimentary clay from their
pit north of Helmer for refractory brick.
Residual clays developed on weathered granitoid in the Helmer-Bovill area are a mixture of halloysite
and kaolinite, with the concentration of each dependent upon the degree of weathering. The halloysite
content increases with depth as the effects of weathering diminish (Yuan, 1994). He reported that
kaolinite abundance can be as high as 100% of the clay fraction in samples taken near surface, while
samples collected deep in old pits reach 100% halloysite. In tests on two samples from the WBL north
pit, GMT (2005) demonstrated that there is a significant halloysite fraction in the residual clay. It is
difficult to say where the samples discussed by Yuan (1994) occur within the weathering profile in this
area. Historically, Simplot produced a filler clay for the paper industry from residual clay mined in the
Moose Meadows area (Hosterman and Prater, 1964). The work done by GMT (2005, 2006) indicates
that the quality of the residual clay from the WBL pit is high enough to be used in some high-end
specialty uses in paper, paint, and ceramic markets. New technologies in kaolin processing have made
further research into the high-grade markets worthwhile. However, work done by I-Minerals and further
continued by GMT (2008) show that a wet process using cyclones can product a halloysite product
that is sufficient to gain attention of halloysite markets.
8 Deposit Type
8.1 Mineral Deposit
The residual deposits consist primarily of K-feldspar, quartz and clays and comprising the mineral
deposit of this report. The mineral deposit is underlain by the Thatuna Batholith, composed mainly of
Na-feldspar, K-feldspar and quartz. Weathering has created a residual saprolite horizon which directly
overlies the bedrock from which it was derived. During the natural processes of weathering, the original
plagioclase feldspars have preferentially broken down to produce the clays kaolinite and halloysite.
The K-feldspars have resisted weathering to a degree and much of the original component remains
as free grains. Similarly, the quartz component of the host rock remains as free grains in the weathered
material.
Halloysite clay, an aluminosilicate with hollow tubular morphology in the submicron range;
Kaolinite clay, hydrated aluminum silicate; used in ceramics, rubber, plastics, etc and when
calcined becomes a metakaolin clay, or dehydroxylated kaolin clay, which is reactive
(Pozzolan) and enhances the strength, density and durability of concrete and ceramics;
K-feldspar, uniquely suited to ceramic formulations requiring an alumina source; and
Quartz, SiO2 silicon dioxide.
9 Exploration
9.1 Procedures and Parameters of Surveys and Investigations
During the period from 1999 through the end of 2001 the exploration work included the acquisition of
over 6,000 ac of mineral lease applications, the compilation of an extensive file on the results of
previous operations, and drilling.
During 2002 and 2003, geologic mapping and petrographic studies were performed. An electron
microprobe analytical study was conducted on field samples, quartz products and feldspar products
from earlier work. Following petrographic and microprobe studies, select intervals of residual deposits
from the 2000-2001 drilling program were sent to Mineral Resource Laboratory (MRL) for process
testing.
All exploration work completed on the property since 2003, has been diamond core drilling.
10 Drilling
10.1 Type and Extent
During 2000-2001, a 41-hole diamond drill program was completed at the Project, focused on both
bedrock feldspar deposits and residual deposits. Approximately 50% of the drillholes penetrated
residual deposits at or very near the surface. A total of 4,063 ft. were drilled during this program. All
holes were surveyed by Rim Rock Surveying. This work is described in two previous Technical Reports
by Hodgson (2000) and Montgomery (2002).
In 2003, a 12-hole, diamond drill program was completed at the Project, testing for residual deposits
over a broad area. A total of 1,333 ft. were drilled in this program. The core was split, sampled, and
described in detail within a previous Technical Report by Clark (2004a) and in petrographic reports
prepared for I-Minerals (Clark, 2003c; 2004b; 2004c; 2004d). All holes were surveyed with a hand held
GPS with an accuracy of several meters.
In 2007, a 28-hole, diamond drill program was conducted to further evaluate the residual deposits. Six
holes were located in the WBL Pit area on 200 to 600 ft spacing. The remaining holes were spread
over the entire property to test those areas believed to be underlain by the weathered Thatuna
granodiorite, establishing several new prospective areas. A total of 3,529 ft were drilled during this
program. The six holes located at WBL Pit were surveyed by Jamar and Associates and all remaining
holes were surveyed by handheld GPS with an accuracy of several meters.
In 2010, a 10-hole, diamond drilling program was completed in the WBL Pit and Middle Ridge areas.
Five holes were completed in each area, on 400 to 900 ft spacing. A total of 1,195 ft were drilled in this
program. All holes were surveyed by Taylor Engineering with a differential GPS to cm accuracy.
In 2011, a 66-hole, diamond drilling program was conducted in the WBL Pit and Middle Ridge areas.
At Middle Ridge, 45 holes were drilled and at WBL, 21 holes were drilled. These holes were mostly
located on 200 ft spacing with a few on 400 ft. A total of 7,747 ft were drilled during this program. All
holes were surveyed by Taylor Engineering with a differential GPS to cm accuracy.
In 2013, a 167-hole, diamond drilling program was conducted in the Middle Ridge deposit and in two
new areas referred to as Kelly’s Hump North and South. At Middle Ridge, 21 additional holes were
completed to provide a drill pattern on 100 ft spacing in the area hosting higher halloysite grades. In
the Kelly’s Hump area, a phase one program was completed with 17 holes spread though out the
elevated area of the north south trending ridge. These were generally spaced at approximately 400-
800 ft with all but one, located in the northern area. A phase two program was completed with 113
additional holes in the northern area and 16 in the south. The majority of drilling at Kelly’s Hump North
is on 100 ft spacing. The drilling at Kelly’s Hump South is all on 200 ft spacing. A total of 17,811 ft.
were drilled during this program. The drill hole locations were first laid out by Taylor Engineering with
a differential GPS and then once the drill rig was set up any offsets were measured with a tape
measure.
The drillhole database supporting the resource estimation of this report consists of 322 diamond core
drillholes totaling 35,909 ft. (Figure 10.1.1). The shallowest hole is 20 ft, the deepest is 260 ft, and the
average is 112 ft. All drillholes are oriented vertically and none of the holes have down hole deviation
surveys. Since all of the drilling is relatively shallow the lack of down hole deviation survey
has no material impact on the sample location. Since many of the older drillholes are located with a
hand held GPS their elevations do not match the current, high resolution topographic surface. For this
reason, all drillhole supporting the resource estimation of this report, are draped onto the high
resolution topography to provide a uniform basis of elevation control. Typically, the sample recovery
was very good ranging from 60 to 100%. The average core recovery is 87%.
The drilling has been conducted by reputable contractors using industry standard techniques and
procedures. This work has defined zones of residual deposits derived from weathered granitoid
overlying the Thatuna batholiths. These zones generally are continuous, following topography or lying
sub horizontal down to an average depth of 70 ft below surface. The zones are thicker along ridges
and thin toward the valleys. The drillholes are all oriented vertical and the deposits are interpreted to
be sub-horizontal. Therefore, the drill intercepts do represent an approximate true thickness of the
mineralization.
SRK is of the opinion that the drilling operations were conducted by professionals, the core was
handled, logged and sampled in an acceptable manner by professional geologists, and the results are
suitable for support of a NI 43-101 compliant resource estimation.
During collection of the drill core samples, the core barrel was removed from the hole and the core was
allowed to slide into the core box, with the top of the interval at the top left of the core box. Poorly
consolidated core was scraped with a sharp instrument and hard core scrubbed with a brush to remove
adherent drilling mud from the core. The core boxes were labeled with hole number and footage interval
on tops and bottoms. The core was transported to the I-Minerals' core facility near Moscow, Idaho at
the end of every drilling shift. The core is all stored in a locked building prior to sampling. Once it has
been logged and sampled it is moved to a locked core shed or a locked storage container. As part of
the logging procedure, drill core was described in detail, and the descriptions were recorded on a
standardized, hand written drill log form. A knife or chisel was used to split the core in half, and quarter-
splits were made from one of the halves. In the 2007 and 2010 programs, one quarter-split in the
visually clay-rich zones was bagged as a geochemical sample in intervals of uniform lithology that
generally did not exceed 5 ft. The clay in the bag was crushed by hand and the bag was shaken up to
thoroughly mix the sample. In general, sample intervals were 5 ft in length for the clay testing and
10 ft in length for whole rock geochemistry unless lithic contacts required a shorter interval. In the 2011
and 2013 programs, the one quarter-split is bagged and saved for clay testing in the laboratory at the
University of Idaho. Sample intervals are no thicker than 5 ft down to 50 ft in depth and 10’ below that.
Two hand-dug channel samples of approximately 150 lb each, were collected from the North WBL Pit
and a single sample of about 120 lb was collected from a pit in the southern portion of the property.
These were collected as channel samples with pick and shovel from the face of the pit after the face
was cleaned by scrapping with a hoe. The sample material was shoveled directly into 5 gal buckets
lined with plastic bags. Bags were tied, and the buckets were sealed, palletized and shipped directly to
the laboratory.
Two large bulk samples of residual deposit were collected from the North WBL Pit. In 2005, a 1.5t
sample was taken and in 2007, a 2.0 t sample was taken. Both were collected by a Kobelco 905LC
excavator with a 3 ft wide bucket. The pit face was scraped to expose fresh material prior to sampling.
The excavator dug across the face, taking as much as possible in both vertical and horizontal
directions. Once the bucket was filled, the material was hand shoveled into a 1-t super sack. These
sacks are brand-new woven plastic bags that are constructed to handle heavy loads. The sacks were
tied shut and shipped directly to the laboratory. In discussions with I-Minerals personnel, it is
understood that these samples are not representative of the entire clay deposit, but they should give
a good idea of the character of the material, such that a testing program can be designed.
11.2 Laboratories
Analysis of the drill core to support the resource estimation was conducted at four laboratories. Whole
rock analysis was completed at ALS Global (ALS) and material characterization studies were
undertaken at Ginn Mineral Technology (GMT), a laboratory at a commercial clay operation(CCL) and
at the University of Idaho (UOI).
Whole rock sample preparation and geochemical analysis was completed at ALS in Vancouver, British
Columbia. The sample preparation was standard procedures to support the X-ray fluorescence (XRF)
analytical method used. ALS is an ISO 9002 certified, international corporation and its analytical
services are highly respected by the mining industry.
GMT is located in Sandersville, Georgia, in the heart of the Georgia kaolin belt. GMT is a technology-
based company focusing on industrial mineral and base metal resources, fine particle process and
product development, and the commercial application of minerals. GMT is the foremost independent
kaolin process testing laboratory in North America. GMT is not ISO certified.
A commercial clay operation’s private laboratory (CCL) was used to determine recoveries of different
size fractions and to obtain specific characteristics of the clay fraction. The laboratory itself is not ISO
certified.
The University of Idaho’s Geological Engineering Department (UOI), located in Moscow, Idaho was
utilized for particle characterization studies and scanning electron microscopy (SEM) for the majority
of the samples supporting the resource estimation of this report. Some of the 2013 SEM work was
completed at Washington State University in Pullman, Washington. The UOI is not ISO certified.
11.3 Analysis
Whole rock sample preparation and geochemical analysis was completed at ALS. The sample
preparation was standard procedures to support the X-ray fluorescence (XRF) analytical method used.
The material characterization studies provide the primary support for the resource estimation of this
PFS. This work involved two general areas of study including particle size analysis and clay
characterization.
The particle size analysis is basically a screening/decantation process. First the material is weighed,
slurred, run through an attrition scrubber and then washed over 50 and 325 mesh screens. The
overflow materials from both represent the sand portion of the sample. The underflow material is then
volume adjusted, run through a high speed mixer and washed over 500, 635 mesh screens. After the
325, 500, and 635 mesh screenings, multiple static settlings occur and the clay decants are collected.
The decant samples collectively comprise the clay portion of the sample. The residual fractions from
the 500 and 635 mesh screenings collectively comprise the waste portion of the sample. The mass
balance of the three sample components, sand, clay and waste equals 100%. The specific procedures
used by UOI are listed below.
Clay characterization includes the differentiation between kaolinite and halloysite. This work was
determined visually using the three clay decants secured from the process described above. The
halloysite clay has a tubular shape while the kaolinite has a plate-like or blocky appearance.
The visual determinations were made using SEM technology. A small portion of each retained clay
decant was prepped for SEM analysis by mounting each sample onto SEM wafers and coating with
carbon. The prepped samples were then placed in the SEM and observed at 800X and 2000X
magnifications. Representative photomicrographs were taken of each sample at each magnification.
Visual reviews for each laboratory processed drillhole interval were then performed and assigned a
qualitative rating based on the amount of halloysite present in each respective sample. The key sample
of interest for each interval was the -325 mesh decant (first decant), with the -500 mesh decant (second
decant) of secondary interest. If present, the halloysite was primarily found in these two decants.
The relative ratios of kaolinite versus halloysite are visually estimated in each decant and then the
entire sample is coded from 1 to 4. The lowest coding (1) has no halloysite present and the highest
coding (4) has approximately 70%+ halloysite. Allocation of the halloysite and kaolinite quantification
was then based on the clay coding parameters as described in Table 11.3.1.
The duplicate analysis of the + 325 mesh and -325 mesh sample portions were completed during the
2011 and 2013 test work conducted at UOI. Because these two size fractions total to 100%, all results
of the +325 mesh are inverse to the -325 mesh. For simplicity, only the -325 mesh results are presented
and discussed. Figure 11.5.1 show a scatter plot of the 2011 UOI analyses versus GMT analyses.
Although there is an expected amount of scatter, the duplicate analysis shows good correlation.
Figures 11.5.2 shows a scatter plot of the 2011 UOI analyses versus CCL analyses. This plot clearly
shows that the CCL has a bias towards the finer size fraction. This bias is not considered a material
effect on the resource estimation since the CCL analytical data only represents the widely spaced
drilling of the first exploration phase and because parts of this data were replaced by the data from
the duplicate analyses. The duplicate analyses from the 2013 UOI testing were all sent to GMT. Figure
11.5.3 shows a scatter plot of the 2013 UOIanalyses versus the GMT analyses. This plot clearly shows
that the 2013 UOI tests have a bias towards the finer size fraction.
Figure 11.5.1: UOI vs. GMT Analyses for 2011,-325 Mesh Duplicates
Figure 11.5.2: UOI vs. CCL Analyses for 2011,-325 Mesh Duplicates
Figure 11.5.3: UOI vs. GMT Analyses for 2013, -325 Mesh Duplicates
The UOI also conducted testing of the non-certified reference material. These were run over the entire
program of testing, resulting in 51 tests by 18 different lab technicians. The results are shown in Figure
11.5.4. Here again, the UOI tests clearly show a bias toward the finer size fraction.
Figure 11.5.4: UOI vs. Non Certified Reference Material for the -325 Mesh, 2013 Analyses
The significant change in UOI’s laboratory practice from 2011 to 2013 was the addition of the high
pressure shower used to complete the initial -325 mesh wet screening. This change has clearly
impacted the comparison between the two laboratories. Since the entire pilot scale metallurgical test
work and associated analyses were completed at GMT and since this data supports the technical
economic model, the GMT results were accepted as more accurate.
