ACKNOWLEDGEMENT

First of all, I wish to express my sincere gratitude to my lovely lecturers Prof. Dr. A.
Ghaffar Ahmad, Prof. Dr. Azizi Bahauddin, and Dr. Safial Aqbar Zakaria who guide us
in this bill of quantity project and help whenever I was in need. I am also indebted to
the dean of School of Housing, Building and Planning for giving me the opportunity to
learn during the studio RDS 301 and providing the facilities to help me complete this
project without any obstruct.

I am grateful to the member of Studio RDS 301 for their supports, advice, sharing
information, and their comradeship especially to all the persons that made this project
a rich experience for me.

Last but not least, I would like to express my deepest gratitude for the constant
support, financial support, understanding and love that I receive from my parents
during the past years. At the end of my acknowledgment, I would like to thank my
roommate, who has helped to clear up my dark corners of my language, and thanks to
all people who make this project a possible and enjoyable experience for me.

2
TABLE OF CONTENTS

Title Block ......................................................................................................................................... 1


Acknowledgments .................................................................................................................................. 2
Table of Contents ....................................................................................................................................3

Chapter 1 : Background of Project .....................................................................................................5


1.1 Building Chosen ..........................................................................................................6
1.2 Location of Building .................................................................................................... 8
1.3 Client .............................................................................................................................9
1.4 Problem Statement .................................................................................................. 11
1.5 Objective of Project .................................................................................................. 12
1.6 Concept ......................................................................................................................13

Chapter 2 : Case studies


2.1 Case Study 1 .............................................................................................................15
2.2 Case Study 2 .............................................................................................................16
2.3 Case Study 3 .............................................................................................................17

Chapter 3 : Spatial Analysis


3.1 Ground Floor Plan .................................................................................................... 19
3.2 First Floor Plan ..........................................................................................................19
3.3 Grand Total Area........................................................................................................ 19

Chapter 4 : Cost Analysis


4.1 Ground Floor Plan .................................................................................................... 21
4.2 First Floor Plan ..........................................................................................................45
4.3 Grand Total Area........................................................................................................ 66

Chapter 5 : Design Analysis


5.1 Style ............................................................................................................................68
5.2 Design Solution .........................................................................................................69

Chapter 6 : Conclusion......................................................................................................................... 77

Bibliography .......................................................................................................................................78

3
CHAPTER 1
BACKGROUND OF PROJECT

4
1.0 BACKGROUND OF PROJECT

Today, the Iban are still a powerful presence, albeit for a different, more
innocuous reason – they are the largest ethnic group, indigenous or not, in Sarawak.
They are considered as a branch of the Dayak lineage, even earning the nickname
‘Sea Dayaks’ from British colonists in the past. As is the case for their native brethren
from other tribes, the Iban have an illustrious spread of culture and tradition that dates
back centuries, making them an indispensable piece of Sarawak’s heritage.

The Iban Heritage Center under the management of Malaysia Tourism


Promotion Board and with support from the Sarawak community, traces the history of
the Iban and South Asian communities in the Southeast Asian region.

The four-storey building is an iconic, unique and sustainable building that blends
both indigenous Iban as well as modern architectural elements. The architectural
design for the facade this building is inspired by the Pua Kumbu,the hand-woven warp
ikat textile of the Iban and seeks to create an urban forum for the celebration and
appreciation of Iban culture. It houses five permanent galleries, small scale museum
facilities, a museum shop as well as programming and activity spaces.

Situated at Gat lebuh Gereja, the centre also serves as a springboard for visitors
to explore the roots of indigenous and enjoy the sights, sounds and scents of the
historical precinct The main objective is promote greater public awareness and
appreciation of Iban heritage, arts and culture.

Thus, Penang island is known for its outstanding aesthetic beauty — it’s an area
that bears testament to the compelling natural history of our planet. Listed as a
UNESCO site, the island will soon be host to a new Iban Heritage Center. The center
is anticipated to become a meeting place set to educate and promote the importance
of preserving the Iban’s culture and its heritage for future generations to come among
East Malaysian.

5
1.1 BUILDING CHOSEN

Taking into consideration the fact that the goal of the proposed building was to
make a good balance between historical heritage and existing contemporary context,
conclusion was that the best way to achieve this was by proposing moderate
intervention carefully implemented into existing surroundings. The intervention aims
to promote qualities of existing public square size and location while trying to add new
qualities by incorporating UNESCO sites into public space and making them
accessible by elements like open rooftop, ramps, landscaping and lighting. Design
proposal tries to reinforce the monuments historical significance.

Square paving consists of cast-in-situ wide concrete patches of several lengths


which are derived from grid in two very bright almost white tones and with slight
difference in surface roughness and crease orientation. Instead of ramps, all small
height alterations are compensated with sloping pavement. Only new structures in the
proposal, beside sky rooftop and big ramp in site, are 2 platforms above parking
area. Lower level is elevated deck connected with main square with stands, ramp,
stairs and elevators, combining greenery and paving.

Having in mind all the challenges of managing culture in this era, and a specific
need to re-establish knowledge, critical thinking and sophistication as values in the
era of commercial spectacle. Particularly, decided to set the design guidelines based

6
on two pieces of information from design brief. One of them is the overview of Iban’s
architectural heritage; the other one is importance of architecture in museum
programs and activities.

To create an engaging facade, the science and technology aspects were taken
from the point of design within the building, and was inspired by the Iban traditional
woven cloth, Pua Kumbu. The pua kumbu, the hand-woven warp ikat textile of the
Iban, represents the quintessence of Iban culture. It is, depending on the design,
historical archive, a mythological or religious story or a personal tale. It is a statement
about the soul of the weaver and her relationship with the spirit. The Pua is treated as
a gift from the Petara (Gods) to the Iban community and for that, it is considered
something very special and sacred thus regarded as a symbol of a cultural identity for
the Iban community in Sarawak.The building’s facade is a reflection of this inspiration
and was created using a concrete mix reinforced with micro-fibers. Pre fabricated
panels were used to create the design, and they included pigmentation to change the
color.

7
1.2 LOCATION OF THE BUILDING

Church Street, or Lebuh Gereja, is one of the streets within the core zone of the
George Town Unesco World Heritage Site. Located within the Commercial District of
19th century George Town, it is one of the early streets to be laid in the town, and has
appeared in the Popham Map of 1798.

The Iban Heritage Center is building developments, which strategically located at


Gat Lebuh Gereja, particularly near at Georgetown adjacent to the Pengkalan Weld.

4 storeys heritage building in Lebuh Gereja provide and environment to work,


relax, shop, play that would suit the needs of any business. The ground floor is fronted
by a landscaped road & walkway, perfect for retail business.

8
1.3 CLIENT

The Malaysia Tourism Promotion Board or Tourism Malaysia is an agency under


the Ministry of Tourism & Culture, Malaysia. Tourism Malaysia focuses on the specific
task of promoting Malaysia at both domestic and international levels.
Driven by its aspiration to promote Malaysia as a destination of excellence in this
region, Tourism Malaysia continues to propel the industry to greater heights.

Vision - To make the tourism industry a primary source of national revenue and a
prime contributor to the socioeconomic development of the nation.

Mission - To market Malaysia as a premier destination of excellence in this region.

Quality Policy - Tourism Malaysia is committed to the professional and effective


dissemination of national tourism information, the fulfillment of customer requirements
and supporting or assisting customers in making their visits to Malaysia a success.

Quality Objective - To produce a skilled and knowledgeable workforce and to


disseminate tourism information accurately and efficiently with customer-friendly
service.

9
Functions of Tourism Malaysia

In accordance with the Malaysian Tourism Promotion Board Act 1992, the functions of
the Board (Tourism Malaysia) are to:

 Stimulate and promote tourism to and within Malaysia


 Invigorate, develop and market Malaysia internationally and domestically as a
tourist focal point
 Coordinate all marketing or promotional activities relating to tourism
conducted by any organization, government or non-governmental agency
 Recommend to the minister relevant measures and programmes that
stimulate development and promotion of the Malaysian tourism industry and to
implement them upon approval

In line with the role of Tourism Malaysia as a promotional organization, the following
objectives are upheld:

 Increase foreign tourist arrivals


 Extend the average length of stay of the visitors to increase tourism revenue
 Stimulate the growth of domestic tourism
 Increase the benefits/share obtained from the Meetings, Incentives,
Conventions and Exhibitions (MICE) market

10
1.4 PROBLEM STATEMENT

 Everyone in East Malaysia including some surrounding people around the main
cultural or world heritages is not even aware of the real stories of the Indigenous
Iban heritages. It is difficult for travelers when they cannot get the desired
information from people around and the websites.

 The shape of the building is rigid and the pattern of the building make it difficult for
the space planning

 Malaysia has been rich of diversity in culture, and one of the sustain ethnic
which need to be promoted among East Malaysia. However, due to the lack of
dissemination of heritage information, tourists and sometimes even nearby
city-dwellers are not well informed about it.

 The current cultural heritage has lack of an aesthetic, emotional experience for
the viewer, leading to personal growth and development. Moreover, these
buildings, artworks, and artifacts can serve as a creative inspiration for
contemporary artists, both those working within traditional forms and those
working in a modern style.

11
1.5 OBJECTIVE OF PROJECT

 To conceive an Iban’s cultural center for people including exhibition galleries,


cultural activities, restaurants and information center as well as their landscape
architecture.

 To create a unique configuration that can compose different public spaces which
offer a suitable urban sequence. This detailed work on public space (gardens and
passages) helps the definition of the empty space between the different
constructions which stands out as the main conception of the project. The
elaboration of a sustainable development of Iban’s culture, with cultural heritage
as important factor.

 To frame such programs as would encourage and involve youth of the cultural
center among themselves and with the youth of the rest of the country in creative
cultural communications through the process of seminars, exchanges and
workshops on matters relating to the cultural heritage of Iban.

 To preserve, protect and promote the unique history and rich culture of those that
once inhabited and settled in Iban’s culture.

 The Iban Heritage Center is first and foremost a culture center – A center
dedicated to honoring those early settlers and inhabitants of the Ibans.

