Sie sind auf Seite 1von 60

J. Indian Water Resour. Soc.

of
Journal Vol.Indian
30 No.Water
1, January, 2010
Resources
Society Vol. 30 No. 1, January, 2010

PROTECTION OF BRIDGE ABUTMENTS FROM SCOUR

V. K. Sarda

ABSTRACT

The failure of bridges due to excessive abutment scour causes high maintenance cost or
even the bridge collapse resulting in interruption of traffic as well as casualties to life. Hence
ability to protect bridge abutment from scour is critical to bridge safety. Review showed that there
are two approaches to scour mitigation viz. bank hardening and flow-altering. Selection of a
countermeasure involves life cycle cost assessment for the particular site along with social and
environmental issues. However, their application for mobile bed and in compound channels is
still to be established.

Key Words : Abutments; Scour protection; Scour countermeasures; Riprap; Spur dyke; Parallel
Walls; Collars; Cable-tied blocks; Geo-bags.

INTRODUCTION In spite of this, the scour at bridge abutments has


received less attention, and countermeasures for
Bridge failures due to local scour at bridge abutment scour are greatly needed.
foundations (i.e., bridge abutments and piers) have
heightened interest in scour prediction and scour BRIDGE ABUTMENT SCOUR MECHANISM
countermeasures.
The general scour mechanism at piers is well
Pier scour and pier scour countermeasures have understood after several comprehensive studies (Ettema,
been studied by Ettema (1980), Jones (1989), Johnson 1980; Kumar, 1998; Melville (1975), in which the
(1994), Richardson and Lagase (1999), Mueller and combined action of down flow and the horse shoe
Landers (1999) and Lagasse et. Al. (2001).On the other vortices and the wake vortices induced by the presence
hand, an extensive review, recommendations and design of the pier have been found to be responsible for the
suggestions for a number of bridge protection devices scour around the pier.
are available in Kumar (1998) and Parker et.al. (1998).
Also several comprehensive technical manuals [Federal Recent studies by Wong (1982), Tey (1984), Kwan
Highway Administration] (HEC-18, HEC-20 and HEC- (1984, 1988), Kandasamy (1985) and Dongol (1994) of
23) for dealing with the problem of bridge scour and its abutment scour have shown that the scour mechanism
protection are in the market. at abutments is very similar to the scour mechanism at
piers. The downflow and the principal vortex at the
Literature and data showed that the problem of upstream corner of the abutment, together with the
scouring at bridge abutments is quite significant. A study secondary vortices and wake vortices at the middle part
(Richardson and Abed, 1993) carried out in 1973 for and the downstream corner of the abutment, result in
the U.S. Federal Highway Administration concluded that complex interactions between the fluids and the bed
of the 383 bridge failures, 25% involved pier damage material to cause scour at abutments. Observations of
and 72% involved abutment damage. On the other hand, flow patterns around abutments derived from flow
of the 108 bridge failures surveyed in New Zealand visualization techniques using dye injection, dye crystals
during the period of 1960 - 1984, 29 were attributed to strategically placed on the sand bed, paper floats, smoke
abutment scour (Melville, 1992). It was also mentioned tunnel experiments by Liu et al. (1961) and Gill (1972)
in this study that 70% of the expenditure on bridge are summarized in Figure 1.
failures in New Zealand was due to abutment scour.
In addition to the vortex systems, seepage effects
Life Member, Principal, North West Institute of Technology, Dhudike,
Dist. Moga (Punjab)
have been found (Hagerty and Parola, 1992) to be very
Paper No. 1193(f)

1
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

important to interact with turbulent vortices to aggravate SCOUR PROTECTION DEVICES FOR
local scour. The fluctuating pressure differences, ABUTMENTS
induced by the flow separation at abutments, cause
seepage into and out of the abutment foundation. This The successful countermeasures for local scour at
results in ejection of sediment particles from the bed abutments work by either diverging the erosive flow
where seepage emerges beside the abutment. away from the structure and are called flow altering
countermeasures or making the area around the
abutment more resistant to erosion which are called
bank hardening countermeasures
In HEC-23 (Lagasse et al. 1997), a countermeasure
matrix has been organized to highlight the various groups
of countermeasures and to identify their individual
characteristics. These countermeasures have been
organized into groups based on their functionality with
respect to scour and stream instability.
Fig. 1 Flow pattern around an abutment
Flow Altering Countermeasures
On the other hand, Molinas et al.(1988)
experimentally studied the shear stress distribution They reduce flow’s energy to scour.
around vertical wall abutments. It was found that for
Spur dykes
Froude numbers ranging from 0.30 to 0.90 and for
protrusion ratios of 0.1, 0.2 and 0.3, the highest values Spur dykes have been studied intensively by Lacey
of shear stresses occurred at the upstream abutment (1929), Inglis (1949), Laursen (1952, 1962), Garde et
corner. In this study, shear stresses around vertical wall al. (1961), Gill (1970), Cunha (1973), Franco (1982),
abutments were found to be amplified up to a factor of Copeland (1983), Rajaratnam and Nwachukwu (1983),
10 depending upon flow conditions and abutment Zaghloul (1983), Brown (1985), Suzuki et al. (1987),
protrusion ratios. It was also found that shear stress Kwan and Chaudhary (1992), Wu and Lim (1993),
amplification due to local effects at the nose region of a Mayerle (1995), Shields et al. (1995), Tominaga et al.
vertical wall is a function of the opening ratio and turning (1997), Zhang and Du (1997), Soliman et al. (1997) and
angle. Shear stress amplification due to channel Kuhnle et al. (1997, 1998, 1999), as river training or
restrictions, on the other hand, were found to be a river rehabilitation structures instead of abutment scour
function of opening ratio, approach Froude number, and countermeasures. Spur dike length, alignment with flow,
protrusion length. The formulas for estimating shear flow structure around spur dykes, construction materials
stress amplification due to local effects at the nose region and many other parameters have been investigated.
of vertical wall abutments and for estimating shear stress Scour depth predictors around spur dykes and spur dyke
amplification due to channel restriction were also design guide lines have also been provided.
proposed. The sum of the two shear stress amplifications
equals the total nose shear stress amplification. Spur dykes are used to alter flow direction, induce
deposition, or reduce flow velocity [Fig. 2]. Their main
In a study by Ahmad and Rajaratnam (2000) for use is to protect banks that contain bridge abutments
flow around a 45° wing-wall bridge abutment, it was from eroding. Spur dykes are commonly used to realign
found that the approach flow turns into a complex 3D streams as they approach a bridge abutment. A bridge
skewed flow in the upstream and surrounding regions abutment may be in danger of being severely eroded
of the abutment. The bed shear stress was found to when it is subjected to high velocity flow from a channel
increase substantially near the abutment, reaching a that has changed course due to meandering of the
peak value of   o  3.63 at the abutment nose, with  channel. Spur dykes may also be used to establish and
and  o being the shear stress and the approach shear maintain the alignment of a channel. They have been
stress at the bed respectively. It was also found that used to decrease the length of the bridge required and
the skewing of the flow around the bridge abutment is reduce the cost and, maintenance of the bridge in
greater than flow around bridge piers. actively migrating braided channels (Lagasse et al.,
2001).

2
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

Fig. 2 Definition Sketch of a spur dyke Fig. 3 Parrallel wall (Guide banks) countermeasure

Liu et al. (1961) conducted clear water and live- and Blodgett (1978), Smith (1984), Richardson and
bed laboratory experiments on a compound channel using Simons (1984) and Lagasse et al. (2001) have studied
spur dykes as scour protection device. It was found guide bank orientation, length, crest height, shape and
that spur dykes can efficiently protect the abutment size, downstream extent and many other concerns.
provided they are properly designed. Design guidelines
were also discussed. The most effective configuration Design guidelines for guide banks have been
to prevent local scour at the abutment consisted of three provided by Neil (1973), Bradley (1978), Ministry of
spur dykes composed of rock located upstream of the Work and Development (1979), Central Board of
abutment and two at the corners. Irrigation and Power (1989) and Lagasse et al. (1996).
Guide banks provide a smooth transition for flow on the
Hard Points floodplain to the main channel. The effectiveness of
guide banks is a function of river geometry, quantity of
HEC-23 (Lagasse et al., 2001) has proposed hard flow on the floodplain, and size of bridge opening
points as one of the scour protection countermeasures. (Richardson and Simons, 1984). By establishing smooth
They consist of stone fills spaced along an eroding bank parallel streamlines in the approaching flow, guide banks
line, protruding only short distances into the channel. A improve flow conditions in the bridge waterway. Scour,
root section extends landward to preclude flanking. if any, is near the upstream end of the guide bank away
Hardpoints are most effective along straight or relatively from the bridge.
flat convex banks where the streamlines are parallel to
the bank lines and velocities are not greater than 3 m/s Guide banks can protect not only bridge abutments
within 15 m of the bank line. Hardpoints may be from local scour, but also the approach embankment
appropriate for use in long, straight reaches where bank because of the still water area behind it. When
erosion occurs mainly from a wandering thalweg at embankments span wide floodplains, the flows from high
lower flow rate. They would not be effective in halting waters must be aligned to flow smoothly through the
or reversing bank erosion in a meander bend unless bridge opening. Overbank flows on the floodplain can
they were closely spaced, in which case spurs, retarder severely erode the approach embankment and could
structures, or bank revetment would probably cost less increase the depth of the scour at the bridge abutment.
(HEC-23). They can be used to redirect the flow from the
embankment and to transfer the scour away from the
Guide banks or Parallel Walls
abutment. They also serve to reduce the separation of
Guide banks are earth or rock embankments placed flow at the upstream abutment face and maximize the
at abutments to improve the flow alignment and move total bridge waterway area and reduce the abutment
the local scour away from the embankment and bridge scour by lessening the turbulence at the abutment face
abutment [Fig. 3]. The major use of guide banks has (Lagasse et al., 2001)
been to prevent erosion by eddy action at bridge There are practically two kinds of guide banks. One
abutments or piers where concentrated flood flow is the American practice, which is to give guide banks
traveling along the upstream side of an approach an elliptical form convergent to the opening, whereas
embankment enters the main flow at the bridge (HEC- the other one used in Pakistan and India gives that guide
23). Spring (1903), Neil (1973), Bradley (1978), Brice banks should be straight and parallel to the opening with

3
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

a curved section at the upstream and downstream ends. Bank Hardening Countermeasures
Parallel guide banks straighten the flow more effectively
than convergent ones (Richardson and Simon, 1984). They comprised of various hard materials located
on the bed and banks in the vicinity of abutment to
Properly designed guide banks and abutment riprap increase the ability of the bed and bank to resist scour
provide an acceptable alternative to designing bridge by flow.
abutments to withstand the development of the full scour
prism predicted by equations currently available for Riprap
estimating abutment scour (Hua et al., 2006). Since they Riprap is the most common countermeasure
have excellent performance in the field, guide banks employed and consists of large rocks arranged flush
should be given serious considerations as scour with the bed and banks in several layers of thickness. A
protection device for abutment scour when developing number of researchers like Simons and Lewis (1971),
plans for repair or replacement of those endangered Lewis (1972), Mackey (1986), Simons and Li (1989),
bridges. They can eliminate many scour problems Croad (1989), Pagan-Ortiz (1991) and Eve (1999) have
associated with bridge crossings and their use can result conducted research on the performance of riprap
in a worthwhile savings to the highway program (Hua protection on abutment slopes and aprons under clear-
et al., 2006). water conditions while Melville et al. (2006) studied the
same under live bed conditions. In these studies, failure
Collars of riprap beds has been observed due to (a) dislodging
Collar is a protection device that has been found to of the individual rocks due to excessive stream velocity,
be helpful for arresting scour around bridge pier. (b) dislodging of individual rocks at the edge of the riprap
Basically it is a piece of circular shaped steel plate blanket due to the flow undermining and lifting the rocks
attached around the abutment [Fig. 4] sitting horizontally up and into direct contact with the flow, and (c) sinking
a short distance from the bed. Much literature on of the riprap blanket due to winnowing of the fine bed
material up through the rocks where it is carried away
attachment of collars on abutment, as scour protection,
by the flow [Fig. 5].
is not available. However, Liu et al (1961) studied flat
horizontal steel collars around wing-wall abutment
ending at the mean channel under clear water flow
conditions in a laboratory flume. It was found that these
collars were able to protect the bridge abutment
efficiently by eliminating secondary vortices that
ordinarily would cause local scour. The minimum collar
dimensions that eliminated local scour were 0.7L  0.23L
[where L is abutment length perpendicular to flow
direction] provided at 0.08y [y is the mean channel flow
depth] below the mean sediment elevation gave the test Fig. 5 Riprap at abutment
results of scour reduction. They also retarded the
development of scour hole. Design consists of the specification of the rock size
to avoid direct dislodging, riprap blanket thickness, the
lateral extent of the blanket to avoid edge failure, the
gradation of riprap, and a filter material to avoid
winnowing of the fines. The size of riprap stone can be
determined from (Pagan-Ortiz, 1991):

0.81
 1.064U 2 y 0.23 
D50    (1)
 S s  1g 

Here D50 is the median riprap size, U is the cross-


sectionally averaged water velocity, Ss is the specific
Fig. 4 Collar device at abutment