To overcome UOI’s 2013 bias towards the finer size fraction, all of the 2013 size fraction analyses from
UOI were adjusted to remove the bias. This was done by first determining the average bias. This was
taken to be the average difference between all of the 2013 UOI -325 mesh samples and the GMT
results for the same. A total of 121 tests were averaged to show that UOI reported 6.5922%
more -325 mesh material than GMT. The database of the 2013 UOI samples was factored by this
amount, as follows. The relative proportion of the clay waste, halloysite and kaolinite constituting the
-325 mesh material was determined. Each of these components was then factored down by its
weighted proportion of the 6.5922% bias. The remaining +325 mesh, sand fraction was then factored
up by 6.5922 to provide a 100% mass balance in the sample. Figures 11.5.5 and 11.5.6 show the
results of the UOI vs. GMT duplicates and reference samples, respectively, with the 2013 bias factored
out.
Figure 11.5.5: UOI vs. GMT Analyses for 2013, -325 Mesh Duplicates, with Bias Removed
Figure 11.5.6: UOI vs. Non Certified Reference Material for the -325 Mesh, 2013 Analyses with
Bias Removed
12 Data Verification
12.1 Procedures
The exploration database delivered to SRK by I-Minerals consisted of an Access database, an Excel
spreadsheet and SEM photomicrographs.
The Access database was originally created by Dr. Mark Groszos of Valdosta State University in
Georgia and subsequently modified by UOI, The database contained tables describing the drillhole
collar locations, drillhole orientations, lithology intervals and descriptions, analytical sample intervals,
XRF assay data, and various laboratory’s material size classification data generated prior to 2012.
The Excel spreadsheet was constructed jointly by I-Minerals and UOI. It is titled “Master Data
Summary” and contains all drill sample intervals, material size classification data and clay identification
information. The Master Data Summary was originally constructed in 2012 and was subsequently
updated in 2014 with additional data.
The SEM photomicrographs are arranged in electronic folders by drillhole, sample interval, size fraction
decant sequence, SEM magnification and photo number. The SEM photomicrographs are in
.tif file format.
The drill collar locations were verified by comparing original layout maps and coordinate sheets with
the Access collar tables. The drillhole collars have been surveyed in Idaho State Plane (ISP)
coordinate system by a licensed surveyor. The drill collar locations were further verified by comparing
original surveyor coordinate data to the coordinates in the Access database. In addition, the original
drillhole layout maps were compared to maps derived from the collar locations in the Access database.
All drillholes are oriented vertical so verification of drillhole azimuth and inclination is not required.
The material size characterization data in the Master Data Summary was originally verified in 2012, by
comparing information from the original, independent laboratory data files to the same records in the
Excel spreadsheet. At that time a total of 112 records representing 17% of the total database were
checked. A few minor errors were corrected.
UOI provided a Master Data Summary which only includes data generated since the original 2012,
verification. Since the 2012 verification, UOI has been entering their results directly into the Master
Data Summary. Because of this, UOI does not generate any other assay certificates or data files from
which to verify the Master Data Summery. SRK believes that UOI staff has assembled the data with
utmost regards to accurate transfer and data entry. SRK did conduct additional verification on the
Master Data Summary by verifying from-to intervals and mass balance results. A total of 295 samples
were verified representing 19% of the total database. Twenty seven errors were detected and corrected
but overall the database represents the actual data very well.
The clay characterization codes were verified by viewing the SEM photomicrographs and visually
estimating the proportion of kaolinite versus halloysite clay. This is essentially in a parallel routine to
the methods used by I-Minerals. A total of 548 records, representing 35% of the total data were
checked. A total of 213 discrepancies were noted and addressed. The discrepancies were related to
clay type assignment codes for intervals which did not have SEM photomicrographs or were missing
size fraction data. I-minerals corrected all of these intervals and the database was accepted by SRK
as suitable to support the current resource estimation.
12.2 Limitations
SRK was not limited in its access to any of the supporting data used for the resource estimation or
describing the geology and mineralization in this Technical Report.
The database verification is limited to the procedures described above. All mineral resource data relies
on the industry professionalism and integrity of those who collected and handled it.
The GMT facility is located at 150 International Drive, Sandersville, Georgia, USA 31082. GMT is a
technology based company focused on industrial minerals and with demonstrated expertise in fine
particle processing, separation, and dewatering technologies, surface chemistry, and thermal
processing of kaolin clays. GMT provided independent professional testing services to I-Minerals as
described below.
The MRL Pilot Plant is located at 180 Cox Avenue, Asheville, North Carolina, USA 28801. The MRL
is an extension facility of NCSU College of Engineering focused on industrial minerals and with
demonstrated expertise in research, development, and implementation of industrial minerals
processing techniques. Due to its North Carolina location, the MRL is particularly knowledgeable in
the beneficiation of both feldspar and quartz minerals.
The following information will discuss the primary clay testing first followed by the feldspar and quartz
testing.
GMT initially performed an evaluation to characterize the clay samples for physical, chemical, and
mineralogical properties. Tests were also performed to determine the responsiveness of the clay to
commercial processing technology. A second test program, Phase II, was performed by GMT on
another WBL primary clay sample as well as the sedimentary clay sample due to the successful results
of the initial work. The purpose of this second phase evaluation was:
Optimize processing parameters as identified in the initial testing phase and evaluate
advanced/specialized brightness processing options;
Produce larger samples for I-Minerals; and
Determine potential end uses for the kaolin products as well as potential co-products from
the +325 mesh separated fraction.
This work was documented in a report titled Kaolinite/Halloysite Clay Evaluation Phase II – February-
March, 2006 (GMT, 2006). Subsequent reference to this work in this report will be as Phase II. As in
the Phase I discussion, the sedimentary clay sample will not be discussed in the results of this
report.
Phase I
In the initial evaluation of I-Minerals clay samples, three clay samples were provided by I-Minerals.
The samples consisted of two WBL ore body samples and one sedimentary clay sample. Using
conventional kaolin beneficiation techniques, approximately 100 lb of each sample were processed
and evaluated (Figure 13.1.1.1).
HIGH-BRIGHTNESS
Figure 13.1.1.1: Helmer-Bovill Clay Processing Plant Phase I Testing Block Flow Diagram
The crude samples were individually blunged at approximately 60% solids with 1 lb/t sodium
polyacrylate dispersant;
The dispersed materials were screened at 325 mesh using a horizontal Sweco screen to
remove the +325 mesh feldspathic sand from the clay fraction;
For each sample a portion of the -325 mesh sample was separated and designated coarse
pigment, while the remainder was classified to an 80% -2µ particle size and designated fine
pigment;
Each pigment fraction was then processed through a super conducting magnet and leached
(H2SO4 and Na2S2O4). They were then filtered and dried; and
The various products, including the crude, were then evaluated. Chemical and mineralogical
characterization of the clays included X-ray Fluorescence (XRF), X-ray Diffraction (XRD),
Scanning Electron Microscopy (SEM), and Cation Exchange Capacity (CEC). The physical
and optical characterization of the clays included Particle Size Distribution, Viscosity at low
and high shear, Abrasion, Tappi Brightness and Whiteness, and color L-a-b values.
Phase II
The samples were processed according to the diagram shown in Figure 13.1.1.2;
The -325 mesh fractions were classified to 90% -2µ particle size and designated ultra-fine
pigment, while the oversize fractions from the previous classification were delaminated to 80%
-2µ particle size using bead milling and designated fine pigment;
WBL pigment fractions were then processed through a Super Conducting Magnet (SCM),
leached, filtered, and dried. The majority of the JH05 sample was thermally processed
(calcined at approximately 875°C) to produce a metakaolin sample;
Additional advanced or specialized processes were also performed and analyzed on the
samples after classification to -325 mesh. These processes included froth flotation, selective
flocculation, and selective separation, and then followed by SCM treatment; and
The various products and crude were then evaluated as in Phase I. The +325 mesh co-
products of quartz and K-spar were also characterized. These evaluations included mineral
analysis (XRF/XRD) and PSD.
BLUNGER
-325 MESH
BEAD MILLING OVERSIZE
(DELAMINATION) CLASSIFIER
UNDERSIZE
SUPERCONDUCTING
SUPERCONDUCTING
MAGNETIC SEPARATOR
MAGNETIC SEPARATOR
(20% SOLIDS)
FILTRATION FILTRATION
DRYER DRYER
PULVERIZER HIGH-BRIGHTNESS
ULTRA-FINE PIGMENT
PULVERIZER
METAKAOLIN
Figure 13.1.1.2: Helmer-Bovill Clay Processing Plant Phase II Testing Block Flow Diagram
In 2008 FLSmidth Krebs tested five 5-gal buckets of -325 mesh clay slurry originated from WBL crude
ore. The cyclone tests evaluated three different cyclone sizes for their effect on fine grit and clay
separation. One cyclone evaluated fine grit while the other two evaluated separation of the kaolinite
and halloysite (FLSmidth Krebs, 2008).
A 3 inch diameter cyclone was mounted in conjunction with a sump, mixer, and pump closed-loop
circuit. Sample was transferred into the sump and the circuit operated to evaluate the overflow and
underflow splits. Particle size, percent solids, flow rates, and yields were determined.
Using the same circuit and procedure described above, 1 inch and 0.5 inch diameter cyclones were
evaluated. Particle size, percent solids, flow rates, and yields were determined.
Representative samples of each fraction separated during the three tests were sent to other
laboratories for additional analysis. SEM photomicrographs were produced through GMT, and
chemical data results were obtained through ALS Minerals Laboratory. All data results were then
compiled and evaluated.
GMT processed approximately 500 lb of crude clay in 2008 for the purpose of evaluating the
efficiency of the cyclone separations (GMT, 2008). The flow sheet included the following:
The crude clay was initially blunged and dispersed with sodium polyacrylate at about 50%
solids and then screened at 325 mesh to remove the feldspathic sand from the clay fraction;
The screen passing fraction was re-mixed and pumped through the 3 inch cyclone. The
underflow fraction was considered fine grit or waste. The overflow clay fraction was captured
and used for subsequent fine hydrocycloning separations; and
The overflow clay fraction was mixed and pumped through a 0.5 inch cyclone. The overflow
and underflow fractions from this first pass were collected and a portion of the overflow mixed
and fed through the 0.5 inch diameter cyclone in a second pass. The products, consisting of
first and second pass overflows and underflows, were then dewatered for product evaluations.
The overflow fractions were representative of concentrated halloysite, and the underflows were
considered concentrated kaolinite.
GMT processed the remaining 2,500 lb and reported the work in July 2010 (GMT, 2010). The flow
sheet was similar except for the following:
Two 0.5 inch cyclones were used in parallel (vs. one cyclone) for each separation pass and
higher feed solids were also used in an effort to expedite the processing time due to the amount
of material;
A small amount of second pass overflow was passed through the 0.5 inch cyclones to produce
a third pass product for SEM examination; and
A majority of the combined underflow fractions from the 0.5 inch cyclone passes, or kaolinite
clay, was dewatered and then calcined to produce a metakaolin product.
A test was performed in August 2010 due to high overflow recovery and less distinctive SEM
visual separation in the July 2010 test. Some of the dry second pass material product was
slurried at lower solids and cyclone;
Another small 300 lb of bulk sample was provided and tested in October 2010. Procedures
mirrored the July 2008 work; and
A small 250 lb of core composite sample was provided and tested in October 2010.
Procedures mirrored the July 2008 work.
Demonstrate the technical feasibility of the overall process consisting of an integrated series
of unit operations or process steps, and
Generate scale-up data, process design criteria, and functional equipment duty specifications
to assist in the design of a commercial processing facility.
The MRL, under the direction of Mr. John W. Schlanz, Chief Engineer, completed pilot plant testing of
I-Minerals’ WBL K-spar tailings and this work was documented in a report titled Pilot Plant Testing of
I-Minerals Moose Creek K-spar Tailings – August 7, 2009. These tests successfully proved:
The secondary objective was also met in support of commercial-scale process plant design.
It should also be noted that prior to the pilot testing program several bench-scale tests were conducted
by the MRL. These tests to identify candidate unit operations were conducted to verify initial mineral
response and recovery using conventional beneficiation techniques for feldspar and quartz, develop a
basic processing flow scheme, and determine operating variables.
Bench tests were performed and reported in 2002 to 2003 for the K-spar using stockpile composite
samples and residual ore face samples.
On June 26, 2006, the MRL took receipt of 35 t of tailings packaged in super sacks. The tailings were
from the WBL tailings stockpile and are residues of material previously processed for clay recovery
from the WBL pits (Section 6) and required only air drying as feed preparation to the pilot testing
program. The configuration of the flowsheet for the beneficiation pilot plant included the following unit
operations:
Automated weigh belt feeder to maintain constant feed rate with a recorder to monitor the
weight of feed to a 36 inch diameter Sweco screen to scalp the feed to the pilot plant at 10
mesh;
The +10 mesh screen oversize reported to an 18 inch diameter x 36 inch long rod mill;
The -10 mesh screen undersize was pumped to a CFS (Classification and Flotation Systems,
Inc.) dense media hydrosizer set at 30 mesh size cut, with the underflow directed to the rod
mill, which operated at 50 wt% solids;
The rod mill discharge was sent to the Sweco screen for a closed-loop grinding operation;
The -30 mesh hydrosizer overflow was pumped to the #1 Cyclone for initial desliming, and the
#1 Cyclone underflow reported to the #1 Screw Classifier for additional desliming and
dewatering;
The Screw Classifier discharge was fed to the Attrition Scrubber equipped with three 3 hp
(2.25 kW) motors. The feed to the attrition scrubber was maintained at 60 wt% solids and
conditioned with 0.4 to 0.5 lb/t of sodium hexametaphosphate [(NaPO3)6] to assist in slime
dispersion;
After conditioning, the Attrition Scrubber discharge was diluted to approximately 10 wt% solids
and pumped to the #2 Cyclone for desliming before the 30 x 200 mesh #2 Cyclone underflow
slurry was dewatered in the #2 Screw Classifier;
The #2 Screw Classifier transported the washed pulp to the agitated mica Conditioning Tank
in which the 35 to 40 wt% solids slurry was conditioned with sulfuric acid for pH control, the
amine collector, and #2 fuel oil in preparation for mica flotation;
The conditioned slurry was discharged to the mica flotation circuit, which consisted of two
Denver D-7 stainless steel flotation cells for removing mica as the froth product. A small
amount of frother was added during flotation to assist in the mica removal;
Tailings from the mica flotation cells consist of a mixture feldspar and quartz. It was discharged
for dewatering in the #3 Screw Classifier before conditioning for feldspar flotation;
The spar conditioning consisted of mixing the pulp at 40 wt% solids with hydrofluoric acid (HF),
amine, and #2 fuel oil and adding small amounts of frother to the spar flotation cells;
The feldspar Rougher Flotation circuit consisted of a bank of three Denver D-7 Flotation Cells
for feldspar float recovery with quartz reporting as rougher tails;
The spar rougher float product was gravity fed to two Denver D-7 Flotation cells in the Cleaner
Flotation circuit. The froth product is the flotation concentrate and the cleaner tails are the
“spar middlings;”
Both spar and quartz were dewatered on 200 mesh Sweco screens and collected in 55 gal
drums. In final runs, a 50 mesh 36 inch Sweco screen was added to the circuit to recover
additional spar from the middlings stream;
Feldspar, quartz, and middling products were dried in a stainless steel Rotary Steam Tube
Dryer;
Any remaining mica (magnetic impurities) in the product(s) was removed in three-pass
magnetic separation using the triple roll rare earth (permanent) magnetic separator from
Outotec, Inc.;
Four to five sampling rounds were conducted, typically one hour apart, during each test run.
