BUILDING SCHEDULE - 30 JULY 2016 Rev 04

ZONE Zone 04 Zone 05 Zone 03 Zone 06 Zone 10 Zone 11 Zone 07 Zone 07 Zone 07 Zone 02 & 01 Zone 08 Zone 09
BUILDING SH SK SN SM - 1 SM - 2 SJ SL SF SG SB SC - 1 SC - 2 SA SQ - 1 SQ - 2 SE SD SP EA SR TB - 1 TB - 2 TC - 1 TC - 2 EB - 1 EB - 2 EB - 3 SS HA EC - 1 EC - 2 TA - 1 TA - 2
WORKS DESCRIPTION ALEC SUBCONTRACTOR LARGE SMALL Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish

AVG Duration
JEVAN / LEON
Complete Superstructure (Concrete) Forecast/ Actual 5-Oct-15 16-Nov-15 12-Nov-15 16-Nov-15 31-Mar-16 23-Dec-15 31-Jan-16 14-Dec-15 28-Mar-16 3-Mar-16 7-Apr-16 9-May-16 9-Apr-16 13-Apr-16 2-May-16 3-May-16 30-May-16 16-Jun-16 28-Feb-16 2-Feb-16 27-May-16 7-Jul-16 27-May-16 26-Jul-16 10-Apr-16 22-May-16 15-Aug-16 19-Apr-16 6-Sep-16 14-Jul-16 16-Jul-16 15-Aug-16 30-Aug-16
/ SELVAM
Planned Roof Completion as per Contract
5-Oct-15 16-Nov-15 12-Nov-15 16-Nov-15 8-Mar-16 23-Dec-15 7-Jan-16 14-Dec-15 12-Mar-16 1-Feb-16 22-Mar-16 28-Apr-16 13-Mar-16 6-Apr-16 6-Apr-16 26-Mar-16 30-Apr-16 12-May-16 11-Feb-16 24-Jan-16 27-Mar-16 27-Apr-16 1-Mar-16 1-May-16 10-Mar-16 20-Apr-16 15-May-16 23-Apr-16 23-Jun-16 17-Apr-16 10-Jun-16 28-Apr-16 30-Jun-16
Programme (Rev 02)

Variance in days to Structure Completion 0 0 0 0 -23 0 -24 0 -16 -31 -16 -11 -27 -7 -26 -38 -30 -35 -17 -9 -61 -71 -87 -86 -31 -32 -92 4 -75 -88 -36 -109 -61

JEVAN / LEON
Parapet Casting 14 6 7‐Oct‐15 13‐Oct‐15 18‐Nov‐15 24‐Nov‐15 14‐Nov‐15 20‐Nov‐15 18‐Nov‐15 24‐Nov‐15 2‐Apr‐16 8‐Apr‐16 25‐Dec‐15 31‐Dec‐15 2‐Feb‐16 8‐Feb‐16 16‐Dec‐15 22‐Dec‐15 30‐Mar‐16 5‐Apr‐16 5‐Mar‐16 15‐Mar‐16 10‐Apr‐16 10‐May‐16 11‐May‐16 16‐May‐16 11‐Apr‐16 17‐Apr‐16 1‐May‐16 7‐May‐16 4‐May‐16 10‐May‐16 9‐May‐16 15‐May‐16 1‐Jun‐16 7‐Jun‐16 18‐Jun‐16 18‐Jul‐16 1‐Mar‐16 17‐Mar‐16 4‐Feb‐16 10‐Feb‐16 29‐May‐16 28‐Jun‐16 9‐Jul‐16 18‐Jul‐16 29‐May‐16 28‐Jun‐16 28‐Jul‐16 6‐Aug‐16 12‐Apr‐16 18‐Apr‐16 24‐May‐16 6‐Jul‐16 17‐Aug‐16 23‐Aug‐16 N/A N/A 8‐Sep‐16 22‐Sep‐16 16‐Jul‐16 25‐Jul‐16 18‐Jul‐16 27‐Jul‐16 17‐Aug‐16 26‐Aug‐16 1‐Sep‐16 10‐Sep‐16
/ SELVAM

Structural Steel Completion - Forecast/ Actual ROYSTUN ASSENT N/A N/A N/A N/A ‐ 25‐Apr‐16 N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A ‐ 30‐Aug‐16 N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A ‐ 15‐Aug‐16 N/A N/A ‐ 15‐Aug‐16 N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A ‐ 2‐Jul‐16 ‐ 1‐Jul‐16 ‐ ‐ 15‐Aug‐16 N/A N/A ‐ 27‐Aug‐16 N/A N/A N/A N/A N/A N/A ‐ 15‐Aug‐16

Planned Structural Steel Completion as per Contract


10‐Apr‐16 4‐Apr‐16 23‐Apr‐16 17‐May‐16 28‐Apr‐16 5‐Mar‐16 10‐May‐16 20‐Jun‐16 22‐Jun‐16
Programme (Rev 02)

Façade/ External Works Access Scaffold ZIYAAD JML 15 6 20‐Oct‐15 26‐Oct‐15 1‐Dec‐15 7‐Dec‐15 27‐Nov‐15 19‐May‐16 1‐Dec‐15 27‐Apr‐16 18‐Apr‐16 24‐Apr‐16 7‐Jan‐16 4‐Feb‐16 15‐Feb‐16 21‐Feb‐16 14‐Jan‐16 10‐Feb‐16 12‐Apr‐16 9‐Sep‐16 18‐Mar‐16 24‐Mar‐16 7‐May‐16 20‐May‐16 24‐May‐16 27‐May‐16 24‐Apr‐16 30‐Apr‐16 5‐May‐16 18‐May‐16 17‐May‐16 23‐May‐16 15‐May‐16 26‐May‐16 27‐Jun‐16 3‐Jul‐16 5‐Aug‐16 11‐Aug‐16 6‐Mar‐16 25‐Apr‐16 17‐Feb‐16 20‐Mar‐16 4‐Jul‐16 27‐Jul‐16 17‐Jul‐16 5‐Aug‐16 23‐Jun‐16 28‐Jul‐16 2‐Aug‐16 12‐Aug‐16 30‐May‐16 5‐Jun‐16 29‐May‐16 11‐Jun‐16 22‐Aug‐16 28‐Aug‐16 10‐May‐16 16‐May‐16 13‐Sep‐16 28‐Sep‐16 30‐Jul‐16 9‐Aug‐16 30‐Jul‐16 9‐Aug‐16 22‐Aug‐16 1‐Sep‐16 6‐Sep‐16 16‐Sep‐16

JEVAN / LEON
Ground Floor- Plinths/Upstands/HD Bolts/MEP 13 5 17‐Oct‐15 22‐Oct‐15 28‐Nov‐15 3‐Dec‐15 24‐Nov‐15 29‐Nov‐15 28‐Nov‐15 3‐Dec‐15 19‐Apr‐16 24‐Apr‐16 4‐Jan‐16 7‐Feb‐16 12‐Feb‐16 17‐Feb‐16 26‐Dec‐15 31‐Dec‐15 9‐Apr‐16 14‐Apr‐16 15‐Mar‐16 12‐Apr‐16 19‐Apr‐16 12‐May‐16 21‐May‐16 7‐Jun‐16 21‐Apr‐16 26‐Apr‐16 25‐Apr‐16 7‐May‐16 14‐May‐16 19‐May‐16 15‐May‐16 20‐May‐16 14‐Jun‐16 19‐Jun‐16 28‐Jun‐16 3‐Jul‐16 5‐Mar‐16 19‐Apr‐16 14‐Feb‐16 19‐Feb‐16 2‐Jun‐16 11‐Jul‐16 13‐Jul‐16 5‐Aug‐16 2‐Jun‐16 11‐Jun‐16 1‐Aug‐16 10‐Aug‐16 16‐Apr‐16 21‐Apr‐16 28‐May‐16 2‐Jun‐16 21‐Aug‐16 26‐Aug‐16 1‐May‐16 8‐May‐16 12‐Sep‐16 25‐Sep‐16 20‐Jul‐16 31‐Jul‐16 22‐Jul‐16 31‐Jul‐16 21‐Aug‐16 30‐Aug‐16 5‐Sep‐16 14‐Sep‐16
/ SELVAM
Rain Water Outlet, Balcony drain pipe Installation
IHAB AEA 4 2 23‐Oct‐15 25‐Oct‐15 4‐Dec‐15 6‐Dec‐15 30‐Nov‐15 2‐Dec‐15 4‐Dec‐15 6‐Dec‐15 7‐May‐16 9‐May‐16 8‐Feb‐16 10‐Feb‐16 18‐Feb‐16 20‐Mar‐16 1‐Jan‐16 3‐Jan‐16 7‐May‐16 30‐May‐16 13‐Apr‐16 9‐May‐16 13‐May‐16 20‐Jun‐16 8‐Jun‐16 20‐Jun‐16 27‐Apr‐16 26‐May‐16 26‐May‐16 30‐Jul‐16 26‐May‐16 30‐Jul‐16 26‐May‐16 28‐May‐16 20‐Jun‐16 28‐Jul‐16 4‐Jul‐16 6‐Jul‐16 7‐Mar‐16 26‐May‐16 20‐Feb‐16 14‐Mar‐16 6‐Jun‐16 8‐Jun‐16 2‐Aug‐16 4‐Aug‐16 24‐Jun‐16 25‐Jul‐16 3‐Aug‐16 5‐Aug‐16 25‐Apr‐16 25‐Jul‐16 25‐Jul‐16 30‐Jul‐16 23‐Aug‐16 25‐Aug‐16 9‐May‐16 19‐May‐16 14‐Sep‐16 18‐Sep‐16 31‐Jul‐16 2‐Aug‐16 31‐Jul‐16 2‐Aug‐16 23‐Aug‐16 25‐Aug‐16 7‐Sep‐16 9‐Sep‐16
(MEP)

