Beruflich Dokumente
Kultur Dokumente
Spaghetti Diagram
Finish
820
958
800
952
Building 2 951
Building 3
760
Start
310
80
570
510
520
810
Building 1
673 666
Value Stream Analysis for the Forging
PRODUCTION
SCHEDULER
Name of Supplier
1 1 1 1 1 1
Setup time: Setup time:
Computer
Number of shift: Number of shift: Number of shift:
I Distance 350 ft
I
Line of Sight Poor
1–8 Computer
Days Computer
Computer NO Computer
8 hours
Computer Computer Distance 140 ft
Computer Computer Computer
Computer Poor
Line of Sight
Computer Ye
s Outside Process
SOLUTION
ABRASIVE SAW BLAST-ROTO COAT-DIP 20000 HAMMER BLAST-ROTO CNC MACHINE Cool down delay = 2hrs PRECIP HEAT TABLE-BLAST CNC MACHINE INSPECT SONIC TEST ETCHING NDT MICRO
TREAT
1 1 2 1 1 1 2 6 2 1 2 1 1 1 1 1 1 1 2 1 1 1 1 1 1 1 1 1
Number of shift: 1
I Number of shift: 1
I Number of shift: 1
I Number of shift: 1
I Number of shift:1
I Number of shift: 3
I Number of shift: 3
I Number of shift: 3
I Number of shift: 1
I Number of shift: 3
I Number of shift: 1
I Number of shift:
I Number of shift: 1
I Number of shift: 1
760 5 hours 510 4 hours 810 10-20 80 8 – 24 510 48-120 310 24 - 48 673 666 520 96-120 310 800 962 & 974 570 958
0 hour 4 hours 8 hours ?? 8 hours 8 hours
C/T= 20/hr C/T= 10min/cycle C/T= 45/hr hours C/T= 36/hr hours C/T= 15min/cycle hours C/T= 1/hr hours C/T= 4hrs/batch C/T= 6-8hrs/batch C/T=20min/24 pcs hours C/T= 1.5hr/pc C/T= 63/hr C/T= 5days/45 pcs C/T= 15min /20pcs C/T= 48/hr
C/O= 10 min C/O= 0 C/O= 0 C/O= 1 hr C/O= 0 C/O= 1.5 hr C/O= 1hr C/O= 2 hr C/O= C/O= C/O= C/O= C/O= C/O=
Distance 350 ft Distance 180 ft Distance 315 ft Distance 440 ft Distance 690ft Distance 750 ft Distance 3 ft Distance 255 ft Distance 690 ft Distance 325 ft Distance N/A Distance 680 ft
S/U= 15 min S/U= 10min S/U= 15 min S/U= 1 hr S/U= 10 min S/U= 1.5 hr S/U= S/U= S/U= S/U= S/U= Distance N/A S/U= S/U= S/U=
Line of Sight Poor Line of Sight Poor Line of Sight Poor Line of Sight Poor Line of Sight Poor Line of Sight Poor Line of Sight Good Line of Sight Poor Line of Sight Poor Line of Sight Poor Line of Sight N/A Line of Sight Poor
Line of Sight N/A
5 hrs 4 hrs 20 hrs 24 hrs 120 hrs 48 hrs 2 hrs 4 hrs 120 hrs 8 hrs ?? hrs 8 hrs 8 hrs 8 hrs
CORRECTION
Repair or MOTION
WAITING
Rework Any wasted motion
Any non-work time to pick up parts,
waiting for tools, stack parts, walking
supplies, parts, etc. to get parts, etc.
Types
PROCESSING of OVERPRODUCTION
Producing more
Doing more work than Waste than is needed
is necessary
before it is needed
INVENTORY
CONVEYANCE
Maintaining excess
inventory of raw Wasted effort to transport
materials, materials, parts, or
parts in process, or finished goods into or
finished goods. out of storage, or
between
processes.
Example: Cost of Inventory1
Say that the annual inventory costs of a company are
$10,000,000. If we assume that work-in-process and
raw materials make up 25% of this inventory, then the
company has locked up $2,500,000 on its shopfloor.
Next, if we assume that the inventory carrying cost is
10%, then the company is paying an additional
$250,000 for warehouse space, security, electricity,
etc. Hence, the penalty being paid by the company for
not moving materials rapidly through its facility is
$2,750,000!
…..
Setup time
on OP#1 Time to travel
Time in queue to OP#2
before OP#1 Wait at OP#1
Material is
Time to move to be moved
received in
to OP#1 To OP#2
warehouse
Future Worth ($)
of all cash flows
Dominant Wastes that ↑ Flow Time
TOTAL TIME
IN THE FACILITY
TOTAL TIME
ON MACHINES
2Harmon, R.L. & Peterson, L.D. (1990). Reinventing the Factory. New York, NY: The
Free Press.