 To create awareness among the people of Penang, especially, to appreciate


others heritage. It includes tangible assets like intangible heritage like art, culture,
performing arts and old business practices which are dying.

12
1.6 CONCEPT DESIGN

Main Concept : The Exquisite Oneness

It was inspired from Puan Kumbu, sacred clothing which made by Iban’s women
and been wearing by Iban’s man warrior before they go to the war. It simply shows
that harmony between each other complete between them. These two opposite
character are complementary each as both mutual depending to each other. And
because of that harmony is reached through balance and brings perfectionist purity
women and men.
Deeply connected & appreciative of the art of hand-weaving, these ladies are
quietly spearheading a demand for the finest, almost extinct handcrafted textiles of
our country. The relationship bet ween the forest and the pua kumbu was one spoke
in the greater wheel of interconnections between the pua, headhunting, land
acquisition, fertility practices, rice farming, spirituality and the vast canon of Iban oral
history. Historically, when the pua kumbu circulated through the forest, it joined the
cloth to the trees and the earth. It pulled together diverse themes, connotations and
remembered notions that were articulated around the cloth. Both forests and the pua
kumbu existed in a reciprocal and interconnected dynamic; the pua kumbu incited the
movement of the Ibans through the forest.

13
Sub-Concept : Emergence of the Unity

The emergence of unity as the sub concept of the project to strengthen the
project’s overall design. It is derived from two principal religions Buddhism and
Hinduis coexist in Nepal. In fact the two religions have merged into one another,
emphasizing the basic character of older and parental faith. The arose out of the
innate spirit of tolerance of one another’s point of vie that permeates the life of the
Nepalese folks. The Buddhist and Hindus cross each other in religion and society with
no strife but in perfect accord, and with a sense of reverence for the respective deities
of each, often worshipped deities in common as amply indicated above.

The spirit of oneness and unity prevalent among them has been strengthened by
the common participation in the various national festivals, welding the diverse sects
and peoples into a united people. Buddhism regards life as the unity of the physical
and the spiritual, the Buddhist of Nepal are not distinguishable from their Hindu
brethen, as they have adopted vital aspects of the traditional and parental faith with
fillial affection and plety. The physical and spiritual aspect of lives are completely
inseparable and of equal importance. Hence, there are two stripes which bent into
helical helical shape as sub concept model. It represent two major religions in Nepal;
Buddhist and Hindu. They live together in the country as a lamp of light arising from a
wicked soaked oil and illuminate their motherland with the common light of their souls.
As the stripes has the same size and shape, it represent the similarities of the both as
both believe in reincarnation, karma and enlightenment. Also while most people these
days consider these concepts to be Budhhist, all of these concepts come from
Hinduism. The two stripes are twisted form to symbolize the gradual improvement of
evolution of each religions while different width along the stripes is to create some
vibrant volumes to sub conceptual model.

14
CHAPTER 2
CASE STUDIES

15
2.1 CASE STUDY 1 : 6 Degrees Cafe

Location: Alam Sutera, Indonesia


Gross floor area: 208 sqm
Client/owner: PT Dinamik Sukses Artaboga
Architecture consultant: OOZN Design - Singapore
Principal designer: Rafal Kapusta
Interior design consultant: OOZN Design - Singapore
Interior contractor: Myspace design
Lighting consultant: OOZN Design - Singapore
Main contractor: Myspace design

Situated inside a mall in Jakarta, 6 Degrees Cafe has a rectangular floor plan with a 16m
long shopfront on the long side. The most visually impact from the exterior was the ceiling and
the rear wall, so we focused on it. We created an undulating skin of timber slats equally spaced
apart at 150mm intervals which covers the entire wall and ceiling to break the monotony of
spatial heights. Undulation of the veneer plywood were hand crafted by the local carpenters,
meticulously following the unwrapped elevations drawn by us. Varying depth of the fins not only
create a strong visual impact, they also hide the ceiling equipment and improve the acoustics
inside the cafe. With music in the background and heavy flow of customers, individuals are still
able to enjoy a chitchat over a nice cup of coffee.
Finishes were carefully chosen to create a cosy and relaxed ambiance using natural
materials & colors, including the selection of the furniture. Timber veneer slats matches the
concrete screed floor to give a rustic touch. Warm timber and natural tones contrast with a dark
interior paint provides an escape from the outside heat. Individual pendant lights hang over
each table, floor recessed strip lights gives a soft illumination to the timber slats, providing just
the right amount of luxe level to create a soothing ambiance.
16
2.2 CASE STUDY 2 : The Indian Heritage Centre

The Indian Heritage Centre (IHC), under the management of the National Heritage Board
and with support from the Indian community, traces the history of the Indian and South Asian
communities in the Southeast Asian region.
The four-storey IHC building is an iconic, unique and sustainable building that blends both
traditional Indian as well as modern architectural elements. The architectural design for the
facade of IHC is inspired by the “baoli” (or Indian stepwell), and seeks to create an urban forum
for the celebration and appreciation of Indian culture. It houses five permanent galleries, small
scale museum facilities, a museum shop as well as programming and activity spaces.
Situated at 5 Campbell Lane, the center also serves as a springboard for visitors to explore
Little India and enjoy the sights, sounds and scents of the historical precinct. IHC was opened
by Prime Minister Lee Hsien Loong on 7th May 2015 and will offer year-round exhibitions,
programmes and activities to promote greater public awareness and appreciation of Indian
heritage, arts and culture.
Embodying IHC’s vision, the four-storey IHC building is an iconic, unique and sustainable
building that blends both traditional Indian as well as modern architectural elements. The
architectural design for the facade of IHC is inspired by the “Baoli” (or Indian step well), and
seeks to create an urban forum for the celebration and appreciation of Indian culture.
The diversity and mufti-faceted nature of Indian culture is also captured in the use of a
translucent shimmering facade to create an impression of IHC as a “shining jewel” in the day,
and the transformation of the IHC into a “glowing lantern” of the Indian community with the
lighting of the colorful facade mural at night.

17
2.2 CASE STUDY 3 : One Main Office Renovation

Architects:dECOi Architects
Location:Cambridge, MA, USA
Area:10000.0 ft2
Project Year:2009
Project Team:Mark Goulthorpe, Raphael Crespin, Gabriel Blue Cira, Matt Trimble, Priyanka
Shah
MIT:Kaustuv de Biswas
Mathematics:Prof Alex Scott (Oxford University)
Consultants:Helen Heitman, Pablo Garcia (Gensler Associates)
General Contractor:Paul Jacobson (Tricore)
Millwork Contractor:Shawn Keller (CWKeller)

From the architect. The project was for the penthouse offices of an investment group in
green building and clean energy technologies (CChange). The design drew from our prior
sculpture, In the Shadow of Ledoux, 1993, and the Galerie Miran, 2003, proposing the milling
of all elements of the interior from sustainably-forested spruce plywood using numeric
command machines: information carves renewable carbon-absorbing resource.

The developed design was nuanced parametric-ally in celebration of the indifference of the
CNC machine to formal complexity. The entire project was nested onto 1200 4ft x 12ft plywood
sheets, and milled using a small 3-axis CNC router, which effortlessly carved the ply sections
according to our prescribed ‘weeping’ tool paths. Well over a million linear feet of cut were
issued, yet the machine process was essentially error-free and highly accurate. Assembly
proved relatively straightforward given the accuracy of the milling, and we enjoyed the
elegance of the emerging forms.

One Main uses sustainability forested Finnish spruce ply with non-toxic water-based glue.
The 10,000sq ft (1000m2) project nested onto 1200 sheets of 1.5” thick 4ft x 12ft ply, milled
locally by a single 3-axis milling machine. dECOi provided the actual tooling paths (over 1
million linear feet of cut), with no plans or sections, just 3D instructional files. Wastage was
about 10%, pulped and recycled.

18
CHAPTER 3
SPATIAL ANALYSIS

19
3.1 SPATIAL ANALYSIS FOR EVERY SPACE
3.1.1 Floor

SPACE
FLOOR LEVEL SUB AREA TOTAL SUB AREA
DESCRIPTION (m2) (m2)
Ngajat Blackbox 220
Kebat Workshop 210
1 900
Ngelaban Gallery 105
Kids Play Area 110
GROUND FLOOR Receptionist 305
Souvenir Shop 130
Computer Laboratory 45
Toilet 45
Misc (stairs, lift and 730
etc)
FIRST FLOOR Interactive gallery 376
Cafeteria 320
1 900
Gawai Gallery 125
Office Administration 310
Sigat Gallery 225
Toilet 45
Misc (stairs, lift and 499
etc)

3.1.2 Grand total area

NO DESCRIPTION TOTAL SUB AREA

Total Sub Area (Ground


1 1 900
Floor)
2 1 900
Total Sub Area (First Floor)

Sub Total 3 800

Plus 15% Contingency 570

Grand Total Area 4 370

20
CHAPTER 4
COST ANALYSIS

21
4.1 GROUND FLOOR
RATE AMOUNT
ITEM PRODUCT DESCRIPTION UNIT QTY.
(RM) (RM)
1 Ground Floor - Black box
Theater
Internal Work
1.1 Floor Finishes nos 2500 39.99 99 975
To supply, delivery and install
Quartz Stone Midnight Black
Gloss Tiles 300mm x 300mm
SKU: 436160 finishes c/w all
necessary as per designer’s
approval
To supply, delivery and install m2 11.314 5000 56 570
1.2
NIVOflex MOT motoric 250mm
height octagon-shape platforms for
(performer) c/w with all needed
hardware and necessary
accessories as per manufacturer’s
detail
To supply, delivery and install m2 11.314 220 2 489.10
1.3
Lumber Mart Burmese Teak
timber flooring finishes with acrylic
impregnated on octagon-shape
platforms for (performer) ; c/w all
necessary fixtures as per
designer’s approval
2 Wall Finishes
2.1 To supply and construct concrete
m2 382 200 76 400.00
wall with cement and sand (1:3)
c/w with all needed hardware and
necessary accessories as per
manufacturer’s detail
2.2 To supply and install 125mm x nos 220 150 33 000.00
170mm x 3800 mm acoustic
veneered wall panels DecorEagle
vertically with all needed hardware
and necessary accessories as
per manufacturer’s detail