Product streams sampled included the feldspar cleaner product, the feldspar cleaner
middlings, the feldspar rougher float product, the quartz rougher tails, mica float product, and
all slimes products consisting of Cyclone and Screw Classifier overflows;
At the end of each test run, samples were collected around the grinding circuit to determine
the performance of the Hydrosizer and to evaluate the efficiency of the grinding operations
(Rod Mill);
Samples of discharges were also collected from the Attrition Scrubber and the Conditioner to
determine flow rates for equipment specifications. These samples, however, were collected at
the end of test run to avoid disrupting the material flow and balance of the Pilot Plant
operations; and
All timed samples were dewatered, dried, and weighed for calculating the mass balances for
each test run.
The MRL, under the direction of Mr. John W. Schlanz, Chief Engineer, completed this bench testing
program and successfully produced three grades of high pure quartz. This work was documented in a
report titled Recovery of High Grade Quartz from I-Minerals WBL Ore Body – September 14, 2011
(Schlanz, 2011).
It should also be noted that prior to this testing program a limited series of bench-scale tests were
conducted by the MRL in 2006 on Kelly’s Basin Na-spar tailings to investigate the potential for high
purity quartz. No formal report was issued on this work but the data results demonstrated a successful
production of high purity quartz grades.
Standard beneficiation techniques were used and unit procedural operations were as follows:
Due to a high amount of clay still present in the sample, a combination of wet and dry 200
mesh screening was used to remove additional -200 mesh fines;
Grinding was performed in an 8 inch x 12 inch stainless steel (SS) rod mill charged with SS
rods. Grinding was performed at 50% solids and done in closed circuit to minimize fines
generation. Grinds included 30 mesh for the initial K-spar recovery and 50 mesh for the quartz
upgrading;
Desliming was performed at low solids using a 30 second settling period followed by
decantation through a 200 or 140 mesh screen;
Attrition scrubbing was accomplished using an octagon-shaped cell and a triple-blade impeller.
The retention time was set at 5 min using 70 to 75% solids, and was followed by desliming at
200 mesh;
Conditioning was performed in 2,000 ml beakers at 50 to 60% solids. Flotation reagents were
added at predetermined rates using three flotation schemes: (1) iron/mica flotation using
sulfuric acid for pH control and amine as the mineral collector (prior to feldspar flotation), (2)
iron flotation using sulfuric acid and petroleum sulfonate collector (prior to quartz upgrading
flotation), and (3) standard hydrofluoric acid and amine collector (for both feldspar recovery
and quartz upgrading). Conditioning was conducted at 2.5 to 2.7 pH and retention times
ranged from 3 to 4 minutes; and
Flotation was performed in a standard Denver lab cell at 20 to 25% solids and included the
addition of small amounts of frother reagent in all steps.
This work commenced in late 2011 and was completed in January 2012.
The work commenced in May 2012 and was completed in July 2012.
Phase I
Initial primary clay test results from the July 2005 tests:
A crude clay characterization was performed on the WBL-1 and WBL-2 samples, and results
summarized in Table 13.2.1.1. Also shown in the table are the analyses for the WBL-1 and
WBL-2 samples after processing;
Good brightness values were achieved with extensive processing methods; and
SEM images from the crude and processed materials for each sample illustrated the range in
particle size and particle morphology of the minerals and showed the presence of the halloysite
with the kaolinite.
Phase II
Phase I
The WBL samples contained predominately quartz with varying amounts of potassium
feldspar, kaolinite, halloysite, and muscovite mica;
The processing of these samples was consistent with processing other primary clay deposits
and technically proved the feasibility; and
The clay generated from these two samples has excellent brightness and color indices, thus
lending itself applicable to the paper, paint, and ceramic industries.
Phase II
The WBL sample is a combination of kaolinite and halloysite clays once the +325 mesh
material is removed. The primary discoloring impurities are iron and titanium oxides within the
dispersed clay water system;
The processed clay from the sample responded well to conventional brightness improvement
processes such as magnetic separation and leaching;
The final clay products produced from the sample resulted in a unique combination of kaolinite
and halloysite clay, and are relatively pure in composition. Additional product applications may
include plastics, pharmaceuticals, and nano-composites;
The majority of the +325 mesh fraction from the sample is quartz sand with a significant amount
of potassium feldspar. The quartz and K-spar could be processed as co-products, diversifying
the WBL clay resource; and
The JH05 sample processed to a metakaolin was successful and noteworthy as future work
will include metakaolin processing of the WBL ore.
As noted above, a significant discovery during the evaluations was evidence of the presence of
halloysite in the samples. Scanning Electron Microscopy photomicrographs confirmed the presence of
the halloysite clay. This unique form of kaolin was found as a film floating on the surface of a kaolin
slurry sample, indicating a gravimetric difference in the physical attributes of the two clays. I- Minerals
subsequently concluded, based on the gravimetric separation characteristics of the kaolinite and
halloysite clays, which specific gravimetric separation testing techniques needed to be evaluated.
Particle size data for the Test 1 grit separation revealed excellent separation of fine grit in the underflow
and contained primarily -325+635 mesh particle size material. Chemistry data also confirmed the
overflow fraction contained principally clay. Test 2 did not produce successful clay separations based
on process data and SEM’s. Test 3 did produce clay separations based on the process data and
SEM’s.
The conclusions from the test work performed at the FLSmidth Krebs facility were developed after all
the analytical work was received from Krebs, GMT, and ACT Laboratory. The 3 inch cyclone proved
to be suitable for the removal of fine grit. The 1 inch cyclone was not shown to provide an adequate
separation of the halloysite and kaolinite clays. The 0.5 inch cyclone demonstrated that a shape
separation was indeed possible using cyclones. Due to these test results, one 3 inch and three
0.5 inch diameter cyclones were purchased and sent to the GMT facilities for additional testing.
13.2.3 Results and Conclusions Based on Pilot Plant Testing of Primary Clay
Primary Clay Pilot Plant Test Results
Discussion of results is centered on the recovery and separation of the halloysite and kaolinite clays.
Additional results, such as clay brightness data and chemistry, are not discussed.
The screened -325 mesh clay fraction yield was 28.88% and considered average for this deposit
(average at 30%). The 3 inch cyclone successfully split the grit fraction from the clay. SEM’s shown in
Figures 13.2.3.1 and 13.2.3.2 demonstrate the separation. Recovery splits through the 0.5 inch
cyclone were very similar and deemed acceptable.
Of most importance, the SEM’s illustrated excellent separation and concentration of the halloysite in
the second pass overflow fraction using the 0.5 inch diameter cyclone. The underflow fractions
contained the highest concentration of kaolinite clay. SEM’s shown in Figures 13.2.3.3 and 13.2.3.4
illustrate the clay fraction separations.
Figure 13.2.3.3: SEM of 0.5" Hydrocyclone 2nd Pass Overflow (Predominantly Halloysite)
Figure 13.2.3.4: SEM of 0.5" Hydrocyclone 2nd Pass Underflow (Predominantly Kaolinite)
The screened -325 mesh clay fraction yield was 31.4%, slightly higher than the previous test. The 3
inch cyclone underflow yielded a lower percentage of grit than the July 2008 test. Recovery splits for
each pass through the 0.5 inch cyclone were again similar.
The SEM’s showed some separation and concentration of the halloysite in the second and third
overflows, but lacked the degree of concentration and separation demonstrated in the previous test
results. It was determined that higher percent solids ranges used in this test were detrimental in
achieving the results from the previous test.
The combined underflows from the first and second passes through the 0.5 inch diameter cyclones
were processed into a metakaolin. The SEM’s for the metakaolin product showed good structure
formation that is considered typical of thermally processed pigments. Further testing of the metakaolin
product was left for I-Minerals to pursue with a concrete laboratory. This is discussed in the marketing
section.
The August 2010 results did not provide results that could be used for further development. The
retesting of the second pass overflow was performed in an effort to understand if the higher percent
solids used during the initial two 0.5 inch diameter cyclone passes was detrimental to the clay
separations. The results were not conclusive, but all indications from published data point to a need
for low percent solids in this process application. The results from this test were not considered
necessary for further investigation.
The October 2010 test provided clay separation results similar to the July 2010 test. Several recovery
deficiencies occurred that were not consistent with known and previously achieved data. Feldspathic
sand fraction recovery should be in the range of 70%, but the feldspathic sand recovery in this test
exceeded 80% and indicated an inadequate separation of the clay fraction. This was attributed to less
than optimum dispersant blunging due to the smaller sample size. The results demonstrated the need
for minimum ore volumes for processing through GMT’s pilot plant (also confirmed in the November
2010 work). The presence of the halloysite in the clay fraction was significant.
The November 2010 test also provided clay separation results similar to the July 2010 test. The
recovery results closely mirrored the data obtained in the October 2010 test. As noted in the October
2010 test results, the presence of halloysite in the clay fraction was significant. The circuit yields and
recoveries for the October 2010 and November 2010 tests are shown in the Table 13.2.3.1.
Specific process variable requirements for GMT’s pilot plant equipment were confirmed with this test.
Adequate dispersant blunging of the crude, considered key for successful clay separation, was
compromised due to the smaller sample provided by I-Minerals. The pilot plant blunging equipment
designated for this service could not be used due to the sample quantity, and an alternative mixing
arrangement was used in its place.
2011 Testing
Testing performed in 2011 was primarily performed to generate additional quantities of halloysite
product for market development work. The principal company involved in this work is DURTEC GmbH
located in Neubrandenburg, Germany and headed by Dr. J. Schomburg. Two major test runs were
performed using GMT’s pilot plant – one completed in September 2011 utilizing approximately 2,000
lb of ore and another in December utilizing approximately 6,500 lb of ore. One significant equipment
modification was incorporated into the clay processing schematic – a solid bowl decanter centrifuge
was used in place of the 0.5 inch diameter cyclone for both passes. The halloysite and kaolin product
yields and quality closely matched the previous results, and the centrifuge equipment will be utilized
in all future work.
2012 Testing
Testing performed in 2012 was again use to generate additional quantities of halloysite product for
market development work. The August 2012 run utilized the approximately 550 lb of ore remaining in
GMT’s inventory.
(1)
Table 13.2.3.1: Primary Clay Pilot Plant Trials Compilation Recovery Data
Pounds, Approximate % Yield Thru Circuit % Recovery "Normalized" Data (2)
Description Jun-08 Jul-10 Oct-10 Nov-10 Jun-08 Jul-10 Oct-10 Nov-10 Jun-08 Jul-10 Oct-10 Nov-10 Average Pounds % Yield % Recovery
Ore Feed 500.00 2,500.00 299.4 250.00 250.00
+325 Mesh Screen Fraction 355.60 1,715.00 243.0 203.00 71.12 68.60 81.16 81.20 71.12 68.60% 81.16% 81.20% 75.52% 175.00 70.00 70.00
-325 Mesh Screen Fraction 144.40 785.00 56.40 47.00 28.88 31.40 18.84 18.80 75.00 30.00
3 inch Cyclone Overflow 131.07 751.45 47.15 35.40 26.21 30.06 15.75 14.16 56.49 22.60
3 inch Cyclone Underflow 13.33 33.55 9.25 11.60 2.67 1.34 3.09 4.64 2.67 1.34% 3.09% 4.64% 2.93% 18.51 7.40 7.40
First Pass Overflow 82.65 509.41 25.80 16.40 16.53 20.38 8.62 6.56 26.17 10.47
First Pass Underflow 48.42 242.04 21.25 19.00 9.68 9.68 7.10 7.60 9.68 9.68% 7.10% 7.60% 8.52% 30.32 12.13 12.13
Second Pass Overflow 52.20 314.82 17.12 12.15 10.44 12.59 5.72 4.86 10.44 12.59% 5.72% 4.86% 8.40% 19.39 7.76 7.76
Second Pass Underflow 30.45 194.59 8.78 4.25 6.09 7.78 2.93 1.70 6.09 7.78% 2.93% 1.70% 4.63% 6.78 2.71 2.71
Total 100.00 100.00 100.00 100.00 100.00 100.00
Feldspathic Sand Recovery 71.12 68.60 81.16 81.20 75.52 70.00
Losses to Waste 2.67 1.34 3.09 4.64 2.93 7.40
Halloysite Recovery (Second Pass Overflow) 10.44 12.59 5.72 4.86 8.40 7.76
Kaolin Recovery (First and Second Pass Underflows) 15.77 17.47 10.03 9.30 13.14 14.84
Total Clay Recovery 26.21 30.06 15.75 14.16 21.55 22.60
Source: I-Minerals
(1) Processing includes 325 mesh screen for degritting, 3 inch cyclone for fine degritting, and 0.5 inch cyclones for clay separation.
(2) Using 70% recovery of feldspathic sand and November 2010 yield data.
The 3 inch cyclone was very efficient at separating and concentrating the grit fraction from the clays.
Of most importance, the SEM’s illustrated excellent separation and concentration of the halloysite in
the second pass overflow fraction using the 0.5 inch diameter cyclone. The underflow fractions
contained the highest concentration of kaolinite clay.
The 3 inch cyclone underflow yielded a lower percentage of grit than the July 2008 test. Recovery
splits for each pass through the 0.5 inch cyclone were again similar. While the SEM’s showed
significant amounts of halloysite, the concentration aspect of the clay separation was not as
pronounced. It was determined that higher percent solids ranges used in this test were detrimental in
achieving the results from the previous test.
The combined clay cyclone underflows were processed into a metakaolin. Further testing of the
metakaolin product is for I-Minerals to pursue with a concrete laboratory. This work is discussed in the
marketing section.
The results demonstrated that specific attention must be placed on the process dispersion and
blunging steps prior to cyclone classification. It is apparent that this area of process preparation is
critical to achieving classification results that mirror the excellent data achieved in the July 2008 testing.
A compromise recovery table was developed to normalize the available data and develop current
product recoveries that best represents the knowledge base achieved to-date. Recovery data was
used from the July 2008, July 2010, October 2010, and November 2010 tests. The July 2008 data
were excellent and representative of the process capabilities. However, subsequent testing did not
replicate these results. Therefore, all recoveries were reviewed to consider obtainable results once
circuit optimization is achieved and the following concluded:
Key consideration was given to the separation of the feldspathic sand and clay fractions. The
large sample tests (July 2008 and July 2010) achieved splits of about 70/30 sand to clay that
were consistent with core analysis data. The small sample tests (October 2010 and November
2010) achieved splits of only about 81/19 sand to clay – not considered representative.
Therefore, a feldspathic sand fraction recovery of 70% was used for the normalized recovery
data;
The 3 inch cyclone grit separation step was adjusted to a very conservative recovery (loss) of
7.40% in the normalized recovery data. The actual results ranged from only 2.67 to 4.64%
loss of grit material. However, it was assumed that once optimum feldspathic sand and clay
separation is achieved the grit fraction will increase. The conservative 7.40% value used was
determined using the normalized clay fraction recovery determinations discussed below. Any
grit reduction change would increase the feldspathic sand recovery; and
The November 2010 test was the only test that used WBL core composite material and
therefore the clay separation data from this test were used for the determination of the
normalized clay recoveries. The clay yields were used in conjunction with the sand/clay data
above to determine normalized recoveries for the halloysite and kaolinite clay fractions. This
test was not considered optimal for use in these calculations, but the results were
representative of composited core and viewed as conservative data that did not bias towards
the best clay recovery data from the July 2008 work. By comparison, the July 2008 data results
were exceptional but not adequately representative of the potential WBL ore body. Also, the
July 2010 results were negatively affected in quality by negative processing practices
discussed earlier. The remaining tests and data, including November 2010, were incorrectly
biased with low clay recoveries due to inadequate feldspathic sand and clay separation. The
main comparable distinction in all the data results was the definite presence of halloysite in
the clay fraction. Table 13.2.3.1 shows all of the pertinent data.