Relating WIP & Moving Costs
• Eliminate operations
• Combine operations • Eliminate handling
• Minimize multiple flows • Minimize handling costs
Source: Apple, J. M. (1977). Plant layout and material handling. New York, NY: John Wiley.
Guidelines for Design For Flow
21.Provisions for expected 26.Activities with specific location
a. In-process material storage requirements situated in proper
b. Scrap storage and transport spots
22.Flexibility in regard to a. Production operations
a. Increased or decreased b. Production services
production c. Personnel services
b. New products d. Administration services
c. New processes 27.Supervisory requirements given
d. Added departments proper consideration
23.Amenable to expansion in pre- a. Size of departments
planned directions b. Shape
24.Proper relationship to site c. Location
a. Orientation 28. Production control goals easily
b. Topography attainable
c. Expansion (plant, parking, 29.Quality control goals easily
auxiliary structures, etc.) attainable
25.Receiving and shipping in proper 30.Consideration given to multi-floor
relation to possibilities (existing and
a. Internal flow proposed)
b. External transportation 31.No apparent violations of health or
facilities (existing and safety requirements
proposed)
Source: Apple, J. M. (1977). Plant layout and material handling. New York, NY: John Wiley.
Strategies from DFMA Practices
• “Inside-Out”: In high mix environments, keep standard modules and
components on the inside and “bolt on” the special features and
options on the outside; keep the product variation as far to the end of
the line as possible
• “Monument Avoidance”: Avoid component designs that require a new
and unique process that has to serve multiple product lines
• “Batch Early”: If processes that necessitate batching (plating, painting,
heat treat, ovens, drying/aging) are absolutely necessary, try to design
products where these “batch” processes can be used as early as
possible (Nothing is worse than requiring an oven/drying cycle in the
middle of the Final Assembly Process)
• “Standardize Modules,not necessarily Products”: Offering a broad
product mix is a competitive advantage, so reducing product SKU’s
may not be a good idea. However, reducing module and component
SKU’s should be a core strategy
Additional Stage
Shop Layout Analysis (SLA): Develops a shop layout that will minimize
intercell flow delays when multiple interdependent cells share “monuments” and
common expensive resources.
Factory Flow Analysis
MATERIAL
28
16 2
15
1
27 3
53 1 3
1
1
1 24
3 1
126
84 151 3
4
8
1
1 12 26
DEPARTMENTS
3 1 = BLANKS
9 27
5 45 1
2 = SHEET METAL WORK
3 3 = FORGE
1 4 = WELDING DEPT
2
5 = MACHINE SHOP
6 = ASSEMBLY
9 = OUTSIDE FIRMS
6 FINISHED
PRODUCT
MATERIALS 1 MATERIALS 1
5 4 3 2 5 3&4 2
6 6
FINISHED FINISHED
PRODUCT PRODUCT
Shop Flow Analysis
K L L M M L M M E E E E E K E E K E M K M M M K E E E K K M E
4 4 4 4 4 4 4 4 4 4 3 1 1 4 4 4 3 3 4 4 4 4 4 3 7 4 3 4 4 6 1
8 8 8 4 7 8 8 4 1 8 4 2 2 7 7 8 4 3 8 4 5 5 8 4 3 6 3 5 3 1 8
2 3 2 2 6 3 1 2 7 5 2 2 2 6 7 5 5 4 2 2 6 6 3 0 9 3 2 1 5 5 6
5 8 6 7 9 8 9 7 9 9 6 0 8 9 8 8 9 9 6 7 9 9 8 9 2 6 9 9 9 9 9
1 8 7 6 3 8 5 6 5 6 7 4 8 7 2 6 6 4 5 6 1 1 6 8 4 5 9 0 2 4
A B E F M C D D C D B H A
Before M
A
C
H
DMT(3)
DM(3)
PG
X
X
X
X
X
X
X
X
X
X
X X
X
X
X
X
X
X X
X
X
X
X
X
X
X
X X
X
I DXY(3) X X X X X X X X
PFAST N
E
/
W
P&GR
PGR
X
X X
PGH
Analysis O
R
K
S
PGG
P&G X X X X X X
X X
X X
X
X X X X X
T
A
T
I
RP
PGB
W&P X
X
X
X X X X
X
X
X
X X
Potential
O
N WG3 X
COMPONENT – MACHINE CHART. INITIAL RECORD. FORGE.