Blockwork to Envelope JEVAN 35 14 23‐Oct‐15 6‐Nov‐15 4‐Dec‐15 18‐Dec‐15 30‐Nov‐15 14‐Dec‐15 4‐Dec‐15 18‐Dec‐15 21‐Apr‐16 2‐May‐16 10‐Jan‐16 14‐Feb‐16 18‐Feb‐16 20‐Mar‐16 11‐Jan‐16 16‐Feb‐16 15‐Apr‐16 29‐Apr‐16 21‐Mar‐16 23‐Apr‐16 10‐May‐16 24‐May‐16 27‐May‐16 5‐Jun‐16 27‐Apr‐16 11‐May‐16 8‐May‐16 22‐May‐16 20‐May‐16 3‐Jun‐16 18‐May‐16 1‐Jun‐16 30‐Jun‐16 5‐Aug‐16 8‐Aug‐16 22‐Aug‐16 7‐Mar‐16 11‐Apr‐16 20‐Feb‐16 14‐Apr‐16 5‐Jul‐16 5‐Aug‐16 18‐Jul‐16 11‐Aug‐16 24‐Jun‐16 5‐Aug‐16 3‐Aug‐16 27‐Aug‐16 31‐May‐16 26‐Jun‐16 30‐May‐16 5‐Aug‐16 23‐Aug‐16 6‐Sep‐16 13‐May‐16 23‐May‐16 14‐Sep‐16 19‐Oct‐16 31‐Jul‐16 24‐Aug‐16 31‐Jul‐16 24‐Aug‐16 23‐Aug‐16 16‐Sep‐16 7‐Sep‐16 1‐Oct‐16

Bitumen Paint JEVAN 16 4 6‐Nov‐15 10‐Nov‐15 18‐Dec‐15 22‐Dec‐15 14‐Dec‐15 18‐Dec‐15 18‐Dec‐15 22‐Dec‐15 2‐May‐16 6‐May‐16 11‐Feb‐16 15‐Feb‐16 20‐Mar‐16 24‐Mar‐16 16‐Feb‐16 20‐Feb‐16 29‐Apr‐16 3‐May‐16 23‐Apr‐16 27‐Apr‐16 24‐May‐16 28‐May‐16 5‐Jun‐16 10‐Jun‐16 11‐May‐16 15‐May‐16 22‐May‐16 30‐May‐16 3‐Jun‐16 7‐Jun‐16 1‐Jun‐16 12‐Jun‐16 5‐Aug‐16 9‐Aug‐16 22‐Aug‐16 26‐Aug‐16 6‐Apr‐16 22‐Apr‐16 14‐Apr‐16 18‐Apr‐16 31‐Jul‐16 11‐Aug‐16 6‐Aug‐16 17‐Aug‐16 31‐Jul‐16 11‐Aug‐16 22‐Aug‐16 2‐Sep‐16 21‐Jun‐16 27‐Jun‐16 31‐Jul‐16 4‐Aug‐16 1‐Sep‐16 5‐Sep‐16 23‐May‐16 27‐May‐16 14‐Oct‐16 30‐Oct‐16 19‐Aug‐16 30‐Aug‐16 19‐Aug‐16 30‐Aug‐16 11‐Sep‐16 22‐Sep‐16 26‐Sep‐16 7‐Oct‐16

Fire Proof Sealant ZIYAAD FSMIE 6 3 7‐Nov‐15 10‐Nov‐15 19‐Dec‐15 22‐Dec‐15 14‐Jan‐16 21‐Jan‐16 14‐Jan‐16 25‐Jan‐16 14‐May‐16 17‐May‐16 12‐Feb‐16 15‐Feb‐16 18‐Apr‐16 21‐Apr‐16 17‐Feb‐16 20‐Feb‐16 7‐May‐16 7‐Jun‐16 5‐May‐16 23‐May‐16 5‐Jun‐16 31‐Jul‐16 28‐Jul‐16 31‐Jul‐16 21‐May‐16 24‐May‐16 6‐Jun‐16 9‐Jun‐16 18‐Jul‐16 31‐Jul‐16 6‐Jun‐16 7‐Jun‐16 18‐Jul‐16 9‐Aug‐16 23‐Aug‐16 26‐Aug‐16 3‐May‐16 9‐May‐16 15‐Apr‐16 18‐Apr‐16 5‐Aug‐16 11‐Aug‐16 11‐Aug‐16 17‐Aug‐16 5‐Aug‐16 11‐Aug‐16 27‐Aug‐16 2‐Sep‐16 14‐Jul‐16 20‐Jul‐16 29‐Jul‐16 4‐Aug‐16 2‐Sep‐16 5‐Sep‐16 24‐May‐16 27‐May‐16 24‐Oct‐16 30‐Oct‐16 24‐Aug‐16 30‐Aug‐16 24‐Aug‐16 30‐Aug‐16 16‐Sep‐16 22‐Sep‐16 1‐Oct‐16 7‐Oct‐16

MEP 1st & 2nd Fix (Internal) IHAB AEA 45 25 26‐Oct‐15 17‐Mar‐16 7‐Dec‐15 5‐Apr‐16 3‐Dec‐15 14‐Apr‐16 7‐Dec‐15 9‐May‐16 3‐May‐16 24‐Jul‐16 13‐Jan‐16 17‐Mar‐16 21‐Feb‐16 23‐Jun‐16 4‐Jan‐16 27‐Jun‐16 1‐May‐16 8‐Aug‐16 27‐Apr‐16 29‐Jun‐16 28‐Apr‐16 4‐Aug‐16 30‐May‐16 4‐Aug‐16 30‐Apr‐16 4‐Aug‐16 14‐Jul‐16 31‐Jul‐16 14‐Jul‐16 8‐Aug‐16 24‐May‐16 5‐Aug‐16 28‐Jul‐16 22‐Aug‐16 28‐Jul‐16 22‐Aug‐16 20‐Mar‐16 4‐Aug‐16 23‐Feb‐16 4‐Aug‐16 21‐Jul‐16 21‐Aug‐16 31‐Jul‐16 31‐Aug‐16 21‐Jul‐16 21‐Aug‐16 16‐Aug‐16 16‐Sep‐16 1‐May‐16 28‐Jul‐16 30‐Jun‐16 5‐Aug‐16 5‐Sep‐16 30‐Sep‐16 15‐May‐16 25‐Jul‐16 13‐Sep‐16 13‐Nov‐16 31‐Jul‐16 31‐Aug‐16 31‐Jul‐16 31‐Aug‐16 5‐Sep‐16 6‐Oct‐16 20‐Sep‐16 21‐Oct‐16

Blockwork (Internal) JEVAN 35 18 28‐Nov‐15 16‐Dec‐15 9‐Jan‐16 27‐Jan‐16 5‐Jan‐16 23‐Jan‐16 10‐May‐16 15‐May‐16 25‐Jul‐16 12‐Aug‐16 13‐Mar‐16 31‐Mar‐16 19‐Jun‐16 30‐Jun‐16 27‐Feb‐16 16‐Mar‐16 12‐Apr‐16 30‐Apr‐16 25‐Jun‐16 13‐Jul‐16 31‐Jul‐16 18‐Aug‐16 31‐Jul‐16 9‐Aug‐16 27‐Apr‐16 15‐May‐16 27‐Jul‐16 14‐Aug‐16 4‐Aug‐16 22‐Aug‐16 1‐Aug‐16 19‐Aug‐16 18‐Aug‐16 5‐Sep‐16 18‐Aug‐16 5‐Sep‐16 22‐Mar‐16 2‐May‐16 20‐Apr‐16 8‐May‐16 20‐Jul‐16 13‐Aug‐16 2‐Aug‐16 26‐Aug‐16 9‐Jul‐16 2‐Aug‐16 18‐Aug‐16 11‐Sep‐16 15‐Jun‐16 5‐Aug‐16 14‐Jun‐16 5‐Aug‐16 7‐Sep‐16 25‐Sep‐16 20‐Jul‐16 4‐Aug‐16 29‐Sep‐16 3‐Nov‐16 15‐Aug‐16 8‐Sep‐16 15‐Aug‐16 8‐Sep‐16 7‐Sep‐16 1‐Oct‐16 22‐Sep‐16 16‐Oct‐16