The solid bowl decanter centrifuge used in place of the 0.5 inch diameter cyclone for both passes
resulted in similar product recoveries and quality when compared to previous testing. The circuit is
somewhat simplified with this change as a single centrifuge at each pass stage of the process can
handle the entire flow stream compared to the high number of 0.5 inch cyclones that would be required
for production operation (at 1.3 gpm feed rate per cyclone). The centrifuge overflow and underflow
splits were set to match the yields obtained by the 0.5 inch cyclone and the product results obtained
were similar.
The Pilot Plant testing of K-Spar Tailings consisted of six shakedown runs to test the mechanical
integrity of equipment in each process step followed by 25 production runs to evaluate performance
as well as to produce feldspar.
The MRL conducted six shakedown runs, the duration of which lasted from 1 to 8 hours and
consumed almost 5 t of feed that is not included in the production figures;
The feed rates varied from 400 to 600 lb/hr during initial production runs (Tests PP1 through
PP5) for adjusting the grind via feed rate and the hydrosizer performance. Fines generated
accounted for over 30 wt% indicating that the slimes result in decreased flotation loads and
increased reagents consumption to recover acceptable grade feldspar;
ACME Labs assays results for initial production runs show that alumina values for the spar
concentrates ranged from 15.5 to 18.2% Al2O3;
Re-calibration of the hydrosizer and increasing the feed rate to 500 lb/hr reduced the amine
dosage to the spar flotation (Test PP11) and the product grade, as reported by Activation Labs,
increased to 17.86 wt% Al2O3, which is very close to the targeted 18 wt% with a yield of 15.8%.
ACME Labs reported 18.52% Al2O3 for this run;
A feed rate of 650 lb/hr was found to be too high as the rod mill began to overload at the end
of the run; and
Table 13.2.4.1 shows that grade increases significantly as hydrofluoric acid (HF) dosage
increases.
Table 13.2.4.2 shows that keeping the HF dosage constant, yield increases with increased amine
dosage while producing acceptable grades at all collector levels.
Table 13.2.4.2: Grade vs. Collector Amine Dosage
Test No. % Yield % Al2O3 Amine, lb/t
(1)
PP17A 17.7 18.27/18.25 0.30
PP17B 18.0 18.31/18.98 0.40
PP17C 20.4 18.18/18.64 0.50
Source: I-Minerals, 2010
(1) Results reported by Activation Lab/ACME Lab
Over 71,000 lb of K-Spar Tailings as feed were processed in a continuous mode of operation
of the Pilot Plant, proving the process and producing bulk samples of approximately 9,000 lb
of feldspar are of acceptable grade with 17,000 lb of quartz and about 3,000 lb of middlings;
The process consistently produced product grades ranging from 18.0 to 18.5% Al2O3 and
13.0 to 13.5% K2O with yield from 17 to 20 wt%; and
Middling evaluation based on further pilot tests show additional spar product of satisfactory
grade (Table 13.2.4.3) can be recovered by simple classification at 50 mesh, with yield
increased by up to 15%.
The relatively large amount of feed tested demonstrated that the second scrubbing step can be
eliminated, with attendant positive results on reducing both capital and operating costs.
13.2.5 Results and Conclusions for Bench-scale Testing of K-spar Flotation for
Quartz
Bench-scale Quartz Testing Results
Feed characterization was performed and contained 33.9% +30 mesh and 14.9% -200 mesh.
Major oxide chemistry in the feed was as follows: 0.23% Fe2O3, 7.55% Al2O3, and 4.23% K2O.
Since only WBL stockpile tailings had been used in all previous K-spar feed test work, initial
tests focused on the recovery of satisfactory K-spar concentrates. Acceptable K-spar
chemistry data and recoveries were achieved and duplicated by the fourth test (<0.01% Fe2O3,
18.19% Al2O3, and 14.48% K2O).
Tests 5 through 8 were conducted to recover upgraded quartz products. Test 5 recovered a
30 mesh quartz (no regrind to 50 mesh) using a spar scavenger float only; Test 6 produced a
50 mesh quartz with a single spar scavenger float; Test 7 produced a 50 mesh quartz product
consisting of both iron and spar scavenger floats (double float); and Test 8 produced a 50
mesh quartz product consisting of iron and two spar scavenger floats (triple float).
Feldspar products collected during the quartz testing continued to produce good grades and
consistent yields. Alumina values ran close to 18% Al2O3, iron remained low at 0.01% Fe2O3,
and potassium stayed high at 14.6-14.7% K2O. K-spar yields ranged 17-19%.
Table 13.2.5.1: Quartz Products Evaluation
Test Wt % Fe (ppm) Al (ppm) K (ppm) Na (ppm) Ca (ppm) Ti (ppm) Li (ppm)
5 53.6 41 838 774 44 11.0 16 0.43
6 43.2 27 176 100 16 9.0 15 0.48
7 38.3 23 145 88 14 8.5 14 0.49
8 32.5 22 131 81 13 8.2 14 0.49
Source: I-Minerals, 2010
13.2.6 Results and Conclusions for Pilot Plant Testing of K-Spar Flotation Tailings
for Quartz
Pilot-scale Quartz Testing Results
Equipment schematic set-up dictated that actual production was performed in reverse where
the triple float product was produced first, followed by the double float and single float runs.
This was necessary to maximize equipment operation efficiency for changeovers and minimize
time requirements. While necessary for logistics, this scheme was not desirable for producing
optimum products.
Due to time requirements and costs associated with product chemistry analyses (outside lab
required), in-process control of key variables such as reagent optimizations and retention
times were not possible. Process variable settings were relegated to data based on previously
performed bench flotation studies, and not amenable to actual operating conditions.
Each flotation run was somewhat limited to the quantity of material available for the testing.
Finished product results were not consistent with previous bench studies as determined by
follow-up chemical analyses.
In order to perform pilot-scale testing for production of high quality quartz, adequate real- time
chemistry analysis must be available so that in-process variable adjustments (primarily
reagents) can be performed.
In conjunction with the previous conclusion, significant feedstock must be available to allow
for process optimization of each flotation run.
13.2.7 Results and Conclusions for Repeat Bench-scale Testing of K-Spar Flotation
Tailings for Quartz
Bench-scale Quartz Testing Results
The number of tests actually performed to produce single, double, and triple float products for
each of the two feedstocks (WBL K-spar Tailings material and composite core K-spar material
from the Bovill Kaolin deposit) was somewhat limited due to time, material, and cost
restrictions associated with the testing, Therefore, complete optimization was not achieved
during these tests.
Even without complete optimization, the tests demonstrated successful results in producing
comparable high quality quartz products for each feedstock. The results are shown in the table
below.
Favorable comparisons between the two feedstocks were achieved in these tests. This was important
to demonstrate the ore body core composite would produce similar quality product results when
compared to the WBL Tailings.
The material used for the K-spar and quartz evaluation work was obtained from the WBL tailings
stockpile located adjacent to the WBL pits (Section 4). This material came from the same Bovill Kaolin
deposit through previously mined operations, where the clay was washed out and the remaining
feldspathic sand fraction was stockpiled. This material is considered to be representative of the Bovill
Kaolin deposit as it represents a significant footprint of mined surface area and vertical depth.
Bench-scale laboratory testing was performed initially to verify quantitative and qualitative parameters
for each mineral being investigated. This was then followed by extensive pilot-scale testing to confirm
previous results, optimize processing parameters, and provide data for production level scale-up.
Detailed specifics for each of the minerals recovered for this Project are described in various sections
within this document.
A significant effort was performed to develop a processing scheme for the separation of the two clays
– halloysite and kaolinite. It was initially observed that the halloysite naturally separated from the
kaolinite by simple gravity separation – allowing the halloysite to remain on the surface of the clay
slurry medium. Therefore, effort was placed on accelerating this separation by increasing the physical
separation process through mechanical means. Hydrocyclones have proved initially successful and
further work is being performed and evaluated on centrifugation techniques. Please reference Sections
13.1.2 and 13.2.2 for more details.
Considerable attention was given to the feldspar flotation processing circuit optimization. This
optimization work included attrition scrubbing retention time requirements optimum conditioning
determinations, and detailed reagent investigations to optimize combinations and dosage
requirements. This work was important to maximize both K-spar product recovery and chemistry.
Please reference Sections 13.1.4 and 13.2.4.
It was determined early in the evaluation process that the quartz fraction of the material was of high
quality. Considerable time and effort was placed on developing high purity grade quartz products for
the marketplace. Ultimately, three grades of quartz product have been developed and integrated into
the Project. Please reference Sections 13.1.5, 13.1.6, and 13.2.5.
There are no known material impacts that could negatively affect mineral resource.
The geologic model was constructed from the drillhole lithologic descriptions. An upper soil horizon
was modeled, by constructing a 3-D base of soil profile. All model blocks located above the base of soil
and below topography were coded as un-mineralized soil. Typically, the soil horizon is 10 to 20 ft deep.
Directly below the soil horizon, the saprolitic weathered zone of Thatuna is approximately 50 to 125 ft
thick. This material hosts the resource products. This zone transitions downward into regolith and un-
weathered batholith. The base of saprolitic weathering was modeled based on relative concentrations
of clay mineral and geologic descriptions from the drill logs. All blocks located above the base of
weathering and below the base of soil were coded as potentially resource bearing. The batholith also
contains widely spaced, flat lying roof pendants of un-mineralized Precambrian gneiss. All pendants
were modeled and excluded from the potential resource material. Miocene age, basalt dikes typically
10 to 25 ft wide, cut all the other lithologies. They strike at azimuth 140° and dip steeply east
approximately 70-75°. These were also modeled and excluded from the potential resource material.
Each sample within the drillhole database is characterized by the relative proportions of sand, kaolinite
clay, halloysite clay and waste. The sum of these four components equals 100% of each sample.
These four variables were estimated as the resource material of this report.
Sand, halloysite and kaolinite were all capped at the value where the log normal cumulative distribution
plots becomes discontinuous and irregular. All capping was completed prior to compositing. All
material capped from the sand, halloysite or kaolinite was added to the clay waste fraction to maintain
a 100% mass balance.
The original assay sample lengths generally range from 5 to 10 ft with an average of 5.8 ft. For the
modeling, these were composited into 10 ft run length composites. This length was chosen mainly so
that approximately two average samples would be composited and the composite length would match
the model block height of 10 ft. The composites were broke at the lithologic contacts. Table
14.3.2 lists the results of the capping and compositing.
14.5 Density
I-Minerals conducted density testing on three samples collected from the WBL Pit area that represent
the residual deposit material. The density testing was completed by ALS Minerals and showed a mean
3
density of 1.7 g/cm for the resource material within the >10% total clay grade shell. A density of 2.0
3
g/cm is used for the material with total clay content of 1-10%. Standard density values were assigned
to soil and basalt dikes according to Table 14.5.1.
Table 14.6.1: Block Model Limits WBL and Middle Ridge Areas
Orientation Minimum Maximum Block Size (ft)
Easting (ISP) 2,441,680 2,444,720 20
Northing (ISP) 1,903,300 1,908,500 20
Elevation 2,840 3,120 5
Source: SRK
The resource estimation is confined within two nested hard boundaries defined by the percentage of
total clay which reflects the extent of weathering within the Thatuna granodiorite. The upper/inner,
higher grade clay shell was constructed based on a combined halloysite and kaolinite content of 10%
or more. This boundary was allowed to extend up to 100 ft from unconfined drillholes. Below or external
to the to the 10% clay shell, a lower grade clay shell was constructed based on clay content threshold
of1% or more. This lower grade boundary is located below and lateral to the higher grade shell,
representing less weathered material. The external grade shell was also allowed to extend 100 ft
from unconfined drillholes. Figure 14.7.1 shows the locations of drillholes and the limits of the nested
clay shells. Table 14.7.1 lists the number of blocks within each clay shell in each of the four model
areas.
Figure 14.7.1: Drillhole Locations (Black Dots), Clay Shell >=10% (Blue), Clay Shell >1-<10%
(Teal)
Four variables are estimated including, sand, kaolinite, halloysite and waste. The estimations are run
independently within each clay shell using only samples within that shell. An inverse distance squared
algorithm was used to estimate all variables. The grade estimation utilized a three pass method
according to the parameters listed in Table 14.7.2. A varied search orientation was used for the second
and third passes based on the strike and dip of the base of soil profile. This profile is interpreted to
reflect the pattern of weathering which has created the residual deposits. The varied search orientation
is controlled by an anisotropy model which is created by the modeling software. An octant restriction
was used to select samples from multiple drill holes. Length weighting was used to account for any
short composites at the bottom of drillholes. The number of samples, number of
drillholes and average distance to all samples was stored for each block to be used in the model
validation. Once the ID2 estimation was run, all four variables in each block were normalized so they
would sum to 100%. As part of the grade estimation, model validation is conducted as an interactive
process. To achieve proper validation, higher grade composites were limited by the distance they could
be interpolated. A high-grade composite restriction, as listed in Table 14.7.2, means that any sample
above the listed grade could only be interpolated over the listed distance. Figures 14.7.2 through 14.7.5
present typical cross-sections showing the estimated block grades for halloysite, kaolinite, sand, and
waste, respectively, for each of the model areas.
Source: SRK
Figure 14.7.2 WBL, East West Cross Section 1,904,800N Viewing North; Composite and Estimated
Block Grades, From Top to Bottom-Sand, Kaolinite, Halloysite and Waste
Source: SRK
Figure 14.7.3 Middle Ridge, East West Cross Section 1,906490N Viewing North; Composite and
Estimated Block Grades, From Top to Bottom-Sand, Kaolinite, Halloysite and Waste
Source: SRK
Figure 14.7.4 Kelly’s Hump North, East West Cross Section 1,907,200N Viewing North; Composite
and Estimated Block Grades, From Top to Bottom-Sand, Kaolinite, Halloysite and Waste
Source: SRK
Figure 14.7.5 Kelly’s Hump South, East West Cross Section 1,904,200N Viewing North; Composite
and Estimated Block Grades, From Top to Bottom-Sand, Kaolinite, Halloysite and Waste
The resources are all classified as indicated based on the drillhole spacing, the sufficiency of the
density testing and the lack of precise QA/QC monitoring of the various analytical techniques.
The proven and probable reserves are presented in the Table 15.1.
16 Mine Design
Section 1 addresses the mine design for the Bovill mine operation. The deposit and surrounding areas
had historically been open-pit mined for clays. This is still the preferred mining method due to the
proximity of the mineralized material to the surface.
As mentioned previously, the operation will produce quartz sand, K-feldspar sand, kaolinite clay,
metakaolin clay, and halloysite clay. The deposit consists of four separate mining areas: WBL Pit,
Middle Ridge (MR), Kelly South (KS) and Kelly’s Hump (KH). The current area of mining is limited by
lease and wetlands boundaries.
Due to the shallow nature of the deposit the stability of the open pit slopes was not considered to be a
significant issue. Proposed overall slope angles of 45 for WBL pit area and 43 for Middle Ridge area
deemed to be achievable over the mine life.
No specific geotechnical report has been commissioned for the Kelly South and Kelly’s Hump deposits.
As the geology in the area is considered relatively homogenous, the geotechnical parameters for the
Middle Ridge area have been applied to the Kelly South and Kelly’s Hump deposits.
