Project Information

Task Description Duration Necessary


(hours) Predecessors

A Set up Pre-staging Area 2 none


B Greet, register and pre-seat 1 A
students

C Greet, robe and pre-seat 0.5 none


faculty

D Graduation Crew to Places 0.15 B,C


for Processional

E Graduation Coordinator 0.25 B


addresses pre-seated
students

F Form Student Processional 0.1 D,E


Columns

G First Stop and Wellness 0.05 F


Check

H Student Processional 0.15 G


Columns proceed to
auditorium entrance

I Form Faculty Column 0.15 F


J Second Stop and Wellness 0.05 H,I
Check

K Student Processional 0.1 J


Columns proceed to seating

L Faculty Processional 0.05 L


Column proceed to stage

M Conferral of Degrees and 1.5 M


Awards

Activity ES EF LS LF
A 0 2 0 2
B 2 3 2 3
C 0 0.5 2.6 3.1
D 3 3.15 3.1 3.25
E 3 3.25 3 3.25
F 3.25 3.35 3.25 3.35
G 3.35 3.4 3.35 3.4
H 3.4 3.55 3.4 3.55
I 3.35 3.5 3.4 3.55
J 3.55 3.6 3.55 3.6
K 3.6 3.7 3.6 3.7
L 3.7 3.75 3.7 3.75
M 3.75 5.25 3.75 5.25

Completion Time of Project (days):


5.25

Path Lengths (yellow indicates critical path)


A-B-E-F-G-H-J-K-L-M 5.25
C-D-F-G-H-J-K-L-M 2.65
A-B-D-F-G-H-J-K-L-M 5.15
A-B-D-F-I-J-K-L-M 5.15
A-B-E-F-I-J-K-L-M 5.2
C-D-F-I-J-K-L-M 2.6
Slack
0
0
2.6
0.1
0
0
0
0
0.05
0
0
0
0