MEP 3rd Fix (Tenant Units) IHAB AEA 12 7 15‐Apr‐16 2‐Aug‐16 15‐Apr‐16 2‐Aug‐16 14‐Apr‐16 2‐Aug‐16 30‐May‐16 2‐Aug‐16 2‐Aug‐16 9‐Aug‐16 15‐Apr‐16 2‐Aug‐16 17‐Apr‐16 2‐Aug‐16 26‐Jul‐16 2‐Aug‐16 2‐Aug‐16 9‐Aug‐16 26‐Jul‐16 2‐Aug‐16 2‐Aug‐16 9‐Aug‐16 2‐Aug‐16 9‐Aug‐16 5‐Aug‐16 12‐Aug‐16 1‐Aug‐16 8‐Aug‐16 9‐Aug‐16 16‐Aug‐16 6‐Aug‐16 13‐Aug‐16 23‐Aug‐16 30‐Aug‐16 23‐Aug‐16 30‐Aug‐16 5‐Aug‐16 17‐Aug‐16 5‐Aug‐16 12‐Aug‐16 22‐Aug‐16 30‐Aug‐16 1‐Sep‐16 9‐Sep‐16 22‐Aug‐16 30‐Aug‐16 17‐Sep‐16 25‐Sep‐16 29‐Jul‐16 5‐Aug‐16 6‐Aug‐16 13‐Aug‐16 1‐Oct‐16 8‐Oct‐16 26‐Jul‐16 2‐Aug‐16 14‐Nov‐16 26‐Nov‐16 31‐Aug‐16 8‐Sep‐16 31‐Aug‐16 8‐Sep‐16 6‐Oct‐16 14‐Oct‐16 21‐Oct‐16 29‐Oct‐16

Plinth for Fall arrest systems BRANDON 8 2 1‐Nov‐15 3‐Nov‐15 23‐Nov‐15 24‐Nov‐15 15‐Mar‐16 16‐Mar‐16 15‐Mar‐16 16‐Mar‐16 7‐Apr‐16 12‐Apr‐16 30‐Dec‐15 31‐Dec‐15 16‐Mar‐16 17‐Mar‐16 21‐Dec‐15 22‐Dec‐15 13‐Apr‐16 18‐Apr‐16 17‐Mar‐16 18‐Mar‐16 12‐May‐16 31‐May‐16 6‐Jun‐16 7‐Jun‐16 12‐Apr‐16 11‐May‐16 26‐May‐16 30‐May‐16 12‐Jun‐16 13‐Jun‐16 26‐May‐16 30‐May‐16 12‐Jun‐16 21‐Jun‐16 23‐Jun‐16 14‐Jul‐16 20‐Mar‐16 27‐Mar‐16 20‐Mar‐16 21‐Mar‐16 29‐Jul‐16 3‐Aug‐16 29‐Jul‐16 3‐Aug‐16 30‐Jun‐16 2‐Aug‐16 2‐Aug‐16 7‐Aug‐16 17‐Apr‐16 9‐May‐16 12‐Jun‐16 26‐Jun‐16 22‐Aug‐16 23‐Aug‐16 N/A N/A 13‐Sep‐16 20‐Sep‐16 31‐Jul‐16 5‐Aug‐16 31‐Jul‐16 5‐Aug‐16 22‐Aug‐16 27‐Aug‐16 6‐Sep‐16 11‐Sep‐16

Blockwork for MEP Openings BRANDON 2 1 2‐Nov‐15 2‐Nov‐15 25‐Nov‐15 25‐Nov‐15 21‐Nov‐15 21‐Nov‐15 25‐Nov‐15 25‐Nov‐15 9‐Apr‐16 10‐Apr‐16 1‐Jan‐16 1‐Jan‐16 9‐Feb‐16 18‐Mar‐16 23‐Dec‐15 23‐Dec‐15 13‐Apr‐16 18‐Apr‐16 16‐Mar‐16 16‐Mar‐16 1‐Jun‐16 1‐Jun‐16 8‐Jun‐16 8‐Jun‐16 18‐Apr‐16 12‐May‐16 22‐May‐16 31‐May‐16 14‐Jun‐16 14‐Jun‐16 31‐May‐16 31‐May‐16 22‐Jun‐16 22‐Jun‐16 15‐Jul‐16 15‐Jul‐16 18‐Mar‐16 19‐Apr‐16 11‐Feb‐16 20‐Mar‐16 4‐Aug‐16 6‐Aug‐16 30‐Jul‐16 31‐Jul‐16 3‐Aug‐16 4‐Aug‐16 7‐Aug‐16 9‐Aug‐16 19‐Apr‐16 26‐Jun‐16 27‐Jun‐16 27‐Jun‐16 24‐Aug‐16 24‐Aug‐16 N/A N/A 23‐Sep‐16 24‐Sep‐16 6‐Aug‐16 8‐Aug‐16 6‐Aug‐16 8‐Aug‐16 27‐Aug‐16 29‐Aug‐16 11‐Sep‐16 13‐Sep‐16

Light weight Screed to Falls - Inc. Fillets and


BRANDON 7 3 24‐Oct‐15 26‐Oct‐15 25‐Nov‐15 27‐Nov‐15 21‐Nov‐15 23‐Nov‐15 25‐Nov‐15 27‐Nov‐15 10‐Apr‐16 25‐Apr‐16 1‐Jan‐16 19‐Jan‐16 18‐Mar‐16 20‐Mar‐16 23‐Dec‐15 19‐Jan‐16 19‐Apr‐16 21‐Apr‐16 16‐Mar‐16 18‐Mar‐16 31‐May‐16 8‐Jun‐16 8‐Jun‐16 10‐Jun‐16 12‐May‐16 14‐May‐16 31‐May‐16 6‐Jun‐16 14‐Jun‐16 16‐Jun‐16 28‐Jun‐16 20‐Jul‐16 27‐Jun‐16 7‐Jul‐16 15‐Jul‐16 4‐Aug‐16 19‐Apr‐16 25‐Apr‐16 20‐Mar‐16 22‐Mar‐16 6‐Aug‐16 10‐Aug‐16 31‐Jul‐16 5‐Aug‐16 4‐Aug‐16 9‐Aug‐16 9‐Aug‐16 14‐Aug‐16 26‐Jun‐16 28‐Jun‐16 27‐Jun‐16 29‐Jun‐16 24‐Aug‐16 26‐Aug‐16 N/A N/A 24‐Sep‐16 30‐Sep‐16 8‐Aug‐16 12‐Aug‐16 8‐Aug‐16 12‐Aug‐16 29‐Aug‐16 3‐Sep‐16 13‐Sep‐16 18‐Sep‐16
chamfers

Installation of Drainage, vent pipes IHAB AEA 6 3 24‐Oct‐15 26‐Oct‐15 26‐Nov‐15 28‐Nov‐15 22‐Nov‐15 24‐Nov‐15 26‐Nov‐15 28‐Nov‐15 11‐Apr‐16 16‐Apr‐16 2‐Jan‐16 19‐Jan‐16 19‐Mar‐16 21‐Mar‐16 17‐Jan‐16 21‐Jan‐16 20‐Apr‐16 24‐Apr‐16 17‐Mar‐16 19‐Mar‐16 1‐Jun‐16 3‐Jun‐16 9‐Jun‐16 11‐Jun‐16 13‐May‐16 15‐May‐16 1‐Jun‐16 3‐Jun‐16 15‐Jun‐16 17‐Jun‐16 29‐Jun‐16 1‐Jul‐16 8‐Jul‐16 10‐Jul‐16 16‐Jul‐16 5‐Aug‐16 20‐Apr‐16 25‐Apr‐16 21‐Mar‐16 14‐Apr‐16 7‐Aug‐16 11‐Aug‐16 1‐Aug‐16 5‐Aug‐16 5‐Aug‐16 9‐Aug‐16 10‐Aug‐16 14‐Aug‐16 27‐Jun‐16 30‐Jun‐16 22‐Jun‐16 24‐Jun‐16 25‐Aug‐16 27‐Aug‐16 N/A N/A 25‐Sep‐16 30‐Sep‐16 9‐Aug‐16 13‐Aug‐16 9‐Aug‐16 13‐Aug‐16 30‐Aug‐16 3‐Sep‐16 14‐Sep‐16 18‐Sep‐16