The integral part of pit optimization is the generation of the nested economical pit shells calculated
using economical parameters with the range of multipliers (from 0.1 to 1.1), also called revenue factors.
The resulting economical pit shells were used as the guide to create mineable pit phases. The
economic pit shell calculated with the multiplier equal to 1 defined the ultimate pit boundaries. The
ultimate pit defines what is economically mineable for the specific deposit given certain mining and
economic parameters.
A single block model which incorporated the Middle Ridge and WBL deposits was provided (Middle
Ridge Block Model), and a single block model which incorporated the Kelly’s Hump and Kelly South
deposits was provided (Kelly’s Hump).
The block models were constrained by the lease boundaries and the delineated wetland areas, both
which were provided by HDR Engineering Inc. Blocks within the block model but outside the designated
“available” areas were coded within the block model and were unavailable to be mined as part of the
optimization process.
16.2.2 Parameters
Whittle™ optimization was completed on the block models received April 21, 2014.
Resulting nested economical shells were used as a guide for the pit creation and phase design.
The economic parameters used at the time of the pit optimization contain some variance from those
stated in the economic model but do not introduce a material change.
Within the block models, a single kaolinite mineral has been modelled. This is used to produce two
products, kaolin and metakaolin, with different selling prices. An estimated weighted average
(depending on recovery and plant capacity) has been used to generate a selling price for the single
mineral Kaolin. The weighted average selling price is US$148/t.
The same situation applies to the modelled variable Sand. It is used to produce k-spar and quartz
products. As the selling price for both K-Spar and Quartz is the same, the selling price of US$220/t
has been used.
The recovery split per product from each variable is fixed and a combined recovery and selling prices
were used for kaolinite products and sand final products within Whittle™. Table 16.2.2.3 shows the
total recoveries per variable (halloysite mineral is not included as it is used to produce single product).
Table 16.2.2.4: Combined Selling Prices for Kaolinite and Sand Minerals
Mineral Product Sell Price (US$/t)
Kaolinite Kaolin 95
Kaolinite Metakaolin 225
Kaolinite Recovered Ton of products 148
Sand K-spar 220
Sand Quartz 220
Sand Recovered ton of products 220
Source: I-Minerals, 2014
16.2.3 Results
As part of the Whittle™ optimization, revenue factors are used as the multiplier for all economic
parameters to produce a multitude of the intermediate shells. Figure 16.2.3.1 and Figure 16.2.3.2 show
a pit by pit graph produced by Whittle™. This graphs shows how each deposit reacts to different
revenue factors ranging from 0.6 to 1.08 based on the assumptions listed in Tables 16.2.3.1 and
16.2.3.2.
Source: SRK
Source: SRK
16.3.1 Parameters
The physical parameters used in the design are detailed in Table 16.3.1.1.
16.3.2 Results
Nine phases were designed in order to achieve the required clay/sand blend. The phases were based
on the distinct pits formed from the Whittle™ optimization. The pits were reviewed and additional
phases were not required to meet the schedule requirements.
Phase 1
Phase 2
Phase 3
Source: SRK
Phase 1
Phase 2
Source: SRK
Phase 1
Phase 2
Source: SRK
Phase 2
Phase 3
Source: SRK
Table 16.3.3.1 and Table 16.3.3.2 show the differences between the designed pit volumes and the
optimized pits.
Table 16.3.3.1: Kelly’s Hump and Kelly South Pit Design versus Optimized Shells
Pit Designed Pits Optimized Shell Difference (%)
Measured & Indicated Tons 4,373,258 4,614,657 95%
Waste Tons 2,152,064 1,968,142 109%
Total 6,525,322 6,582,798 99%
Source: SRK
Table 16.3.3.2: Middle Ridge and WBL Pit Design versus Optimized Shells
Pit Designed Pits Optimized Shell Difference (%)
Measured & Indicated Tons 3,221,823 3,408,611 95%
Waste Tons 1,875,412 1,637,941 114%
Total 5,097,235 5,046,552 101%
Source: SRK
Source: SRK
Figure 16.3.3.1: Kelly’s Hump and Kelly South Pit Designs and Optimized Shells
Source: SRK
Figure 16.3.3.2: Middle Ridge and WBL Pit Designs and Optimized Shells
Figure 16.3.3.3 shows an indicative cross section showing the optimized shell (orange) and the
designed shell with topography (blue).
Source: SRK
The waste dumps were designed in 20 ft lifts providing an overall slope angle of 26⁰. This design will
allow easy slope contouring during mine closure. The waste dump design parameters are shown in
Table 16.3.4.1.
3
The Kelly’s Hump waste dump has approximately 1.4 Mm capacity. The Kelly’s Hump and Kelly South
3
deposits require approximately 1.3 Mm to store the waste material. A 30% swell factor has been
applied to calculate volume requirements.
Figure 16.3.4.1 shows a plan view of the Kelly’s Hump Dump design.
Source: SRK
3
The Middle Ridge waste dump has approximately 1.9 Mm capacity. The Kelly’s Hump and Kelly South
3
deposits require approximately 1.5 Mm to store the waste material. A 30% swell factor has been
applied to calculate volume requirements.
Figure 16.3.4.2 shows a plan view of the Middle Ridge Dump design.
Source: SRK
The waste storage requirements for both dumps have a 10% multiplier on requirements to ensure
that any additional unplanned waste can be accommodated in the designed dumps.
Source: SRK
Identified
Wetlands
License Boundary
(pale grey)
For the purposes of the following graphs, Halloysite and Kaolin are to be fed to the “Clay Plant”, and
all Sand material is to be fed to the “Sand Plant”.
Figure 16.4.1 displays the total material movement of the operation on an annual basis.
Source: SRK
Source: SRK
Figure 16.4.3 displays the material feed to the Sand plant on an annual basis.
Source: SRK
Source: SRK
The primary target of the mine schedule was to meet Halloysite production. This was followed by
achieving maximum throughput through the sand plant.
Maximizing the throughput through the sand plant and meeting the Halloysite production target
resulted in a stockpiling requirement of Halloysite material.
All waste material from the pits is forecast to be benign, and as such not require any specific handling
procedures. All waste is planned to be dumped ex-pit at external waste dumps, within the boundaries
of the mining lease. At a further stage of planning, an opportunity exists to analyze the potential to
backfill some of pits with waste material.
A contractor (Debco) is currently planned to be used for all earthmoving activities. The contractor is
expected to supply all equipment and operators. The client will supply all fuel required to perform all
activities.
The site is expected to operate 7 days per week, 8 hours per day, during daylight hours only.
The final fleet will be determined by a third party contractor; however, SRK has estimated the type of
fleet equipment likely to be employed by the contractor.
Indicative fleet equipment is listed in Table 16.5.2.1. SRK notes the equipment brand and manufacturer
is indicative and will be interchanged with the fleet available from the contractor.
SRK has based Table 16.5.2.1 equipment models on previous conversations with the planned
contractor.
The hydraulic excavator was estimated to be able to free-dig the majority of the material within the
planned open pit. Table 16.5.4.1 shows SRK’s estimate of selected loading statistics for the existing
and planned loading units.
Table 16.5.4.1: SRK Estimate of Material Loading Statistics by Loading Unit Type
Bucket Size Matched Number of Total Truck Moving and Prod. per Unit (2)
Equipment
and Fill Factor Truck Size Passes Load Time (1) Delay Time (100% Avail)
Type
(yd3) & (%) (t) (units) (min) (min/op hr) (dt/op hr)
Hyd Ex 330CL 3.0 - 86% 30 6 2.50 7.50 120
Source: SRK
1. Includes truck spotting time.
2. Average 10% moisture assumed.
3
SRK’s planned excavator will be able to load 3.0 yd per bucket to the 30 t trucks (assuming loaded
rock swell factor of 35% and 10% moisture). Total truck loading time for ore is estimated to be 2.5
minutes (including initial positioning of the trucks for loading). Allowance was made in the loading
productivities for cleaning up working faces, and for moving the loading equipment to new working
areas.
As part of the operation, there will be some stockpiling required. The contractor will be responsible for
any rehandle requirements to meet a smooth grade blend for production.
Approximately three miles of roadway will require some work between the existing haul road and the
proposed processing facility. Mile 0 to 1.0 will require blade work, pull ditches, and the addition of 4 in.
of gravel for the 24 ft wide road. Mile 1.0 to 2.3 will have excavations of cut and fill to establish a 24 ft
road width. Mile 2.3 to 3.3 will require excavations of cut and fill to establish a 24 ft road width along
with additional gravel for the widened road sections and additional drainage structures.
Stream crossings for the new haul road will be limited to intermittent drainage crossings with culvert
installations. It is planned to install a 6 inch water line within the bed of the existing and new access
road. This water line will be used to transport water from the water wells and reservoir to the processing
plant for use in processing.
The truck selection was influenced by Debco’s planned equipment, loading unit/truck matching, and
with respect to meeting production requirements. Ore will be hauled either to the plant ore crusher, or
plant crusher stockpiles. The haul distance from the pit to the plant is approximately three miles one-
way. Waste will generally be placed in a dump west of the pit, approximately 0.7 miles one-way.
SRK estimated a salaried staff allocation of 25% of a senior superintendent to the project, and a full
time general foreman position, and assisted by a secretary/clerk.
One mine production and maintenance crew will be necessary. Equipment operator labor allocations
were based on the assumption that some of the operators will be cross-trained, and when required to
replace another person on leave will be able to operate another type of heavy equipment unit. The
mining equipment operators were estimated to number approximately 13 to 14 hourly positions,
including one operator for an integrated tool handler, and one operator for a flatbed truck (with crane).
A mining equipment maintenance department will be staffed with six mechanics. Hourly maintenance
staffing was estimated based on an average of 45% of major mining equipment operations man-hours
required.
Additional positions would include a blaster, blaster helper, and surveyor. These positions would not
require full-time work allocations to those specific roles, so that a variety of general work duties could
be performed by these employees.
An allowance was included for a 25% burden in the wage rates. Given the basic shift hours, the total
base paid hours per hourly employee per year were estimated to be 2,080 hours (260 days x 8 hours).
Based on an annual vacation allowance of 10 days, six statutory holidays, and assuming six
sick/absent days per year the total worked hours per hourly employee per year was estimated to be
1,904 hours [2,080 hours – (10 days x 8 hours) – (2 x 6 days x 8 hours)].
I-Minerals will provide power and industrial water for use at the mining contractor’s facilities (for normal
usage levels to be established as part of the final mining contract).
I-Minerals staff will perform ore feed blending using its own wheel loader from the RoM (run-of-mine)
ore stockpiles into the crusher, with two operators covering different shifts (as required). Diesel
generators will power sump pumps required in the pit. Two mobile light plants have been included.
I-Minerals will perform its own routine light vehicle equipment maintenance, while other maintenance
will be out-sourced through a contract with a local equipment dealership.
17 Recovery Methods
Section 17 summarizes operation results, processing methods, a conceptual flowsheet, plant design,
and plant consumables.
Clay Recovery
It was determined that approximately 30% of the feed reported to the clay separation circuit and the
remaining material reported to the feldspathic sand circuit. Following grit removal and fractionation of
the two clays, about 22.6% of overall recovery was attributed to the clay (based on overall feed). Of
this 22 .6% clay recovery, almost 22% yielded halloysite product (about 7% overall recovery) and the
rest yielded kaolinite product (about 15.6% overall recovery).
It was determined that of the material feeding the feldspathic sand circuit approximately 18% was
recovered as K-spar product (meeting acceptable product quality specifications). Over 50% of the
feldspathic sand circuit feed was recovered as quartz products (Quartz 1, 2, and 3 based on acceptable
product quality specifications). Incorporating a marketing product matrix for the desired three quartz
products, the yields for each were as follows: Quartz 1 at 25.2%, Quartz 2 at 14.4%, and Quartz 3 at
11.1%. Overall recoveries based on ore were 17.6%, 10.1%, and 7.8%, respectively. It should be noted
these yield and recovery values were based on yearly operating criteria developed through the desired
product matrix – not hourly – due to the fact that actual hourly production operating criteria allows only
for either Quartz 1 and Quartz 2 production or Quartz 1 and Quartz 3 production.
The basic fixed operating parameters used for the development of the material balance were as
follows: 24 hours per day, 7 days per week, 50 weeks per year, and a 93% operating efficiency. This
equated to a conservative 7,812 hours per year.
The finished product matrix originally developed for the design of the material balance and subsequent
circuit/equipment sizing utilized a couple of specific product “drivers” (halloysite and K- spar).
Halloysite production was set at a minimum of 15,000 t/y for the clay circuit, while a minimum 28,000
t/y was used for the feldspathic sand circuit. The remaining product production rates were then
determined by the resulting material balance criteria.
residual (or primary) deposits of kaolin, which also contain K-feldspar and quartz. The clay contains
both kaolinite and halloysite (aluminosilicate clay minerals) with the empirical formula Al Si O (OH) .
2 2 5 4
Ore Processing
Quartz 3 Grade Product final upgrading using Rare Earth Magnetic Separators; and
Quartz 3 Grade Product to packaging or fine grinding using Air-swept Stirred Media Mill/Air
Classifier and packaging.
Continue evaluating alternative equipment options to improve the clay circuit both by product
quality and reduce overall capital equipment costs. These options include centrifuge
optimization and alternative separation techniques to improve halloysite quality, pH
adjustment and flocculation for clay filtration, and dryer optimization;
Methods of packaging the products are dictated by the markets. The most common form of
packaged kaolin is the 50 lb (Kraft) bag. Kaolin clay is also supplied in dry bead and dry powder
form in supersacks (bulk bags) and fiberboard containers. Halloysite nanotubes will be
packaged per customer requirements yet to be determined; and
Continue product development of halloysite, metakaolin, K-spar, and quartz products per
market development requirements.
17.3 Flowsheet
Two pictorial flowsheets are provided for the Project as shown in Figures 15-2 and 15-3.
17.4.3 Degritting
The screw overflows are transferred to the Derrick Linear Motion sizing screens to make a 325 mesh
cut. The +325 mesh retains report to the Derrick Hi-Cap screen, while the underflow passing fraction
reports to a holding/mix tank. The -325 mesh material is intensely mixed and then fed through a bank
of Krebs 3 inch cyclone circuit.
Each 3 inch cyclone is capable of a feed rate of approximately 31 gpm at an inlet pressure of 8 to 10
psi. A distribution feed manifold system is used to uniformly maintain constant and consistent feed
variables. The 3 inch cyclones effectively make about a 20 μm cut. The overflow fraction (-44+20 μ)
reports to waste, while the underflow clay fraction reports to a holding/mix tank.
The calciner operates at a temperature of approximately 900°C to produce a pozzolanic clay material
known as a metakaolin. The metakaolin product is discharged and pneumatically conveyed to a holding
bin, packaged in supersacks or Kraft bags.
The circuit handling dried kaolin will have built-in flexibility to handle either kaolin as a product for
packaging and/or to calcine and package a portion of the kaolin clay into metakaolin product.
The hydrocyclone overflow is pumped to the pre-flotation recycle water tank/clarifier system and the
underflow is mixed with dispersant sodium hexametaphosphate [Na 2(PO3)4] in a two-stage attrition
scrubber. The scrubbed product is deslimed in a hydrocyclone.
The feldspar and quartz-rich “tailings” are floated in a bank of six feldspar rougher flotation cells
followed by a bank of four feldspar cleaner flotation cells. The tailings fractions from both banks are
the feed for the quartz circuits, while the concentrate from the cleaner cells is the K-spar fraction.