4
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

gravity of the riprap material, and g is the gravitational include Parker et al. (1998), Jones et al. (1995), Hoe
constant. (2001), Cheung (2002) and Melville et al. (2006). Three
possible failure mechanisms for cable-tied blocks used
The thickness of the riprap blanket, t = 1.5D100 , as scour protection at bridge piers were identified
where D100 is the largest size of the rip rap stone (Parker et al., 1998). These are overturning and rolling
(Lagasse et al., 2001). The lateral extent of the riprap up of the leading edge, uplift of the center of the mat,
blanket can be found form: and winnowing of sediment between the mat and the
Wmin  C1 d s  d b  D50  (2) bridge pier. The latter is more likely if the mat is not
sealed tightly to the pier, or wing wall. Anchoring of the
Here, Wmin is the minimum riprap blanket extent leading edge of the mat is important to prevent
across the channel, C1 is constant equal to 1.68 and overturning and rolling up.
1.19 at the upstream and downstream comers of the
Design issues include primarily the block size, lateral
riprap layer, respectively, ds is the depth of equilibrium
extent, and edge treatment. Block size can be estimated
scour, and db is the depth of the riprap blanket bottom
by the following equation:
below the average channel bed level (Fig. 5). ds can be
found for bedform-dominated cases by: Hb  a cb   2
   Fr (4)
d s  C2 H (3) y   cb   1  p  
Here H is maximum bed-form height and C2 is a Here, Hb is the height of the block, y is the flow
constant values for which are 1.2 and 1.0 for the depth, acb is a constant equal to 0.1,  cb is the block
upstream and downstream comers of the riprap layer, density,  is the fluid density, and Fr is the Froude
respectively (Melville et al., 2006). Otherwise, add other Number.
scour components to ds. The proper gradation of riprap
can be found Table 1. CTB blocks are typically manufactured as a
truncated pyramid shape with a square base and top.
Table 1. Riprap gradation for abutment protection
The spacing between CTB units should be adequate to
Stone Size Percentage of allow the mattress to have a sufficient degree of
Range gradation smaller than flexibility, and that block shape should not inhibit mat
1.5D50 to 1.7D50 100 flexibility. Typically, synthetic filters are used beneath
1.2D50 to 1.4D50 85
CTB mats. Lateral extent of the cable-tied block
1.0D50 to 1.1D50 50
0.4D50 to 0.6D50 15
mattress can be determined from:

To design the filter material the pore space should W = 1.55(ds -db)
be finer than the natural riverbed material. (5)

Cable-tied Blocks Here W is the apron width, ds is the scour depth (=


mat settlement depth) at the outer edge of the mat, and
Cable-tied block consist of a series of blocks linked db is the placement (burial) depth of the mat [Fig. 6].
together with cable to hold them together as a coherent
mat. Where riprap of adequate size is unavailable or
where environmental or geometric constraints preclude
use of riprap, alternatives to riprap, such as cable-tied
blocks, are necessary.
Cable-tied blocks (CTB) comprise concrete blocks
interconnected with metal or non-metallic cables
(Prezedwojski et al., 1995). CTB have the advantages
of ease of construction, minimal encroachment into the
river channel, and a lower weight than riprap per unit
area covered. Previous studies and experiments on the
Fig. 6 Cable tied blocks at abutment
use of CTB for scour protection of bridge foundations

5
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

To prevent the uplifting of the leading edge of the However, as long as the primary objectives are achieved
mat, the size can be determined from in the short-term as a result of countermeasure
installation, the countermeasure installation can be
H b  158  2 n 2 deemed a success (HEC-23). Therefore, to achieve
  Fr 0.33 (6) long-term protection, maintenance, reconstruction, and
y  S cb  1  y installation of additional countermeasures as the
responses of streams and rivers to natural and man-
Here Scb is the specific gravity of the blocks and n induced changes is needed.
is the Manning coefficient. Care needs to be taken to
ensure that the leading edge of the mat remains buried. Among armouring countermeasures, riprap and
cable tied blocks are of the most interest by hydraulic
Geobags engineers. These two countermeasures have been
Geobags are bags of pervious material that are filled investigated by various researchers as erosion control
with a pervious granular material (sand or gravel) that devices and bank revetments.
are used as bank hardening elements, thereby possessing However, all these countermeasures are needed to
enough weight to hold sediment in place, but allowing be tested for oblique flow, for their effectiveness in
the flow of water through them to reduce uplifting cohesive soil and stratified beds. Also no working
pressure to reduce the likelihood of uplifting of the bag relationship for determination of maximum scour depth
or winnowing of the fines underneath. The bag material with any of the above countermeasures on abutment,
can be a geosynthetic fabric such as the filter layer of over a wide range of flow conditions and geometries is
riprap discussed above. Design considerations include available. In addition, information on temporal variation
sizing, linking of bags, angle of placement and placement of scour and location of deepest scour point in the flow
extent (Korkut et al., 2006). past abutments using most of these countermeasures is
Minimum size can be determined by that of still lacking.
equivalent riprap as mentioned above. The individual REFERENCES
bags should be tied together to help them function as a
single mattress thereby allowing flexibility to conform 1. Ahmed, F and Rajaratnam, N.2000. Observations on
to the irregular bed shape. The geobag mattress should flow around an abutment. J. Engineering Mechanics,
have a maximum slope of 2H: 1 V with a toe extending ASCE, 125 (1) 51-59.
a downward length equal to at least 2 bags into the 2. Bradley, J. N. 1978. Hydraulics of Bridge Waterways.
riverbed. Hydraulic Design Series No.1, U.S. Dept.
Transportation, Federal Highway Administration, 2nd
CONCLUSIONS Ed., Washington, D.C.
Although many studies have been carried out for 3. Brice, J. C. and Blodgett, J. C. 1978. Countermeasures
each of these countermeasures, there is still need for for hydraulic problems at bridges. Federal Highway
Administration, Report FHW A-RD- 78-162 and Report
further studies of their use in protecting bridge
FHW A-RD- 78-163.
abutments. For instance, spur dikes have not specifically
been tested and used for abutment protection. Guide 4. Brown, S. A. 1985. Design of spur-type stream bank
banks have been tested and used for spill-through stabilization structures. Final Report. FHWA/RD-84-
abutments on rivers with wide floodplains or rectangular 101, Federal Highway Administration, Washington, DC.
channel only. For small country bridges with wing-wall 5. Central Board of Irrigation and Power. 1989. River
abutments terminating on the main channel bank, studies behavior management and training. Edited by C. V.J.
are still needed. In addition, there are many controversial Verma, K.R Saxena and M.K. Rao, Publication No. 204,
design guidelines and small design issues that need to Vol. 1, Central Board of Irrigation and Power, New
Delhi, India, pp. 469.
be clarified. Collars have been tested for pier scour
protection rather than for abutment protection. 6. Cheung, K. M.2002. Cable-tied blocks as a
countermeasure. ME thesis, Civil and Environmental
Countermeasures are often damaged or destroyed Engg Dept., The Univ. of Auckland, Auckland, New
by the stream, and stream banks and beds often erode Zealand.
at locations where no countermeasure was installed.

6
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

7. Copeland, R. R. 1983. Bank protection techniques using 21. Jones, J. S. 1989. Laboratory Studies of the Effect of
spur dykes. Hydraulics Laboratory, U. S. Army Footings and Pile Groups on Bridge Pier Scour. Proc.
Waterways Experiment Station, Vicksburg, Mississippi, of 1989 Bridge Scour Symposium, FHW A, Washington,
USA. D.C.
8. Croad, R. N. 1989. Investigation of the pre-excavation 22. Jones, J. S., Bertoldi, D. A. and Stein, S. 1995.
of the abutment scour hole at bridge abutments. Rep. Alternative scour countermeasures.” Proc. Hydraulic
No. 89-A9303, Central Laboratories, Works and Engineering ‘95, ASCE, New York, pp.1819-1823.
Development Services Corporation (NZ) Ltd., Lower 23. Johnson, P. A. 1994. Quantification of bridge pier scour
Hutt, New Zealand. uncertainty. Machine Intelligence and Pattern
9. Cunha, L. Veigda. 1973. Discussion on “Erosion of Recognition, 17, 407.
Sand Bed around Spur Dikes.” Journal Hydraulic
24. Kandasarny, J. K. 1985. Local scour at skewed
Division, ASCE, Vol. 98, No. HY9.
abutments. School of Engineering, Report No. 375,
10. Dongol, D.M.S. 1994. Local scour at bridge abutments. University of Auckland.
Report No. 544, University of Auckland, School of 25. Kandasamy, J. K. 1989. Abutment scour. Rep. No. 458,
Technical Engineering, Department of Civil School of Engrg., University of Auckland, Auckland,
Engineering Private Bag, Auckland, New Zealand. New Zealand.
11. Ettema, R. 1980. Scour at bridge piers. Ph. D thesis,
26. Khan, K. W. and M. H. Chaudhry, M. H. 1992. Numerical
University of Auckland, Department of Civil
Modeling of Flow around Spur Dykes. Proc. 4th Int.
Engineering, Report No. 216.
Conference of Hydraulic Engineering Software
12. Eve, N. J. 1999. Riprap protection of bridge abutments. HYDROSOFT/92, pp 223.
ME thesis, Civil and Resource Engineering Dept., The
27. Kuhnle, R. A., Alonso, C.V. and Shields, F.D. 1997.
Univ. of Auckland, Auckland, New Zealand.
Volume of scour holes associated with spur dikes. Proc.
13. Franco, J. J. 1982. Summary report: model-prototype 27th Cong. Int. Assoc. Hydraulic Research Part: B-1,
comparison study of dyke systems. Mississippi River. pp. 418.
U.S. Army Engineer Waterways Experiment Station, 28. Kuhnle, R. A., Alonso, C.V. and Shields, F.D. 1998.
Vicksburg, Mississippi, Technical Report HL-82-11, 55. Volume of scour holes associated with spur dikes. Proc.
14. Garde, R. J., Subramanya, K. and Nambudripad, K. D. 1998 Int. Water Resources Engg. Conf. Part 2 (of 2) v 2,
1981. Study of scour around spur dykes. Journal of the ASCE, pp.1613.
Hydraulics Division, ASCE, 87(HY6), 23-37. 29. Kuhnle, R. A., Alonso, C.V. and Shields, F.D. 1999.
15. Gill, M. A. 1970. Bed erosion around obstructions in Geometry of scour holes associated with 90-degree spur
rivers. Ph.D thesis, The University of London (Imperial dikes. J. Hydraulic Engg., 125 (9), 972.
College of Science and Technology).
30. Kumar, V. 1998. Effect of Down-flow on Scour around
16. Gill, M. A. 1972. Erosion of sand beds around spur Bridge Pier. J. of The Institution of Engineers (India),
dikes. Journal of Hydraulics Division, 98(HY9), 1587- Vol. 79, May, pp 41-47.
1602.
31. Korkut, R., Martinez, E. J., Ettema, R. and Barkdoll,
17. Hagerty, D. A. and Parola, A. C. 1992. Seepage Brian. 2006. Geobag performance as scour
influence on stability of bridge abutments. Conf. Proc. countermeasure for wing wall abutments. J. Hydraulic
Hydraulic Engg. ASCE, pp. 900. Engg., ASCE.
18. Hoe, D. A. 2001. Cable-tied block protection of bridge 32. Kwan, F. 1984. Study of Abutment Scour. Report No.
abutments. Project Rep. No. PCRE 01: 18, Dept. of Civil 328, University of Auckland, School of Engineering,
and Resource Engineering, Univ. of Auckland, Department of Civil Engineering Private Bag,
Auckland, New Zealand. Auckland, New Zealand.
19. Hua, L., Kuhnle, R. A.and Barkdoll, B. D. 2006. 33. Kwan, F. 1988. Study of Abutment Scour. Report No.
Countermeasures against scour at abutments. National 451, University of Auckland, School of Engineering,
Sedimentation Laboratory, Rep. No. 49, USDA, Department of Civil Engineering Private Bag,
Mississippi, Jan. Auckland, New Zealand.
20. Inglis, C. C. 1949. The behavior and control of rivers 34. Lacey, G.1929. Stable channel in Alluvium. J. of
and canals. Research Publication No. 13, Parts I and Institution of Engineers, Paper No. 4736, Vol. 229.
II, Central Waterpower Irrigation and Navigation
35. Laggasse, P.F., Richardson, E.V. Zevenbergen, L. W.
Research Station, Poona, India.
1996. Design of guide banks for Bridge Abutment