Surface Preparation for Waterproofing BRANDON 6 2 28‐Oct‐15 29‐Oct‐15 28‐Nov‐15 29‐Nov‐15 24‐Nov‐15 25‐Nov‐15 28‐Nov‐15 29‐Nov‐15 26‐Apr‐16 5‐May‐16 20‐Jan‐16 20‐Mar‐16 21‐Mar‐16 22‐Mar‐16 20‐Jan‐16 21‐Jan‐16 25‐Apr‐16 26‐Apr‐16 19‐Mar‐16 10‐Apr‐16 9‐Jun‐16 14‐Jun‐16 11‐Jun‐16 12‐Jun‐16 15‐May‐16 16‐May‐16 7‐Jun‐16 14‐Jun‐16 17‐Jun‐16 18‐Jun‐16 21‐Jul‐16 2‐Aug‐16 10‐Jul‐16 11‐Jul‐16 5‐Aug‐16 6‐Aug‐16 26‐Apr‐16 1‐May‐16 23‐Mar‐16 9‐May‐16 11‐Aug‐16 16‐Aug‐16 6‐Aug‐16 10‐Aug‐16 10‐Aug‐16 14‐Aug‐16 15‐Aug‐16 19‐Aug‐16 29‐Jun‐16 30‐Jun‐16 30‐Jun‐16 2‐Aug‐16 27‐Aug‐16 28‐Aug‐16 N/A N/A 1‐Oct‐16 6‐Oct‐16 13‐Aug‐16 18‐Aug‐16 13‐Aug‐16 18‐Aug‐16 4‐Sep‐16 8‐Sep‐16 19‐Sep‐16 23‐Sep‐16

Priming, WP, Watertest, Insulation, Geotextile BRANDON IKK 18 9 2‐Nov‐15 10‐Nov‐15 30‐Nov‐15 8‐Dec‐15 26‐Nov‐15 4‐Dec‐15 30‐Nov‐15 8‐Dec‐15 17‐May‐16 16‐Jun‐16 21‐Mar‐16 9‐Apr‐16 23‐Mar‐16 31‐Mar‐16 22‐Jan‐16 30‐Jan‐16 27‐Apr‐16 5‐May‐16 11‐Apr‐16 5‐Jun‐16 27‐Jun‐16 5‐Jul‐16 25‐Jun‐16 29‐Jun‐16 17‐May‐16 13‐Jul‐16 24‐Jun‐16 2‐Jul‐16 19‐Jun‐16 27‐Jun‐16 2‐Aug‐16 10‐Aug‐16 7‐Aug‐16 15‐Aug‐16 7‐Aug‐16 15‐Aug‐16 2‐May‐16 5‐Jun‐16 10‐May‐16 5‐Jun‐16 17‐Aug‐16 29‐Aug‐16 11‐Aug‐16 24‐Aug‐16 15‐Aug‐16 28‐Aug‐16 20‐Aug‐16 1‐Sep‐16 10‐Aug‐16 18‐Aug‐16 3‐Aug‐16 11‐Aug‐16 29‐Aug‐16 6‐Sep‐16 N/A N/A 7‐Oct‐16 24‐Oct‐16 19‐Aug‐16 31‐Aug‐16 19‐Aug‐16 31‐Aug‐16 9‐Sep‐16 21‐Sep‐16 24‐Sep‐16 6‐Oct‐16

Insulation of Parapet Walls + EIFS Render BRANDON NAGI 12 6 11‐Nov‐15 16‐Nov‐15 9‐Dec‐15 20‐Jan‐16 5‐Dec‐15 21‐Jan‐16 9‐Dec‐15 25‐Jan‐16 17‐Jun‐16 5‐Aug‐16 10‐Apr‐16 28‐Apr‐16 1‐Apr‐16 3‐May‐16 31‐Jan‐16 5‐Feb‐16 23‐Jun‐16 31‐Jul‐16 6‐Jun‐16 2‐Aug‐16 31‐Jul‐16 5‐Aug‐16 31‐Jul‐16 3‐Aug‐16 2‐Aug‐16 7‐Aug‐16 7‐Aug‐16 12‐Aug‐16 7‐Aug‐16 12‐Aug‐16 11‐Aug‐16 16‐Aug‐16 16‐Aug‐16 21‐Aug‐16 16‐Aug‐16 21‐Aug‐16 1‐Jun‐16 2‐Aug‐16 6‐Jun‐16 11‐Jun‐16 25‐Aug‐16 3‐Sep‐16 20‐Aug‐16 28‐Aug‐16 24‐Aug‐16 1‐Sep‐16 28‐Aug‐16 6‐Sep‐16 14‐Aug‐16 19‐Aug‐16 7‐Aug‐16 12‐Aug‐16 7‐Sep‐16 12‐Sep‐16 N/A N/A 20‐Oct‐16 31‐Oct‐16 27‐Aug‐16 5‐Sep‐16 27‐Aug‐16 5‐Sep‐16 17‐Sep‐16 26‐Sep‐16 2‐Oct‐16 11‐Oct‐16

Fall arrest anchor point Installation BRANDON SSG 2 1 Mock Up Work 


27‐Mar‐16 12‐Apr‐16 28‐Mar‐16 12‐Apr‐16 29‐Mar‐16 12‐Apr‐16 6‐Aug‐16 6‐Aug‐16 30‐Mar‐16 13‐Apr‐16 1‐Apr‐16 14‐Apr‐16 14‐Apr‐16 31‐Jul‐16 31‐Jul‐16 1‐Aug‐16 31‐Jul‐16 31‐Jul‐16 6‐Aug‐16 6‐Aug‐16 4‐Aug‐16 4‐Aug‐16 8‐Aug‐16 8‐Aug‐16 13‐Aug‐16 13‐Aug‐16 13‐Aug‐16 13‐Aug‐16 17‐Aug‐16 17‐Aug‐16 22‐Aug‐16 22‐Aug‐16 22‐Aug‐16 22‐Aug‐16 3‐Aug‐16 4‐Aug‐16 12‐Jun‐16 2‐Aug‐16 4‐Sep‐16 5‐Sep‐16 29‐Aug‐16 30‐Aug‐16 2‐Sep‐16 3‐Sep‐16 7‐Sep‐16 8‐Sep‐16 20‐Aug‐16 20‐Aug‐16 13‐Aug‐16 13‐Aug‐16 13‐Sep‐16 13‐Sep‐16 N/A N/A 1‐Nov‐16 2‐Nov‐16 6‐Sep‐16 7‐Sep‐16 6‐Sep‐16 7‐Sep‐16 27‐Sep‐16 28‐Sep‐16 12‐Oct‐16 13‐Oct‐16
Inspection Approved 
WR 6611
Waterproofing Repairs to Fall arrest installation BRANDON IKK 2 1 13‐Apr‐16 13‐Apr‐16 13‐Apr‐16 13‐Apr‐16 13‐Apr‐16 13‐Apr‐16 7‐Aug‐16 7‐Aug‐16 14‐Apr‐16 14‐Apr‐16 15‐Apr‐16 15‐Apr‐16 1‐Aug‐16 1‐Aug‐16 2‐Aug‐16 2‐Aug‐16 1‐Aug‐16 1‐Aug‐16 7‐Aug‐16 7‐Aug‐16 5‐Aug‐16 5‐Aug‐16 9‐Aug‐16 9‐Aug‐16 14‐Aug‐16 14‐Aug‐16 14‐Aug‐16 14‐Aug‐16 18‐Aug‐16 18‐Aug‐16 23‐Aug‐16 23‐Aug‐16 23‐Aug‐16 23‐Aug‐16 5‐Aug‐16 6‐Aug‐16 3‐Aug‐16 3‐Aug‐16 6‐Sep‐16 7‐Sep‐16 31‐Aug‐16 2‐Sep‐16 4‐Sep‐16 6‐Sep‐16 9‐Sep‐16 11‐Sep‐16 21‐Aug‐16 21‐Aug‐16 14‐Aug‐16 14‐Aug‐16 14‐Sep‐16 14‐Sep‐16 N/A N/A 3‐Nov‐16 4‐Nov‐16 8‐Sep‐16 9‐Sep‐16 8‐Sep‐16 9‐Sep‐16 29‐Sep‐16 1‐Oct‐16 14‐Oct‐16 16‐Oct‐16