A portion of the Quartz 1 grade fraction is processed further into either Quartz 2 grade or Quartz 3
grade materials. The Quartz 1 grade fraction is conditioned with hydrofluoric acid, amine, fuel oil, and
frother, and refloated in a bank of two flotation cells to complete another iron flotation step. The iron
rich concentrate is pumped to the tailings tank, while the tailings are again conditioned and “scavenger”
floated in a bank of six quartz flotation cells. The concentrate is recycled to the feldspar flotation circuit
while the tailings are processed as Quartz 2 grade material or subjected to further flotation. The Quartz
3 grade material is achieved by performing one more conditioning and scavenger flotation step as
described for the Quartz 2 grade.
Quartz 2 and Quartz 3 grade materials are individually processed through a separate circuit in the
same manner as described for the Quartz 1 grade.
Both electricity and natural gas will be provided by Avista Utilities. Avista has been informed and kept
updated on the project for quite some time, and has provided current cost data for the economic
modeling.
Reagents for the project include specific flotation reagents for feldspar and quartz, dispersing reagents,
flocculation reagents, and pH adjustment reagents. Suppliers will be regionally located with the
probable exception of the flotation reagents. The flotation reagents are very specific to the flotation of
feldspar and quartz, and the domestic supplier may not be regionally based.
The equipment maintenance parts are variable and will be dependent on detailed analysis of inventory
and replacement requirements moving forward with the project. Accountability at this time has been
accessed by applying a percentage to the purchased equipment cost estimate contained in the capital
cost estimate.
18 Project Infrastructure
18.1 Site Access Road
Primary access to the Project will be via the Moose Creek Road. The mine site is approximately 5
miles north and west from the access point on Idaho State Highway 3, just west of Bovill. Access to the
plant site is also via Moose Creek Road approximately 2.3 miles from State Highway 3. In order to
eliminate traffic near Moose Creek Reservoir, a “reservoir bypass road” of approximately one mile will
be improved north of Moose Creek Reservoir.
The processing facility will encompass approximately 4.0 ac of storage areas for pre-processing ore.
Post-primary crushing material will cover approximately 1.5 ac. Post-processing storage of products
2
will be in silos and/or warehouses that will collectively cover approximately 10,000 ft (0.25 ac). Pre-
shipment storage of packaged product in warehouse facilities will cover approximately 0.75 ac. Offices,
facilities, and workstations for support services and staff will cover approximately 5.0 ac.
The Project complex will have a connected load of 6.5 MW. The largest loads required will be 0.5 MW
for the Primary Rod Mill and 0.3 MW for the Quartz Fine Grinding System.
This power will be purchased from Avista Corp and will be received at its substation on transmission
lines owned by Avista Corp. Substation transformers will have a capacity of 11.0 MVA, and reduce
voltage from 138 kV to 13.8 kV for on-site distribution.
Natural gas is primarily used for Rotary Dryers and the Calciner for the Clay circuits, Fluid Bed Dryers
for the feldspar circuits, and multiple HVAC units for general facility heating during colder temperatures
at the plant. Natural gas is purchased from Avista Corp and supplied to the Project via a gas pipeline
owned and operated by Avista Corp. The annual consumption of natural gas is calculated to be
3,300,000 therms per year based on the equipment needs for the plant design. Unit costs were given
directly by Avista Corp for this Project.
18.4 Water
Water needed at the processing plant can be provided by ground water wells at the processing plant
and a reservoir north of the mine site. Despite a considerable amount of in-circuit flow, the majority of
the water is recycled within the various plant circuits. The amount of water consumed in the processing
plant is approximately 170 gpm. All the water within the circuits is recycled (including collection ponds)
or lost due to drying or evaporation, and therefore no water is discharged to waters of the U.S. or
State. The water balance within the plant is shown in Figure 18.4.1
The proposed Boyle TSF is designed to accommodate approximately 2.4 Mt of thickened tailings from
the processing plant and will handle tailings up to a nominal rate of 87,000 t/y with an assumed average
tailings dry density of 90 pcf. Currently the tailings facility will operate for approximately 25 years and
will be required to handle tailings at an annual rate of 78,000t/y or a total of 1.9 Mt of thickened tailings.
Table 16.5.1 summarizes the design criteria adopted for the TSF design.
The ultimate TSF embankment rises at a 2H:1V (2 Horizontal units to 1 Vertical unit) slope to a
maximum elevation of approximately 3,040 ft above mean sea level. The construction of the
embankment will occur in three stages utilizing a modified centerline method. The tailings
characteristics and deposition plan are assumed to result in a beach slope of approximately 0.5 percent
for the Boyle TSF. The Boyle TSF will be lined with a compacted 3 ft clay liner to inhibit seepage from
the facility. The TSF includes an overliner drain system to enhance tailings dewatering and
consolidation and reduce hydraulic head on the liner system. The TSF design includes an underdrain
system to reduce uplift groundwater seepage and a toe drain system to enhance stability.
Three collection ponds are present immediately downstream of the TSF embankment to collect water
from the overliner drain and toe drain systems. This water will be carried through a reclaim pipeline to
the plant for reuse. Underdrain water will be collected at a sump, checked for water quality, and
released downstream. An access road is also designed to the east of the facility for the slurry pipeline
and for the reclaim water pipeline to the plant.
Halloysite clay, an aluminosilicate with hollow tubular morphology in the submicron range;
Kaolinite clay, hydrated aluminum silicate;
Metakaolin clay, refined kaolin clay (aluminum silicate) or dehydroxylated kaolin clay calcined
to create amorphous aluminosilicate, which is reactive (Pozzolan) and enhances the strength,
density and durability of concrete;
K-Spar, also known as potash feldspar uniquely suited ceramic formulations requiring an
alumina source; and
Quartz, SiO2 silicon dioxide.
The following discussion is supported through an independent market study by Charles River
Associates of Boston, MA, (CRA) dated December 2011. Furthermore, I-Minerals continues to study
potential markets for its products as is common in the industrial minerals industry.
19.1.1 Halloysite
Halloysite has historically been used in the manufacture of porcelain, bone china, and fine china due
to purity of the clay and the low iron and titanium content resulting in ceramic ware with exceptional
whiteness and translucency. Fine particle size enables halloysite to also be used as a suspension
agent in glaze preparations as well as in filters and inkjets, and as an ingredient in special paints
applied to ships to prevent barnacles from growing on the ships' hulls.
The largest supplier of commercial halloysite product available at present is located in Matauri Bay,
New Zealand. Limited production is reported from Poland, Turkey and China, and a development stage
project is located in Utah with negligible commercial production. I-Minerals’ halloysite is differentiated
from those known halloysite deposits because of its high aspect ratio and minimal trace elements.
Halloysite nanotubes (HNTs) are considered a high value product. The high aspect ratio (tube length
to diameter) of the tubes allows the tubes to be filled or coated with substances to achieve a wide
variety of electrical, chemical, and physical properties. The markets interested in filling halloysite hollow
tubes with active ingredients include cosmetics, household and personal care products, pesticides,
paint, pharmaceuticals and the life sciences market.
I-Minerals has received inquiries from the following industries: personal care products, Nano-
composites, fire retardants, biocides, plastic fillers, animal feed, paint, ceramics, two undisclosed R &
D projects and several universities.
19.1.2 Kaolin
I-Minerals kaolin characterization is in development stage. Market analysis indicates several high- end
applications such as metakaolin (Section 19.1.3), plastics and ceramics which are of interest to the
western North American market. Also within the western North America market mid- and low-end
applications will be evaluated such as paint, fiber glass, catalysts, refractories, roofing granules, and
bricks. Initial testing has determined the company’s kaolin product fires white. Interest from end- users
will be followed with samples which are highly anticipated by ceramic, paint, and brick companies
whose geographic proximity to the deposit will allow transportation savings as opposed to receiving
kaolin from southeastern United States.
19.1.3 Metakaolin
Metakaolin is considered a premium material adding extra strength and durability. The market requires
a consistent product and the ability to meet prescribed ASTM standards. For clarification, ASTM C 618
is the gateway to the metakaolin market. The company’s metakaolin was determined to be a pozzolan
metakaolin product through meeting ASTM C 618-08: Chemical and Physical Analysis of a Natural
Pozzolan and Chemical and Physical Analysis of Fly Ash. The company’s metakaolin also shows
significant ASR mitigation capabilities meeting ASTM C 1567 Alkali Silica Reaction standard.
Direct contact with western states’ Departments of Transportation and Ready Mix companies reveal a
market for metakaolin both in paving and bridge cap repairs. The company’s geographic location will
afford significant transportation savings and an opportunity for use of a once-too-expensive product in
the Western United States and Canada. Metakaolin is valued for ASR mitigation, particle size, and low
water requirement which mean higher quality—all descriptive of the company’s metakaolin test results.
19.1.4 Feldspar
Potassium feldspar (K-feldspar) is primarily used in ceramic bodies and glazes. The company notes
strongest market potential for its K-feldspar in Western North American markets; however, Midwest
and Eastern North American ceramic, tableware, tile, and sanitary ware manufacturers have expressed
an interest in the low iron, high alumina chemical composition of MC K-Feldspar. The chemical quality
of the company’s product is not available in the North American market today by other feldspar
producers. Samples have been distributed widely; the product performs to expectations in testing by
end users.
K-feldspar is also used in the coating industry as functional filler; samples have been submitted to a
major coatings manufacturer. K-feldspar is valued for the physical properties of dispersability,
weatherability, scrubability, and mildew resistance in industrial and marine coatings.
19.1.5 Quartz
The chemistry of I-Minerals’ quartz products ranging from SiO2 of 99.8% to 99.97+% (high purity and
low iron) gained immediate attention within the glass industry as the results were announced in news
releases and the website. Manufacturers expressing an interest are from North America and the Pacific
Rim region from several high-end markets: LCD glass, solar glass, sodium silicate, and lighting
manufacturers to low-end container and float glass markets. Melt tests in second quarter 2014 are
arranged. Manufactures of glass fiber, art glass, ceramic applications, and paint add to the interested
users of 99.8% SiO2 product. High-end quartz product of 99.97+% commands an attractive price within
the specialty quartz market.
However, the QP for this PFS confirms that I-Minerals has, in fact, completed a market study for its
products which included preliminary negotiations to supply a series of clay and sand products. The QP
also confirms that the process facility is capable of producing these products. While negotiated prices
are confidential, composite market prices are presented in Table 19.2.1.
19.3.1 Terms
Mineral products will be sold FOB at the Bovill Processing Plant along with product shipped and
delivered to buyers in the area.
Soils are shallow to moderately deep with loamy to sandy textures and usually contains volcanic ash.
Most of the Project area has been used for mining, grazing, and/or timber harvest and therefore a
relatively disturbed landscape is present. Evidence of past mining is found in borrow pits, tailings piles,
as well as mine pits. Forested areas primarily occur on slopes and ridge tops and are intensively
managed for timber production. Forests in the Project area are composed of Douglas fir, grand fir, and
western red cedar. Open wet meadows, occurring primarily in the basins along intermittent and
perennial stream channels, are dominated by grassland with intermittent shrubs.
The Project area is located near the headwaters of Moose Creek, in the Potlatch River watershed. The
Potlatch River originates northeast of Bovill, ID in the Beals Butte area and runs for 90 km (56 miles)
in a southwesterly direction through the southern half of Latah County with roughly 3,000 km (1,900
miles) of tributary streams. The Project area is drained by several branching ephemeral streams.
Springs in the area are both ephemeral and perennial.
A wetland and ordinary high water mark (OHWM) delineation of the Project area was conducted in the
summer and fall 2012. The delineation efforts focused on areas of potential land disturbance
associated with roads, processing facilities, pits, and tailing areas. The goal of the delineation was to
map the boundaries of wetlands and other waters of the U.S., and to provide this information to the
project design team so that disturbance of these areas could be avoided. As such, if there is no fill or
disturbance to wetlands or other waters of the U.S., no CWA Section 404 permit is required. A wetland
delineation report will be submitted to the USACE for a formal jurisdictional determination. Following
this determination, additional changes to Project facility layout may be required in order to avoid
wetlands and other waters of the U.S.
The Idaho Surface Mining Act, Title 47, Chapter 15, Idaho Code requires the operator of a surface
mine to obtain an approved reclamation plan and bond. The Project is on state leased land and as
such no federal mine permit approval is required.
The IDL is the lead agency for surface mine activity in Idaho and requires an approved operating plan
and reclamation plan prior to mining. In addition, IDL is the lead agency for implementing the anti-
degradation policy for surface mining and may solicit comments from other resource agencies in
reviewing and approving the permit including Idaho Department of Fish and Game (IDFG), Idaho
Department of Water Resources (IDWR), and Idaho Department of Environmental Quality (IDEQ). It is
anticipated that these agencies will be requested by IDL to participate in the mine permitting process.
Work conducted to date includes pre-feasibility level design of the tailings facility, processing plant,
and quarry areas that includes standard water management control features.
Remaining tasks include completing the analysis of potential impacts to ground and surface waters
and development of a plan to maintain compliance with surface and groundwater quality standards, as
needed. In addition, a reclamation plan will be required that identifies, evaluates, and provides
mitigation for areas disturbed by mining. This information, along with the rest of the Project plans will
be submitted to IDL as the Bovill Kaolin Mine Operation and Reclamation Plan Application. IDL, with
support from resource agencies, will review and provide subsequent comment on the application and,
once any outstanding issues have been resolved, will provide mining authorization.
In Idaho there are three types of air quality permits: Permits to Construct (PTC), Tier I Operating
Permits, and Tier II Operating Permits. Air quality permit requirements are addressed under IDAPA
58.1.1 – Rules for the Control of Air Pollution in Idaho. The PTC program is required for new or
modified sources. PTC permits do not expire unless construction has not begun within two years of its
issue date or if construction is suspended for one year. Tier II Operating permits are issued to facilities
when IDEQ has determined that a facility needs an air quality permit to comply with applicable rules,
or when an applicant has specifically requested one. The most common type of Tier II operating permit
that IDEQ issues are those which the applicants have requested in order to establish synthetic minor
emission limits. For the construction of a new source it is a PTC that is required. A Tier II operating
permit is generally developed after site startup (often one year after operations begin). A Tier I
operating permit (also known as Title V permit) is required for all major sources of air pollution. Tier I
Operating permits are required for major sources even if the facility already has a PTC. Tier I permits
expire within five years.
An assessment of emission sources (emissions inventory) for roads, tailings, and the processing
facility must be completed. Limited stack emissions are typically associated with this type of project
and can be controlled through air pollution control devices. Tasks remaining to be completed include
an emissions inventory for the Project, modeling these emissions, and preparation of the PTC that
includes expected impacts, minimization measures, and any monitoring, as needed.
No significant air quality issues have been identified to date. This is primarily due to the limited quantity
and composition of stack emissions associated with a project of this type. Emissions sources include
emissions from gas-fired dryers, generators, diesel truck operation, and fugitive dust. Also, while
fugitive dust can be a significant concern, use of mitigation measures (e.g. proposed dust collectors,
material wetting, and other controls) and presence of few receptors in the Project area reduce this
concern.
Construction and operation activities associated with the Project will be covered by the 2012 NPDES
General Permit for Discharges from Construction Activities and the NPDES MSGP for Stormwater
Discharges Associated with Industrial Activity. Both are general permits that require a NOI to be filed
and the development of a SWPPP. The general construction permit covers temporary activities such
as facility structure construction, while the MSGP covers on-going mine related activities such as
overburden removal and general mining activities.