7
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

Protection. Proc. North American Water and 49. Mueller, D. S. and M. N. Landers, M. N. 1999. Portable
Environment Congress and Destructive Water, ASCE, Instrumentation for Real-Time Measurement of Scour
New York, pp. 4188-4197. at Bridges. Federal Highway Administration
36. Lagasse, P. F., Zevenbergen, L.W., Schall, J. D. and Publication No. FHW A-RD-99-085 (FHW A approval
Clopper, P. E. . 2001. Bridge Scour and Stream pending), Turner-Fairbank Highway Research Center,
Instability Countermeasures. Publication No. FHWA McLean, VA.
NHI 01-003, Hydraulic Engineering Circular No. 23, 50. Neil, C. R. 1973. Guide to bridge hydraulics. Roads
U. S. Department of Transportation, Federal Highway and Transportation Assoc. of Canada, Univ. of Toronto
Administration. pp. 2.7, 2.9, 4.6, 6.16, 6.18, Design Press, Toronto, Canada.
Guidelines 1, 9, 10. 51. Pagan-Ortiz, J. E.1991. Stability of rock riprap for
37. Laursen, E. M. 1952. Observation on the nature of scour. protection at the toes of abutment located at the flood
Proc. 5th Hydraulics Conference, Iowa. plain. Rep. No. FHWA-RD-91-057, Federal Highway
Administration, U. S. Dept. of Transportation,
38. Laursen, E.M. 1962. Discussion of “Study of scour
Washington, D.C.
around spur dikes. Journal of the Hydraulics Division,
ASCE, 89(HY3), 225-228. 52. Parker, G., C. Toro-Escobar, C. and Voigt Jr., R. L. 1998.
39. Lewis, G. L.1972. Riprap protection of bridge footings. Countermeasures to protect bridge piers from scour.
Doctor of Philosophy thesis, Colorado State Univ., Fort Final Report (Project NCHRP 24-7) prepared for
National Co-operative Highway Research Program,
Collins, Colo.
University of Minnesota, Minneapolis, Minnesota,
40. Liu, M. K., Chang, F. M. and Skinner, M. M.1961. Effect U.S.A., pp. 402.
of bridge construction on scour and backwater. Report
53. Przedwojski, B., Blazejeski, R. and Pilarczyk, K. W.
No. CER60-HKL22, Department of Civil Engineering,
1995. River training techniques. Balkema, Rotterdam,
Colorado State University, Fort Collins, Colorado.
The Netherlands.
41. Macky, G. H. 1986. Model testing of bridge abutment
54. Rajaratnam, N. and Nwachukwu, B. A. 1983. Erosion
scour protection. Rep. No. 3-86/12, Central
near groyne-like structures. Journal of Hydraulic
Laboratories, Ministry of Works and Development,
Research, IAHR, 21 (4), 277 - 287.
Lower Hutt, New Zealand.
42. Mayerle, R., Toro, F. M. and Wang, S. S. Y. 1995. 55. Richardson, E. V. and Abed, L. 1993. Top width of pier
Verification of a three-dimensional numerical model scour holes in free and pressure flow. Proc. Nat. Conf.
simulation of the flow in the vicinity of spur dikes. J. Hydraulic Engg. Part 1 (of 2), ASCE, July, pp. 25-30.
Hydraulic Research, 33 (2), 243. 56. Richardson, E. V. and Lagasse, P. F. 1999. Stream
43. Ministry of Works and Development.1979. Code of Stability and Scour at Highway Bridges. Compendium
practice for the design of bridge waterways. Civil of Papers ASCE Water Resources Engineering
Division Publication CDP 705/C, Ministry of Works Conferences 1991 to 1998.
and Development, Wellington, New Zealand, pp. 57. 57. Richardson, E. V. and Simons, D. V. 1984. Use of spurs
and guide banks for highway crossing. Proc.
44. Melville, B. W. 1975. Local scour at bridge sites. School
Transportation Research Record, 2 nd Bridge Engg.
of Engineering, Report No. 117, University of Auckland,
New Zealand. Conf. 2, 184.
58. Shields Jr., F. D. C., Cooper, C. M. and Knight. S. S.
45. Melville, B. W. 1992. Local Scour at Bridge Abutments.
1995. Experiment in stream restoration. J. of Hydraulic
Journal of Hydraulic Engineering, ASCE, Vol. 118,
Engg, 121 (6), 494-502.
No.4, April, pp. 615.
46. Melville, B.W., Ballegooy, S. Van, Coleman, S. and 59. Simons, D. B. and Lewis, G. L. 1971. Flood protection
Barkdoll, B. 2006. Scour countermeasures for wing at bridge crossings. C.S.U. Civil Engineering Rep. No.
wall abutments. J. of Hydraulic Engineering, ASCE, CER71-72DBS-GL10, prepared for the Wyoming State
132, (6), 563-574. Highway Dept. in conjunction with the U.S. Dept. of
Transportation, Washington, D.C.
47. Melville, B. W., van Ballegooy, R. and van Ballegooy, S.
2006. Flow induced failure of cable-tied blocks. J. 60. Simons, D. B. and Li, R. M. 1989. Sizing riprap for the
Hydraulic Eng., 132 (3), 235- 245. protection of approach embankments and spur dykes
and limiting the depth of scour at bridge piers and
48. Molinas, A., K., Kheireldin, K. and Wu Baosheng, Wu. abutments. Rep. No. FHWA-AZ- 89-260, Arizona Dept.
1988. Shear stress around vertical wall abutments. .J. of Transportation, Vol. 1, Pheonix.
Hydraulic Engg,, ASCE, 124 (8), 822.

8
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

61. Smith, C. D.1984. Scour Control at Outlook Bridge—a NOTATIONS


Case Study. Canadian Journal of Civil Engineering,
11 (4), 709-716. ac constant equal to 0.1
C1 constant equal to 1.68 and 1.19 at the upstream
62. Soliman, M. M. K., Atria, K.M. A., Kotb, A.M. Talaat
and Ahmed, A. F.1997. Spur dike effects on the river and downstream comers of the riprap layer,
Nile morphology after high Aswan dam. Proc., Congo respectively
Int. Assoc. Hydraulic Research, Part-V, pp. 805. C 2 constant the values for which are 1.2 and 1.0 for
the upstream and
63. Spring, F. J. E. 1903. River training and control of the
guide bank system. Technical Paper No. 153, Railway downstream comers of the riprap layer
Board, Government of India, New Delhi. db depth of the riprap blanket bottom below the
average channel bed level
64. Suzuki, K., Michiue, M. and Hinokidani, O. 1987. Local
ds depth of equilibrium scour
bed form around a series of spur dikes in alluvial
channel.” Proceedings 22nd Congress, IAHR Lausanne,
D 50 the median riprap size
Switzerland, pp. 316-321. D 100 largest size of the rip rap stone
Fr Froude Number.
65. Wong, W. H. 1982. Scour at Bridge Abutments. Report
g gravitational constant
No. 275, Dept. of Civil Engineering, University of
Auckland, Auckland, New Zealand.
H maximum bed-form height
H b height of the cable tied-block
66. Tey, C. B. 1984. Local scour at bridge abutments. Report L abutment length perpendicular to the flow direction
No. 329, University of Auckland, School of Engineering,
n Manning coefficient
Department of Civil Engineering, Private Bag,
Auckland, New Zealand.
p porosity of cable-tied blocks
Scb specific gravity of the blocks
67. Tominaga, A, Nagao, M. and Nezu, I. 1997. Flow S s specific gravity of the riprap material
structures and mixing processes around porous and t thickness of the riprap blanket
submerged spur dikes. Proc. 27th Congress of the Int.
U cross-sectionally averaged water velocity
Assoc. of Hydraulic Research. IAHR, Part B-1, pp. 251.
W apron width
68. Wu, X. and Lim, S.Y. 1993. Prediction of maximum scour Wmin minimum riprap blanket extent across the channel
depth at spur dykes with adaptive neural networks. y flow depth
Civil-Comp93, Part 3: Neural Networks and
 fluid density
Combinatorial Optimization in Civil and Structural
Engineering Civil-Comp93, pp. 61.  cb cable-tied block density
 shear stress at the bed
69. Zaghloul, N. A. 1983. Local scour around spur-dykes.  o approach shear stress
J. of Hydrology, 60, 123-140.
70. Zhang, Y. and Du, X.1997. Limited scour around spur
dyke and the evaluation of its depth. J. Xi’an Highway
Transportation University, 17 (4), 56.

9
J. Indian Water Resour. Soc.of
Journal Vol.Indian
30 No.Water
1, January, 2010
Resources
Society Vol. 30 No. 1, January, 2010

RAINFALL PATTERN IN NORTHERN KERALA

P. A. Lisha, P. K. Pradeep Kumar and K. V. Jayakumar

ABSTRACT

Available daily rainfall data for 81 years (1901 – 1969, 1990 – 1996 and 2001 – 2005) of
five stations Kannur, Kozhikode, Quilandy, Vythiri and Vadakara in northern Kerala have been
transformed into annual, southwest monsoon, northeast monsoon and non monsoon components
for each year and analyzed for a study of the rainfall behaviour. Regression analysis of south-
west monsoon rainfall and annual rainfall showed a variation in intercept from 734.60 to 1153.86
and in slope from 0.87 to 1.07 with standard error of estimate varies from 282.93 to 389.82.
Correlation analysis shows the variation in coefficient from 0.80 to 0.95. Maximum values of
annual and southwest monsoon rainfall yield a parallel behaviour. Average annual and south-
west monsoon rainfall values also yield a parallel behaviour. Overall southwest monsoon rain-
fall is 76.99% of annual rainfall in the area of study. The variation of annual and southwest
monsoon rainfall show a regular pattern in increase or decrease.

Key words: Kerala monsoons, Regression analysis, RFA, RFSWM, RFNEM, RFNM

INTRODUCTION Floods and landslides are a common occurrence


during the rainy seasons in Kerala. Heavy rains during
Kerala experiences rainfall for nearly nine months southwest monsoon period (June-September) and
in a year in the form of monsoon rain and northeast monsoon (October – December) result in
thudershowers. The fluctuation in annual rainfall of increased risk of high floods. Rivers in Kerala are
Kerala is much less than that compared with other parts generally narrow and short, which flow down from the
of the Indian sub-continent. The hills and mountains of Western Ghats through steep gorges and are therefore
the Western Ghats located on the eastern boundary of highly susceptible to flash floods which cause immense
the State provide orographic lifting for the southwest damage to the embankments, corps and cattle.
monsoon winds resulting in heavy precipitation over the Landslides give rise to blockages, snapping of
western slopes and good rain over midlands and low communications and damage to the property. It is
lands. The average annual rainfall of the State is 3500 essential to have a detailed knowledge on different
mm. The southwest monsoon (June-September) is the patterns of rainfall during different seasons at a
principal rainy season as the State receives about 70% particular region for various planning and execution
of its annual rainfall. Southwest monsoon rainfall as purposes. In that light, this particular study has been
percentage of annual rainfall decreases from north to carried out to know the different rainfall patterns at
south and varies from 83% in the northern most District five locations of northern Kerala. The outcome of the
of Kasargod to 50% at southern most District of analysis may help various developmental agencies in
Thiruvananthapuram. Northeast monsoon rainfall as their activities.
percentage of annual rainfall increases from north to
south and varies from 9% in northern most District of The interaction between topography and
Kasaragod to 27% in southern most District of meteorological elements involves several basic
Thiruvananthapuram. characteristics of any relief feature. The overall
dimensions and the orientation of a mountain range with
respect to prevailing winds are important for large scale
Centre for Water Resources Development and Management
P.O. Kunnamangalam, Kozhikode - 673 571, Kerala
processes, relative relief and terrain shape are
Paper No. 1228
10
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

particularly important on a regional scale, while slope by the mighty Himalayas, extending from north-west to
angle and aspect cause striking local differentiation of east. Besides, the Khasi and Jayantiya hills in the
climates. The effects that an orographic barrier northeast, the Vindhya and Satpura hills in central India,
produces on air motion depend first on the dimensional the Western Ghats running all along the west coast from
characteristics of the barrier – its height, length, width Maharashtra to Kerala and the broken hill ranges of
and the spacing between successive ridges – and, Eastern Ghats largely determine and guide the Country’s
second, on the properties of the airflow itself – the wind rainfall pattern during the summer as well as winter.
direction relative to the barrier, the vertical profiles of Isolated hill ranges like, the Aravalis and Nilgiris also
wind and of stability. Each of the three dimensions of a influence the rainfall occurrence in those areas.
mountain barrier interacts with a particular atmospheric
scale parameter (Smith, 1979). The air arriving at a Dhar et al (1978) carried out a study of the heavy
barrier must have sufficient kinetic energy in order to rainfall stations in India. For the purpose of the study,
rise over it against the force of gravity (Stringer, 1972). stations with mean annual rainfall of 500 cm were
considered as heavy rainfall stations. Some of the heavy
Cloud type in mountain areas is primarily determined rainfall stations lie in the Western Ghats and the rest
by air mass characteristics and is therefore related to are located in the hills of northeast India. There are,
the regional climate conditions. The spatial distribution however, none in the Himalayan region. There are some
of convective upcurrents in mountain regions shows stations in the Darjeeling hills with short period means
some pronounced effects of topography. There may over 500 cm. During the onset of the southwest
be strong contrasts between shaded and sunny slopes. monsoon, the moisture laden monsoon winds first
Fujita et al (1968) reported rapid cumulus build-up on approach the Western Ghats and the Khasi Jayantiya
the slope of Mt.Fuji between 0845 – 0915 hrs in July as hills and precipitate most of the moisture over these
the solar altitude increased from 47° to 53° and surface regions. By the time they approach the Himalayan
temperature on the rocky slopes exceeded 30° C. regions much of the moisture is lost and, therefore, the
Verma (1993) correlated the monsoon rainfall values less rainfall in these areas.
with the gridded surface air temperature over northern
hemisphere land at various time lags of months to identify Dhar and Bhattacharya (1976) made a study on
teleconnections of monsoon with the northern the variations of precipitation with elevation in the
hemisphere surface air temperature anomalies. As per Central Himalayas. A relationship between precipitation
the study, two regions in the higher latitudinal belt of and elevation was obtained for the Central Himalayas
40°N – 70°N over North America and Eurasia show using 15 to 20 years data of more than 50 stations.
positive correlations with temperatures during northern Variation of rainfall with the elevation showed that there
winter. The region located over northwest India and are two zones of maximum precipitation. One near the
adjoining Pakistan show maximum positive correlation foot of the Himalayas and other at an elevation of 2.0
during the pre-monsoon months of April and May. to 2.4 km. For higher elevations beyond 2.4 km the
These relationships suggest that cooler northern precipitation decreases sharply.
hemisphere during the proceeding seasons of winter/ Climatologically the onset of the southwest monsoon
spring over certain key regions are generally associated over extreme south Kerala is 1 st June. The onset,
with below normal summer monsoon rainfall over India however, can take place earlier or later and in some
and vice versa which could be useful for predictions years there are multiple onsets when the initial onset
for long – range forecasting of monsoon. takes place too early. Multiple onsets mean that there
Systematic and scientific studies on variation of is a recession of the monsoon after the initial onset and
precipitation with elevation are limited mainly because another onset of the current that to take place before it
of lack of sufficient information on the amount of gets established. Between 1901 and 1985, the earliest
precipitation at higher elevation. This is due to non - onset is 11th May in 1918 and 1955 while the most
availability of automated recording precipitation gauges delayed onset date is 18th June in 1972 (Menon and
and problem associated with measurement of Rajan, 1989). On 47 occasions out of 85 between 1901
precipitation at such higher elevation on a routine basis. and 1985, the onset has taken place between 29th May
Nearly 35% of the geographical area in India is and 7th June. During this period, the maximum number
mountainous. Of these nearly 58 % is accounted for of onset of southwest monsoon occurred on 1st June.