ROYSTUN /
Façade capping and insulation JML 20 8 31‐May‐16 31‐May‐16 16‐Jun‐16 18‐Jun‐16 17‐Jun‐16 17‐Jun‐16 2‐Sep‐16 9‐Sep‐16 8‐Aug‐16 15‐Aug‐16 31‐May‐16 31‐May‐16 30‐Jun‐16 30‐Jun‐16 3‐Aug‐16 10‐Aug‐16 26‐Aug‐16 2‐Sep‐16 2‐Aug‐16 9‐Aug‐16 5‐Sep‐16 12‐Sep‐16 23‐Aug‐16 28‐Aug‐16 7‐Aug‐16 14‐Aug‐16 3‐Sep‐16 10‐Sep‐16 3‐Sep‐16 10‐Sep‐16 7‐Sep‐16 14‐Sep‐16 8‐Sep‐16 15‐Sep‐16 3‐Oct‐16 10‐Oct‐16 18‐Aug‐16 6‐Sep‐16 2‐Aug‐16 9‐Aug‐16 24‐Sep‐16 8‐Oct‐16 1‐Oct‐16 15‐Oct‐16 22‐Sep‐16 6‐Oct‐16 8‐Oct‐16 22‐Oct‐16 10‐Sep‐16 17‐Sep‐16 10‐Sep‐16 17‐Sep‐16 21‐Oct‐16 28‐Oct‐16 N/A N/A 4‐Dec‐16 23‐Dec‐16 5‐Oct‐16 19‐Oct‐16 5‐Oct‐16 19‐Oct‐16 30‐Oct‐16 13‐Nov‐16 14‐Nov‐16 28‐Nov‐16
ZIYAAD

Earth Conductor Installation IHAB AEA 6 4 1‐Jun‐16 4‐Jun‐16 19‐Jun‐16 22‐Jun‐16 18‐Jun‐16 21‐Jun‐16 10‐Sep‐16 13‐Sep‐16 16‐Aug‐16 19‐Aug‐16 26‐May‐16 30‐May‐16 1‐Jul‐16 4‐Jul‐16 11‐Aug‐16 14‐Aug‐16 3‐Sep‐16 6‐Sep‐16 10‐Aug‐16 13‐Aug‐16 13‐Sep‐16 16‐Sep‐16 29‐Aug‐16 1‐Sep‐16 15‐Aug‐16 18‐Aug‐16 11‐Sep‐16 14‐Sep‐16 11‐Sep‐16 14‐Sep‐16 15‐Sep‐16 18‐Sep‐16 16‐Sep‐16 19‐Sep‐16 11‐Oct‐16 14‐Oct‐16 7‐Sep‐16 12‐Sep‐16 10‐Aug‐16 13‐Aug‐16 9‐Oct‐16 13‐Oct‐16 16‐Oct‐16 20‐Oct‐16 7‐Oct‐16 11‐Oct‐16 23‐Oct‐16 27‐Oct‐16 18‐Sep‐16 21‐Sep‐16 18‐Sep‐16 21‐Sep‐16 29‐Oct‐16 1‐Nov‐16 N/A N/A 24‐Dec‐16 29‐Dec‐16 20‐Oct‐16 24‐Oct‐16 20‐Oct‐16 24‐Oct‐16 14‐Nov‐16 18‐Nov‐16 29‐Nov‐16 3‐Dec‐16

Façade First Fix - Curtain Wall ZIYAAD JML 25 15 8‐Nov‐15 23‐Feb‐16 29‐Nov‐15 21‐Jan‐16 29‐Nov‐15 25‐May‐16 27‐Dec‐15 10‐Feb‐16 25‐Apr‐16 9‐May‐16 7‐Feb‐16 2‐Mar‐16 22‐Feb‐16 12‐Apr‐16 7‐Feb‐16 21‐Feb‐16 3‐May‐16 31‐Jul‐16 25‐Mar‐16 2‐May‐16 30‐May‐16 14‐Jul‐16 3‐Jun‐16 14‐Jul‐16 1‐May‐16 29‐Jun‐16 30‐May‐16 20‐Jul‐16 30‐May‐16 20‐Jul‐16 30‐May‐16 30‐Jun‐16 18‐Jul‐16 1‐Aug‐16 11‐Aug‐16 25‐Aug‐16 22‐Mar‐16 19‐May‐16 21‐Mar‐16 5‐Apr‐16 28‐Jul‐16 14‐Aug‐16 4‐Aug‐16 21‐Aug‐16 29‐Jul‐16 15‐Aug‐16 13‐Aug‐16 31‐Aug‐16 7‐Jun‐16 2‐Aug‐16 7‐Jul‐16 2‐Aug‐16 29‐Aug‐16 12‐Sep‐16 17‐May‐16 26‐May‐16 29‐Sep‐16 18‐Oct‐16 10‐Aug‐16 28‐Aug‐16 10‐Aug‐16 28‐Aug‐16 2‐Sep‐16 20‐Sep‐16 17‐Sep‐16 5‐Oct‐16

Façade First Fix - Other Cladding ZIYAAD JML 25 15 15‐Feb‐16 20‐Mar‐16 16‐Feb‐16 14‐Apr‐16 14‐Mar‐16 7‐Jun‐16 14‐Mar‐16 22‐Mar‐16 14‐May‐16 28‐May‐16 19‐Feb‐16 7‐Apr‐16 1‐Mar‐16 12‐Apr‐16 25‐Apr‐16 15‐May‐16 1‐Aug‐16 15‐Aug‐16 3‐May‐16 30‐May‐16 15‐Jul‐16 29‐Jul‐16 15‐Jul‐16 24‐Jul‐16 30‐Jun‐16 14‐Jul‐16 21‐Jul‐16 4‐Aug‐16 21‐Jul‐16 4‐Aug‐16 14‐Jul‐16 2‐Aug‐16 2‐Aug‐16 16‐Aug‐16 26‐Aug‐16 9‐Sep‐16 25‐Apr‐16 29‐May‐16 25‐Apr‐16 29‐May‐16 15‐Aug‐16 2‐Sep‐16 22‐Aug‐16 9‐Sep‐16 16‐Aug‐16 3‐Sep‐16 1‐Sep‐16 18‐Sep‐16 3‐Aug‐16 17‐Aug‐16 3‐Aug‐16 17‐Aug‐16 13‐Sep‐16 27‐Sep‐16 7‐Jun‐16 2‐Aug‐16 19‐Oct‐16 3‐Nov‐16 29‐Aug‐16 15‐Sep‐16 29‐Aug‐16 15‐Sep‐16 21‐Sep‐16 8‐Oct‐16 6‐Oct‐16 23‐Oct‐16

Curtain Wall Glazing ZIYAAD JML 25 15 14‐Jan‐16 29‐Feb‐16 16‐Jan‐16 23‐Feb‐16 1‐Mar‐16 9‐Jun‐16 23‐Feb‐16 15‐May‐16 15‐May‐16 27‐Jul‐16 29‐Feb‐16 29‐May‐16 18‐Apr‐16 5‐May‐16 17‐Feb‐16 20‐Mar‐16 29‐Jun‐16 5‐Aug‐16 25‐Apr‐16 19‐May‐16 9‐Jun‐16 31‐Jul‐16 14‐Jul‐16 31‐Jul‐16 12‐Jun‐16 14‐Jul‐16 14‐Jul‐16 2‐Aug‐16 14‐Jul‐16 2‐Aug‐16 2‐Jul‐16 15‐Aug‐16 7‐Aug‐16 21‐Aug‐16 31‐Aug‐16 14‐Sep‐16 11‐May‐16 20‐Jun‐16 11‐May‐16 30‐May‐16 17‐Aug‐16 3‐Sep‐16 14‐Aug‐16 31‐Aug‐16 8‐Aug‐16 25‐Aug‐16 23‐Aug‐16 10‐Sep‐16 2‐Aug‐16 16‐Aug‐16 2‐Aug‐16 16‐Aug‐16 8‐Sep‐16 22‐Sep‐16 1‐Aug‐16 15‐Aug‐16 9‐Oct‐16 2‐Nov‐16 20‐Aug‐16 7‐Sep‐16 20‐Aug‐16 7‐Sep‐16 12‐Sep‐16 30‐Sep‐16 27‐Sep‐16 15‐Oct‐16

Façade MEP 1st & 2nd Fix (External) (including Low


IHAB AEA 25 10 19‐Feb‐16 17‐Mar‐16 20‐Feb‐16 8‐Apr‐16 18‐Mar‐16 25‐Apr‐16 18‐Mar‐16 17‐Apr‐16 18‐May‐16 29‐Jul‐16 23‐Feb‐16 5‐Apr‐16 5‐Mar‐16 15‐May‐16 1‐May‐16 22‐May‐16 1‐Jul‐16 5‐Aug‐16 7‐May‐16 12‐Jun‐16 19‐Jul‐16 28‐Jul‐16 21‐Jun‐16 5‐Aug‐16 14‐Jun‐16 28‐Jun‐16 31‐Jul‐16 9‐Aug‐16 31‐Jul‐16 9‐Aug‐16 28‐Jun‐16 21‐Jul‐16 6‐Aug‐16 15‐Aug‐16 30‐Aug‐16 8‐Sep‐16 7‐May‐16 16‐Jun‐16 2‐May‐16 26‐Jun‐16 19‐Aug‐16 6‐Sep‐16 26‐Aug‐16 13‐Sep‐16 20‐Aug‐16 7‐Sep‐16 5‐Sep‐16 22‐Sep‐16 7‐Aug‐16 16‐Aug‐16 7‐Aug‐16 16‐Aug‐16 17‐Sep‐16 26‐Sep‐16 12‐Jun‐16 21‐Jun‐16 22‐Oct‐16 15‐Nov‐16 2‐Sep‐16 19‐Sep‐16 2‐Sep‐16 19‐Sep‐16 25‐Sep‐16 12‐Oct‐16 10‐Oct‐16 27‐Oct‐16
Current)