22
3 Ceiling Finishes

3.1 To supply and install 100 mm thk m2 220 500 110 000.00
of Gypsum board panel false
ceiling using galvanized sections
for hanging and holding the
gypsum board panels of 12mmtk
with approved design works
around duly painted with three
coats of plastic emulsion paint
after necessary works provisions
are to be made for fixing of
A.C.Grills, light fittings as
manufacturer’s detail
3.2 To supply and install 2100 mm x nos 820 95.86 78 605.20
130mm x 100 mm thk octagon
shape decorative suspended
ceiling by MDF Rustic Pine Board
with high gloss spray paint
finishes;c/w inner lighting system,
all necessaries and fixtures as per
designer approval
4 Fitting and Equipment
Fixed Furniture
Sitting
4.1 To supply and install auditorium nos 160 450 72 000.00
theater seating Wood or PP writing
pad with aluminum alloy supporter
and High density molded foam
padding 870 mm x 690 mm x
540mm or approved equivalent as
per designer’s approval
4.2 Riser
To supply and install riser 200 mm
Nos 28 450 12 600.00
thk theater riser platform; c/w
installation and all necessary
accessories and fixtures as per
manufacturer’s detail
4.3 Sign Board
To supply and install 420 mm
height “Ngajat Theater Room” sign
board with stainless steel; nos 1 5000 5 000.00
including white color neon back
light; c/w installation and all
necessary accessory and fixture
as per designer’s approval
5 Other Equipment

23
5.1 To supply, delivery and apply Nos 1 1500 1 500.00
SWD solid wood door, Alexander
range, model B650; c/w
installation and all necessary
accessories and fixture per
designer’s approval
6 System
6.1 To supply and install emergency m2 220 350 77 000.00
fire sprinkler; c/w installation and
all necessary accessories and
fixture as per manufacture’s detail
6.2 To supply and install photoelectric
smoke detector; c/w installation
Nos 10 1500 15 000.00
and all necessary accessories and
fixture as per manufacture’s detail
6.3 To supply and install emergency Nos 1 800 800.00
extinguishers; c/w installation and
all necessary accessories and
fixture as per manufacture’s detail
6.4 To supply and install duct type air Nos 4 8000 32 000.00
purification HT-C@46HLEI and
piping system; c/w installation and
all necessary accessorries
according to designer’s approval
6.5 To supply and install CCTV nos 2 50 000 100 000.00
system equipment, zooms and
PTZ camera rear view CCTV
system, auto recording system,
video transmitter and receiver and
all necessary accessories and
fixture as per manufacturer’s detail
7 Lighting
To supply and install selected Nos 30 250 14 670.00
7.1
down lights with energy saving
LED Down light 20W Recessed
Ceiling Down lights Spot Light
85-265V Wall Down Lights White
Body Natural White
(4000-4500K)c/w installation and
all necessary accessories and
fixture as per designer’s approval
7.2 To supply and install selected Nos 3 69 207.00
down lights with energy saving
LED Lights Strip SMD 5050 12V

24
300 LED (5 meter) White
8 Accessories
8.1 To supply, delivery and apply
Nos 2 11 899 23 798
automatic touch screen ticket
vending machine as per designer’s
approval
8.2 To supply and install Klipsch LS 1 50 000 50 000.00
Sound System equipment;
inclusive audio system, net
working system and other; c/w
installation and all necessary
accessories and fixture as per
designer approval
TOTAL TO COLLECTION 1 870 513.30

25
Workshop

RATE AMOUNT
ITEM PRODUCT DESCRIPTION UNIT QTY.
(RM) (RM)
Ground Floor - Workshop
Internal Work
m2 210 10 000 2 100 000.00
Demolition Work
Hacking off all existing finishes
screed beds and backing, cleaning
keying bases and preparatory
work to receive new finishes
(measured separately) removing
debris form site, making good all
work undisturbed
1 Floor Finishes
1.1 To supply, delivery and install
nos 2500 39.99 99 975.00
Quartz Stone Midnight Black
Gloss Tiles 300mm x 300mm
SKU: 436160 finishes c/w all
necessary as per designer’s
approval

2 Wall Finishes
2.1 To supply and install Living Green m2 12 1500 18 000
Wall C- shaped System vertically
inclusive plants all necessaries
and fixtures as per designer’s
approval
2.2 To supply and install wall m2 10.8 921.26 9 949.61
decorative panel C-shaped
Burmese teak wood and all
necessaries and fixtures as per
designer approval
3 Ceiling Finishes
To supply and install 100 mm thk
3.1 m2 210 500 105 00.00
decorative shape decorative
suspended ceiling by MDF Rustic
Pine Board with high gloss spray
paint finishes;c/w inner lighting
system, all necessaries and
fixtures as per designer approval

26
Fitting and Equipment Nos 1 25 700 25 700.00
4 Loose Furniture
4.1 Workshop Table
To supply and install custom made
workshop wood table with chrome
plated stainless steel trestle
approved equivalent as per
designer’s approval
4.2 To supply and install custom made Nos 1 47000 47 000.00
biomorphic umbrella-shaped
bamboo structure approved
equivalent as per designer’s
approval
5 Other Equipment Nos 1 1500 1 500.00

5.1 To supply, delivery and apply


SWD solid wood door, Alexander
range, model B650; c/w
installation and all necessary
accessories and fixture per
designer’s approval
6 System
6.1 To supply and install emergency m2 210 350 73 500.00
fire sprinkler; c/w installation and
all necessary accessories and
fixture as per manufacture’s detail
6.2 To supply and install photoelectric
smoke detector; c/w installation
Nos 10 1500 15 000.00
and all necessary accessories and
fixture as per manufacture’s detail
6.3 To supply and install emergency Nos 1 800 800.00
extinguishers; c/w installation and
all necessary accessories and
fixture as per manufacture’s detail
6.4 To supply and install duct type air Nos 4 8000 20 000.00
purification HT-C@46HLEI and
piping system; c/w installation and
all necessary accessories
according to designer’s approval

27
7 Lighting Nos 25 489 12 225.00
To supply and install selected
7.1
down lights with energy saving
LED Down light 20W Recessed
Ceiling Down lights Spot Light
85-265V Wall Down Lights White
Body Natural White
(4000-4500K)c/w installation and
all necessary accessories and
fixture as per designer’s approval
TOTAL TO COLLECTION 2 2 434 149.61

28
Ngelaban Gallery
RATE AMOUNT
ITEM PRODUCT DESCRIPTION UNIT QTY.
(RM) (RM)
Ground Floor - Workshop
Internal Work
Demolition Work
Hacking off all existing finishes
screed beds and backing, cleaning
m2 105 10 000 1 050 000.00
keying bases and preparatory
work to receive new finishes
(measured separately) removing
debris form site, making good all
work undisturbed
1 Floor Finishes
To supply, delivery and install
1.1 Dolce Walnut HDF Effect m2 60 95.74 5 744.40
Laminate Flooring High Gloss
1210mm x 140mm x 12mm
finishes c/w all necessary as per
designer’s approval
1.2 To supply, delivery and install
Quartz Stone Midnight Black
Gloss Tiles 300mm x 300mm Nos 500 39.99 19 995.00
SKU: 436160 finishes c/w all
necessary as per designer’s
approval (for 45m2 area)
2 Wall Finishes
2.1 To supply and construct 2 piece of m2 147.6 112.57 16 615.33
19mm Clear Decorative Curve
tempered Float Glass c/w all
necessary as per designer’s
approval
2.2 To supply and construct indoor
Stainless steel AC 24V underwater nos 1 312984 312 984.00
led light glass water wall fountain .00
c/w all necessary as per designer’s
approval
3 Ceiling Finishes m2 105 500 52 500.00
3.1 To supply and install 100 mm thk
of Gypsum board panel false
ceiling using galvanized sections
for hanging and holding the
gypsum board panels of 12mmtk
with approved design works
around duly painted with three
29
coats of plastic emulsion paint
after necessary works provisions
are to be made for fixing of
A.C.Grills, light fittings as
manufacturer’s detail
3.2 To supply and install Decorative m2 105 108.68 11410.88
Iban Style Suspended Fiberglass
Ceiling board c/w inner lighting
system, all necessaries and
fixtures as per designer approval
4 Fitting and Equipment
Fixed Furniture nos 6 691.73 4150.38
4.1 Display Stand
To supply and install Freestanding
IPad Mini Kiosk Display Stand
TSK2011-IPad-MINI :229 x 178 x
20 mm or approved equivalent as
per designer’s approval
4.2 To supply and install door shape nos 6 250.00 1500.00
hanging on ceiling stand display
for exhibition size 1200x2000mm
or approved equivalent as per
designer’s approval
4.3 Sign Board nos 1 7000 7 000.00
To supply and install 420 mm
height “Ngelaban Gallery” sign
board with stainless steel;
including white color neon back
light; c/w installation and all
necessary accessory and fixture
as per designer’s approval
5 System m2 105 350 36 750.00
5.1 To supply and install emergency
fire sprinkler; c/w installation and
all necessary accessories and
fixture as per manufacture’s detail
5.2 To supply and install photoelectric 1500 4 500.00
smoke detector; c/w installation Nos 3
and all necessary accessories and
fixture as per manufacture’s detail
5.3 To supply and install duct type air Nos 3 8 000 24 000.00
purification HT-C@46HLEI and
piping system; c/w installation and
all necessary accessorries
according to designer’s approval
5.4 To supply and install CCTV nos 1 50 000 50 000.00
30
system equipment, zooms and
PTZ camera rear view CCTV
system, auto recording system,
video transmitter and receiver and
all necessary accessories and
fixture as per manufacturer’s detail
6 Lighting
6.1 To supply and install selected Nos 15 250 3 750.00
down lights with energy saving
LED Down light 20W Recessed
Ceiling Down lights Spot Light
85-265V Wall Down Lights White
Body Natural White
(4000-4500K)c/w installation and
all necessary accessories and
fixture as per designer’s approval
6.2 To supply and install selected Nos 3 69 207.00
down lights with energy saving
LED Lights Strip SMD 5050 12V
300 LED (5 meter) White c/w
installation and all necessary
accessories and fixture as per
designer’s approval
TOTAL TO COLLECTION 3 1 601 106.99