11
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

Ananthakrishnan et. al (1979), discussed in detail RFSWM - Southwest monsoon rainfall (June to
about the meteorology of Kerala. It is suggested that September)
the most outstanding feature of the meteorology of RFNEM - Northeast monsoon rainfall (October to
Kerala is the seasonal reversal of the wind circulation December)
which constitutes the summer and winter monsoons. RFNM - Non monsoon rainfall (January to May)
This seasonal reversal is linked with the seasonal
reversal of temperature and pressure gradients following RFSWM component has been obtained by adding
the apparent north-south movement of the Sun in the the rainfall values of the southwest monsoon months,
course of a year. The seasonal progressions of viz. June, July, August and September. RFNEM is the
temperature, pressure and winds at the surface and in total of the rainfall values of the northeast monsoon
the upper air are illustrated and the significant points months, viz. October, November and December. RFNM
high lighted. The rainfall time series of 75 rain recording component is the total rainfall values of non monsoon
stations over Kerala for the 80 year period 1901 to 1980 months, viz. January, February, March, April and May.
have been statistically examined by Soman et al (1988) All values of RFA, RFSWM, RFNEM and RFNM are
for long term trends. Application of Mann – Kendall given in mm.
rank statistic test to the time series of annual and
seasonal totals as well as extreme rainfall of 1,2,….,10
day durations revealed a significant decreasing trend in
the rainfall over the eastern high lands and adjacent
areas to the west. This finding is supported by the fact
that the mean rainfall for the second half of the period
is 10 to 20% lower than for the first half over the same
area.
STUDY AREA
Five stations, Kannur, Kozhikode, Quilandy, Vythiri
and Vadakara, in Northern Kerala (Fig.1) are selected
for the study. The locations of the stations in regard to
their respective latitude and longitude are given in Table
1.
Table 1 Details of the raingauge stations
Fig. 1 Locations of the selected raingauge stations on the relief
Sl.No. Name of station Latitude Longitude map of northern Kerala
1 Kannur 11° 52' 75° 22'
2 Kozhikode 11° 15' 75° 47' ANALYSIS
3 Quilandy 11° 27' 75° 42'
4 Vythiri 11° 33' 76° 02' RFSWM – RFA relationship
5 Vadakara 11° 36' 75° 35'
It is widely believed that the annual rainfall (RFA)
DATA of India, as a whole is a reflection of the total southwest
monsoon rainfall (RFSWM). On the average, the
Daily rainfall data of the five stations for 81 years RFSWM is around 77% of the RFA of the country. To
(i.e., 1901 to 1969, 1990 to 1996 and 2001 to 2005) examine this contention in Northern Kerala, the 81 year
have been made available for the present study. RFSWM – RFA data of each station is tested for
From these data, monthly rainfall data was regression and correlation. The regression constants
calculated and grouped into annual rainfall, southwest of intercept and slope and also the correlation
monsoon rainfall, northeast monsoon rainfall and non coefficients are found and given in Table 2. The
monsoon rainfall. standard errors of estimate about the regression line
are also calculated for each station and given in Table
The following are the short forms used in this paper: 2.
RFA - Annual rainfall (January to December)

12
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

Table 2 RFSWM – RFA relationship values

Parameter Kannur Kozhikode Quilandy Vythiri Vadakara


Intercept 771.52 1153.86 788.79 868.91 734.60
Slope 0.95 0.87 0.99 0.98 1.07
Std. error of estimate 308.59 334.58 312.54 282.93 389.82
Correlation coefficient 0.88 0.80 0.91 0.95 0.86

The RFSWM has been found to correlate well with increases with RFSWM and hence correlation coeffi-
the RFA in Vythiri (correlation coefficient = 0.95) while cient is positive at all stations. The regression lines for
the correlation is less in Kozhikode (correlation coeffi- each station are as shown in Figures 2a – 2e.
cient = 0.80). Also, as RFSWM is a part of RFA, RFA

KANNUR
KOZHIKODE
6000
6000

5000
5000
y =771.52+0.95x
RFA (y) in mm

r = 0.88
RFA (y) in mm
4000 4000 y =1153.86+0.87x
r = 0.80
3000 3000

2000 2000
Observed
Observed
Linear Linear
1000 1000
1000 2000 3000 4000 5000 1000 2000 3000 4000

RFSWM (x) in mm RFSWM (x) in mm

Fig. 2a Relationship between RFSWM and RFA at Kannur Fig. 2b Relationship between RFSWM and RFA at Kozhik

QUILANDY VYTHIRI
6000 9000

8000

5000
7000
y =788.79 + 0.99x y =868.91 + 0.98x
RFA (y) in mm
RFA (y) in mm

r = 0.91 6000 r = 0.95


4000

5000

3000
4000

3000
2000
Observed Observed
2000
Linear Linear
1000 1000
0 1000 2000 3000 4000 5000 1000 2000 3000 4000 5000 6000 7000 8000

RFSWM (x) mm RFSWM (x) in mm

Fig. 2c Relationship between RFSWM and RFA Fig. 2d Relationship between RFSWM and RFA at Vythiri
at Quilandy

13
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

VADAKARA 3918.1 mm at Kozhikode both during the year 1961.


6000 Considering the maximum RFNEM at the five stations,
maximum was 1227.3 mm at Quilandy during the year
5000 y =734.60 + 1.07x 1943 and the lowest was 808.7 mm at Vythiri during
r = 0.86 the year 1902. In the case of maximum RFNM at the
five stations, maximum was 1642.6 mm at Vadakara
RFA (y) in mm

4000
during the year 1942 and the lowest was 1010.7 mm at
3000
Kannur during the year 2004.
Similarly, observing minimum RFA at the five
2000
Observed
stations, the highest value was 2437.5 mm at Vythiri
Linear
during the year 1993 and the lowest value was 1056.9
1000
mm at Quilandy during the year 1964. Among minimum
1000 2000 3000 4000 5000
RFSWM, the highest value was 1637.8 mm at Vythiri
RFSWM (x) in mm
during the year 1918 and lowest value was 889.8 mm
Fig. 2e Relationship between RFSWM and RFA at Vadakara at Quilandy during the year 1964. In the case of
minimum RFNEM at the five stations, the highest value
Maximum and Minimum of RFA, RFSWM,
was 116.0 mm at Vadakara during the year 2003 and
RFNEM and RFNM
the lowest value was 58.0 mm at Quilandy during the
The maximum and the minimum of RFA, RFSWM, year 1963. Considering minimum RFNM, the highest
RFNEM and RFNM observed at the five stations during value was 72.9 mm at Kozhikode during the year 1917
the period of study are given in Table 3 in mm along while the stations Quilandy, Vythiri and Vadakara had
with the respective years of occurrence. only 0 mm rain, all during the year 1990.

Considering maximum RFA at the five stations, Figure 3 represents the variation in the maximum
maximum was 8233.2 mm at Vythiri during the year and minimum values of RFA, RFSWM, RFNEM and
1961. The lowest value among maximum RFA was RFNM at the five stations.
4962.3 mm at Kozhikode during the same year 1961.
From the figure it is clear that maximum RFA and
Among maximum RFSWM at these stations, maximum
maximum RFSWM show a parallel behaviour which
was 6959.5 mm at Vythiri and the lowest value was
occurred in the same years.

Table 3 Maximum and minimum of the respective groups and its year of occurrence
Type Group Kannur Kozhikode Quilandy Vythiri Vadakara
RFA 5660.5 4962.3 5227.0 8233.2 5846.9
YEAR 1961 1961 1959 1961 1907
RFSWM 4663.3 3918.1 4349.5 6959.5 4486.7
MAX YEAR 1961 1961 1959 1961 1907
(mm) RFNEM 920.6 951.5 1227.3 808.7 970.5
YEAR 2002 1932 1943 1902 1932
RFNM 1010.7 1206.0 1163.8 1100.0 1642.6
YEAR 2004 1933 1955 2004 1942
RFA 1497.3 2311.9 1056.9 2437.5 1597.1
YEAR 1968 1911 1964 1993 2003
RFSWM 1270.9 1069.3 889.8 1637.8 1379.2
MIN YEAR 1968 1918 1964 1918 1918
(mm) RFNEM 79.2 68.8 58.0 62.7 116.0
YEAR 1968 1906 1963 1968 2003
RFNM 11.7 72.9 0.0 0.0 0.0
YEAR 1934 1917 1990 1990 1990

14
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

9000

8000

7000

R a in f a ll in m m
6000

5000

4000

3000
M A X R FA
2000 M A X R FSWM
M A X R FNEM
1000
M A X R FNM

0 M IN RFA
M IN RFSWM
Kannur Kozhikode Quilandy Vythiri Vadakara
M IN RFNEM
STATIONS M IN RFNM

Fig. 3 Variation in maximum & minimum of RFA, RFSWM, RFNEM and RFNM at the five stations

It is significant to observe that the maximum values Table 4. and fig. 4 The percentages of RFSWM to
of non monsoon rainfall exceed maximum RFNEM RFA at these stations are also given in the Table.
except at Quilandy. These values also exceed minimum
RFA at Quilandy and Vadakara and exceed minimum The percentage value of the RFSWM to RFA ranges
RFSWM except at Kannur and Vythiri. These values from 73.33% at Kozhikode to 81.37% at Vythiri. The
exceed minimum RFNEM at all the five stations. overall average percentage comes to 76.99%.
Considering the maximum values it is evident that non The overall average values of RFA, RFSWM,
monsoon rainfall values cannot be neglected towards RFNEM, and RFNM were found to be 3494.4 mm,
the assessment of rainfall resources in this region. 2698.2 mm, 409.9 mm and 386.3 mm respectively.
Averages and percentages
Figure 4 shows variation in the averages of RFA,
The average RFA, RFSWM, RFNEM and RFNM RFSWM, RFNEM and RFNM at the five stations.
values observed at the five stations are given in
4500

4000

3500
R a in f a ll in m m

3000

2500

2000

1500

1000

500 AVE RFA

AVE RFSWM
0
Kannur Kozhikode Quilandy V ythiri Vadakara AVE RFNEM

STATIONS AVE RFNM

Fig. 4 Variation in average of RFA, RFSWM, RFNEM and RFNM at the five stations

Table 4 Average RFA, RFSWM, RFNEM and RFNM and % of RFSWM w.r.t. RFA
Ave. RFA Ave. RFSWM Ave. RFNEM Ave. RFNM %
Station
(mm) (mm) (mm) (mm) RFSWM / RFA
Kannur 3247.3 2601.0 347.4 298.8 80.10
Kozhikode 3166.8 2322.3 441.3 403.1 73.33
Quilandy 3255.3 2485.2 414.4 355.6 76.34
Vythiri 4278.5 3481.6 436.9 360.0 81.37
Vadakara 3524.2 2600.7 409.7 513.8 73.80
Average 3494.4 2698.2 409.9 386.3 76.99

15
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

Fig. 5 Variation in annual rainfall at the five stations

Fig. 6 Variation in southwest monsoon rainfall at the five stations

Fig. 7 Variation in northeast monsoon rainfall at the five stations

Fig. 8 Variation in non monsoon rainfall at the five stations

16
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

The variations in RFA, RFSWM, RFNEM and RFNM their respective values at all the stations indicative of a
over the 81 years at the five stations are presented in uniform pattern.
Figures 5, 6, 7 and 8 respectively. The lines showing
the variations in the annual and southwest monsoon Rainfall frequency distribution
rainfall values at the five stations over the 81 years The frequency distribution of annual rainfall at the
broadly present a regularity in increase or decrease in five stations is presented in Table 5. The rainfall values
and ranges are given in mm.
Table 5 Rainfall frequency distribution (RFA)
Kannur Kozhikode Quilandy Vythiri Vadakara
<1000 0 0 0 0 0
1000 - 2000 1 0 2 0 1
2000 - 3000 27 33 30 3 18
3000 - 4000 45 40 37 28 43
4000 - 5000 7 8 10 39 16
5000 - 6000 1 0 2 8 3
>6000 0 0 0 3 0