Insulation ZIYAAD JML 25 10 23‐Feb‐16 22‐Mar‐16 24‐Feb‐16 14‐Apr‐16 22‐Mar‐16 9‐Jun‐16 20‐Mar‐16 29‐Mar‐16 22‐May‐16 10‐Jun‐16 19‐Mar‐16 9‐Apr‐16 16‐Mar‐16 24‐Apr‐16 5‐May‐16 18‐May‐16 5‐Jul‐16 20‐Aug‐16 11‐May‐16 28‐Jun‐16 23‐Jul‐16 1‐Aug‐16 18‐Jul‐16 31‐Jul‐16 18‐Jun‐16 10‐Jul‐16 4‐Aug‐16 13‐Aug‐16 4‐Aug‐16 13‐Aug‐16 2‐Jul‐16 31‐Jul‐16 10‐Aug‐16 19‐Aug‐16 3‐Sep‐16 12‐Sep‐16 3‐May‐16 27‐May‐16 6‐May‐16 22‐May‐16 23‐Aug‐16 10‐Sep‐16 30‐Aug‐16 17‐Sep‐16 21‐Aug‐16 8‐Sep‐16 6‐Sep‐16 23‐Sep‐16 11‐Aug‐16 20‐Aug‐16 11‐Aug‐16 20‐Aug‐16 21‐Sep‐16 30‐Sep‐16 13‐Jul‐16 2‐Aug‐16 25‐Oct‐16 15‐Nov‐16 3‐Sep‐16 20‐Sep‐16 3‐Sep‐16 20‐Sep‐16 28‐Sep‐16 15‐Oct‐16 13‐Oct‐16 30‐Oct‐16

METALCRAFT/J
External Door Frame including sub frame ZIYAAD 12 5 23‐Mar‐16 25‐May‐16 25‐May‐16 30‐May‐16 24‐May‐16 24‐Jul‐16 26‐Jul‐16 31‐Jul‐16 31‐Jul‐16 4‐Aug‐16 25‐May‐16 30‐May‐16 25‐May‐16 31‐Jul‐16 31‐Jul‐16 31‐Jul‐16 21‐Aug‐16 25‐Aug‐16 22‐May‐16 31‐Jul‐16 2‐Aug‐16 6‐Aug‐16 1‐Aug‐16 3‐Aug‐16 31‐Jul‐16 4‐Aug‐16 14‐Aug‐16 18‐Aug‐16 14‐Aug‐16 18‐Aug‐16 31‐Jul‐16 4‐Aug‐16 20‐Aug‐16 24‐Aug‐16 13‐Sep‐16 17‐Sep‐16 26‐May‐16 31‐Jul‐16 23‐May‐16 31‐Jul‐16 1‐Sep‐16 9‐Sep‐16 8‐Sep‐16 16‐Sep‐16 30‐Aug‐16 7‐Sep‐16 14‐Sep‐16 22‐Sep‐16 21‐Aug‐16 25‐Aug‐16 21‐Aug‐16 25‐Aug‐16 1‐Oct‐16 5‐Oct‐16 2‐Aug‐16 5‐Aug‐16 16‐Nov‐16 27‐Nov‐16 11‐Sep‐16 19‐Sep‐16 11‐Sep‐16 19‐Sep‐16 6‐Oct‐16 14‐Oct‐16 21‐Oct‐16 29‐Oct‐16
ML

Inspection of Tenant Units/ snagging/ T&C/ As built AEA 15 10 25‐May‐16 6‐Aug‐16 25‐May‐16 6‐Aug‐16 25‐May‐16 6‐Aug‐16 27‐Jul‐16 6‐Aug‐16 6‐Aug‐16 16‐Aug‐16 25‐May‐16 6‐Aug‐16 27‐Jul‐16 6‐Aug‐16 27‐Jul‐16 6‐Aug‐16 19‐Aug‐16 29‐Aug‐16 2‐Aug‐16 6‐Aug‐16 12‐Aug‐16 22‐Aug‐16 3‐Aug‐16 13‐Aug‐16 9‐Aug‐16 16‐Aug‐16 12‐Aug‐16 22‐Aug‐16 NA 13‐Aug‐16 23‐Aug‐16 30‐Aug‐16 9‐Sep‐16 11‐Sep‐16 21‐Sep‐16 11‐Aug‐16 21‐Aug‐16 10‐Aug‐16 16‐Aug‐16 1‐Sep‐16 16‐Sep‐16 8‐Sep‐16 23‐Sep‐16 30‐Aug‐16 14‐Sep‐16 17‐Sep‐16 2‐Oct‐16 17‐Aug‐16 1‐Sep‐16 17‐Aug‐16 1‐Sep‐16 30‐Sep‐16 15‐Oct‐16 9‐Aug‐16 19‐Aug‐16 19‐Nov‐16 4‐Dec‐16 11‐Sep‐16 26‐Sep‐16 11‐Sep‐16 26‐Sep‐16 6‐Oct‐16 21‐Oct‐16 21‐Oct‐16 5‐Nov‐16

Tenant Access Date as per Contract Programme (Rev


20-Jun-16 NA NA NA NA 20-Jun-16 NA 20-Jun-16 20-Jun-16 20-Jun-16 20-Jun-16 31-Jul-16 20-Jun-16 NA NA 20-Jun-16 28-Jul-16 18-Aug-16 20-Jun-16 20-Jun-16 20-Jul-16 N/A 15-Jul-16 31-Jul-16 15-Jul-16 15-Jul-16 15-Jul-16 20-Jun-16 20-Sep-16 31-Aug-16 31-Aug-16 31-Aug-16 NA
02) - F&B/ Leisure Units
Tenant Access Date as per Contract Programme (Rev
20-Aug-16 20-Aug-16 20-Aug-16 20-Aug-16 20-Aug-16 20-Aug-16 20-Aug-16 20-Aug-16 20-Aug-16 NA NA NA 20-Aug-16 20-Aug-16 NA NA NA 18-Aug-16 20-Aug-16 20-Aug-16 N/A 20-Aug-16 20-Aug-16 20-Aug-16 20-Aug-16 20-Aug-16 20-Aug-16 NA 20-Sep-16 31-Aug-16 31-Aug-16 NA 20-Sep-16
02) - Retail Units

Complete Grey BOX and Handover 6-Aug-16 6-Aug-16 6-Aug-16 6-Aug-16 16-Aug-16 6-Aug-16 6-Aug-16 6-Aug-16 29-Aug-16 6-Aug-16 22-Aug-16 13-Aug-16 16-Aug-16 22-Aug-16 NA 23-Aug-16 9-Sep-16 21-Sep-16 21-Aug-16 16-Aug-16 16-Sep-16 23-Sep-16 14-Sep-16 2-Oct-16 1-Sep-16 1-Sep-16 15-Oct-16 19-Aug-16 4-Dec-16 26-Sep-16 26-Sep-16 21-Oct-16 5-Nov-16

Previous Week Float available for Grey Box (F&B and


‐42 N/A N/A N/A N/A ‐40 N/A ‐42 ‐63 ‐42 ‐56 ‐7 ‐49 N/A N/A ‐64 ‐43 ‐27 ‐55 ‐50 ‐58 N/A ‐61 ‐64 ‐48 ‐48 ‐87 ‐53 ‐69 ‐27 ‐27 ‐52 N/A
Leisure Unit)
Previous Week Float available for Grey Box (Retail
19 19 19 19 4 21 19 19 ‐2 N/A N/A N/A 12 2 N/A N/A N/A ‐27 6 11 N/A ‐28 ‐25 ‐43 ‐12 ‐12 ‐51 N/A ‐69 ‐27 ‐27 N/A ‐47
Unit)
Current Week Float available for Grey Box (F&B and
‐47 N/A N/A N/A N/A ‐47 N/A ‐47 ‐70 ‐47 ‐63 ‐13 ‐57 N/A N/A ‐64 ‐43 ‐34 ‐62 ‐57 ‐58 N/A ‐61 ‐64 ‐48 ‐48 ‐92 ‐60 ‐75 ‐27 ‐27 ‐52 N/A
Leisure Unit)
Current Week Float available for Grey Box (Retail
14 14 14 14 4 14 14 14 ‐9 N/A N/A N/A 4 ‐2 N/A N/A N/A ‐34 ‐1 4 N/A ‐34 ‐25 ‐43 ‐12 ‐12 ‐56 N/A ‐75 ‐27 ‐27 N/A ‐47
Unit)
Variance in Float during the week
‐5 N/A N/A N/A N/A ‐7 N/A ‐5 ‐7 ‐5 ‐7 ‐6 ‐8 N/A N/A 0 0 ‐7 ‐7 ‐7 0 N/A 0 0 0 0 ‐5 ‐7 ‐6 0 0 0 N/A
(F&B and Leisure Unit)