31
Kids Play Area
RATE AMOUNT
ITEM PRODUCT DESCRIPTION UNIT QTY.
(RM) (RM)
Ground Floor - Workshop
Internal Work
Demolition Work
Hacking off all existing finishes
screed beds and backing, cleaning
m2 110 10 000 1 100 000.00
keying bases and preparatory
work to receive new finishes
(measured separately) removing
debris form site, making good all
work undisturbed
1 Floor Finishes
To supply, delivery and install
1.1 Dolce Walnut HDF Effect m2 70 95.74 6 689.35
Laminate Flooring High Gloss
1210mm x 140mm x 12mm
finishes c/w all necessary as per
designer’s approval
1.2 To supply, delivery and install
Quartz Stone Midnight Black
Gloss Tiles 300mm x 300mm Nos 540 39.99 21 594.60
SKU: 436160 finishes c/w all
necessary as per designer’s
approval (for 49m2 area)
2 Wall Finishes
2.1 Wall Finishes m2 110 200 22 000.00
To supply and construct concrete
wall with cement and sand (1:3)
c/w with all needed hardware and
necessary accessories as per
manufacturer’s detail.
2.2 To supply and install customized Nos 195 1500 292 500.00
curve timber slats c/w with all
needed hardware and necessary
accessories as per manufacturer’s
detail.
3 Ceiling Finishes m2 220 500 110 000.00
3.1 To supply and install 100 mm thk
of Gypsum board panel false
ceiling using galvanized sections
for hanging and holding the
gypsum board panels of 12mmtk

32
with approved design works
around duly painted with three
coats of plastic emulsion paint
after necessary works provisions
are to be made for fixing of
A.C.Grills, light fittings as
manufacturer’s detail .
3.2 To supply and install 100 mm thk m2 69.87 13.57 948.14
of Rucca WPC Wood Plastic
Composite False Ceiling coated
with approved design necessary
works provisions are to be made
for fixing of A.C.Grills, light fittings
as manufacturer’s detail.
4 Fitting and Equipment Nos 2 13 26 000.00
Fixed Furniture 000.00
4.1 Sitting
To supply and install custom built
in seating transparent plastic with
aluminum alloy supporter
approved equivalent as per
designer’s approval.
4.2 To supply and install Metal Library nos 3 400 1 200.00
Book Shelf 3000mm x 600 mm x
1000 mm with electrostatic powder
coated approved equivalent as per
designer’s approval.
4.3 Loose Furniture
Counter Nos 1 98 000 98 000.00
To supply, delivery and install
custom made bench tree look alike
A317M Dark Brown Oak; c/w
installation and all necessary
accessories and fixture as per
designer’s approval
4.4 To supply, delivery and install Nos 1 20 000 20 000.00
custom made bench
parametric-slats designed; A317M
Dark Brown Oak; c/w installation
and all necessary accessories and
fixture as per designer’s approval
4.5 Sign Board nos 1 15000 15 000.00
To supply and install 420 mm
height “Bejalai Kids Room” sign

33
board with stainless steel;
including white color neon back
light; c/w installation and all
necessary accessory and fixture
as per designer’s approval
5 Other Equipment
5.1 To supply, delivery and apply Nos 1 1500 1 500.00
SWD solid wood door, Alexander
range, model B650;
5.2 To supply, and install Sony 49" 4K Nos 1 2 2 689.00
HDR Andriod LED TV 689.00
KD49X7000D ;c/w installation and
all necessary accessories and
fixture per designer’s approval
6 System m2 110 350 38 500.00
6.1 To supply and install emergency
fire sprinkler; c/w installation and
all necessary accessories and
fixture as per manufacture’s detail
6.2 To supply and install photoelectric Nos 2 1500 3 000.00
smoke detector; c/w installation
and all necessary accessories and
fixture as per manufacture’s detail

6.3 To supply and install duct type air Nos 2 8 000 16 000.00
purification HT-C@46HLEI and
piping system; c/w installation and
all necessary accessorries
according to designer’s approval
7 Lighting
7.1 To supply and install selected Nos 15 250 3 750.00
down lights with energy saving
LED Down light 20W Recessed
Ceiling Down lights Spot Light
85-265V Wall Down Lights White
Body Natural White
(4000-4500K)c/w installation and
all necessary accessories and
fixture as per designer’s approval
TOTAL TO COLLECTION 4 1 779 371.09

34
Receptionist Area (305 m2)
RATE AMOUNT
ITEM PRODUCT DESCRIPTION UNIT QTY.
(RM) (RM)
Ground Floor - Workshop
Internal Work
Demolition Work
Hacking off all existing finishes
screed beds and backing, cleaning
m2 305 10 000 3 050 000.00
keying bases and preparatory
work to receive new finishes
(measured separately) removing
debris form site, making good all
work undisturbed
1 Floor Finishes
To supply, delivery and install
1.1 Dolce Walnut HDF Effect m2 150 95.74 14 361.00
Laminate Flooring High Gloss
1210mm x 140mm x 12mm
finishes c/w all necessary as per
designer’s approval
1.2 To supply, delivery and install
Quartz Stone Midnight Black
Gloss Tiles 300mm x 300mm Nos 1790 39.99 71 582.10
SKU: 436160 finishes c/w all
necessary as per designer’s
approval (for 45m2 area)
2 Wall Finishes
2.1 Wall Finishes m2 305 200.00 61 000.00
To supply and construct concrete
wall with cement and sand (1:3)
c/w with all needed hardware and
necessary accessories as per
manufacturer’s detail.
2.2 To supply and install customized Nos 30 1500.0 45 000.00
curve timber slats c/w with all 0
needed hardware and necessary
accessories as per manufacturer’s
detail.
2.3 To supply and install flexible led nos 1 17614. 17 614.90
screen full color soft led display 90
modules L 13m x H 4.1m c/w with
all needed hardware and
necessary accessories as per
manufacturer’s detail.

35
2.4 To supply and construct Double
Tempered Glass Aluminum Fix m2 80 389.00 31 120.00
Blind Doors c/w all necessary as
per designer’s approval
2.5 To supply and construct customize m2 96 526.00 50 496.00
wood wall paneling Iban’s design
c/w all necessary as per designer’s
approval
3 Ceiling Finishes m2 160 500.00 80 000.00
3.1 To supply and install 100 mm thk
of Gypsum board panel false
ceiling using galvanized sections
for hanging and holding the
gypsum board panels of 12mmtk
with approved design works
around duly painted with three
coats of plastic emulsion paint
after necessary works provisions
are to be made for fixing of
A.C.Grills, light fittings as
manufacturer’s detail
3.2 To supply and install shine pvc m2 160 30.00 4 800.00
glossy film for stretch ceiling c/w
all necessaries and fixtures as per
designer approval
4 Fitting and Equipment
Fixed Furniture nos 1 35 35 000.00
4.1 To supply and install custom made 000.00
receptionist wood table with
chrome plated stainless steel
trestle approved equivalent as per
designer’s approval
Display Stand
To supply and install custom made
receptionist wood table with
chrome plated stainless steel
trestle approved equivalent as per
designer’s approval
4.2 To supply and install custom made nos 2 15 30 000.00
computer wood table with chrome 000.00
plated stainless steel trestle
approved equivalent as per
designer’s approval
4.2 To supply and install custom made nos 2 15 30 000.00
computer wood table with chrome 000.00
plated stainless steel trestle
36
approved equivalent as per
designer’s approval
4.2 To supply and install custom made nos 1 20 20 000.00
wood bench with chrome plated 000.00
stainless steel trestle approved
equivalent as per designer’s
approval
4.3 Sign Board nos 1 10 10 00.00
To supply and install 420 mm 000.00
height “Iban Heritage Center” sign
board with stainless steel;
including white color neon back
light; c/w installation and all
necessary accessory and fixture
as per designer’s approval
5 System m2 160 350 56 000.00
5.1 To supply and install emergency
fire sprinkler; c/w installation and
all necessary accessories and
fixture as per manufacture’s detail
5.2 To supply and install photoelectric Nos 5 1500 7 500.00
smoke detector; c/w installation
and all necessary accessories and
fixture as per manufacture’s detail
5.3 To supply and install duct type air Nos 6 8 000 144 000.00
purification HT-C@46HLEI and
piping system; c/w installation and
all necessary accessories
according to designer’s approval
5.4 To supply and install CCTV nos 1 50 000 50 000.00
system equipment, zooms and
PTZ camera rear view CCTV
system, auto recording system,
video transmitter and receiver and
all necessary accessories and
fixture as per manufacturer’s detail
6 Lighting
6.1 To supply and install selected Nos 20 250 5 000.00
down lights with energy saving
LED Down light 20W Recessed
Ceiling Down lights Spot Light
85-265V Wall Down Lights White
Body Natural White
(4000-4500K)c/w installation and
all necessary accessories and
37
fixture as per designer’s approval
6.2 To supply and install selected Nos 3 59 207.00
down lights with energy saving
LED Lights Strip SMD 5050 12V
300 LED (5 meter) White c/w
installation and all necessary
accessories and fixture as per
designer’s approval
TOTAL TO COLLECTION 5 3 856 881.00

38
Souvenir Shop (130m2)
RATE AMOUNT
ITEM PRODUCT DESCRIPTION UNIT QTY.
(RM) (RM)
Ground Floor - Workshop
Internal Work
Demolition Work
Hacking off all existing finishes
screed beds and backing, cleaning
m2 130 10 000 1 300 000.00
keying bases and preparatory
work to receive new finishes
(measured separately) removing
debris form site, making good all
work undisturbed
1 Floor Finishes
To supply, delivery and install
Dolce Walnut HDF Effect
1.1 Laminate Flooring High Gloss m2 130 95.74 12 446.20
1210mm x 140mm x 12mm
finishes c/w all necessary as per
designer’s approval
2 Wall Finishes
2.1 To supply and construct 2 piece of
m2 160 112.57 18 011.20
19mm Clear Decorative Curve
tempered Float Glass c/w all
necessary as per designer’s
approval
2.2 To supply and construct customize m2 80 526.00 42 080.00
wood wall paneling Iban’s design
c/w all necessary as per designer’s
approval
3 Ceiling Finishes m2 105 500 52 500.00
To supply and install 100 mm thk
3.1
of Gypsum board panel false
ceiling using galvanized sections
for hanging and holding the
gypsum board panels of 12mmtk
with approved design works
around duly painted with three
coats of plastic emulsion paint
after necessary works provisions
are to be made for fixing of
A.C.Grills, light fittings as
manufacturer’s detail
3.2 To supply and install shine pvc m2 130 30.00 3 900.00