A preliminary assessment of stormwater discharges has been completed. Issues identified include
construction stormwater runoff, and potential discharge of contaminants from runoff from waste dumps
and tailings. Based on the processing plant operation plan, no direct effluent discharges to waters of
the US would occur so an individual NPDES permit for process water will not be needed. Remaining
tasks to be completed include final identification of water balance and management plans for all runoff
sources. This will include development of a site-wide SWPPP for construction stormwater and for the
MSGP.
The NPDES stormwater general permits described above are the only identified environmental federal
permits associated with the Project. As a federal action, these general permits have requirements for
complying with the Endangered Species Act, Section 106 of the National Historic Preservation Act,
and Clean Water Act Section 401 Certification. Each of the items is addressed below.
Endangered Species Act - In order to obtain coverage under both stormwater general permits, the
applicant must avoid adverse effects on federally listed threatened and endangered species from the
stormwater discharges and discharge related activities. An updated evaluation of endangered species
will need to be conducted at the time of submitting the NOI for the stormwater permits. Threatened
and endangered species or critical habitat identified for Latah County based on review of the current
list (June 10, 2014) from the U.S. Fish and Wildlife Service (USFWS) are:
A formal hair snare survey was conducted from March 29, 2011 through April 27, 2011 to determine
the presence or absence of the Canada lynx with the general Project area (Tetra Tech, 2011). A
combination of remote cameras and hair snares were used to monitor lynx activity within and around
the general Project area. Hair snare surveys were performed in general accordance with the survey
methods used during the National Interagency Canada Lynx Detection Survey in Minnesota,
Wisconsin, and Michigan (Burdett, et al., 2006). Due to the distance from the nearest Canada lynx
critical habitat, large amount of human disturbance and year round use, relatively small amount and
poor quality of usable habitat, and results of the 2011 hair snare surveys, the Project area does not
appear to support Canada lynx or its critical habitat.
The Spalding’s catchfly prefer Palouse prairie habitat, which does not exist in the Project area. During
wetlands surveys of the project area in 2008 and 2012, no habitat for water howellia individuals was
found.
Several federally listed fish species and essential fish habitat occurs in the Potlatch River drainage,
which is over 4 miles from the Project site. Impacts from proposed site activities on the Potlach River
is unlikely due to the distance between the Project and the occupied habitat, as well as the fact that
best management practices through implementation of the SWPPP would help eliminate or
substantially reduce any indirect effects from water quality impacts.
Section 106 of the National Historic Preservation Act – Under a federal stormwater general permit, the
applicant is required to make certain certifications regarding the potential effects of stormwater
discharge, and discharge related activities on properties listed or eligible for listing on the National
Register of Historic Places. A study of the Project disturbance areas (mine quarries, access roads,
processing facility, and tailings/dump areas) will be completed to assess for the presence/- absence
of cultural resources. A study in the general Project area (but not at the exact locations of Project
features) was completed by Dr. Lee Sappington of the University of Idaho in 2007. Findings from that
study indicated no effect on listed or eligible historic sites. The State Historic Preservation Office
(SHPO) concurred with this finding. Based on the similar conditions found in the Project area it is
anticipated that there will be little, if any impact to historic resources associated with stormwater
discharge and related activities. A cultural survey of the Project area will be conducted to support the
NOI application for the general stormwater permits.
Section 401 Certification – The Clean Water Act requires state certification for any permit or license
issued by a federal agency for an activity that may result in a discharge into waters of the U.S. The
IDEQ issued Section 401 certification for construction general permit on April 3, 2012 and MSGP on
December 5, 2008. The certifications identify monitoring requirements as part of the permit if
stormwater is discharged to impaired waters. Monitoring and reporting requirements will be
incorporated into the SWPPP.
Other Federal Permits and Requirements
As described above, the only identified federal permit is related to NDPES general stormwater permits
and their requirements associated for the Endangered Species Act, Section 106 Historic Resources,
and Clean Water Act Section 401 Certification. The goal for the Project is to avoid fill in wetlands and
waters of the U.S., and as such, no Section 404 permit would be required. With no federal actions
other than stormwater general permits, no National Environmental Policy Act (NEPA) evaluation,
Section 7 consultation, or Section 106 consultation are necessary. If it is determined following more
detailed mine design that fill in wetlands cannot be avoided, then a Section 404 permit and supporting
NEPA evaluation would be required.
develop a complete list of permits until the project design is more fully developed, however, the
major permits are included in this table.
In addition to the permit/authorizations described in Table 20.2.1.1, several other permits and
approval will be required. A preliminary list includes:
According to a report from Idaho Department of Labor, the 2011 per capita income for Latah County
was US$31,809 compared to a state average of US$32,881. In Latah County, approximately 10.2%
of Latah County families are below poverty level between 2007 and 2011 (U.S. Census Bureau, 2013).
Approximately 12% of the Bovill residents were reported to have an income below the poverty level in
the year 2011.
Construction of the mine could create 30 to 50 new jobs and provide an economic boost to Latah
County. The economic stability of the communities in Latah County would benefit by having the current
workforce living in the communities and employed at the mine. In addition to the direct employment,
indirect and induced employment will also be generated. The indirect and induced employment is that
of suppliers to the mine and employment due to spending by employees of the mining operations.
Based on the current employment and wage report, Latah County’s average hourly wage for a
construction laborer is US$14.41 generating yearly salary of approximately US$29,979 (Idaho
Department of Labor, 2013). Hence, the direct income may increase at peak construction in the Bovill
region. Additional temporary indirect income will be generated in construction supporting industries in
nearby Bovill, ID.
The current housing market and community service facilities of the region would likely be sufficient to
absorb the increase in the local population. Therefore, no increased demand on the housing market
and on the community services is expected as a result of the temporary increases in population during
construction and operational phase of the extraction pit.
Operation of the mine would result in the long-term employment opportunities as the mine is expected
to be operable for 26 years. In addition to the direct jobs created by the operation of the mine, additional
indirect jobs would be created in other supporting industries.
LoM capital costs are shown in Table 21.1.1. The initial capital estimate is US$72.7million. An
additional US$18.2 million in sustaining capital will be required. Total LoM capital will therefore be
about US$90.8 million.
21.1.1 Mining
Mining will be performed by a contractor and therefore the purchase of production equipment will not
be required. Owner-related mine capital associated with mining are for minor support functions, which
will not be performed by the mining contractor. A provision for mine equipment is included in the
process cost estimate. Capital costs estimated in this section include provisions for site development
and mine shop equipment. In addition, there is provision for a flatbed truck, two pickups, two light
plants, and computer equipment and software.
Owner-related mine capital costs, as shown in Table 21.1.1.1 will initially be US$919,000 and will total
US$1.4 million over the LoM. Mine-related support equipment is shown in Table 21.1.1.2.
Sustaining capital, totaling US$467,000 over the 25-year LoM provisions scheduled equipment
replacements and software license renewals.
The basis for this cost is the capital cost estimate provided by R&S/KBR and shown in Table
21.1.2.2. Sustaining capital was estimated to be 2% per annum of the Purchased Equipment Cost from
the R&S/KBR estimate.
Per Mr. Gary Nelson of I-Minerals, the operating cost estimate was based on 7,812 working hours per
year with approximately 87,000 t/y of tailings. The current estimate indicated that an average rate of
78,000 t/y of tailings will be used.
Table 21.1.3.2 presents an estimate of the material quantities and unit construction costs anticipated
for the major components of the Boyle TSF.
LoM operating costs are shown in Table 21.2.1. Over the LoM, operating costs will be about
US$65.35/t of product produced.
21.2.1 Mining
Mine operating costs will average US$7.30/t-RoM (US$10.10/t-product) as summarized in Table
21.2.1.1. The majority of the cost is attributable to an average contract mining rate of US$4.33/t- mined.
The mine contractor cost estimate as developed by SRK is summarized in Table 21.2.1.2. Contract
mining will be performed at an average cost of US$4.33/t-material moved. This equates to a value of
US$7.52/t-RoM over the LoM.
Mine G&A costs, shown in Table 21.2.1.3 include leasing space from the mine contractor’s
maintenance facility (US$100,000/year), dewatering the pit (US$40,000/year) and exploration
(US$250,000/3-years). Mine-related supervisory, engineering, geology, and surveying personnel are
included in the process operating cost estimate in Section 21.2.2.
Mine G&A costs will be US$5.0 million over the LoM or US$0.73/t-RoM over the LoM.
Support equipment costs are estimated from first principles using the productivity table presented
below. Table 21.2.1.4 estimates operating costs based upon equipment operating parameters for the
project. Support equipment costs will be US$861,000 over the LoM, or US$0.13/t RoM.
Support equipment annual hours are based upon 60% utilization operating 260 day/year, and 1-8 hour
shift per day.
Fuel and lubricant costs are based upon budget estimates of US$3.50/gal and US$7.50/gal,
respectively.
21.2.2 Processing
Process operating costs for the Project were estimated by R&S/KBR. LoM average processing
operating cost is US$59.18/t-Product as shown in Table 21.2.2.1.
Process operating costs were developed using first principles and based upon the flowsheet described
in Section 17.2, shown in Figures 17.2.1 and 17.2.2, and detailed in Table 21.2.2.2.
Labor will consist of five supervisory personnel and 50 operators. It should be noted that mine
supervisory and engineering tasks are included in this estimate, and therefore are not in the mine G&A
(owner) operating costs as presented in Section 21.2.1. Salary and hourly rates are consistent with
those in the Northwest US.
Flotation reagent consumption rates were determined from process testwork. Reagent unit costs are
based upon budgetary quotes provided to I-Minerals.
Operating/Maintenance cost for the tailings storage facility was developed by Tetra Tech and include
the pumping and placement cost for the thickened tailings in the Boyle TSF. The cost is estimated to
be US$1.0 million LoM or US$0.15/t of RoM.
21.2.3 G&A
G&A costs will average US$1.04/t-product, or an average of US$280,000/y over the LoM. The estimate
includes general maintenance, outside services, permitting and environmental, and a provision for the
operation of the laboratory.
22 Economic Analysis
The financial results of this report are based upon work performed by SRK, R&S/KBR, Tetra Tech,
and I-Minerals and have been prepared on an annual basis. All costs are in Q1 2014 US dollars.
A 2-year preproduction period is assumed to allow for permitting, detailed engineering, and due
diligence/financing. The mine will have an estimated mine life of 25 years given the Mineral Reserve
described in this report.
The analysis calculates a LoM weighted average market price of US$254.79/t for all products produced
and sold. All products will be sold FOB at the Bovill Processing Plant.
Table 22.2.2 shows the annual production tonnage, free cash flow for debt servicing, and present
values at a 6% discount rate for the project on a yearly after-tax basis.
The AMT is determined in three steps. First, regular taxable income is adjusted by recalculating certain
regular tax deductions, based on AMT laws, to arrive at AMT Income (AMTI). Second, AMTI is
multiplied by 20% to determine TMT. Third, if TMT exceeds regular tax, the excess is the AMT amount
payable in addition to the regular tax liability.
22.3.3 Royalty
I-Minerals is required to pay 5.0% of the gross revenues from the sale of all products, as discussed in
Section 4.4.
$275,000
$250,000
NPV @ 6% US$(000)
$225,000
$200,000
$175,000
$150,000
$125,000
-15% -10% -5% Base 5% 10% 15%
Revenues Operating Costs Capital Costs
Source: SRK
23 Adjacent Properties
Hammond Engineering currently operates a small raw clay operation on the old A.P. Green
Refractories pit north of Helmer. About 10 years ago, the owner revealed that the operation produced
roughly 1,300 t/y RoM product of Maple member clays, which were sold at a price of US$20/t (fob).
The clay was used by Wendt Pottery in Lewiston, Idaho to produce a buff-firing porcelain ceramic body
and by Clayburn Industries as a clay binder for refractories. The owner of Wendt Pottery states that he
still uses this clay, about the same amount each year. In 1997 reserves for this property, which are
considered historic and were not prepared in accordance with NI 43-101, were 1.65 Mt, based upon 50
ft drill centers. This was extrapolated from an Information Memorandum offered by A.P. Green
containing tonnages and property information in an effort to sell the operation.
25.1 Results
The results of this PFS evaluation indicate that I-Minerals can produce 800 t/d of clay (halloysite, kaolin,
metakaolin), K-feldspar, and quartz mineral products. Products such as halloysite clay and kaolinite
clay are used in a number of applications such as ceramic wares, household and personal care
products, cosmetics, pharmaceuticals, paint, glass, roofing granules, and bricks. Metakaolin adds
extra durability to pozzolan cement and is used in ready mix concrete and paving and bridge repair
products. K-feldspar is used in ceramic products and glazes, and quartz is used in a variety of glass
products depending on purity. Inquiries have come for these mineral products from potential markets
in western U.S. and Canada. The materials would be sold FOB at the Bovill Processing Plant and/or
shipped to customers depending on the product.
The Project is on state-leased land and as such, no federal mine permit approval is required. The
Idaho Department of Land is the lead agency. I-Minerals will work with IDL to secure approval for its
operating and reclamation plan. The mine permitting process requires permits from a number of other
state agencies such as IDFG, IDWR, and IDEQ. Work completed to date includes PFS-level
engineering design of the pit and plant facilities and the TSF. The geochemical characterization work
completed to date indicates that the potential to generate acid or alkaline drainage from the ore and
waste materials is extremely low to non-existent under normal environmental conditions. Some
delineations and environmental studies have been initiated or completed. Some remaining tasks
include:
Completing the analysis of potential impacts to groundwater and surface water and
developing plant to ensure compliance with all water quality standards;
Preparing an air quality emissions inventory, model and permit application; and
Based on the updated mineral reserves and mine plan, approximately 5.0 Mt of mineral materials would
be produced from small pits with an anticipated Project mine life of 25 years. The economic analysis
results indicate an after-tax NPV of US$212.7 million at a 6% discount rate with an IRR of 30.5%. The
economics are based on a consolidated LoM average price for all products of US$254.79/t-produced.
The gross income, after a 5% royalty on gross proceeds is applied, is estimated to be US$1,202 million
or US$241.05/t-produced. Direct operating costs are estimated at US$70.68/t-produced. Total
operating costs are US$352.4 million. Total capital costs are estimated at US$90.8 million, consisting
of initial capital costs of US$72.7 million, and ongoing sustaining capital over the life of operations of
US$18.2 million. Mine closure costs are estimated to be US$5.1 million with no allowance for salvage
value.
Should a geosynthetic liner be required, this will affect the quantities and cost of the TSF;
Should the wetlands boundaries vary and be within the footprint of construction for the Boyle
TSF, the facility will need to be modified or moved;
Wetlands may be indirectly impacted by the TSF at the Boyle site location;
It is estimated that the average in situ dry density of the tailings is 90 pcf; should the actual
density vary significantly, the capacity of the TSF will change; and
The schedules are based on 7,812 hour work year; should this vary over time, the scheduled
costs will change.
25.2.6 Environmental
A number of environmental permits are required for construction and operation of the facilities.
Environmental permitting has an estimated completion time line of six months to one year. A moderate
risk exists that that permitting may take longer than estimated thus delaying the start of the project by
several months. If I-Minerals proceed as they have indicated and avoid wetlands, such that no CWA
404 permit is required, then the only Federal permitting is for stormwater (Section 402 NPDES) and
the remaining permits (Idaho Mine Operation and Reclamation Authorization and Air Quality Permit)
are with the State of Idaho. Furthermore, by not having a CWA 404 permit, there is no federal nexus
triggering the NEPA process, and fewer potential delays related to environmental permitting would
therefore be encountered.