From Table 5, it can be seen that 70 to 81 of the during 1968 at Kannur and 1597.1 mm during 2004 at
years (ie, 86.4% to 100%) are covered by annual rains Vadakara. The 3000-4000 mm range of the annual
ranging from 2000 mm to 5000 mm. For the entire rainfall values covers all the five stations during more
zone, there are only 3 rainfall values exceeding 6000 than 28 years of the 81 years of observations. Figure 9
mm, viz. 6022.6 mm, 6420.1 mm and 8233.2 mm all at shows the frequency distribution of total annual rainfall
Vythiri during the years 1923, 1924 and 1961 at the five stations.
respectively. There are four annual rainfalls which
Table 6 illustrates the frequency distribution of the
are less than 2000 mm, viz. 1912.9 mm during 1963 and
occurrence of southwest monsoon rainfall at the five
1056.9 mm during 1964 both at Quilandy, 1497.3 mm
stations.
Table 6 Southwest monsoon rainfall frequency distribution
Kannur Kozhikode Quilandy Vythiri Vadakara
<1000 0 0 1 0 0
1000 - 2000 11 23 17 2 9
2000 - 3000 53 50 48 22 56
3000 - 4000 16 8 13 43 14
4000 - 5000 1 0 2 10 2
5000 - 6000 0 0 0 3 0
>6000 0 0 0 1 0
50
45
O F YE A R S

40
35
O .YEAR

30
25
20
NO.NOF

15
10 Kannur
5 Kozhikode

0 Quilandy
<1000 1000 - 2000 2000 - 3000 3000 - 4000 4000 - 5000 5000 - 6000 >6000 Vythiri
RAINFALL RANGE Vadakara

Fig. 9 Frequency distribution of annual rainfall at the five stations

17
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

During the southwest monsoon season of the study than 6000 mm, i.e. 6959.5 mm at Vythiri during the year
period there is only one incident having the value less 1961.
than 1000 mm, i.e.889.8 mm at Quilandy during the year
1964. Also, there is only one RFSWM value higher Figure 10 shows the frequency distribution of
southwest monsoon rainfall at the five stations.

60

50
F YE A R S

40
. OYEAR

30
NO
NO. OF

20

Kannur
10
Kozhikode
0 Quilandy
<1000 1000 - 2000 2000 - 3000 3000 - 4000 4000 - 5000 5000 - 6000 >6000 Vy thiri
RAINFALL RA NGE
Vadakara
Fig. 10 Frequency distribution of southwest monsoon rainfall at the five stations

Figure 10 gives the fact that in all the years there is than 6000 mm.
southwest monsoon rainfall ranging from 1000 to 5000
mm at all the stations except at Quilandy having rain The frequency distribution of northeast monsoon
less than 1000 mm and at Vythiri having rain higher rainfall at the five stations is given in Table 7.

Table 7 Northeast monsoon rainfall frequency distribution

Kannur Kozhikode Quilandy Vythiri Vadakara


<200 15 4 11 5 9
200 - 400 36 32 25 30 33
400 - 600 26 29 36 33 29
600 - 800 3 14 7 12 7
800 - 1000 1 2 1 1 3
>1000 0 0 1 0 0

All the stations have RFNEM value less than 200 mm. mm, i.e. 1227.3 mm at Quilandy during the year 1943.
Also, all the stations have covered within 78 to 80 years
of total 81 years in the range between 0 mm and 800 The frequency distribution of northeast monsoon
mm. There is only one RFNEM value higher than 1000 rainfall at the five stations is given Fig. 11.

40

35
O F YE A R S

30

25
O . YEAR

20
NO.NOF

15

10 Kannur
5 Kozhikode
0 Quilandy
<200 200 - 400 400 - 600 600 - 800 800 - 1000 >1000 Vy thiri
RAINFALL RANGE
Vadakara

Fig. 11 Frequency distribution of northeast monsoon rainfall at the five stations

18
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

Table 8 Non monsoon rainfall frequency distribution

Kannur Kozhikode Quilandy Vythiri Vadakara


<200 36 18 20 14 14
200 - 400 28 36 37 46 18
400 - 600 5 8 12 9 26
600 - 800 7 11 6 6 9
800 - 1000 4 6 4 5 8
>1000 1 2 2 1 6

50
45
O F YE A R S

40
35
O . YEAR

30
25
N OF

20
NO.

15 Kannur
10
Kozhikode
5
Quilandy
0
Vy thiri
<200 200 - 400 400 - 600 600 - 800 800 - 1000 >1000
RA INFALL RANGE Vadakara

Fig. 12 Frequency distribution of non monsoon rainfall at the five stations

Table 8 indicates the frequency distribution of non The highest of the maximum annual rainfall (RFA)
monsoon rainfall at the five stations, of which the observed was 8233.2 mm at Vythiri during the year 1961
graphical representation is Fig. 12. and the lowest of the minimum non monsoon rainfall
(RFNM) observed was 0 mm at Quilandy, Vythiri and
During non monsoon period Kannur, Quilandy and Vadakara all during the year 1990.
Vythiri cover 69 years out of the total 81 years (85% of
the years) having the range less than 600 mm rainfall Maximum annual rainfall and southwest monsoon
while Kozhikode and Vadakara cover 62 years (76.5%) rainfall show a parallel behaviour and fall during the
of the 81 years and 58 years (71.6%) of the 81 years same years.
respectively by the same range.
The overall average RFA, RFSWM, RFNEM and
CONCLUSIONS RFNM were found to be 3494.4 mm, 2698.2 mm, 409.9
mm and 386.3 mm respectively. Also overall southwest
The study was carried out to find out the rainfall monsoon rainfall was 76.99% of the overall annual
distribution at the five stations of northern Kerala during rainfall.
different periods; annual, southwest monsoon, northeast
monsoon and non monsoon periods. The analysis was The variations of annual rainfall and southwest
done making use of 81 years of daily rainfall data. monsoon rainfall at the five stations for the 81 years
show a parallel behaviour in increase and decrease of
Regression analysis of the southwest monsoon values.
rainfall with respect to annual rainfall of 81 years yield
intercept values varying from 734.60 to 1153.86 and The frequency distributions vary depending upon
slopes varying from 0.87 to 1.07. For each relation, the groups of the study. There is only one RFSWM
standard error of estimate was also calculated. value higher than 6000 mm and only one RFNEM value
higher than 1000 mm.
Correlation analysis of RFSWM – RFA gives the
coefficients varying between 0.80 and 0.95. This shows ACKNOWLEDGEMENTS
very close relationship between them.
The authors express their sincere and heartful

19
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

thanks to Mr.C.K.Gopinathan for all the help and support temperatures. Journal of Applied Meteorology, Vol.7,
extended for the study. The immense help rendered by pp. 801-816.
Ms.E.Deepa during the analysis of data and computer 6. Gulezian, R.C., 1979. Statistics for decision making.
works is also gratefully acknowledged. W.B.Saunders Company, Philadelphia.
Due acknowledgement is given to India 7. Jagannadha Sarma, V.V., 2005. Rainfall pattern in the
Meteorological Department for the source of data used coastal zone of Krishna Godavary Basin, Andra
in this study. Pradesh, India. Journal of Applied Hydrology, Vol.
XVIII, (1 & 2), 1 – 11.
REFERENCES 8. Menon, P.A. and Rajan, C.K., 1989. Climate of Kerala.
1. Ananthakrishnan, R., Parthasarathy, B. and Pathan, Classic Publishing House, Cochin.
J.M., 1979. Meteorology of Kerala. Contribution to 9. Muthuchami, A. and Ravikumar, P.V., 1992. The inverse
Marine Sciences Dedicated to Dr. C.V. Kurian, pp. 60- relationship between the activity of monsoon systems
125. and the intensity of southern hemispheric equatorial
2. CWRDM, 1995. Water Atlas of Kerala. Centre for Water trough. Vayu Mandal, 22 (1-2), 40-45.
Resources Development and Management, Kozhikode. 10. Smith, R.B., 1979. The influence of mountains on the
3. Dhar, O.N. and Bhattacharya, B.K., 1976. Variation of atmosphere. Advances in Geophysics, 21, 87-130.
rainfall with elevation in the Himalayas- a pilot study. 11. Soman, M.K., Krishna Kumar, K. and Nityanand Singh,
Indian Journal of Power and River Valley Development, 1988. Decreasing trend in the rainfall of Kerala.
26, 179-185. Current Science. 57 (1), 7-12.
4. Dhar, O.N., Nandal, B.N. and Ghose, G.C., 1978. Heavy 12. Stringer, E.T., 1972. Foundations of climatology. W.H.
rainfall stations of India. Indian Journal of Power and Freeman and Co., San Francisco, pp. 141-167.
River Valley Development, 25, 123-134.
13. Verma, R.K., 1993. Variability of Indian summer
5. Fujita, T., Baralt, G. and Tsuchiya, K., 1968. Aerial monsoon, relationship with surface air temperature
measurements of radiation temperatures over Mt. Fuji anomalies over northern hemisphere. Mausam, 44,
and Tokyo areas and their application to the 191-198.
determination of ground and water – surface

20
J. Indian Water Resour. Soc.of
Journal Vol.Indian
30 No.Water
1, January, 2010
Resources
Society Vol. 30 No. 1, January, 2010

SUSTAINABLE MANAGEMENT OF THE WATER STRESSED AQUIFERS IN


SABARMATI BASIN GUJARAT, INDIA

R. C. Jain1 and A. K. Sinha2


ABSTRACT

The Sabarmati basin is underlain by a multi-aquifer system, with prolific yields but the
excessive groundwater pumping over many years has resulted in de-watering of a substantial
aquifer thickness and reduction in pressure heads as reflected in long term decline in ground
water levels. The ground water use in the basin being practiced currently is considered
unsustainable as the ground water draft far exceeds the replenishable recharge. For providing
sustainability to ground water withdrawal structures and keeping in view the increasing thrust on
development of ground water resources, there is an urgent need to address the problem of ground
water depletion through both supply side as well as demand side management interventions .
Based on the in depth analysis of hydrogeology, long term water level trends , aquifer parameters
and the availability of surplus runoff a strategy for managed aquifer recharge (MAR) has been
formulated to augment the ground water resources of the water stressed aquifers. Typical designs
of different types of structures suitable for artificial recharge have been included based on the
lessons learnt. The paper presents a matrix of recommendations for implementing MAR in the
basin through various stakeholders. For demand side management it is essential that ground
water development is controlled and regulated through appropriate legal and administrative
measures in view of the fast emerging aquifer depletion in large part of Basin.

Key words : long term decline, managed aquifer recharge, unsustainable, management inter-
ventions, virtual water.

INTRODUCTION added to the capital cost of construction of the tube


wells and the energy bill but have also added to annual
Sabarmati river basin is located in the western part cost of maintenance of tube wells (INREMF,2001).
of India (Fig.1). The basin in its western ,central and Conventional dug wells and dug-cum-bored wells are
southern parts is underlain by a multi-aquifer system, already, gradually going out of operation and in many
with prolific yields but the excessive groundwater areas the dug wells have dried up since many years.
pumping over many years has resulted in de-watering Further, during drought years sustained ground water
of a substantial aquifer thickness and reduction in withdrawals due the pumpage of groundwater far
pressure heads. Agriculture production has been exceeds that of normal years resulting in permanent
seriously affected due to conspicuous decline in water de-watering of aquifers (Jain, et al,2000).
levels caused by over- exploitation of groundwater
(Jain, et al,2001). In fact because of economic factor, farmers are
largely growing the cash crops in the area and are taking
The basin is more vulnerable for such adverse high risks in construction of the deep tube wells even
effects due to low rainfall reliability and recurrence of with a reduced life span due to lowering in water levels
droughts. and consequent reduction in discharge, higher and higher
The detrimental effects of over exploitation of maintenance cost. Large financial investments made in
groundwater i.e., decline in water levels have not only construction of tube wells need to be protected from
1
implied hazards of over exploitation of ground water.
West Central Region, Central Ground Water Board, Ahmedabad.
2
Deptt. of Geology, University of Rajasthan, Jaipur.
Paper No. 1239