39
glossy film for stretch ceiling c/w
all necessaries and fixtures as per
designer approval
4 Fitting and Equipment
Fixed Furniture
nos 5 25 125 000.00
Souvenier Shelf
To supply and install custom made 000.00
4.1
wood shelf with chrome plated
stainless steel trestle approved
equivalent as per designer’s
approval
4.2 Sign Board nos 1 7000 7 000.00
To supply and install 420 mm
height “Souvenir Shop” sign board
with stainless steel; including white
color neon back light; c/w
installation and all necessary
accessory and fixture as per
designer’s approval
5 System
5.1 To supply and install photoelectric
Nos 3 1500 4 500.00
smoke detector; c/w installation
and all necessary accessories and
fixture as per manufacture’s detail
5.2 To supply and install duct type air Nos 2 8 000 16 000.00
purification HT-C@46HLEI and
piping system; c/w installation and
all necessary accessories
according to designer’s approval
6 Lighting
To supply and install selected Nos
6.1 16 250 4 000.00
down lights with energy saving
LED Down light 20W Recessed
Ceiling Down lights Spot Light
85-265V Wall Down Lights White
Body Natural White
(4000-4500K)c/w installation and
all necessary accessories and
fixture as per designer’s approval
TOTAL TO COLLECTION 6 1 585 437.40

40
Computer Laboratory (45 m2)
RATE AMOUNT
ITEM PRODUCT DESCRIPTION UNIT QTY.
(RM) (RM)
Ground Floor - Workshop
Internal Work
Demolition Work
Hacking off all existing finishes
screed beds and backing, cleaning
m2 45 10 000 450 000.00
keying bases and preparatory
work to receive new finishes
(measured separately) removing
debris form site, making good all
work undisturbed
1 Floor Finishes
1.1 To supply, delivery and install
Palm Beach Carpet finishes c/w all Nos 1 8772.8 8 772.84
necessary as per designer’s 4
approval (for 45m2 area)
2 Wall Finishes
2.1 To supply delivery and install m2 147.6 112.57 16 615.33
CASELIO Midnight 2 Wallpaper
Black (19199113) c/w all
necessary as per designer’s
approval
3 Ceiling Finishes m2 45 500 22 500.00
3.1 To supply and install 100 mm thk
of Gypsum board panel false
ceiling using galvanized sections
for hanging and holding the
gypsum board panels of 12mmtk
with approved design works
around duly painted with three
coats of plastic emulsion paint
after necessary works provisions
are to be made for fixing of
A.C.Grills, light fittings as
manufacturer’s detail
3.2 To supply and install Style m2 45 108.68 4 890.60
Suspended Fiberglass Ceiling
board c/w inner lighting system, all
necessaries and fixtures as per
designer approval
4 Fitting and Equipment
Fixed Furniture nos 10 1862.3 18 620.95

41
4.1 To supply and install modern office 5
computer table 1400W x 1200 D x
1050H mm with chair or
approved equivalent as per
designer’s approval
4.2 To supply and install Forest Bright nos 1 869.10 869.10
Semi Solid Core Flush Door
or approved equivalent as per
designer’s approval
5 System m2 45 350 15 750.00
5.1 To supply and install emergency
fire sprinkler; c/w installation and
all necessary accessories and
fixture as per manufacture’s detail
5.2 To supply and install photoelectric
smoke detector; c/w installation Nos 1 1500 1 500.00
and all necessary accessories and
fixture as per manufacture’s detail
5.3 To supply and install duct type air Nos 1 8 000 8 000.00
purification HT-C@46HLEI and
piping system; c/w installation and
all necessary accessorries
according to designer’s approval
6 Lighting
6.1 To supply and install selected Nos 5 250 1 250.00
down lights with energy saving
LED Down light 20W Recessed
Ceiling Down lights Spot Light
85-265V Wall Down Lights White
Body Natural White
(4000-4500K)c/w installation and
all necessary accessories and
fixture as per designer’s approval
6.2 To supply and install selected Nos 3 69 207.00
down lights with energy saving
LED Lights Strip SMD 5050 12V
300 LED (5 meter) White c/w
installation and all necessary
accessories and fixture as per
designer’s approval
TOTAL TO COLLECTION 7 548 975.82

42
Toilet (Ground Floor) (45 m2)
RATE AMOUNT
ITEM PRODUCT DESCRIPTION UNIT QTY.
(RM) (RM)
Ground Floor - Workshop
Internal Work
Demolition Work
Hacking off all existing finishes
screed beds and backing, cleaning
m2 45 10 000 450 000.00
keying bases and preparatory
work to receive new finishes
(measured separately) removing
debris form site, making good all
work undisturbed
1 Floor Finishes
To supply, delivery and install
1.1 Carreaux de marble Italien Black m2 45 321 14 445.00
Porcelain Tiles Matte
1210mm x 140mm x 12mm
finishes c/w all necessary as per
designer’s approval
2 Wall Finishes
2.1 To supply delivery and install m2 110 156.44 17 208.40
Italy grey marble hexagon mosaic
bathroom c/w all necessary as per
designer’s approval
3 Ceiling Finishes m2 45 500 22 500.00
3.1 To supply and install 100 mm thk
of Gypsum board panel false
ceiling using galvanized sections
for hanging and holding the
gypsum board panels of 12mmtk
with approved design works
around duly painted with three
coats of plastic emulsion paint
after necessary works provisions
are to be made for fixing of
A.C.Grills, light fittings as
manufacturer’s detail
4 Fitting and Equipment
Fixed Furniture nos 10 2 25 00
4.1 Display Stand 500.00
To supply and install Bathroom
Automatic Flushing Smart Toilet
with Nightlight 800 x 420 x 620MM
or approved equivalent as per

43
designer’s approval
4.2 To supply and install brushed m 20 250.00 5 000.00
grate 304 stainless steel wet room
floor linear shower drain
or approved equivalent as per
designer’s approval
4.3 Sign Board nos 2 90.00 180.00
To supply and install acrylic wall
hang toilet restroom door sign
; c/w installation and all necessary
accessory and fixture as per
designer’s approval
4.4 To supply and install sanitary ware nos 6 869.10 5 214.60
solid surface wall mounted man
made stone basin along with
faucet; c/w installation and all
necessary accessory and fixture
as per designer’s approval
4.5 To supply and install bathroom Nos 1 2 2 500.00
back lit led lighted toilet frameless 500.00
wall mirror ; c/w installation and all
necessary accessory and fixture
as per designer’s approval
5 System m2 45 350 15 750.00
5.1 To supply and install emergency
fire sprinkler; c/w installation and
all necessary accessories and
fixture as per manufacture’s detail
5.2 To supply and install photoelectric
smoke detector; c/w installation Nos 4 1500 6 000.00
and all necessary accessories and
fixture as per manufacture’s detail
5.3 To supply and install duct type air Nos 2 8 000 16 000.00
purification HT-C@46HLEI and
piping system; c/w installation and
all necessary accessorries
according to designer’s approval
6 Lighting
6.1 To supply and install selected Nos 15 250 3 750.00
down lights with energy saving
LED Down light 20W Recessed
Ceiling Down lights Spot Light
85-265V Wall Down Lights White
Body Natural White
(4000-4500K)c/w installation and
44
all necessary accessories and
fixture as per designer’s approval
6.2 To supply and install selected Nos 3 69 207.00
down lights with energy saving
LED Lights Strip SMD 5050 12V
300 LED (5 meter) White c/w
installation and all necessary
accessories and fixture as per
designer’s approval
TOTAL TO COLLECTION 8 561 255.00

45
4.2 FIRST FLOOR
Interactive Gallery

RATE AMOUNT
ITEM PRODUCT DESCRIPTION UNIT QTY.
(RM) (RM)
Ground Floor - Interactive Gallery
Internal Work
m2 300 10 000 3 000 000.00
Demolition Work
Hacking off all existing finishes
screed beds and backing, cleaning
keying bases and preparatory
work to receive new finishes
(measured separately) removing
debris form site, making good all
work undisturbed
Ground Floor - Workshop
Internal Work
1 Floor Finishes
1.1 To supply, delivery and install nos 3000 39.99 119 970.00
Quartz Stone Midnight Black
Gloss Tiles 300mm x 300mm
SKU: 436160 finishes c/w all
necessary as per designer’s
approval

2 Wall Finishes
2.1 To supply and construct concrete
m2 270 200 54 000.00
wall with cement and sand (1:3)
c/w with all needed hardware and
necessary accessories as per
manufacturer’s detail

2.2 To supply and install customized Nos 88 1500 132 000.00


curve timber slats c/w with all
needed hardware and necessary
accessories as per manufacturer’s
detail
2.3 To supply and install customized Nos 260 150 39 000.00
100mm x 1550mm x 40mm detail
red cedar aromatic wall slats c/w
with all needed hardware and
necessary accessories as per
designer’s approval

46
2.4 To supply, delivery and install Nos 250 60 15 000.00
Silver mirrored mirror beveled wall
tiles 200mm x 75mm finishes c/w
all necessary as per designer’s
approval
2.5 To supply, delivery and install m2 35 264.64 9 262.40
toughen curved glass panels c/w
all necessary as per designer’s
approval

