Halfaya Oil Field Surface Facility

PetroChina Phase : III Page 1 / 2


Halfaya
FIELD DESIGN CHANGE FORM (FDC)
TECHNICAL CLARIFICATION REQUEST FORM – PART 01
ORIGINATOR Al Sanida Co. DOCUMENT No: HFY3-3385-PIP-FDC-0001 DATE: 29.01.2018
REFERENCE HFY3-3385-PIP-DWG-0002_0 Water supply pipeline routing plan

Due to the limited quantity of GRE pipes for the ditch water supply & in order to be insure
that all parts of east side ditch can be filled by water, We suggest to extend the GRE pipe in
DESCRIPTION
east side of CPF1 by using 650 m UPVC pipes DN 150 as highlighted in the attached design
drawings.

DISCIPLINE □ Water Supply & Drainage=WSD REASON DUE TO


□ Process=PRO □ Pipeline=PPL □ Plot Plan Changed
□ Civil=CIV □ Electrical=ELE □ P&ID Changed
□ Mechanical=MEC □ Instrument =INT □ Specifications Changed
 Piping=PIP □ Telecommunication=TEL □ Field Condition Changed
□ Cathodic Protection=CP □ Heating ventilating and air conditioning □ Other
□ Architecture=ARC =HVA
□Safety = SAF

ACTION PROPOSED To insure that all parts of east side ditch can be filled by water

Material if required is available If answer is No then provide MTO to EPC Procurement


Yes
in stock? team

If impact to schedule? No Add/Reduce Days (if answer is Yes)

If impact to project budget? No Add/Reduce $ (if answer is Yes)


Originator Field Engineer Site Manager

Signature

Name Zain Al Abdeen Abdul Razzaq A. Ahmed Khamil

Position QA/QC Engineer Construction Engineer Site Manager

PMC/PMT FIELD&ENGINEERING RESPONSE TO THE REQUEST – PART 02

PMC/PMT Response:
Indicate Potential Impact:
- The FDC is accepted.
- CONTRACTOR to use the 150 rating at least, and granted the proper connection between the GRE and UPVC
at the tie-in point.
- The change shall be marked and updated in the as-built stage.

SOW Change , Cost , Schedule, Re-Hazop (if Yes, need Project Change Order Request (additional Cost or Reduction Cost)

Template No. HFY-PMT-GEN-TMP-0004_Rev. 1 Issue Date : 03/09/2016


Halfaya Oil Field Surface Facility

PetroChina Phase : III Page 2 / 2


Halfaya
FIELD DESIGN CHANGE FORM (FDC)
Accepted Accepted with attached information/resolution
Decision
Not Accepted

PMC
Engineer
PMC Engineering Manager F/ PMC Project Manager

Signature    
 

Name Khalid Sir Khalid Elsir Khalid Khalid Elsir Khalid


Date Feb.2nd 018 Feb.2nd 018 Feb.2nd 018

*(NOTE): Field Engineer at Site to capture the accepted changes on latest IFC document for as built marking.

Team Leader GES Contractor (If required)

Signature Zhang Jie


Name

Date Feb.2nd 018

Template No. HFY-PMT-GEN-TMP-0004_Rev. 1 Issue Date : 03/09/2016


18/07/2017

490 ML

120 ML

1200 ML

ISSUED FOR CONSTRUCTION


ISSUED FOR CONSTRUCTION