Beruflich Dokumente
Kultur Dokumente
…. Respondents
ORDER
(Passed on 29/09/2014)
Agreement from CSPGCL on the basis of monthly meter reading of the actual
energy injected into the grid. Fixed cost and energy charges are billed without
applying ABT and deviations from schedule is also not taken into
consideration.
Page 1 of 8
National Electricity Policy states as under:
“The ABT regime introduced by CERC at the national level has had a
experiencing deficits. SERCs are advised to introduce the ABT regime at the
fixed charges for peak and off peak hours for better management of load.”
has to implement the intra state ABT along with DSM in Chhattisgarh state.
Deviations for entities of the State supplying power under interstate open
owned power utilities along with SLDC were directed to start mock billing in
mock billing, the utilities had raised various difficulties being faced .The
Page 2 of 8
Commission convened various meetings between CSPGCL, CSPTCL, CSPDCL
and SLDC and issued suitable directions from time to time. It is pertinent to
4. While monitoring the mock billing for DSM billing, Commission has
observed that even after elapse of more than 3 years when first directive
were issued for mock billing, CSPGCL has requested to continue mock billing
as per ABT and DSM for some more period. But the suggestions of CSPGCL
cannot be agreed upon as sufficient time has been given to CSPGCL before
the same on 13th Aug 2014 as petition no. 36 of 2014. A notice for inviting
Haribhoomi, Deshbandhu and Hitvada. Above notice was also uploaded in the
Suggestions and comments were invited from all stake-holders including State
6. M/s CSPGCL, M/s CSPDCL and M/s SLDC have submitted their written
Page 3 of 8
8. CSPDCL vide letter no 1623 dated 07/08/2014 submitted that as per
CSPDCL further stated that in case when grid frequency is more than 50.1 Hz
liable to pay compensation @ Rs.1.78 for the entire under drawl quantum
down process and many times it happens that it takes too much time for
backing down. Consequent upon, CSPDCL has to pay penal charges mostly in
9. As CSPDCL meet its major power requirement from State owned power
company i.e. CSPGCL, it is felt necessary that for maintaining grid discipline,
ABT and DSM should be implemented in the State for supplied by CSPGCL.
Looking to the urgency of the matter, Commission has decided to adopt the
Mechanism and related matters) Regulation 2014 (here in after called “DSM
DSM settlement with effect from 1st October 2014 on the power purchased
10. In view of the above facts, Commission decides that CSPGCL shall raise
monthly bill of capacity charge and energy charge for thermal generating
Page 4 of 8
for determination of Expected revenue from Tariff and Charges) Regulations,
2012” except for 1X500 Korba west extension plant. Approved annual fix
charges as specified in Table 241 of Tariff Order 2013-14 for FY 2014-15 shall
applicable as specified in Table 242 of above tariff order. Deviations from the
Mechanism (APM) as fuel, Commission has decided not to apply any cap rate
as specified at Clause 5 (1) (i) of DSM regulation 2014 because of the reason
drawl pattern of CSPDCL for the power drawn by it from the regional grid and
the fact that CSPGCL is a regulated entity but at this stage, it does not
appear reasonable to apply cap rate for CSPGCL’s thermal stations. ABT
12. Commission is aware that sent out energy of DSPM plant is not metered
one but the same is being calculated from the different meters reading. In this
directs CSPGCL to install ABT meters as per CEA metering regulations 2006 by
March 2015 so that sent out energy of DSPM may be taken directly from the
Page 5 of 8
13. SLDC shall prepare a statement of Charges for Deviations including
14. As the Commission has approved single part tariff for 1X500MW Korba
extension so to implement ABT and DSM on this plant, Commission shall issue
separate direction/order.
15. At present, FCA for CSPGCL power stations are being calculated on
16. Commission makes a provision that CSPGCL and CSPDCL shall have 7
days time to make any representation to SLDC to point out any discrepancy in
17. Commission directs the CSPGCL to provide the data downloaded from SEM
by 3rd day of the next month in the format (protocol) which is appropriate for
shall maintain the connectivity for online transmission of meter reading data
in the format as mentioned above through AMR to SLDC so that SLDC may
use this data as back-up for cross check of the data and to acquire data of
18. For preparation of DSM Statement, the SLDC shall consider Implemented
schedule as available SLDC websites. SLDC shall be responsible for timely (as
Page 6 of 8
per Grid Code) updation and uploading of the implemented schedule in the
SLDC website.
19. For preparation of DSM Statement, the SLDC shall consider frequency as
20. It has to be noted that CSPGCL power stations are regulated and are
Commission decides that SLDC shall prepare bill for deviations at 100% rate
21. Accepting the suggestion of SLDC, Commission decides that to avoid any
error, before processing of the DSM bill, SLDC shall again obtain confirmation
CSPGCL. CSPGCL shall the required confirmation within 2 working days from
22. SLDC shall prepare DSM bill within 3 working days after the receipt of all
requisite data from CSPGCL as above. Further SLDC shall issue the DSM bill to
CSPGCL and CSPDCL both in hardcopy and softcopy. The DSM bill shall be
made available in the SLDC website immediately after issue of bill. Any
thermal power stations shall be adjusted in the monthly power purchase bill of
additional orders or directions which may deem fit for removing difficulties to
Page 7 of 8
give effect to this order and directions. Commission shall review the impact of
Sd/- Sd/-
(Vinod Shrivastava) (Narayan Singh)
Member Chairman
Page 8 of 8