26 Recommendations
Recommendations for future work programs, the approximate timeline, and costs are provided in the
sections below. The studies, data, and engineering designs derived in the Feasibility Study phase will
be sufficient to prepare an Operations and Reclamation Plan, initiate the environmental permitting
process, and justify a full production decision.
26.1 Exploration
SRK recommends that I-Minerals conduct additional infill drilling within the areas supporting the first
10 years of mine life to increase the confidence of the reserve to a proven classification. This could be
achieved with approximately 75 additional drillholes located on 100 ft centers. . Additional density
testing should also be conducted to better characterize the relation between clay content and density.
At least 300 samples from a range of total clay contents and different resource areas need to be
analyzed to provide better confidence in the current density model. Upon completion of the drilling,
analytical testing, and density measurements, a revised resource and reserve estimation should be
completed. This will reduce project risk during the critical payback period.
Review the key drivers of the project (e.g. Halloysite, Kaolin versus Sand);
Consider the use of mining pits that contain only Sand material (i.e. no clay);
Review waste dump locations (consider sterilization drilling);
Consider tendering the earthworks contract to ensure a competitive bid is being used for
costing purposes; and
Complete a review of geotechnical conditions for the Kelly’s Hump and Kelly South deposits;
The timeline for securing the major permits is estimated to be 12 months once the application
documents have been prepared. The major permits and expected timeline includes:
Idaho Mine Operation and Reclamation Authorization – 12 months from time of submittal of
the Plan of Operation, Reclamation Plan, and application;
Air Quality Permit – 12 months from time of sufficient facility design (would occur after
feasibility stage is completed).
Section 402 NPDES – these are general permits and require submittal of a NOI and
development of a SWPPPs. There is a 30-day waiting period after submittal of NOI. The
SWPPPs and NOI application are expected to be completed two months prior to project
construction startup.
A combined stress-strain and seepage model should be completed to further understand the
consolidation, seepage, evapotranspiration, infiltration rate, and the cover design of the Boyle
TSF;
A liquefaction analysis is required due to the gradation of the tailings and their non-plastic
nature;
Bench level tailings testing is required, as the tailings rheology and materials have changed
since the last test;
Additional investigations and laboratory testing of the native soils should be completed to
further understand how much native material is suitable for use as the clay liner and structural
fill;
An investigation of springs and seeps in the impoundment area should be completed to assess
the flow that may occur within the foundation of the TSF;
A tradeoff study is recommended to optimize the type of liner system; and
A tradeoff study is recommended to evaluate the potential for a dry stack versus a conventional
tailings facility to reduce earthwork quantities.
26.6.1 Costs
The estimated costs for the recommended work programs to be completed in the next 12 to 18 months
are presented in Table 26.6.1.1. SRK has reviewed this program and believes that the costs and
timeline are reasonable.
27 References
Browne, James L., 2006, The report on the Helmer-Bovill feldspar, quartz, and kaolin mineral leases,
Latah County, Idaho: unpublished report prepared for I-Minerals Vancouver, B.C., March 13, 2006.
Bush, J.H., Odenborg, L.J. and Odenborg, N.D., 1999, Bedrock map of the Deary Quadrangle, Latah
County, Idaho: Idaho Geological Survey Tech. Report 99-3.
Clark, J.G., 2003a, Geological evaluation of two feldspar-clay prospects associated with intrusive rocks
of the Idaho batholith in Latah County, east of Moscow, Idaho: Confidential Report prepared for
Alchemy Ventures Ltd., 122 p.
Clark, J.G., 2003b, Petrographic and mineralogical characterization of feldspar-quartz ores and
products from the Helmer-Bovill project and comparison with selected commercial and prospective
commercial feldspar-quartz ores and products: Confidential Report prepared for Alchemy
Ventures Ltd., 170 p.
Clark, J.G., 2003c, Petrographic characterization of feldspar and quartz products and residuals from
the Blue Lagoons bulk tailings sample and from drill core intervals MC-3, 14-40’ and MC-22, 45-
80’: Confidential Report prepared for Alchemy Ventures Ltd., 89 p.
Clark, J.G., 2004a, Report on the Helmer-Bovill feldspar, quartz, and kaolin mineral leases, Latah
County, Idaho: Confidential NI 43-101 Report prepared for I-Minerals Inc., 73 p.
Clark, J.G., 2004b, Petrographic/cathodoluminescence characterization of drill core samples from the
Alchemy Kaolin 2003 WBL drilling program: Confidential Report prepared for Alchemy Ventures
Ltd., 175 p.
Clark, J.G., 2004d, Petrographic/cathodoluminescence study of bulk sample feldspar and quartz
products from the 2003 exploration drilling program, Helmer-Bovill project, Latah County, Idaho:
Confidential Report prepared for I-Minerals Inc., 89 p.
Clark, J.G., 2005, Petrographic/Cathodoluminescence characterization of drill core samples from the
Kelly's Basin 2005 diamond drilling program: Confidential Report prepared for I-Minerals Inc., 149
p.
Erikson, E.H., 1986, Northwest kaolin resources – A review of the Bovill deposits, northern Idaho:
paper presented at Northwest Mining Association’s Annual Meeting, 1986, 18 p.
FLSmidth Krebs, 2008, Laboratory Report For I-Minerals – File N: 1716, Series No: 3044.
Ginn Mineral Technology, Inc., 2005, Kaolinite/Halloysite clay evaluation: Unpublished confidential
report prepared for I-Minerals Inc., 20 p.
Ginn Mineral Technology, Inc., 2006, Kaolinite/Halloysite clay evaluation, Phase II: Confidential Report
prepared for I-Minerals Inc., 26 p.
Ginn Mineral Technology, Inc., 2008, Hydrocyclone Evaluation: Confidential Report prepared for I-
Minerals Inc., 30 p.
Ginn Mineral Technology, Inc., 2010, Hydrocyclone Evaluation: Confidential Report prepared for I-
Minerals Inc., 33 p.
Hodgson, C.J., 2000, Interim report on Bovill kaolin project, Latah County, Idaho: Unpublished
confidential NI 43-101 report prepared for Alchemy Ventures Ltd., 22 p.
Hosterman, J.W., and Prater, C.S., 1964, Clays, in Mineral and Water Resources of Idaho, Idaho
Bureau of Mines and Geology Special Report #1, p. 51 – 57.
Hosterman, J.W., Scheid, V.E., Allen, V.T., and Sohn, I.G., 1960, Investigations of some clay
deposits in Washington and Idaho: U.S. Geol. Survey Bull. 1091, 147 p.
Kelly, H.J., Carter, G.J., and Todd, G.H., 1963, Bovill clay and sand deposit, Latah County, Idaho:
U.S. Bureau of Mines R.I. 6330, 56 p.
Kirkham, V.R.D., and Johnson, M.M., 1929, The Latah formation in Idaho: Jour. Geology, v. 37, p.
483 – 504.
Montgomery, J.H., 2002, Helmer-Bovill feldspar, clay and silica mineral leases, Latah County, Idaho:
Unpublished confidential NI 43-101 report prepared for Alchemy Ventures Ltd., 76 p.
Murray, H.H., Partridge, P., and Post, J.L., 1978, Alteration of a granite to kaolin – Mineralogy and
geochemistry: Schriftenr. Geol. Wiss. 11, Berlin, p. 197-208.
Priebe, K.L., and Bush, J.H., 1999, Bedrock geologic map of the Stanford quadrangle, Latah County,
Idaho: Idaho Geological Survey Technical Report 99-8.
Schlanz, J.W., 2011, Recovery of high grade quartz from I-Minerals WBL ore body: unpublished report
prepared by Minerals Research Laboratory, North Carolina State University, September 14, 2011..
SRK Consulting, 2010, NI 43-101 Technical Report Helmer-Bovill Project, Kelly’s Basin Mine, Latah
County, Idaho: technical report published on SEDAR filing system, November 5, 2010.
SRK Consulting, 2012a, NI 43-101 Preliminary Economic Assessment, Bovill Kaolin Project, Latah
County, Idaho: technical report published on SEDAR filing system, January 18, 2012.
SRK Consulting, 2012b, NI 43-101 Technical Report on Resources, WBL Tailings Project, Latah
County, Idaho: technical report published on SEDAR filing system, January 18, 2012.
STRATA, 2012, Geotechnical Exploration-Prefeasibility, High Wall Stability, Plant Site, Access Road
study on the Bovill Kaolin Project, File No. IMINER M012040A, June 27, 2012.
Streckeisen, E.C., 1976, To each plutonic rock its proper name: Earth Science Reviews, International
Magazine for Geo-scientists, Amsterdam, vol. 12, p. 1-33.
Swanson, D.A., Wright, T.L., Hooper, P.R., and Bentley, R.D., 1979, Revisions in stratigraphic
nomenclature of the Columbia River Basalt group: U.S. Geol. Survey Bull. 1457-G, 59 p.
Tetra Tech, 2012, Volume 5: Tailings Management Technical Report, Bovill Kaolin Project, Bovill,
Latah Country, State of Idaho. Tetra Tech Project No. 114-311277: Unpublished report prepared
for I-minerals Inc., October 5, 2012.
Tullis, E.L., 1944, Contributions to the geology of Latah County, Idaho: Bulletin of the Geol. Soc. of
America, v. 55, p. 131-164.
U.S. Fish and Wildlife Service (USFWS) June 10, 2014. Idaho Fish and Wildlife Office Endangered,
Threatened, Proposed, and Candidate Species With Associated Proposed and Critical Habitats in
Idaho
Yuan, J., 1994, Clay mineralogy and its influence on industrial uses of some kaolin clay deposits from
south China and eastern Washington – Idaho, U.S.A.: [Ph.D. Thesis] Indiana University, 153 p.
28 Glossary
28.1 Mineral Resources
The mineral resources and mineral reserves have been classified according to the “CIM Standards on
Mineral Resources and Reserves: Definitions and Guidelines” (November 27, 2010). Accordingly, the
Resources have been classified as Measured, Indicated or Inferred, the Reserves have been classified
as Proven, and Probable based on the Measured and Indicated Resources as defined below.
An ‘Inferred Mineral Resource’ is that part of a Mineral Resource for which quantity and grade or quality
can be estimated on the basis of geological evidence and limited sampling and reasonably assumed,
but not verified, geological and grade continuity. The estimate is based on limited information and
sampling gathered through appropriate techniques from locations such as outcrops, trenches, pits,
workings and drillholes.
An ‘Indicated Mineral Resource’ is that part of a Mineral Resource for which quantity, grade or quality,
densities, shape and physical characteristics can be estimated with a level of confidence sufficient to
allow the appropriate application of technical and economic parameters, to support mine planning and
evaluation of the economic viability of the deposit. The estimate is based on detailed and reliable
exploration and testing information gathered through appropriate techniques from locations such as
outcrops, trenches, pits, workings and drillholes that are spaced closely enough for geological and
grade continuity to be reasonably assumed.
A ‘Measured Mineral Resource’ is that part of a Mineral Resource for which quantity, grade or quality,
densities, shape, physical characteristics are so well established that they can be estimated with
confidence sufficient to allow the appropriate application of technical and economic parameters, to
support production planning and evaluation of the economic viability of the deposit. The estimate is
based on detailed and reliable exploration, sampling and testing information gathered through
appropriate techniques from locations such as outcrops, trenches, pits, workings and drillholes that
are spaced closely enough to confirm both geological and grade continuity.
A ‘Probable Mineral Reserve’ is the economically mineable part of an Indicated, and in some
circumstances a Measured Mineral Resource demonstrated by at least a Preliminary Feasibility
Study. This Study must include adequate information on mining, processing, metallurgical, economic,
and other relevant factors that demonstrate, at the time of reporting, that economic extraction can be
justified.
A ‘Proven Mineral Reserve’ is the economically mineable part of a Measured Mineral Resource
demonstrated by at least a Preliminary Feasibility Study. This Study must include adequate information
on mining, processing, metallurgical, economic, and other relevant factors that demonstrate, at the
time of reporting, that economic extraction is justified.
Term Definition
Sill A thin, tabular, horizontal to sub-horizontal body of igneous rock formed by the
injection of magma into planar zones of weakness.
Smelting A high temperature pyrometallurgical operation conducted in a furnace, in which the
valuable metal is collected to a molten matte or doré phase and separated from the
gangue components that accumulate in a less dense molten slag phase.
Stope Underground void created by mining.
Stratigraphy The study of stratified rocks in terms of time and space.
Strike Direction of line formed by the intersection of strata surfaces with the horizontal
plane, always perpendicular to the dip direction.
Sulfide A sulfur bearing mineral.
Tailings Finely ground waste rock from which valuable minerals or metals have been
extracted.
Thickening The process of concentrating solid particles in suspension.
Total Expenditure All expenditures including those of an operating and capital nature.
Variogram A statistical representation of the characteristics (usually grade).
28.4 Abbreviations
The following abbreviations may be used in this report.
Appendices
T: 303.985.1333
F: 303.985.9947
denver@srk.com
www.srk.com
th
Dated this 26 Day of June, 2014.
“Signed” “Sealed”
1. I am a Geological Engineer with Tetra Tech with a business address at 350 Indiana
Street, Suite 500. Golden, Colorado, U.S.A. 80401.
2. This certificate applies to the technical report titled “NI 43-101 Updated Prefeasibility,
Technical Report, Bovill Kaolin Project, Latah County, Idaho” with an Effective Date of
April 20, 2014 (the “Technical Report”).
3. I am a graduate of The Colorado School of Mines at Golden, Colorado (Bachelor of
Science, 1983). I am a member in good standing of the Board of Professional
Engineers of the State of Idaho (License No. 8350). My relevant experience includes
over twenty five years of professional experience in the design and construction of
tailings storage facilities in the United States, Mexico, Panama, Guatemala, El Salvador,
Venezuela, Guyana, Bolivia, Peru, Chile, Argentina, Dominican Republic, Turkey, and
Australia. I am a “Qualified Person” for purposes of National Instrument 43-101 (the
“Instrument”).
4. I have read the definition of “qualified person” set out in National Instrument 43-101 (NI
43-101) and certify that by reason of my education, affiliation with a professional
association (as defined in NI 43-101) and past relevant work experience, I fulfill the
requirements to be a “qualified person” for the purposes of NI 43-101.
5. I am responsible for preparation of the Tailings Sections 18.5, 21.1.3, 25.2.5 and 26.4 of
the Technical Report.
6. I am independent of the issuer applying all of the tests in section 1.5 of NI 43-101.
7. I have had limited prior involvement in the Pre-Feasibility Study for the subject of the
Technical Report. I was also an authoring QP of the report titled “NI- 43-101
Prefeasibility Technical Report, Bovill Kaolin Project, Latah County, Idaho,” with an
Effective Date of November 23, 2012.
8. I have read NI 43-101 and Form 43-101F1 and the sections of the Technical Report I
am responsible for have been prepared in compliance with that instrument and form.
9. As of the aforementioned effective date, to the best of my knowledge, information and
belief, the sections of the Technical Report I am responsible for contains all scientific
and technical information that is required to be disclosed to make the Technical Report
not misleading.
[SIGNED, SEALED]
David S. Hallman, PE
SRK Denver
7175 West Jefferson Avenue.
Suite 3000
Lakewood, CO 80235
T: 303.985.1333
F: 303.985.9947
denver@srk.com
www.srk.com
CERTIFICATE OF AUTHOR
th
Dated this 26 Day of June, 2014.
“Signed” “Sealed”