Variance in Float during the week (Retail Unit) ‐5 ‐5 ‐5 ‐5 0 ‐7 ‐5 ‐5 ‐7 N/A N/A N/A ‐8 ‐4 N/A N/A N/A ‐7 ‐7 ‐7 N/A ‐7 0 0 0 0 ‐5 N/A ‐6 0 0 N/A 0

Façade Metal Cladding & misc cladding (JML) ZIYAAD JML 30 20 15‐Mar‐16 30‐May‐16 26‐May‐16 15‐Jun‐16 10‐May‐16 30‐May‐16 15‐May‐16 20‐May‐16 26‐May‐16 14‐Jun‐16 10‐May‐16 30‐May‐16 25‐Apr‐16 15‐May‐16 21‐May‐16 2‐Aug‐16 15‐Jul‐16 3‐Aug‐16 3‐Jul‐16 2‐Aug‐16 2‐Aug‐16 21‐Aug‐16 28‐Jul‐16 16‐Aug‐16 9‐Jul‐16 31‐Jul‐16 14‐Aug‐16 2‐Sep‐16 14‐Aug‐16 2‐Sep‐16 2‐Aug‐16 21‐Aug‐16 2‐Aug‐16 1‐Sep‐16 13‐Sep‐16 2‐Oct‐16 19‐May‐16 2‐Aug‐16 13‐Jul‐16 2‐Aug‐16 2‐Sep‐16 23‐Sep‐16 9‐Sep‐16 30‐Sep‐16 31‐Aug‐16 21‐Sep‐16 16‐Sep‐16 7‐Oct‐16 21‐Aug‐16 9‐Sep‐16 21‐Aug‐16 9‐Sep‐16 1‐Oct‐16 20‐Oct‐16 15‐Aug‐16 5‐Sep‐16 4‐Nov‐16 31‐Oct‐16 13‐Sep‐16 4‐Oct‐16 13‐Sep‐16 4‐Oct‐16 8‐Oct‐16 29‐Oct‐16 23‐Oct‐16 13‐Nov‐16

Stone Ballast placing BRANDON 6 2 4‐Jun‐16 5‐Jun‐16 11‐Apr‐16 12‐Apr‐16 19‐Apr‐16 26‐Apr‐16 13‐Sep‐16 14‐Sep‐16 19‐Aug‐16 21‐Aug‐16 27‐May‐16 29‐May‐16 4‐Jul‐16 5‐Jul‐16 14‐Aug‐16 15‐Aug‐16 6‐Sep‐16 7‐Sep‐16 13‐Aug‐16 14‐Aug‐16 16‐Sep‐16 17‐Sep‐16 1‐Sep‐16 2‐Sep‐16 18‐Aug‐16 19‐Aug‐16 14‐Sep‐16 15‐Sep‐16 14‐Sep‐16 15‐Sep‐16 18‐Sep‐16 19‐Sep‐16 19‐Sep‐16 20‐Sep‐16 14‐Oct‐16 15‐Oct‐16 12‐Sep‐16 17‐Sep‐16 13‐Aug‐16 14‐Aug‐16 13‐Oct‐16 17‐Oct‐16 20‐Oct‐16 24‐Oct‐16 11‐Oct‐16 15‐Oct‐16 27‐Oct‐16 31‐Oct‐16 21‐Sep‐16 22‐Sep‐16 21‐Sep‐16 22‐Sep‐16 1‐Nov‐16 2‐Nov‐16 N/A N/A 29‐Dec‐16 3‐Jan‐17 24‐Oct‐16 28‐Oct‐16 24‐Oct‐16 28‐Oct‐16 18‐Nov‐16 22‐Nov‐16 3‐Dec‐16 7‐Dec‐16

Fall arrest cable installation BRANDON SSG 1 1 12‐Jun‐16 12‐Jun‐16 12‐Jun‐16 12‐Jun‐16 20‐Jun‐16 20‐Jun‐16 15‐Sep‐16 15‐Sep‐16 22‐Aug‐16 22‐Aug‐16 12‐Jun‐16 12‐Jun‐16 6‐Jul‐16 6‐Jul‐16 16‐Aug‐16 16‐Aug‐16 8‐Sep‐16 8‐Sep‐16 15‐Aug‐16 15‐Aug‐16 18‐Sep‐16 18‐Sep‐16 3‐Sep‐16 3‐Sep‐16 20‐Aug‐16 20‐Aug‐16 16‐Sep‐16 16‐Sep‐16 16‐Sep‐16 16‐Sep‐16 20‐Sep‐16 20‐Sep‐16 21‐Sep‐16 21‐Sep‐16 16‐Oct‐16 16‐Oct‐16 18‐Sep‐16 18‐Sep‐16 15‐Aug‐16 15‐Aug‐16 18‐Oct‐16 19‐Oct‐16 25‐Oct‐16 26‐Oct‐16 16‐Oct‐16 17‐Oct‐16 1‐Nov‐16 2‐Nov‐16 23‐Sep‐16 23‐Sep‐16 23‐Sep‐16 23‐Sep‐16 3‐Nov‐16 3‐Nov‐16 N/A N/A 4‐Jan‐17 4‐Jan‐17 29‐Oct‐16 30‐Oct‐16 29‐Oct‐16 30‐Oct‐16 23‐Nov‐16 24‐Nov‐16 8‐Dec‐16 9‐Dec‐16

Façade GRC Cladding ZIYAAD NOTREDAME 30 20 1‐Mar‐16 27‐May‐16 N/A N/A N/A N/A 15‐May‐16 10‐Jun‐16 12‐Jun‐16 7‐Aug‐16 N/A N/A N/A N/A N/A N/A 2‐Aug‐16 21‐Aug‐16 N/A N/A N/A N/A N/A N/A N/A N/A 14‐Aug‐16 2‐Sep‐16 14‐Aug‐16 2‐Sep‐16 N/A N/A N/A N/A N/A N/A 19‐Jul‐16 17‐Aug‐16 N/A N/A 2‐Sep‐16 23‐Sep‐16 9‐Sep‐16 30‐Sep‐16 31‐Aug‐16 21‐Sep‐16 16‐Sep‐16 7‐Oct‐16 21‐Aug‐16 9‐Sep‐16 21‐Aug‐16 9‐Sep‐16 1‐Oct‐16 20‐Oct‐16 15‐Aug‐16 3‐Sep‐16 N/A N/A 13‐Sep‐16 4‐Oct‐16 13‐Sep‐16 4‐Oct‐16 8‐Oct‐16 29‐Oct‐16 23‐Oct‐16 13‐Nov‐16

Façade Stone ZIYAAD SITAL 30 15 N/A N/A 24‐May‐16 29‐May‐16 22‐May‐16 27‐May‐16 N/A N/A N/A N/A 27‐Apr‐16 16‐May‐16 N/A N/A 10‐Jun‐16 24‐Jun‐16 24‐Jul‐16 25‐Aug‐16 7‐Jul‐16 25‐Aug‐16 21‐Aug‐16 4‐Sep‐16 28‐Jul‐16 22‐Aug‐16 1‐Jul‐16 22‐Aug‐16 N/A N/A N/A N/A 23‐Aug‐16 6‐Sep‐16 24‐Aug‐16 7‐Sep‐16 13‐Sep‐16 27‐Sep‐16 20‐Jun‐16 15‐Aug‐16 20‐Jun‐16 15‐Aug‐16 2‐Sep‐16 23‐Sep‐16 9‐Sep‐16 30‐Sep‐16 31‐Aug‐16 21‐Sep‐16 16‐Sep‐16 7‐Oct‐16 21‐Aug‐16 4‐Sep‐16 21‐Aug‐16 4‐Sep‐16 1‐Oct‐16 15‐Oct‐16 15‐Aug‐16 29‐Aug‐16 4‐Nov‐16 3‐Dec‐16 N/A N/A N/A N/A N/A N/A N/A N/A