21
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

Groundwater Resource Availability Scenario


In the Sabarmati River basin the net ground water
availability is 2342.59 MCM/yr. The gross ground water
draft has increased from 1580 MCM/yr as in
1991(CGWB,1995) to an alarming level of 2415 MCM/
yr as in 2004 (CGWB,2006). As per the latest ground
water resource computations a negative balance
of (-)72.37 MCM/yr is indicated. The stage of ground
water development has increased from nearly 60% of
replenishable recharge in 1991 in the basin to >103%
of replenishable recharge in 2004 over a period of last
one and a half decade. A comparative depiction of
change in stage of ground water development in
important talukas in the basin is shown in Fig.3.
Based on overall stage of ground water
development of 103.09 % of replenishable recharge ,
Fig. 1 Location map of Sabarmati Basin the basin is categorised as OVER EXPLOITED .The
During the early sixties the tube wells were drilled between present status of development is unsustainable as the
60 and 100 m and their water levels ranged between 10 and 15 aquifers are under stress .the stage of ground water
m bgl. These tube wells have also gone out of use. The tube development varies widely from as low as 28% of
wells being drilled now are between 250 and 300m depth with replenishable recharge as in Anand taluka in the southern
the water levels ranging between 80 to more than 120 m bgl. part of the basin to nearly 230% replenishable recharge
(GOG,2002 ). of in Mansa taluka in western part of the basin (2004).
The adoption of high yielding crops for boosting the Groundwater depletion – Management options
agricultural production ,fodder production to meet the
demand for dairy cattle and the impetus in rural electrification The Sabarmati river basin has the problem of
has resulted in substantial increase in ground water pumping. intensive ground water extraction / overexploitation
Earlier through conventional open well with discharge 4-6 leading to long term decline in water levels in the
m3/hr. an area of 0.4 to 0.6 ha could be irrigated. Now with northern, central and eastern part ,while in the southern
energisation of open wells and construction of deep tube
part the level of ground water extraction is comparatively
wells the average ground water abstraction rates have gone
low due to availability of ample surface water irrigation
as high as 90 to 112 m3/hr. with command areas ranging from
40 to 60 ha ( Jain,2003). facilities through the imported water from the Mahi
River Basin. At present the gross irrigated area in the
Magnitude of ground water depletion Sabarmati basin is 7,89,500 ha., which will increase to
12,43,500 ha by the year 2025 (ICID,2005).
Because of increased pace of development during
last three decades for meeting the increasing demands The total mean annual surface water resources in
for irrigation, drinking water supplies and industrial needs Gujarat part of the basin are estimated at 2018.20 MCM
the dependence on ground water has tremendously including 150 MCM from neighbouring states. Further
increased (Govt. of Gujarat,2005). The increase in the as per Plans of the Gujarat Govt. surface water potential
ground water draft has been mainly due to increased to the extent of 1587.13 MCM is committed , leaving
pumping for meeting the ever increasing water demand nearly 431.07 MCM untapped , which accounts for 21%
of irrigation, drinking water and industrial sector. This of mean annual runoff in the Sabarmati River
is clearly evident from a perusal of few representative basin(CDO,2003).
hydrographs shown in figure 2 which very clearly depict For providing sustainability to ground water
the alarming declines ranging from more tahn 5 to 15 m withdrawal structures in Sabarmati River basin and
in the shallow aquifers and from more than 20 up to 60 keeping in view the increasing thrust on development
m in the deeper aquifers during the last one decade or of ground water resources for meeting the growing
so. (Jain,2008)

22
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

Fig. 2 Hydrographs of select observation wells in Sabarmati Basin

23
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

design of artificial recharge structures(Kovalevsky, et


al, 2004). While assessing the availability of source water,
which is one of the prime requisites for ground water
recharge, careful consideration has to be given to
committed monsoon storages, so that the harvesting of
non committed surplus monsoon run off from the area
does not have adverse environmental impact like drying
up of existing lakes/ponds/reservoirs due to reduction
in inflows from their catchments. Detailed knowledge
of dimensional data of the aquifer viz. their thickness
and lateral extent is necessary for evaluation of the
Fig. 3 Stage of ground water development in Sabarmati River
basin during 1991-2004. storage potential. The availability of sub-surface storage
space and its replenishment capacity governs the extent
demands of water in agriculture, industrial and domestic of recharge.
sectors, there is an urgent need to adopt both the supply Identification of areas feasible for managed aquifer
side and demand side management interventions to recharge in Sabarmati Basin
augment and conserve the depleting ground water
resources in the active recharge zone. The basin is having total area of 22,260 sq.kms in
Gujarat. The geological formations in the basin are
Managed aquifer recharge - Supply side alluvium, igneous, metamorphic and other soft rocks. In
management the major part of the basin alluvium consisting of re-
Natural replenishment of ground water reservoir is worked aeolian sand, silt, kankar and clay forms the
slow process. It is unable to keep pace with the principal aquifer (Fig. 4).
excessive continued exploitation of ground water
resources . In order to augment the natural supply of
ground water, managed aquifer recharge ( MAR) is
an important and frontal management strategy which
can provide succor to address the problem of ground
water depletion (Jain& Sinha,2004). MAR is the
process by which the ground water reservoir is
augmented at a rate exceeding that under natural
conditions of replenishment. The recharge efforts are
basically augmentation of natural movement of surface
water into ground water reservoir through suitable civil
structures under suitable hydrogeological and hydrologic
conditions. As the rainfall occurrence in the basin is
limited to about 10 to 22 days during three months
monsoon period,the natural recharge to ground water
reservoir is restricted to this period only. The Managed
aquifer Recharge aims at increasing the recharge Fig. 4 Hydrogeological map of Sabarmati River basin
period in the post-monsoon season by about 3 more
months . This results in providing sustainability to ground The unsaturated thickness of rock formations,
water development during the lean season. occurring beyond eight metres below ground level has
been considered to assess the requirement of water to
The efficacy of artificial recharge schemes depends build up the sub-surface storage by saturating the entire
largely on the source water availability and capability thickness of the vadose zone to 8 metres below ground
of ground water reservoir to accommodate it ,which level. The upper 8 m of the unsaturated zone is not
requires detailed knowledge of geological and considered for MAR; in view of the prevailing
hydrological features of the area for site selection and hydrological, hydrogeological, geomorphic and

24
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

topographic conditions. The post-monsoon depth to general except the western part which is saline having
water level represents a situation of minimum thickness TDS more than 2500 mg/l (Fig 6). Based on the quality,
of vadose zone available for recharge which can be post monsoon water level and the declining trend the
considered with reference to surplus monsoon run off feasible areas for managed aquifer recharge are
in the area. identified in the northern and western parts of the basin(
Fig.7). The south, central and the western part of
The average post monsoon water level (1998-2007) basin having post monsoon decadal average depth to
ranges between less than 8 and 35 mbgl in the Sabarmati water level less than 8mbgl and saline ground water
basin (Fig 5). The quality of ground water is good in are not considered feasible for MAR.
It is estimated that an area of 14,517 Sq.km. having
depth to water table more than 8 m bgl, spread over all
the geological formations is feasible for managed aquifer
recharge through different type of recharge structures
at appropriate sites. The total volume of vadose zone
of this area is 41,348 MCM. Further in an area of 464
sq.kms the declining trend of water level is observed
and the volume of vadose zone in this area is 66.93
MCM. Thus the total volume of de-saturated zone
feasible for recharge in the basin is 41,414 MCM.
Considering percentage of clay in alluvium, coefficient
Fig. 5 Average post monsoon depth to ground water level (1998-
2007) in Sabarmati Basin
replenishment of different formations, it is estimated
that about 3,534 MCM of water is required for recharge
to bring the water level up to 8 m bgl .
The non-committed monsoon flow of 431 MCM/
annum could be used as source water for managed
aquifer recharge for augmenting the storage in the
stressed aquifers (UNDP,1988). This surplus runoff can
be utilised for MAR through proven techniques of
recharge like injection wells, dug wells, check dams,
spreading channels and percolation tanks in the area
(Jain, 2003). Based on an average recharge rate of
0.088 MCM/annum for a check dam/percolation tank,
0.015MCM/annum for injection wells and 0.019MCM/
Fig. 6 Ground water quality in Sabarmati Basin during annum for dug wells it is estimated that 13,300 Dug
pre-monsoon 2007
wells, 4,700 injection tube wells/connector wells, 500
percolation tanks and 1,400 check dams are needed for
transferring the non-committed runoff to the stressed
aquifer. This will cost about Rs. 1400 Million. All the
structures are not required to be constructed afresh, In
fact , a large number of existing dug wells /tube wells
can be provided with suitable siltation/filtration chambers
for removing the physical impurities in source water
derived from monsoon flows. Similarly the deepening
of existing ponds for increased storage and percolation
into the aquifer would also be very useful , as creation
of new surface storages adds more to the evaporation
losses than to percolation to the underlying aquifers .The
spreading channels are feasible in the limited area of
Fig. 7 Areas feasible for artificial recharge to ground water in
Sabarmati basin common recharge zone at the foot hill of Arvalli’s in

25
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

RCC M 20 GRADE SLAB


6000 MM

2800 MM
400 MM DIA
INJECTION
CONNECTING PIPE WELL
150 MM DIA WITH 2600 MM
CONTROL VALVE
150 MM DIA PVC
CASING PIPE
SOURCE WATER UPPER 10 M
6250 MM
DRAIN BLANK & LOWER
35 M STAINER
PCC 1:3:6, 150 MM THICK (6KG / CM2)
SCUM BOARD

ANNULUS
WITH 10 TO 20
MM Ø PEBBLE
IN SPACE

1500 X 2000 X 1500 MM SIZES FILTER


CHAMBERS, ONE FILLED WITH
COARSE SAND & ANOTHER FILLED
WITH PEBBLES OF 10 TO 20 MM DIA 15 MM DIA AIR
SIZE. ALL THE WALLS ARE B. M. VENT PIPE 30 M
WALLS IN C. M. (1:3), 230 MM THICK. LONG WITH 5 MM
PROVIDE 3 PIPES 150 MM DIA WITH DIA HOLES IN
PIPE CAP HAVING HOLES ON ENTRY LOWER 10 M
SITE. LENGTH

SECTIONAL VIEW

400 MM DIA
6000 MM INJECTION WELL

1500 MM 150 MM DIA PVC


2000 MM 1500 MM
CASING PIPE
UPPER 10 M
BLANK & LOWER
2500 MM 2000 MM 35 M STAINER
(6KG / CM2)

15 MM DIA AIR VENT PIPE


MAN HOLE COVER 30 M LONG WITH 5 MM DIA
HOLES IN LOWER 10 M
PLAN LENGTH

Fig. 11. Typical design of an injection well in alluvial area

27
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

north eastern part of the area. Typical design of various In addition to the requirement of water for dairy
type of structures is given in Fig.8,9,10 &11. development, fodder for the cattle is also grown which
leads to over exploitation of ground water. If the fodder
As the predominant contribution of recharge to requirement could be met from agriculture production
deeper aquifers is through the vertical leakage from in the central and southern part of Gujarat having low
the aquitards underlying the shallow aquifers, the stage of ground water development, which can then be
recharge of surplus monsoon water in the shallow aquifer transported to over exploited areas .Thus a large
will benefit both the phreatic as well as deeper aquifers quantity of ground water can be conserved in the form
.This will go a long way in arresting the rate of decline of virtual water.
in ground water levels and providing sustainability to
the fast depleting stressed aquifers (Jain & Sinha,2002). More emphasis should be laid on adoption of
micro-irrigation technology like drip irrigation etc,
Demand side management - Regulation and which will help in conservation of the precious resource.
control of ground water development-
Strategy for implementation of MAR
As the available ground water resources are finite
and aquifer depletion is fast emerging in large part of By far the most critical response to stressed aquifers
Sabarmati basin ,it is essential that ground water in the Sabarmati Basin demands exploring synergies
development is controlled and regulated through from a variety of players for the basin wide recharge
appropriate legal and administrative measures. To begin program. Evolving a groundwater recharge strategy
with any additional abstraction from the deeper aquifers needs to begin with an appreciation of the variety of
should be banned, because the ground water resource actors that can contribute through different kinds of
of deeper aquifers get replenished over large no. of recharge structures as suggested in the Table 1.
years unlike the shallow aquifer which gets replenished
every year(World Bank,1999). The in-storage reserves Public agencies with strong science and engineering
of ground water in the deep multi-aquifer system should capabilities need to play a major role in constructing
be treated as strategic resource to be utilised in times and managing large recharge structures (Planning
of emergency only (UNDP,1976). However, exception Commission,2007). However, an intelligent strategy can
can be made for drinking water supply ,where a limited also involve millions of farmers and householders and
quantity of withdrawal can be permitted not exceeding thousands of their communities—each of whom can
safe yield of the aquifer. Fortunately, Gujarat state has contribute small volumes to recharge dynamic
a State Ground Water Authority in place, but the need groundwater. The Table 1 indicates who can play what
of the hour is to control and regulate the ground water role to achieve the purpose of resource augmentation
abstraction by effective implementation of the ground under prevailing conditions.
water legislation.

