NIOC DAILY DRILLING PROGRESS REPORT

DATE: 1389/03/20 FIELD: CHeshmehKh WELL NO.: CK-006WO5 LOC: W10N OP. TYPE: Delineation-W WELL PROF.: Side Tracking
RIG NO OOK2 Spud Date: 1389/03/10 Release Date RESV Asmari
CONT. NIDC BIT NO. MUD PROPERTIES.
PROJ. TD. 3762.4 BIT SER.NO. MW: MAX 62.4 MIN 62.4 REP.TIME 62.4
EST. TTL RIG DAYS. 74 BIT SIZE MUD TYPE: Water
ACT RIG DAYS 11 BIT TYPE. M.F.VIS FAN600
R.T.E WATER DEPTH -3489 IADC CODE: F.L./HPHT FAN300
MORNING DEPTH 4906 NOZZLE SIZE/TFA PH/ALK 10 PV
MIDNIGHT DEPTH 4906 BIT METR.(TOTAL) CLORIDE (PPM) YP
PREVIOUS DEPTH 4906 BIT HOURS (TOT) CALCIUM (PPM) INITIAL GEL
METERAGE 0 WT. ON BIT(MN/MX) RETORT SOLID% 10MIN GEL
DRILLING TIME RPM: AIR/FOAM-CFM TEMP (F)
CUM. DRLG TIME 0 TORQUE OIL (%) O/W GASOIL 70000
FORMATION As@3472 BIT ROP (M/H) E-STABILITY (VOLT) KCL (PPB)
LITHOLOGY: BIT CONDITION MBT MUD SYSTEM 634
LAST CAS L PUMP TYPE PF MF WATER ON LOC. 1200
LINER LAP PUMP LINER SIZE MUD STORAGE 1 500 BBL WTR PCF
WELLSITE SUPT. Soroushnia/Askari PUMP OUTPUT(GPM) MUD STORAGE 2 BBL PCF
OPN.SUPT. Veysi PUMP PRESSURE SLOW PUMP 1 PSI@ SPM
PROG. ENG. H.Z.Ezatpour ANNULAR VELOCIT SLOW PUMP 2 PSI@ SPM
GEOLOGIST Bahrami/Nabavi BIT HSI FORMATION LOSS BBL@ HR@ 4906 M
CONT.T.PUSH.(1) S.R.Mosavi CMT DRL(MTR-H) MUD LOSS@UNITS BBL
CONT.T.PUSH.(2) S.B.Makvandi W&R(MTR-H) MUD GAINS BBL@ HR@ 4906 M
PREV.DRILL DEPTH BIT CHANGE(IN/OUT) CHEMICAL MATERIALS
KOP W/ST.PT. BOTTOM HOLE ASSEMBLY MATERIAL UNIT USED REC.STOCK O/S REQ Sent
TOOLS/Failure Make BHA# Wt.KLB Length CAUSTIC SODA SX 17
SODA ASH SX 40
SALT TON 0
CACL2 SX 1980
JAR(TYPE) Size SN HRS LIME SX 566
P.EMUL.DRILLV DR 83
MWD(TYPE) Size SN HRS SHELL FISH SX 130
String Drag Up Down MICA SX 80
DH MOTOR (TYPE) Size SN HRS D/P SIZE 3 1/2” 2 7/8” SEC.EMUL.DRIL DR 50
D/P GRADE G-105 G-105 PIPELAX DR 2
DIR. SERVICE CO. STABILIZER Drill Gel SX 120
DAILY DRILLING COST LAST CASING DATA EQUIPMENT
DAY RATE. SIZE GRADE PPF THREAD LENGTH EQUIPMENT UNIT USED REC STOCK O/S REQ Sent
MUD 0
CEMENT.
EQUIPMENT
SERVICE.
OTHERS
TODAY TOTAL
GRAND TOTAL
R $0
19276100
0
0
LAST SURVEY DATA SOLID CONTROL HRS U.F. O.F. FEED CONS F.PRS.
MD DEG AZ TVD N-S E-W Section HD DLS
DESILTER
DESANDER
SHAKER HOUR: 0 SCREEN SIZE 1: 6*84 2: 6*84 BYPASS
BOP/SAFETY DRILL: F.ACC.PRESS: RECHARGE: @ LTBT: 7 LTKT: 7
TOTAL PERSONEL: 45 PERSONNEL ON JOB NIOC: 3 NIOC TRAINEE: 1 SERVICE PER: 4
T.PUSHER: 2 DRILLER: 2 ASST. DRILLER: 2 MUD ENG: 2 MECH: 2 ELEC: 2 TRAINEE: 1 CONT LAB: 12 CASU LAB: 12
OPERATION TIME OP.C FROM TO REMARKS
RIGGING&MOVING COMP 00:00 R/UP 2 7/8”DPS RUNNING EQUIP, RIH W/2 7/8”DPS (JT BY JT) TO 286M, CONT RIH W/3
DRILLING TIME 1/2”DPS TO 3510M. L/UP CEMENTING LINE, TEST TO 3KPSI, OK. PUMP F.WTR AS SPACER
ROUND TRIP AHEAD, MIX 47SXS CMT ”G-KERMAN” W/7.5BBL SOL (F.WTR+10.34LB R-8+ANTIFOAM) &
PUMP 12BBL 115PCF CMT SLURRY. DISPLACE W/81BBL F.WTR AS BALANCE. (NO LOSS REP
BOP TESTING
WHILE CMT JOB).
H.COND/LOS.CIRC
R.DEV,RIG SERV.
COMP 24:00 POH TO 3340M (4ST WET), FLUSH PIPES, CONT POH TO 2900M. OBS WELL STATIC.
DIRECT.DRILLING
CASING & TUBING COMP 00:00 07:00 CONT POH F/2900 TO 300M.
CEMENTING
NT NOTE: SLOW OPERATION WHILE RUNNING 2 7/8”DPS.
NIP.UP/DRILL OUT
FORMATION
LOGGING
REPAIR
FISHING
CONTINGENCY
COMPL./ABAND. 24
NIOC WAITING
CONT. WAITING
SERVICE COMPANY
OTHER WAITING
N.OBV.WAIT.
OTHERS

PROBLEM: DEPTH: DESCRIPTION:

SUMMARY: RIH W/2 7/8”DPS & 3 1/2”DPS TO 3510M.L/UP CEMENTING LINE,TEST TO 3KPSI,OK.PUMP MIX 47SXS CMT ”G-KERMAN” W/7.5BBL
SOL & PUMP 12BBL 115PCF CMT SLUR.DISPL W/81BBL F.WTR AS BALANCE.POH TO 3340M,FLUSH PIPES,CONT POH TO 300M.
WIND SPEED/DIR: WAVE/VISIB: F.WATER: FUEL:
M/V
Page 1 of 1