Fibre C Cladding ZIYAAD AUSTRIAN 20 12 N/A N/A N/A N/A 7‐Apr‐16 16‐Jun‐16 20‐Aug‐16 1‐Sep‐16 20‐Aug‐16 1‐Sep‐16 23‐May‐16 4‐Jun‐16 16‐May‐16 20‐Jul‐16 14‐Jul‐16 31‐Aug‐16 N/A N/A 25‐Aug‐16 6‐Sep‐16 25‐Aug‐16 6‐Sep‐16 25‐Aug‐16 6‐Sep‐16 N/A N/A 28‐Aug‐16 9‐Sep‐16 28‐Aug‐16 9‐Sep‐16 N/A N/A 20‐Aug‐16 1‐Sep‐16 N/A N/A N/A N/A N/A N/A 2‐Sep‐16 16‐Sep‐16 9‐Sep‐16 23‐Sep‐16 31‐Aug‐16 14‐Sep‐16 16‐Sep‐16 30‐Sep‐16 21‐Aug‐16 2‐Sep‐16 21‐Aug‐16 2‐Sep‐16 1‐Oct‐16 13‐Oct‐16 N/A N/A N/A N/A 13‐Sep‐16 27‐Sep‐16 13‐Sep‐16 27‐Sep‐16 8‐Oct‐16 22‐Oct‐16 23‐Oct‐16 6‐Nov‐16

Graphic Concrete ZIYAAD ALEC PRECAST 20 12 N/A N/A 2‐May‐16 14‐May‐16 N/A N/A N/A N/A N/A N/A 16‐May‐16 28‐May‐16 15‐May‐16 9‐Jun‐16 N/A N/A 17‐Jul‐16 15‐Aug‐16 N/A N/A N/A N/A N/A N/A N/A N/A 16‐Aug‐16 27‐Aug‐16 16‐Aug‐16 27‐Aug‐16 N/A N/A N/A N/A N/A N/A 5‐Jun‐16 21‐Aug‐16 N/A N/A N/A N/A N/A N/A 2‐Sep‐16 16‐Sep‐16 18‐Sep‐16 2‐Oct‐16 23‐Aug‐16 3‐Sep‐16 23‐Aug‐16 3‐Sep‐16 3‐Oct‐16 14‐Oct‐16 N/A N/A N/A N/A 15‐Sep‐16 29‐Sep‐16 15‐Sep‐16 29‐Sep‐16 10‐Oct‐16 24‐Oct‐16 25‐Oct‐16 8‐Nov‐16

MEP 3rd Fix IHAB AEA - * 30‐Apr‐16 21‐Jul‐16 15‐Jun‐16 8‐Aug‐16 20‐May‐16 8‐Aug‐16 19‐May‐16 8‐Aug‐16 13‐Jun‐16 8‐Aug‐16 25‐May‐16 8‐Aug‐16 10‐May‐16 8‐Aug‐16 8‐Aug‐16 6‐Aug‐16 8‐Aug‐16 7‐Aug‐16 10‐Aug‐16 6‐Aug‐16 17‐Aug‐16 25‐Aug‐16 12‐Aug‐16 20‐Aug‐16 10‐Aug‐16 15‐Aug‐16 29‐Aug‐16 6‐Sep‐16 29‐Aug‐16 6‐Sep‐16 17‐Aug‐16 25‐Aug‐16 17‐Aug‐16 24‐Aug‐16 28‐Sep‐16 6‐Oct‐16 11‐Jun‐16 6‐Aug‐16 28‐Jul‐16 6‐Aug‐16 17‐Sep‐16 27‐Sep‐16 24‐Sep‐16 4‐Oct‐16 15‐Sep‐16 25‐Sep‐16 1‐Oct‐16 11‐Oct‐16 5‐Sep‐16 13‐Sep‐16 5‐Sep‐16 13‐Sep‐16 16‐Oct‐16 24‐Oct‐16 30‐Aug‐16 4‐Sep‐16 19‐Nov‐16 24‐Nov‐16 23‐Sep‐16 8‐Oct‐16 28‐Sep‐16 8‐Oct‐16 23‐Oct‐16 29‐Oct‐16 7‐Nov‐16 13‐Nov‐16

Strike Façade Scaffolding (F) ZIYAAD 15 6 19‐Jul‐16 24‐Jul‐16 6‐Aug‐16 11‐Aug‐16 6‐Aug‐16 11‐Aug‐16 9‐Aug‐16 14‐Aug‐16 6‐Aug‐16 11‐Aug‐16 6‐Aug‐16 11‐Aug‐16 9‐Aug‐16 14‐Aug‐16 7‐Aug‐16 12‐Aug‐16 8‐Aug‐16 13‐Aug‐16 7‐Aug‐16 12‐Aug‐16 26‐Aug‐16 31‐Aug‐16 21‐Aug‐16 26‐Aug‐16 16‐Aug‐16 21‐Aug‐16 7‐Sep‐16 10‐Sep‐16 7‐Sep‐16 10‐Sep‐16 26‐Aug‐16 31‐Aug‐16 25‐Aug‐16 30‐Aug‐16 7‐Oct‐16 10‐Oct‐16 7‐Aug‐16 21‐Aug‐16 7‐Aug‐16 12‐Aug‐16 19‐Sep‐16 3‐Oct‐16 26‐Sep‐16 10‐Oct‐16 17‐Sep‐16 1‐Oct‐16 3‐Oct‐16 17‐Oct‐16 5‐Sep‐16 10‐Sep‐16 5‐Sep‐16 10‐Sep‐16 16‐Oct‐16 21‐Oct‐16 5‐Sep‐16 10‐Sep‐16 16‐Nov‐16 30‐Nov‐16 4‐Oct‐16 14‐Oct‐16 30‐Sep‐16 10‐Oct‐16 19‐Oct‐16 2‐Nov‐16 3‐Nov‐16 17‐Nov‐16

JOSEPH /
Surface Preparation - * 1‐May‐16 to 12‐June‐16 (100% Completed) 01‐Aug‐16 to 14‐Sep‐16 01‐Sep‐16 to 15‐Octr‐16 01‐Aug‐16 to 24‐Aug‐16 (80% Completed) 25‐Sep‐16 to 24‐Oct‐16 11‐Sep‐16 to 30‐Oct‐16 25‐Oct‐16 to 05‐Dec‐16 06‐Oct‐16 to 23‐Nov‐16 
ANTON

Water Proofing External - Plaza Level ANTON IKK - * 3‐May‐16 to 17‐June‐16 ( 100% completed) 04‐Aug‐16 to 18‐Sep‐16 05‐Sep‐16 to 20‐Oct‐16 04‐Aug‐16 to 28‐Aug‐16 (80% Completed) 30‐Sep‐16 to 27‐Oct‐16 16‐Sep‐16 to 05‐Nov‐16 30‐Oct‐16 to 10‐Dec‐16 10‐Oct‐16 to 28‐Nov‐16

JOSEPH /
Protection Screed - * 5‐May‐16 to 20‐June‐16 (100% Completed) 08‐Aug‐16 to 22‐Sep‐16 09‐Sep‐16 to 24‐Oct‐16 08‐Aug‐16 to 26‐Sep‐16 04‐Oct‐16 to 30‐Oct‐16 20‐Sep‐16 to 10‐Nov‐16 03‐Nov‐16 to 15‐Dec‐16 15‐Oct‐16 to 03‐Dec‐16
ANTON

Layer Works (Sub-base) Below Paving ANTON DESERT - * 7‐May‐16 to 22‐June‐16 (95% Completed) 12‐Aug‐16 to 26‐Sep‐16 13‐Sep‐16 to 28‐Oct‐16 12‐Aug‐16 to 30‐Sep‐16 07‐Oct‐16 to 04‐Nov‐16 24‐Sep‐16 to 15‐Nov‐16 05‐Nov‐16 to 20‐Dec‐16 20‐Oct‐16 to 08‐Dec‐16

MEP below Paving/Irrigation ANTON AEA & DESERT - * 9‐May‐16 to 25‐June‐16 (95% Completed) 16‐Aug‐16 to 30‐Sep‐16 18‐Sep‐16 to 02‐Nov‐16 16‐Aug‐16 to 04‐Sep‐16 15‐Oct‐16 to 07‐Nov‐16 28‐Sep‐16 to 20‐Nov‐16 13‐Nov‐16 to 25‐Dec‐16 25‐Oct‐16 to 11‐Dec‐16

Paving/ Copings/ (Hardscaping)/ light fittings &


ANTON DESERT - * 10‐May‐16 to 30‐June‐16 (70% Completed) 20‐Aug‐16 to 04‐Oct‐16 22‐Sep‐16 to 06‐Nov‐16 20‐Aug‐16 to 08‐Sep‐16 21‐Oct‐16 to 11‐Nov‐16 02‐Oct‐16 to 25‐Nov‐16 15‐Nov‐16 to 30‐Dec‐16  30‐Oct‐16 to 14‐Dec‐16
protection

Updated as of: 30-Jul-16


LEGEND
Forecast Up to: 13-Aug-16 COMPLETED/ STARTED ON TIME

TASKS STARTING WITHIN 2 WEEKS

DELAYED