3 Ceiling Finishes

3.1 To supply and install 100 mm thk m2 445 150 66 750


decorative shape decorative
suspended ceiling by MDF Rustic
Pine Board with high gloss spray
paint finishes;c/w inner lighting
system, all necessaries and
fixtures as per designer approval
3.2 To supply and install 50mm x Nos 26.91 532 14 316.12
50mm thk ceiling wood panels
high gloss spray paint finishes;c/w
inner lighting system, all
necessaries and fixtures as per
designer approval
Fitting and Equipment
Loose Furniture
4 Counter
4.1 To supply, delivery and install Nos 1 16000 16 000.00
custom made counter
parametric-slats designed; A317M
Dark Brown Oak; c/w installation
and all necessary accessories and
fixture as per designer’s approval
4.2 To supply, delivery and install Nos 1 10000 10 000
custom made bench
parametric-slats designed; A317M
Dark Brown Oak; c/w installation
and all necessary accessories and
fixture as per designer’s approval

47
5 Other Equipment
Nos 1 12000 12 000.00
5.1 To supply, delivery and apply
Transparent Holographic
projection Screens 2000mm x
1500mm; c/w installation and all
necessary accessories and fixture
per designer’s approval
5.2 To supply, delivery and apply fully Nos 1 32 000 32 000.00
transparent Toughened Glass
Display Case with a 300mm high
base plinth display cabinet with
lighting; c/w installation and all
necessary accessories and fixture
per designer’s approval
6 System
6.1 To supply and install emergency m2 410 350 143 500.00
fire sprinkler; c/w installation and
all necessary accessories and
fixture as per manufacture’s detail
6.2 To supply and install photoelectric Nos 15 150 2 250.00
smoke detector; c/w installation
and all necessary accessories and
fixture as per manufacture’s detail
6.3 To supply and install emergency Nos 2 800 1 600.00
extinguishers; c/w installation and
all necessary accessories and
fixture as per manufacture’s detail
6.4 To supply and install duct type air Nos 5 8000 40 000.00
purification HT-C@46HLEI and
piping system; c/w installation and
all necessary accessories
according to designer’s approval
6.5 To supply and install CCTV Nos 2 30 000 60 000.00
system equipment inclusive of
bullet and IR camera, zooms and
PTZ camera rear view CCTV
system, auto recording system,
video transmitter and receivers
and all necessary accessories and
fixture as per manufacturer’s detail

48
7 Lighting
To supply and install selected
7.1 Nos 10 250 2 500.00
down lights with energy saving
LED Down light 40W Recessed
Ceiling Down lights Spot Light
85-265V Wall Down Lights White
Body Natural White
(4000-4500K)c/w installation and
all necessary accessories and
fixture as per designer’s approval
7.2 To supply and install warm white Nos 20 299 5 980
color floor concealed neon lighting
or approved equivalent, including
power supply, lighting controller
system, and all necessary
accessories for complete
installation as per designer’s
approval
8 Accessories Nos 2 5000 10 000.00
8.1 To supply, delivery and install
Sony 55 inch NX720 Series Bravia
Full HD 3D TV; c/w installation and
all necessary accessories and
fixture as per designer’s approval
8.2 To supply, delivery and apply all LS 1 80000 80 000.00
display item as per designer’s
approval
8.3 To supply and install all necessary LS 1 39 000 39 000.00
equipment; inclusive audio
system, net working system and
other; c/w installation and all
necessary accessories and fixture
as per designer’s approval
8.4 To supply, delivery and apply Nos 2 6000 6 000.00
Apple iMac desktop as per
designer’s approval
TOTAL TO COLLECTION 9 3 911 128.52

49
Cafeteria (320 m2)
RATE AMOUNT
ITEM PRODUCT DESCRIPTION UNIT QTY.
(RM) (RM)
Ground Floor - Workshop
Internal Work
Demolition Work
Hacking off all existing finishes
screed beds and backing, cleaning
m2 320 10 000 3 200 000.00
keying bases and preparatory
work to receive new finishes
(measured separately) removing
debris form site, making good all
work undisturbed
1 Floor Finishes
To supply, delivery and install
1.1 Dolce Walnut HDF Effect m2 60 200 12 000.00
Laminate Flooring High Gloss
1210mm x 140mm x 12mm
finishes c/w all necessary as per
designer’s approval
1.2 To supply, delivery and install
Quartz Stone Midnight Black
Gloss Tiles 300mm x 300mm Nos 1 400 39.99 55 986.00
SKU: 436160 finishes c/w all
necessary as per designer’s
approval (for 45m2 area)
2 Wall Finishes
2.1 To supply and construct 2 piece of m2 77 116.88 9 000.00
19mm Clear DecorativeLinear
tempered Float Glass c/w all
necessary as per designer’s
approval
2.2 To supply and construct 2 piece of
19mm Clear Decorative Curve nos 1 50 50 000.00
tempered Float Glass c/w all 000.00
necessary as per designer’s
approval
2.3 To supply and construct Artificial m2 57.75 1211.9 69 988.38
decorative vertical green plant wall 2
c/w all necessary as per designer’s
approval
3 Ceiling Finishes m2 320 500 160 000.00

50
3.1 To supply and install 100 mm thk
of Gypsum board panel false
ceiling using galvanized sections
for hanging and holding the
gypsum board panels of 12mmtk
with approved design works
around duly painted with three
coats of plastic emulsion paint
after necessary works provisions
are to be made for fixing of
A.C.Grills, light fittings as
manufacturer’s detail
3.2 To supply and install customized Nos 100 1500.0 150 00.00
curve timber slats c/w with all 0
needed hardware and necessary
accessories as per manufacturer’s
detail.
4 Fitting and Equipment
Fixed Furniture
nos 18 5 90 000.00
Set Table
To supply and install custom made 000.00
4.1
wood table and chair set approved
equivalent as per designer’s
approval
4.2 To supply and install custom made nos 11 669 7 359.00
bar stool approved equivalent as
per designer’s approval
4.3 To supply and install custom made nos 1 15 15 000.00
bar lounge cabinet approved 000.00
equivalent as per designer’s
approval
4.4 Sign Board nos 1 7000 7 000.00
To supply and install 420 mm
height “Cafeteria” sign board with
stainless steel; including white
color neon back light; c/w
installation and all necessary
accessory and fixture as per
designer’s approval
5 System
5.1 To supply and install photoelectric
Nos 4 1500 6 000.00
smoke detector; c/w installation
and all necessary accessories and
fixture as per manufacture’s detail

51
5.2 To supply and install duct type air Nos 3 8 000 24 000.00
purification HT-C@46HLEI and
piping system; c/w installation and
all necessary accessories
according to designer’s approval
6 Lighting
To supply and install selected Nos
6.1 20 250 5 000.00
down lights with energy saving
LED Down light 20W Recessed
Ceiling Down lights Spot Light
85-265V Wall Down Lights White
Body Natural White
(4000-4500K)c/w installation and
all necessary accessories and
fixture as per designer’s approval
6.2 To supply and install customize Nos 10 3500.0 35 000.00
pendant lamps with energy saving 0
LED Down light 20W Recessed
Ceiling Down lights Spot Light
85-265V Wall Down Lights White
Body Natural White
(4000-4500K)c/w installation and
all necessary accessories and
fixture as per designer’s approval
TOTAL TO COLLECTION 10 3 746 483.38

52
Gawai Gallery (125 m2)
RATE AMOUNT
ITEM PRODUCT DESCRIPTION UNIT QTY.
(RM) (RM)
Ground Floor - Workshop
Internal Work
Demolition Work
Hacking off all existing finishes
screed beds and backing, cleaning
m2 125 10 000 1 250 000.00
keying bases and preparatory
work to receive new finishes
(measured separately) removing
debris form site, making good all
work undisturbed
1 Floor Finishes
To supply, delivery and install
1.1 Dolce Walnut HDF Effect m2 125 95.74 11 967.50
Laminate Flooring High Gloss
1210mm x 140mm x 12mm
finishes c/w all necessary as per
designer’s approval
2 Wall Finishes
2.1 To supply and construct 2 piece of m2 147.6 112.57 16 615.33
19mm Clear Decorative Curve
tempered Float Glass c/w all
necessary as per designer’s
approval
2.2 To supply and install customized Nos 100 1500.0 150 000.00
curve timber slats c/w with all 0
needed hardware and necessary
accessories as per manufacturer’s
detail.
3 Ceiling Finishes m2 125 500 62 500.00
3.1 To supply and install 100 mm thk
of Gypsum board panel false
ceiling using galvanized sections
for hanging and holding the
gypsum board panels of 12mmtk
with approved design works
around duly painted with three
coats of plastic emulsion paint
after necessary works provisions
are to be made for fixing of
A.C.Grills, light fittings as
manufacturer’s detail

53
4 Fitting and Equipment
Fixed Furniture nos 8 700.00 5 600.00
4.1 Display Stand
To supply and install Freestanding
Television Display Stand
TSK20156 or approved equivalent
as per designer’s approval
4.3 Sign Board nos 1 7000 7 000.00
To supply and install 420 mm
height “Gawai Gallery” sign board
with stainless steel; including white
color neon back light; c/w
installation and all necessary
accessory and fixture as per
designer’s approval
5 System m2 125 350 43 750.00
5.1 To supply and install emergency
fire sprinkler; c/w installation and
all necessary accessories and
fixture as per manufacture’s detail
5.2 To supply and install photoelectric 1500 7 500.00
smoke detector; c/w installation Nos 5
and all necessary accessories and
fixture as per manufacture’s detail
5.3 To supply and install duct type air Nos 5 8 000 40 000.00
purification HT-C@46HLEI and
piping system; c/w installation and
all necessary accessories
according to designer’s approval
5.4 To supply and install CCTV nos 1 50 000 50 000.00
system equipment, zooms and
PTZ camera rear view CCTV
system, auto recording system,
video transmitter and receiver and
all necessary accessories and
fixture as per manufacturer’s detail
6 Lighting
6.1 To supply and install selected Nos 10 250 3 750.00
down lights with energy saving
LED Down light 20W Recessed
Ceiling Down lights Spot Light
85-265V Wall Down Lights White
Body Natural White
(4000-4500K)c/w installation and
all necessary accessories and