PART/PRODUCT
Cells in this
L K M E K L E K K K M M M E E E E E M K L M M M K E E E E E M
4
8
2
6
3
4
5
9
4
8
2
6
3
3
4
9
4
4
2
7
4 7 3 4 4
8 3 4 5 3
3 9 0 1 5
8 2 9 9 9
6
1
5
9
4
8
1
9
4
4
2
7
3
4
2
6
1
2
2
0
1
8
6
9
4
1
7
9
4
8
5
9
4
8
3
8
4
8
2
5
4
8
3
8
4
5
6
9
4
5
6
9
4
4
2
7
4
7
6
9
4
7
7
8
4
6
3
6
1
2
2
8
3
3
2
9
4
8
5
8
4
7
6
9
Machine
7 6 5 4 6 8 8 9 0 2 5 6 7 4 4 5 6 6 1 8 1 1 6 7 2 4 8 5 6 3
PG
B
X X
D
X X
C
X
M
X
A C D H A D B E F
Shop
GROUP-1
DM 3/1 X X X X
After M
A
DXY 3/1
RP
X X
FAMILY - 1
X
PFAST H
I
N
E
P&G
DMT 3/2
DM 3/2
X
X
X
X
X
X
X
X
X
X
X
X X
X
X
X
X
X
X
X
X X X
X
ONE “EXCEPTION” X
GROUP-2
/
Analysis W
O
R
DXY 3/2
W&P
WG3
X
X
X
X
X
X
X
X
X
X
X
X
K
S FAMILY - 2
T
GROUP-3
PGG X X X
A
T PGB X X X X X X
I PGR X X
O
N DMT 3/3 X X X X
DM 3/3 X X X
P&GR X
FAMILY –3
COMPONENT – MACHINE CHART. AFTER FINDING FAMILIES AND
GROUPS
Cell Flow Analysis
MATERIAL
65 7
1
1 2 3 2
HS4 MO HS
1
2 6
11
3 3 2 4
5 7 6 4
MV DH MH DS
1 1
1
8
SA
41 2 5 4 4 16 2
MATERIALS
72
1
HS4
17 6 4 3
4 2 6 1 7 1 5
42
DH MH DS MV
1 2
8
15
5
8
SA
72
Enterprise
Factory Factory
Supplier Networks
Factory/Site
Shop
Cell
Machine
Factory
Factory
Factory
P-Q Analysis P-Q-$ Analysis
From-To Chart
P-R Analysis Type IV
Flow Diagram
M4 2 M1 1 M3
3 1 M2
Feasibility
Analysis for
Evaluation of Initial Menu of Cellular
Current and Lean Advisory Manufacturing
Proposed Layouts Tools powered
by PFAST
Design of Hybrid
Product Mix Rationalization Cellular Layouts
Success Stories
Factory Flow Analysis
Before After
M4
2
12 3
6
8 < 1000
M7 Machine Shop
25 57
1000-2000
55 54 53
7 48 2000-3000
52 3000-4000
External >4000
10 11
16 9 56 28 27 26
29 50 4
M2
M5
M3
1 40 21 22
17 39
M1
M6
33
12
41
Welding Cell
OP OUTGOING RACK
Co-located machines,
BEAD
M/C
GRINDER
MILL
equipment, tooling and processes
WELDING
FIXTURES to minimize part transportation
BENCH
WELDING FIXTURES
and waiting
MISCELLANEOUS BENCH
LATHE
WELD WELD
BOOTH #3 BOOTH #1
3 2
6 1
4 5
7 9 8
10
11
12
Finish Machining of Castings
Pipe Fabrication Jobshop
S Module 2
801 Raw
907 837 835
Module 1 Material
885 949 853 940 948 818 889 856 838 834
922 881
Cell 1 Cell 2 Raw
Material
2620 2610 2640 2650 2615
2500
842
958
2670 2550
841
955
S
Assembly of Industrial Scales
761
761 761
HSTUD/
DBURR SPWLD
761PEM
761PUNCH
811ASM
761 761 761
761ASY
FORM TWELD POLSH
763IRONW
771HCFIN/
771TEXTR
770WHLBR
763DRLPR 771
VIKIN
764PSMA
763BDSAW
763ACRO
Acknowledgements
The PRO-FAST Program is enabled by the
dedicated team of professionals representing
the Defense Logistics Agency, Department of
Defense and industry. These team mates are
determined to ensure the Nation’s forging
industry is positioned for the challenges of the
21st Century. Key team members include:
R&D Enterprise Team (DLA J339), Logistics
Research and Development Branch (DLA –
DSCP), and the Forging Industry Association
(FIA).
Acknowledgements
W
W WEBER METALS, INC.
ALUMINUM AND TITANIUM FORGINGS
Project Champion: Thomas Stys
Project Engineer: Jorge Alvarez