Table 1. Actors and their roles in implementation of MAR

Aquifers Key players Numbers Recharge Location of


Actors affected of actors Volumes/ structures
who can structure
contribute
Small structures for Dynamic Individual millions 100-5000 m3 Private farm
recharging wells and groundwater in farmers and urban lands and
roof-water harvesting alluvial and citizens homes
structures hard-rock areas
Check dams, Dynamic Communities Tens of 100,000- Common-
percolation tanks, groundwater in using a common thousands 5,000,000 m3 property or
Sub-surface dykes, etc alluvial and aquifer system government
hard-rock areas land
Large structures on Confined Public agencies few 0.1 to 1 km3 Government
government land for aquifers: large with hydro- or more waste lands or
recharge to confined alluvial aquifers geology forest lands
aquifers expertise;

28
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

In view of the criticality of groundwater recharge, distinct capabilities and limitations. If MAR is to be a
a Special Purpose Vehicle (SPV) needs to be created major response to provide succour to the stressed
for overseeing private and NGO-implemented aquifers in the Sabarmati River Basin , the state needs
groundwater recharge programs as well as for to evolve an integrated groundwater recharge strategy
executing, operating and maintaining large-scale (Jain,& Sinha, 2004)and work with role and space for
groundwater recharge program. Besides the scientific various players to contribute as outlined in the
talent such a SPV needs to build engineering and Table 2.
management capacity needed for the purposes on hand.
Acknowledgements : The author acknowledges the
In our country water policy has so far focussed on Chairman, Central Groundwater Board, Govt. of India
what governments and government agencies can do. for the permission to publish this paper .
Now, it needs to target networks of players, each with
Table 2. Outline of an MAR Strategy for Sabarmati River Basin
Key actors Arid alluvial Hard rock Roles that need to be played by State Govt, Recharge SPV,
aquifer areas aquifer areas other public agencies
Farmers Dug wells, Dug wells, farm Vigorous Information, Education, Communication campaign to
roof-water ponds, roof- promote MAR to stressed aquifers through dug wells
harvesting; water harvesting; Technical support in construction of desiltation/filtration pits
other private other private for recharge, and periodic desiltation of wells
recharge recharge Financial incentives and support to farmers adopting MAR
structures structures
NGOs, local Percolation ponds, check dams, Technical and financial support to local communities, NGOs for
communities sub-surface dykes on streams construction and maintenance
Supportive policy environment and incentive structures
Support for building local institutions for groundwater recharge
Groundwater Recharge canals to transport Create a Special Purpose Vehicle to execute, operate and
recharge surplus flood waters for recharge maintain large-scale recharge structures
SPV in groundwater-stressed areas e.g.,
Sujalam- Sufalam in North
Gujarat
Build and operate large-scale recharge structures in upstream
Large recharge structures in areas of confined aquifers. e.g. at the base of Aravalli’s in North
recharge zones of confined Gujarat
aquifers

REFERENCES 6. Government of Gujarat, 2005. Report of the Committee


on Estimation of Ground water resources and
1. Central Designs Organisation, 2003. Report on Irrigation Potential in Gujarat. Narmada and Water
Integrated river basin planning, development and Resources Department.
management of Sabarmati River basin. Govt. of Gujarat.
7. Indian Natural Resource Economics and management
2. Central Ground Water Board, 2002. Master Plan for Foundation, 2001. Integrated water resources
Artificial Recharge to Ground Water in India, Ministry management in Sabarmati Basin: Some issues and
of Water Resources, Government of India. options.
3. Central Ground Water Board, 2006. Dynamic Ground 8. International commission on Irrigation and Drainage,
Water Resources of India, Ministry of Water Resources, 2005, Water Resources Assessment of Sabarmati River
Government of India. Basin, India.
4. Central Ground Water Board, 2007. Ground water Year 9. Jain,R.C., Nagar,A., Jain,P.K. and Krishna, V.S.R.,2000.
Book, Tech. Report, CGWB, WCR, Ahmedabad. Declining Water levels in deep aquifers of Gujarat. Tech.
5. Government of Gujarat, 2000.White paper on water in Report ,CGWB, WCR, Ahmedabad.
Gujarat , Narmada Water Resources and Water Supply 10. Jain, R.C., Jain,P.K., Jain,A.K. and Krishna,V.S.R.,2001.
Department. Hydrogeological framework of Gujarat State with

29
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

special emphasis on issues related to Ground Water Seminar on Water for Future, Organised by Narmada
Development and Management. Workshop on and Tapi river Basin Organisation, Central Water
Sustainable Development and Management of Ground Commission, March 4-5,2009. Ahmedabad, Gujarat,
Water Resources in Gujarat . Tech. Report ,CGWB, WCR, India.
Ahmedabad .
16. Jain, R.C., 2009.Emerging challenges for sustainable
11. Jain,R.C. and Sinha,A.K.,2002. Intensive use of Ground ground water management in India. Journal of Applied
water in North Gujarat, India- Challenges and Hydrology, Vol. XXII, No.1, 2009.
opportunities. Proceedings of the SINEX Symposium
17. Jain, R. C., 2009. Trends and sustainability of
,Barcelona, Spain,2002. Published in “Groundwater
groundwater in highly stressed aquifers of Gujarat,
Intensive Use ” Sahuquillo, A.,Capilla,J., Martinez-
India . Trends and Sustainability of Groundwater in
Cortina,L., Sanchez-Villa,X.,(Editors),Publication No.
Highly Stressed Aquifers .Proc. of Symposium JS.2 at
SP 7 of the International Association of
the Joint IAHS & IAH Convention, Hyderabad, India,
Hydrogelogists.2005.
September 2009. IAHS Publ. 329, 2009.
12. Jain,R.C. , 2003. Hydrological opportunities and
18. Kovalevsky, Kruseman,G.P.and Rushton,K.R.,2004.
limitations of Artificial Recharge to Ground Water in
Ground Water Studies -An international guide for
Gujarat. Publication of The International Water
hydrogeological investigations, Unesco-IHP-VI,Series
Management Institute, Anand Centre, Gujarat.
on Ground water No.3,p.430.
13. Jain,R.C. and Sinha,A.K. , 2004. Hydrogeological
19. Planning Commission , 2007. Report of the Expert group
framework of the over-exploited multi-aquifer system
on Ground water Management and Ownership. Govt.
in North Gujarat, India –Problems and prospects of
of India.
sustainability. Proceedings  of  the  32nd  International
Geological Congress, Italy,2004. 20. United Nations Development Programme, 1976.
Ground water surveys in Rajasthan and Gujarat.
14. Jain,R.C. and Sinha,A.K., 2008. Groundwater
Technical Report.
management in Sabarmati river basin - Perspectives
& Options. International Groundwater Conference on 21. United Nations Development Programme, 1988. Pilot
Groundwater Dynamics and Global Change , March project on artificial recharge to ground water in
11-14, 2008. Mehsana and coastal area of Gujarat. Terminal report-
summary of findings and recommendations.
15. Jain, R.C., 2009. Hydrogeological Framework,
Groundwater Resources and Strategies for sustainable 22. World Bank, 1999.Ground water Regulation and
management in Gujarat. Proceedings of the National Management , Water sector report. .New Delhi.

30
J. Indian Water Resour. Soc.of
Journal Vol.Indian
30 No.Water
1, January, 2010
Resources
Society Vol. 30 No. 1, January, 2010

RUNOFF ESTIMATION BY DISTRIBUTED CURVE NUMBER TECHNIQUE


USING REMOTE SENSING AND GIS

Susanta Kumar Jena1, Kamlesh Narayan Tiwari2 and Ashish Pandey3


ABSTRACT

A study was undertaken to compare composited and distributed Curve Number (CN)
techniques for estimation of runoff from a medium size agricultural watershed namely Tarafeni
(West Bengal). Indian remote sensing satellite digital images were used for classifying the land
use/ land cover of the study watershed. The study watershed was divided into grids and weighted
CN was calculated for individual grids by intersecting the grid with CN coverage. Using distributed
CN technique runoff was simulated at each grid and averaged at the outlet of the watershed and
finally compared with the values obtained from traditional compositing technique. The different
initial abstractions (Ia) of 0.2S and 0.3S (S is the maximum potential retention) have also been
taken in different simulations and results were compared with the observed runoff. The study
revealed that there is definite increase in runoff value estimated by distributed CN technique over
composited technique. The amount of increase in runoff value calculated is more for the case of
Ia=0.3S than Ia=0.2S. The percent increase in runoff is very high for small events, moderate for
medium and low for high rainfall events. The results from statistical analysis, which includes
percent deviation, model efficiency, coefficient of determination, coefficient of residual mass,
root mean square error and student’s t-test for significant difference, show that distributed CN
with Ia=0.2S estimated runoff values are closely matching the observed runoff.

Key words: Distributed curve number, GIS, Remote sensing, Runoff, Statistical test

INTRODUCTION One of the most widely used techniques for


estimating direct runoff depths from storm rainfall is
Watershed management, which is a comprehensive the United States Department of Agriculture (USDA)
term meaning the rational utilization of land and water Soil Conservation Service’s (SCS) (now the Natural
resources for optimal production and minimum hazard Resources Conservation Service) Curve Number (CN)
to natural resources can solve the problems of soil method (Mishra and Singh, 2003). The SCS method
erosion and degradation in quality and quantity of water has been used by many researchers to determine the
resources. In many countries, non-availability of data rainfall runoff relationship (Stuebe and Johnston, 1990;
on amount and rate of runoff, sediment yield, nutrient Sharma et al., 2001; Sharma and Kumar, 2002; Mishra
loss, etc., is the major handicap to start with watershed et al. 2004; Pandey and Dabral, 2004; Pandey and Sahu,
development programme. There are numerous methods 2004; Pandey et al. 2005; Mishra et al. 2005; Jain et al.
to estimate runoff for ungauged watersheds, which is 2006). Prior to the widespread use of computers,
the most important input required for design of hydraulic averaging techniques were necessary to reduce
structures, flood forecasting and erosion prediction and calculations in manual runoff analysis. Although high-
to link with water quality problems etc. in a watershed speed personal computers have reduced the tedious of
management programme. repetitive calculations, compositing is still widely used.
1 This is because many practicing professionals have not
Directorate of Water Management (Formerly WTCER) (ICAR),
Chandrasekharpur, Bhubaneswar-751023 yet been able to take full advantage of new computer
2
Dept. of Agricultural & Food Engineering, Indian Institute of technology, and because accepted approaches are
Technology Kharagpur-721302 usually slow to change unless significant advantages
3 for an alternate approach are widely publicized. Runoff
Dept. of WRD&M, Indian Institute of Technology Roorkee
Paper No. 1243 estimation using traditional composite technique is still
31
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

in use worldwide. The increased availability of digital


(P  0.2S) 2
spatial databases and the use of GIS in recent times Q (5)
has helped in improving the practicality of estimating (P  0.8S)
runoff depth using distributed curve numbers. However, 25400
if distributed CN approaches are to be adopted, it is S  254 (6)
CN
important to understand how results from this approach
compare with results from the traditional composited where CN is the curve number which depends upon
CN technique. Keeping this in mind, this study was land use, hydrologic soil group and antecedent soil
undertaken to estimate runoff depth using different CN moisture condition.
methods and with different values of initial abstraction
and results thus obtained were compared with the Narayana (1993) recommended  equal to 0.3 for
observed runoff from a medium agricultural watershed. most of the regions in India except for the regions having
black clay soils where  = 0.1 seems more appropriate.
THEORETICAL CONSIDERATIONS
MATERIALS AND METHODS
The SCS-Curve Number method (Mishra and Singh,
2003.) is based on the water balance equation and two The study was undertaken in the Tarafeni watershed
fundamental hypotheses. The first hypothesis states that in Midnapore district of West Bengal in India. The
the ratio of the actual amount of direct runoff to the watershed lies within 22037 to 22047 N latitude and
maximum potential runoff is equal to the ratio of the 86038 to 86048 E longitudes. The study area falls under
amount of actual infiltration to the amount of the potential subtropical humid zone with an annual rainfall of 1350
maximum retention. The second hypothesis states that mm. The area of the watershed is 158.06 km2 and the
the amount of initial abstraction is some fraction of the relief varies from 110 m to 290 m above mean sea level.
potential maximum retention. Expressed mathematically, The shape of the watershed is almost circular and it is
the water balance equation and the two hypotheses, covered by Survey of India (SOI) toposheet number:
respectively, are 73/J-9, 10, 13 and 14 (1:50000 scale). The outlet of river
Tarafeni is considered at the Tarafeni barrage, which
P  Ia  F  Q (1) comes under Kangsabati irrigation project, West Bengal.
Q F Hydrologic data
 (2)
P  Ia S
The “Irrigation and Waterways Department” of
I a  S (3) Government of West Bengal measures the hydrologic
data such as runoff at the outlet of the watershed every
where, P = total precipitation (mm), Ia= initial one hour. An automatic rain gauge and another non-
abstraction (mm), F = cumulative infiltration excluding recording rain gauge were installed at the outlet of the
Ia (mm), Q = direct runoff (mm), and S = potential watershed from which daily rainfall as well as eventwise
maximum retention or infiltration (mm). rainfall amount and intensity with respect to time were
The current version of the SCS-CN method found out. The data are available from the year 1995
onwards.
assumes  equal to 0.2 for usual practical applications.
As the initial abstraction component accounts for Land use/ land cover data
surface storage, interception, and infiltration before
Indian Remote Sensing satellite digital image (IRS-
runoff begins,  can take any value ranging from 0 to
1A, LISS-II-B1, row: 20, path: 52 with spatial resolution
. Combining equations (1) and (2), one can write an of 36.25 m) of year 1989 (dates of pass 21st February
equation for Q as follows: and 13th November) as well as (IRS-1D, LISS-III, row:
107, path: 56 with resolution 23.5 m) for the year 2000
(P  I a ) 2 (dates of pass 22nd February and 14th November) were
Q (4)
P  Ia  S imported to the ERDAS/ IMAGINE image processing
software. These images were rectified and
Substituting Ia by 0.2S, the equation in its standard geometrically corrected with respect to already rectified
form is and mosaic topo-sheets of that area. This process of