54
fixture as per designer’s approval
TOTAL TO COLLECTION 11 2 042 432.83

55
Office Administration (310 m2)
RATE AMOUNT
ITEM PRODUCT DESCRIPTION UNIT QTY.
(RM) (RM)
Ground Floor - Office
Administration m2 310 10 000 3 100 000.00
Internal Work
Demolition Work
Hacking off all existing finishes
screed beds and backing, cleaning
keying bases and preparatory
work to receive new finishes
(measured separately) removing
debris form site, making good all
work undisturbed
1 Ground Floor - Workshop
1.1 Internal Work 60 435.12
Floor Finishes Nos 1 60
To supply, delivery and install 435.12
Palm Beach Carpet finishes c/w all
necessary as per designer’s
approval (for 45m2 area)
2 Wall Finishes
2.1 To supply and construct concrete m2 310 200 62 000.00
wall with cement and sand (1:3)
c/w with all needed hardware and
necessary accessories as per
manufacturer’s detail
2.2 To supply and install design Nos 30 130 3 900.00
non-woven wallpaper 5.3m2 c/w
with all needed hardware and
necessary accessories as per
manufacturer’s detail
2.4 To supply, delivery and install Nos 250 60 15 000.00
Silver mirrored mirror beveled wall
tiles 200mm x 75mm finishes c/w
all necessary as per designer’s
approval
2.5 To supply, delivery and install m2 30 300 9 000.00
toughen glass panels 7m x 3.85m
c/w all necessary as per designer’s
approval
3 Ceiling Finishes
3.1 To supply and install 100 mm thk m2 310 150 46 500
decorative shape decorative

56
suspended ceiling by MDF Rustic
Pine Board with high gloss spray
paint finishes;c/w inner lighting
system, all necessaries and
fixtures as per designer approval
Fitting and Equipment
Loose Furniture
4 Counter Nos 16000 32 000.00
4.1 To supply, delivery and install 2
custom made office table
completed with chair themed;
A317M orange; c/w installation
and all necessary accessories and
fixture as per designer’s approval
4.2 To supply, delivery and install Nos 1 5 5 000.00
custom made shelf designed; 000.00
A317M Dark Brown Oak; c/w
installation and all necessary
accessories and fixture as per
designer’s approval
4.3 To supply, delivery and install Nos 1 16 16 000.00
custom made acrylic solid surface 000.00
conference office furniture meeting
table c/w installation and all
necessary accessories and fixture
as per designer’s approval
4.4 To supply, delivery and install Nos 4 1590.4 6 361.80
custom made stackable 2 chiars 5
and 1 table small bar set coffee
shop outdoor tables illuminated
plastic led chair c/w installation
and all necessary accessories and
fixture as per designer’s approval
4.5 To supply, delivery and install Nos 2 15 30 000.00
custom made file shelf c/w 000.00
installation and all necessary
accessories and fixture as per
designer’s approval

57
5 System
5.1 To supply and install emergency m2 310 350 108 500.00
fire sprinkler; c/w installation and
all necessary accessories and
fixture as per manufacture’s detail
5.2 To supply and install photoelectric Nos 10 150 1 500.00
smoke detector; c/w installation
and all necessary accessories and
fixture as per manufacture’s detail
5.3 To supply and install emergency Nos 2 800 1 600.00
extinguishers; c/w installation and
all necessary accessories and
fixture as per manufacture’s detail
5.4 To supply and install duct type air Nos 5 8000 40 000.00
purification HT-C@46HLEI and
piping system; c/w installation and
all necessary accessories
according to designer’s approval
5.5 To supply and install CCTV Nos 2 30 000 60 000.00
system equipment inclusive of
bullet and IR camera, zooms and
PTZ camera rear view CCTV
system, auto recording system,
video transmitter and receivers
and all necessary accessories and
fixture as per manufacturer’s detail
6 Lighting
To supply and install selected
6.1 Nos 10 250 2 500.00
down lights with energy saving
LED Down light 40W Recessed
Ceiling Down lights Spot Light
85-265V Wall Down Lights White
Body Natural White
(4000-4500K)c/w installation and
all necessary accessories and
fixture as per designer’s approval
6.2 To supply and install warm white Nos 20 299 5 980
color floor concealed neon lighting
or approved equivalent, including
power supply, lighting controller
system, and all necessary
accessories for complete
installation as per designer’s
approval

58
8 Accessories Nos 1 5000 5 000.00
8.1 To supply, delivery and install
Sony 55 inch NX720 Series Bravia
Full HD 3D TV; c/w installation and
all necessary accessories and
fixture as per designer’s approval
8.3 To supply and install all necessary LS 1 39 000 39 000.00
equipment; inclusive audio
system, net working system and
other; c/w installation and all
necessary accessories and fixture
as per designer’s approval
8.4 To supply, delivery and apply Nos 14 6000 84 000.00
Apple iMac desktop as per
designer’s approval
TOTAL TO COLLECTION 12 3 739 276.92

59
Sigat Gallery (225 m2)
RATE AMOUNT
ITEM PRODUCT DESCRIPTION UNIT QTY.
(RM) (RM)
Ground Floor - Workshop
Internal Work
Demolition Work
Hacking off all existing finishes
screed beds and backing, cleaning
m2 225 10 000 2 250 000.00
keying bases and preparatory
work to receive new finishes
(measured separately) removing
debris form site, making good all
work undisturbed
1 Floor Finishes
To supply, delivery and install
1.1 foam epoxy polyurethane Barrel 15 1 27 000.00
waterproof coating finishes; jade 800.00
green color; c/w all necessary as
per designer’s approval
2 Wall Finishes Nos 150 1500.0 225 000.00
2.1 To supply and install customized 0
curve timber slats c/w with all
needed hardware and necessary
accessories as per manufacturer’s
detail.
2.2 To supply and construct custom
made indoor Stainless steel nos 1 36 36 000.00
exhibition wall c/w all necessary as 000.00
per designer’s approval
3 Ceiling Finishes m2 225 500 112 500.00
3.1 To supply and install 100 mm thk
of Gypsum board panel false
ceiling using galvanized sections
for hanging and holding the
gypsum board panels of 12mmtk
with approved design works
around duly painted with three
coats of plastic emulsion paint
after necessary works provisions
are to be made for fixing of
A.C.Grills, light fittings as
manufacturer’s detail
4 Fitting and Equipment
Fixed Furniture nos 17 799 13 583.00

60
4.1 Display Stand
To supply and install Freestanding
glass with aluminum display case
with fully quality certificate 450mm
x 450 mm x 1050 mm or approved
equivalent as per designer’s
approval
4.3 Sign Board nos 1 7000 7 000.00
To supply and install 420 mm
height “Sigat Gallery” sign board
with stainless steel; including white
color neon back light; c/w
installation and all necessary
accessory and fixture as per
designer’s approval
5 System m2 225 350 78 750.00
5.1 To supply and install emergency
fire sprinkler; c/w installation and
all necessary accessories and
fixture as per manufacture’s detail
5.2 To supply and install photoelectric 1500 4 500.00
smoke detector; c/w installation Nos 3
and all necessary accessories and
fixture as per manufacture’s detail
5.3 To supply and install duct type air Nos 4 8 000 32 000.00
purification HT-C@46HLEI and
piping system; c/w installation and
all necessary accessorries
according to designer’s approval
5.4 To supply and install CCTV nos 1 50 000 50 000.00
system equipment, zooms and
PTZ camera rear view CCTV
system, auto recording system,
video transmitter and receiver and
all necessary accessories and
fixture as per manufacturer’s detail
6 Lighting
6.1 To supply and install selected Nos 12 250 3 000.00
down lights with energy saving
LED Down light 20W Recessed
Ceiling Down lights Spot Light
85-265V Wall Down Lights White
Body Natural White
(4000-4500K)c/w installation and

61
all necessary accessories and
fixture as per designer’s approval
6.3 Lighting
To supply and install selected Nos 10 250 2 500.00
track lighting with energy saving
LED Down light 20W Recessed
Ceiling Down lights Spot Light
85-265V Wall Down Lights White
Body Natural White
(4000-4500K)c/w installation and
all necessary accessories and
fixture as per designer’s approval
6.2 To supply and install selected Nos 12 69 207.00
down lights with energy saving
LED Lights Strip SMD 5050 12V
300 LED (5 meter) White c/w
installation and all necessary
accessories and fixture as per
designer’s approval
TOTAL TO COLLECTION 13 2 842 040.00

62
Toilet (First Floor) (45 m2)
RATE AMOUNT
ITEM PRODUCT DESCRIPTION UNIT QTY.
(RM) (RM)
Ground Floor - Workshop
Internal Work
Demolition Work
Hacking off all existing finishes
screed beds and backing, cleaning
m2 45 10 000 450 000.00
keying bases and preparatory
work to receive new finishes
(measured separately) removing
debris form site, making good all
work undisturbed
1 Floor Finishes
To supply, delivery and install
1.1 Carreaux de marble Italien Black m2 45 321 14 445.00
Porcelain Tiles Matte
1210mm x 140mm x 12mm
finishes c/w all necessary as per
designer’s approval
2 Wall Finishes
2.1 To supply delivery and install m2 110 156.44 17 208.40
Italy grey marble hexagon mosaic
bathroom c/w all necessary as per
designer’s approval
3 Ceiling Finishes m2 45 500 22 500.00
3.1 To supply and install 100 mm thk
of Gypsum board panel false
ceiling using galvanized sections
for hanging and holding the
gypsum board panels of 12mmtk
with approved design works
around duly painted with three
coats of plastic emulsion paint
after necessary works provisions
are to be made for fixing of
A.C.Grills, light fittings as
manufacturer’s detail
4 Fitting and Equipment
Fixed Furniture nos 10 2 25 00
4.1 Display Stand 500.00
To supply and install Bathroom
Automatic Flushing Smart Toilet
with Nightlight 800 x 420 x 620MM
or approved equivalent as per

63
designer’s approval
4.2 To supply and install brushed m 20 250.00 5 000.00
grate 304 stainless steel wet room
floor linear shower drain
or approved equivalent as per
designer’s approval
4.3 Sign Board nos 2 90.00 180.00
To supply and install acrylic wall
hang toilet restroom door sign
; c/w installation and all necessary
accessory and fixture as per
designer’s approval
4.4 To supply and install sanitary ware nos 6 869.10 5 214.60
solid surface wall mounted man
made stone basin along with
faucet; c/w installation and all
necessary accessory and fixture
as per designer’s approval
4.5 To supply and install bathroom Nos 1 2 2 500.00
back lit led lighted toilet frameless 500.00
wall mirror ; c/w installation and all
necessary accessory and fixture
as per designer’s approval
5 System m2 45 350 15 750.00
5.1 To supply and install emergency
fire sprinkler; c/w installation and
all necessary accessories and
fixture as per manufacture’s detail
5.2 To supply and install photoelectric
smoke detector; c/w installation Nos 4 1500 6 000.00
and all necessary accessories and
fixture as per manufacture’s detail
5.3 To supply and install duct type air Nos 2 8 000 16 000.00
purification HT-C@46HLEI and
piping system; c/w installation and
all necessary accessorries
according to designer’s approval
6 Lighting
6.1 To supply and install selected Nos 15 250 3 750.00
down lights with energy saving
LED Down light 20W Recessed
Ceiling Down lights Spot Light
85-265V Wall Down Lights White
Body Natural White
(4000-4500K)c/w installation and
64
all necessary accessories and
fixture as per designer’s approval
6.2 To supply and install selected Nos 3 69 207.00
down lights with energy saving
LED Lights Strip SMD 5050 12V
300 LED (5 meter) White c/w
installation and all necessary
accessories and fixture as per
designer’s approval
TOTAL TO COLLECTION 14 561 255.00

65
TOTAL FROM COLLECTION AMOUNT (RM)
TOTAL TO COLLECTION 1 870 513.30
TOTAL TO COLLECTION 2 2 434 149.61
TOTAL TO COLLECTION 3 1 601 106.99
TOTAL TO COLLECTION 4 1 779 371.09
TOTAL TO COLLECTION 5 3 856 881.00
TOTAL TO COLLECTION 6 1 585 437.40
TOTAL TO COLLECTION 7 548 975.82
TOTAL TO COLLECTION 8 561 255.00
TOTAL TO COLLECTION 9 3 911 128.52
TOTAL TO COLLECTION 10 3 746 483.38
TOTAL TO COLLECTION 11 2 042 432.83
TOTAL TO COLLECTION 12 3 739 276.92
TOTAL TO COLLECTION 13 2 842 040.00
TOTAL TO COLLECTION 14 561 255.00
TOTAL COST 30 080 306.86

Calculation

Profit Attendance
RM 30 080 306.86 x 13% Grand Total Area= 4 370 sqm
(Subtotal 1)= RM 3 910 439.90
Grand Total Cost= RM 40 578 333.96

(Total Cost)+ 15% Contingency


=RM 30 080 306.86 + 15% Contingency Construction Cost (RM/m2)
=RM 30 080 306.86 + RM 4 512 046.03
(Subtotal 1) =RM 34 592 352.89 =(Subtotal 2) / Grand Total Area
10.76
(Subtotal 1) + 6% GST
=RM 34 592 352.89 + 6% GST = RM 36 667 894.06/ 4 370 sqm
= RM 34 592 352.89 + RM 2 075 541.17 10.76
(Subtotal 2) =RM 36 667 894.06
= RM 779.82 / ft2
RM 36 667 894.06 + Profit Attendance
= RM 36 667 894.06 + RM 3 910 439.90
= RM40 578 333.96

66
CHAPTER 5
ANALYSIS

67
5.1 STYLE
The style that been chosen is contemporary Iban style. Iban Heritage Center is a
parametrically modeled and detailed forefront of design. To refine the concept,
self-developed parametric tools and cloud rendering technology to reduce cost,
decrease fabrication time, and apply an aesthetic that perfectly aligns to the agendas
of the Iban itself will be used. While the center has a contemporary traditional look, it is
envisioned as a fluid space characteristics – a traditional element of Puan
Kumbu,Iban’s traditional sacred woven fabric

A fluid sculptural wooden was made to this magnificent 1 000 square meter Iban
Heritage Center at the heart of Georgetown financial district. For best results, the
project was created in a parametric environment, allowing multiple iterations in the
shortest time possible to reach a fluid surface and the structural components were
updated automatically without having to redraw over and over again. The structure
made of 1,500 pieces seamlessly joined together into 172 arctic birch sections, each
one slightly different from the rest. Inside the shell of this building, intricate,
nature-inspired geometry to support the structure, which lends architectural substance
and eye-catching design, while allowing efficient use of the busy space by the user.

Iban contemporary style is one of the style that emphasize the beauty of simplicity
and naturally. Most of the material that been proposed is comes from the natural
resources, it is because to create the natural ambiance to the user. Installed on every
corners and edges in undulating angular planes, the wood strips clad the walls, ceiling,
creating a fluid volume that redefines the way interior spaces are perceived.

68
5.2 DESIGN SOLUTION
PROPOSED FLOOR PLAN

Major Area 1 - Black Box Theater

This 220 square meter, multipurpose room is great for rehearsing, classes, meetings,
private functions or even as a Black Box Theater. Providing a space that is easily built
and maintained, and is usually home to performances with very basic technical
arrangements, such as limited sets, simple lighting effects, and an intimate focus on
the story, writing, and performances rather than technical elements. The seating is
typically composed of loose chairs on platforms, which can be easily moved or
removed to allow the entire space to be adapted to the artistic elements of a
production.

69
Major Area 2- Sigat Gallery

This gallery and exhibition area is provided for user to let them has a chance to
discovery and explore the history of Iban’s culture. The galleries present, through
artifact and interactive displays, the history of interactions between deep jungle and
Iban’s culture, depict the experiences of the Iban community in Malaya during the
colonial period, and highlight the contributions of the Iban communities to Malaysia’s
nation-building efforts.

Minor Area 1- Receptionist Area

As the saying goes, people only have one chance to make a good first impression.
In its most basic form, a reception area is a section of The Iban Heritage Center that is
used to greet all visitors and to provide a waiting area for them until they are met by the
person that they came to the business to meet with.

The layout of your reception area is something you will need to plan carefully.
Furniture placement, decor and space consider taken into all need to be a part of the
design so that visitors get a positive first impression the second they step through the
door.

70
Major Area 1 - Black Box Theater

71
Major Area 2- Sigat Gallery

72
Minor Area 1- Receptionist Area

73
Other Area (Ground Floor)

Ngelaban Gallery

Kids Play Area

Souvenir Shop

74
Other Area (First Floor)

Gawai Gallery

Sigat Gallery

Cafeteria

75
CHAPTER 6
CONCLUSION

76
6.1 CONCLUSION

What has become particularly clear is that the process of listening is central to the
transmission of cultural value and identity, even though the goal of being an attentive
listener in the quest to understand is something that we tend to take for granted.
However, in an Iban environment, listening is to do with being actively involved and
trying to interpret the deep meanings of their conversations. Thus, to a certain
extent, pua kumbu inspired-design embodies this deep meaning as much, if not more
so than traditional means of story-telling.

During the process of trying to understand the problems and issues around what
kind of meanings are involved with this center, an examination of how a group of
people respond to such an article was activated. An analysis of their narratives
revealed the close bonds they have with their landscape and a fleeting perception of
their sense of self which, in turn led to a realization of how culture itself can be a
material from which one might inspired one’s identity.

One of the most important roles of community centers is developing social


intellectual of individuals. The Iban Heritage Centers are not formal centers of
communities, but at an informal level they may fulfill their functions. The activities of the
culture center are necessary for the community. Generally, such forms of cultural
activities prevail which are related to music, theater, singing and dancing. The culture
centers should continuously analyze the needs of the inhabitants and look for new
possibilities to provide more varied cultural services.

The presence of arts and culture in a specific neighborhood or community location


can increase attention and foot traffic, bringing in visitors and attracting more
development. Furthermore, formal and informal training in the arts can abet the
development of skills valued in the global economy — such as strong oral and written
communication skills, precise and high-quality work performance, ease in working in
teams and ensembles, comfort in new and innovative situations, and the ability to work
well with people from diverse cultures.

A sign of a healthy community is its simultaneous ability to preserve and invent its
culture — that is, to conserve its history and heritage and at the same time develop
new expressions for current times. Arts and cultural activity and the leadership of
artists, historians, folklorists, anthropologists, planners, and other community leaders
play important roles in preserving the history and heritage of a place, as well as easing
tensions and encouraging respect for the changing cultural landscape. Despite the
importance of Iban’s history and heritage, preservation is rarely seen as a potential
basis for innovation and advancement. As a result, too often sufficient resources are
not dedicated to preserving significant meaningful spaces and objects, documenting
stories from elders, and recording a community's contemporary cultural practices.

77
BIBLIOGRAPHY

78
BIBLIOGRAPHY

 http://www.tandfonline.com/doi/full/10.1080/14631369.2015.1106305
 http://www.tilemountain.co.uk/black-quartz-tiles/p/quartz-stone-midnight-black.html
 http://greenwallaustralia.com.au/
 https://www.alibaba.com/
 http://www.lumbermart.ca/
 https://en.wikipedia.org/wiki/Iban_people
 http://indianheritage.org.sg/en
 http://www.ebay.co.uk/itm/Silver-mirrored-mirror-bevelled-wall-tiles-suitable-for-any-b
athroom-kitchen-/351357869825
 https://www.glassatwork.co.uk/curved-glass-frameless-office-partitioning-p-22.html
 http://www.woodworkerssource.com/shop/product/12balpack3.html
 http://www.luminati.co.uk/glass-cabinets/?pg=2
 https://www.lowes.com/pd/CedarSafe-3-75-in-x-4-ft-Red-Cedar-Aromatic-Wall-Plank/37
26921
 http://www.timberstoreuk.co.uk/mdf/
 http://www.lamboo.us/
 http://www.archdaily.com/788728/the-bamboo-garden-atelier-rep
 http://www.ikea.com/ca/en/catalog/categories/departments/workspaces/11845/
 http://www.supawood.com.au/
 http://www.kerfkore.com/kerfkore.html
 http://livewall.com/living-wall-system/indoor-living-wall/

79

Das könnte Ihnen auch gefallen