32
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

rectification was done by transferring the coordinates curve number values corresponding to different land
of permanent features like road and rail crossings; uses, then the weighted curve number for that grid was
bridges, barrages etc. on the river; as well as road- found out by using the formula
canal or rail-canal crossings present on rectified topo-
sheets to satellite images. The three basic colours of CN1  A1  CN 2  A2  ...  CN n  An
red, blue and green were assigned to different bands of CN  (7)
A
image, which produced false colour composite (FCC)
image. Then the Tarafeni watershed portion was subset where A1, A2 , ……, An correspond to area of each
from the full image. The classification of FCC was polygon having CN value CN 1 , CN 2 ,…, CN n
carried out with ERDAS/ IMAGINE software using respectively, and A = area of each grid
maximum likelihood classifier (MLC) algorithm and =A1 +A2 +…..+An .
ground truth information. All the three levels of land
use/land cover classification system (NRSA, 1995) were Composited CN method
adopted for classification. A total of eight classes were In composited method, CN was estimated using a
considered for classification. The classified images in procedure in which area weighted average curve
raster format was changed to vector format (polygons) numbers are calculated either for the entire area under
using ERDAS/IMAGINE software. Each polygon had consideration, or for a small number of relatively
different attributes, like its area, perimeter and land use homogeneous sub-areas. Composite curve numbers
/land cover class. Next, this coverage was intersected were determined by overlaying land-use and soils maps
with the watershed grid coverage to find out grid wise to delineate polygons with unique land use and
land use /land cover values. The resolution of the grid hydrologic soil group (HSG) combinations within the
was kept at 400 m × 400 m. In individual grids, there watershed or sub-watershed being studied. A CN value
were several polygons having different attributes. was then assigned to each grid and the area-weighted
Soil coverage average was calculated to determine the composite CN
for the watershed.
Soil map of the study area was procured from All
India Land Use and Soil Survey, and it was scanned, Distributed CN method
rectified and geometrically corrected. Then different In the distributed approach, runoff depth was
soil polygons representing different types of soil texture estimated for each individual grid cell or polygon in the
were digitized using ARC/INFO software. Different watershed, based on the land use and soil conditions at
attributes of soil such as texture, hydrologic soil groups, that location. There was no CN averaging, rather
etc., were assigned to these polygons. separate CN values were determined for each cell or
Curve number coverage polygon and separate runoff values were calculated for
each cell or polygon. These runoff values were then
The generated land use coverage and the soil averaged to find out the total runoff depth for the whole
coverage were merged using UNION command of watershed.
ARC/INFO software. The resultant coverage contained
attributes of both the coverage. The antecedent moisture Simulation studies
condition was assumed to be AMC II. Using ARC/ Four different simulations with different
INFO software, all the polygons having a particular land combinations of CN methods and initial abstraction
use and a hydrologic soil group were selected at a time values were considered in this study. In simulation I,
and then curve numbers were assigned to these polygons runoff was estimated using composited CN method and
using conditional assignment of attributes. Thus, a curve initial abstraction (Ia) value as 0.3S, for simulation II it
number coverage is generated in which different was distributed CN with initial abstraction (Ia) value as
polygons have different curve number values. Similarly 0.3S, simulation III was composited CN with Ia as 0.2S,
curve number coverages were developed for other and for simulation IV it was distributed CN with Ia as
AMC conditions. Finally, these coverages were 0.2S. Then runoff values obtained by these four
intersected with watershed grid. For each grid, the curve combinations were compared with the observed runoff
number was determined by using weighted area method. values for different rainfall events. The runoff values
If a grid contains n number of polygons having different obtained by all these four methods were then statistically

33
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

evaluated to find out the superior method for estimating that of equation (8). The E values can vary from 0 to 1,
runoff. The statistical methods used are explained in with 1 indicating a perfect fit. The model efficiency, E
the following paragraphs. has been widely used to evaluate the performance of
hydrologic models (Wilcox et al., 1990). Model efficiency
Evaluation criteria of different CN methods represents an improvement over the R 2 for model
The different curve number approaches were evaluation purposes, in that it is sensitive to differences
evaluated using different statistical techniques as in the observed and model simulated means and
suggested by ASCE Task Committee (1993). The variances.
following performance evaluation criteria were adopted Another technique is determination of coefficient
in this study. of residual mass (CRM) (Hack-ten Broeke and
The coefficient of determination (R2) describes the Hegmans, 1996). CRM statistics gives the degree to
proportion of the total variance in the observed data which the prediction is overestimated or underestimated.
that can be explained by the model. It ranges from 0.0 Positive value of CRM indicates that the model
to 1.0, with higher values indicating better agreement, underestimates the measured or observed and a negative
and is given by: value of CRM indicates a tendency to overestimate.
The expression of CRM can be given as:
2
  N N
 N 

 
Oi  O avg Si  Savg    Oi   Si
  i 1 i 1
2 i 1 CRM 
R  N (11)
0.5 
 N 0.5
 N
2  (8)  Oi

  Oi  Oavg  
2

  Si  Savg  
 
i 1
  i 1   i 1  
Another measure of the accuracy of prediction
capability of a model is the root mean square error
where, Oi = the ith observed data, Oavg = mean of (RMSE), defined as (Thomann, 1982):
the observed data, Si= the ith simulated value, Savg =
the mean of simulated value, and N = total number of N
events.  O i  Si 2 (12)
i 1
RMSE 
The percent deviation, Dv is one “goodness of fit” N
criterion (Martinec and Rango, 1989), which is
expressed by RMSE describes the difference between the model
simulations and observations in the units of the variable.
V  V
D v (%)   100 (9)
V Based on the probability concept, pairwise
comparison for significant difference between the
where V is the observed value of variable and V  is means of observed and model simulated values were
the simulated value. Smaller value of Dv indicates better done by using Student’s t statistics and given by:
model prediction. For a perfect model, Dv is equal to D av N 0.5
zero. Another basic goodness of fit criterion is the model tc  (13)
efficiency, E (Nash and Sutcliffe, 1970) which is given
S D 
by
where D av is the average of the differences
N between the model simulated (Si) and observed (Oi)
 O i  Si 2 values, N is the number of observations and SD is the
E  1  i 1 sample standard deviation of the difference values.
N (10) Following hypotheses is tested for determining that
 O i  O avg 2 whether the difference between the observed and
i 1
predicted values is significant or not.
The notations of above equation are the same as H0: Dav = 0.0 and H1: Dav  0.0

34
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

Criteria for acceptance: if |tc|  t0.975, N-1 accept H0. was then calculated at each grid level and averaged to
The calculated value of student’s t (tc), less than that of find out the runoff at the outlet. Runoff was calculated
the t-tabulated value at N-1 degree of freedom and 5% using both composited and distributed CN techniques
level of significance (i.e. probability of type-I error/ using two different values of Ia : 0.2S and 0.3S. The
significance level of the test () = 0.025 for two tailed results are presented in figure 1.
‘t’-test), indicates that the difference between means
is not significant at 5% significance level. The rejection It is observed from figure 1 that there is definitely
of null hypothesis at 5% significance level indicates that an increase in runoff value estimated by distributed CN
there exists significant difference between the means technique over composited CN technique for both the
of observed and simulated values. cases of initial abstraction values of 0.2S and 0.3S.
However, the percentage increases in runoff incase of
RESULTS AND DISCUSSION 0.3S is comparatively higher than that of 0.2S case.
Hence for choosing which CN technique should be used
The results of land use/ land cover classification for estimation of runoff in a watershed, it is desirable to
are presented in Table 1. The classification accuracy compare runoff values obtained by different techniques
for the Tarafeni watershed for the year 2000 is 91.2% with the observed values. The results are presented in
and for 1989 is 89.3%. From Table 1, it is observed that Figure 2 and Table 2.
in the Tarafeni watershed dense forest, degraded and
fallow land have been reduced, open forest area 30.0

increased from 13.3% to 19.3%, waste land developed 25.0 Composited,0.3S

to 2.3% area of total watershed from nil. 20.0


Distributed, 0.3S
Composited,0.2S
Runof f , mm

Distributed, 0.2S
The distributed CN technique was applied to the 15.0
Observed

Tarafeni watershed. The gridwise curve number 10.0

coverage was generated both for seedbed preparation 5.0

stage and growing stage for both the years. The runoff 0.0
25.0 30.0 32.6 34.0 36.0 38.0 40.0 43.0 45.5 48.6 51.0 63.0 70.0 77.0 80.0
Rainf all, mm
40
(% )

35
Fig. 2. Funoff estimated by different methods
seed bed (2000)
in r u n o f f

30 growing (2000)
It is observed from figure 2 that runoff estimated
s erunoff

25 seed bed (1989)


growing (1989)
using both composite and distributed CN techniques
20
considering Ia=0.3S yields lower runoff compared to
In c r e ain

15
Increase

10
the observed one in all the events considered for rainfall
5
amounts varying from 25 mm to 80 mm during 1999 to
0
2001. Runoff estimated using composite technique for
30 40 50 60 70 80 90 100 110 120 130 Ia=0.2S yields comparable results with the observed
Rainfall (mm)
runoff for rainfall events of more than 63 mm of rainfall.
(a) Ia=0.2S However runoff estimated using distributed technique
140 and Ia=0.2S gave almost same results as observed.
in r u n o ff ( % )

120 seed bed (2000) To support the above findings, statistical analysis
growing (2000)
100 was carried out to find out superiority of one approach
In c r e ains erunoff

seed bed (1989)


80
growing (1989)
over the other in terms of closeness of predicted and
60 the observed values. The results are presented in Table
Increase

40 2. It is observed from the table that percent deviation


20 of runoff estimated using composited method for Ia=0.3S
0
from the observed runoff varies from 21.27% to 99.88%.
30 40 50 60 70 80 90 100 110 120 130 The lowest deviation is for the largest event (80 mm on
Rainfall (mm) 20th July 1999) and the highest deviation of 99.88% is
(b) Ia= 0.3S for the smallest event (25 mm on 1st September 2000)
Fig. 1 Increase in runoff estimated by distributed CN over considered for this study. Similarly for distributed CN
composited CN technique for Ia=0.2S and Ia=0.3S. method with Ia=0.3S, percent deviation varies from

35
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

Table 1. Land use/ land cover statistics of the Tarafeni watershed

Land use/ land cover Year 1989 Year 2000 Change in


Area (ha) % Area (ha) % area (%)
Dense forest 2715.0 17.18 1874.9 11.86 -5.32
Open forest 2109.6 13.35 3046.6 19.28 +5.93
Degraded forest 3337.0 21.11 2932.7 18.55 -2.56
Cropland 1961.6 12.41 2207.0 13.96 +1.55
Fallow land 4029.8 25.5 3815.4 24.14 -1.36
Wet land 605.0 3.83 639.4 4.05 +0.22
Waste land 0.0 0.0 367.9 2.33 +2.33
Water bodies 1048.1 6.63 922.13 5.83 -0.80
Total 15806.1 100 15806.1 100

Table 2. Evaluation of different CN techniques for estimation of runoff (t- critical value for two tail t distribution=2.145)

13.91% to 63.64%. This deviation is lower as compared From the other statistical analysis results presented
to the composited method with same initial abstraction in Table 2, it is observed that the coefficient of residual
value. For initial abstraction of 0.2S the composited mass (CRM) is positive and it varies from 0.399 to 0.103
method estimated runoff with percent deviation varying for composited methods (for both Ia=0.2S and 0.3S)
from 0.15% to 63.95%. Though it has very low percent and also for distributed method (Ia=0.3S). In distributed
of deviation for larger events, the deviation is greater CN approach for Ia=0.2S, the CRM is very low (-0.022)
for small events. For the distributed CN method and which reflects the closeness of prediction with a very
Ia=0.2S, the percent deviation varies from 16.86% to little tendency of over prediction. Model efficiency varies
23.03%. Though this method does not give definite trend from 0.699 to 0.990. The highest value being for
to predict runoff, the percent deviation is lowest in distributed CN with Ia=0.2S. Coefficient of determination
comparison to all other methods considered in this study. (R2) value is very high for all the cases. This is due to

36
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

the fact that runoff estimated using different case of Ia=0.3S than Ia=0.2S. The percent increase in
methodologies use the same equation. RMSE is only runoff is very high for small events, moderate for
0.73 mm for distributed CN (Ia=0.2S), whereas it is as medium and low for high rainfall events. Hence,
high as 4.12 mm for composited (Ia=0.3S). From the distributed CN technique with initial abstraction as 0.2
above results, it is seen that percentage deviation and times of potential maximum retention of soil should be
RMSE are lowest for runoff values estimated using used for runoff estimation in medium or large agricultural
distributed CN technique with Ia=0.2S. In students’ t- watersheds having large variation in land use. Further,
test, it is found that calculated t value for first three remote sensing and GIS can be effectively used to
techniques yield higher value than the critical table value accurately estimate runoff through distributed curve
(t0.975,14 ) for two tail distribution. This proves the number technique.
superiority of distributed CN technique (Ia=0.2S) over REFERENCES
all other techniques as the calculated t value of –1.191
is lower than the critical table value of 2.145. 1. ASCE task committee. 1993. Criteria for evaluation of
watershed models. J. Irri. and Drain. Engg., Vol. 119,
No. 3, pp. 429-442.
30
Distributed CN, Ia=0.2S 2. Hack-ten Broeke M J D; Hegmans J H B M. 1996. Use of
25 1:1 line
soil physical characteristics from laboratory
simulated runoff (mm)

measurements or standard series of modeling


20 unsaturated water flow, Agril. Water. Manag. Vol.29,
No. 2, pp. 201-213.
15 3. Jain, M.K., Mishra, S.K. and Singh, V.P. 2006.
Evaluation of AMC-dependent SCS-CN-based models
10 using watershed characteristics,’ J. Water Resources
Management, 20(4): 531-555.
5
4. Martinec J; Rango A. 1989. Merits of statistical criteria
0 for the performance of hydrological models. Water
0 5 10 15 20 25 30 Resour. Bull. AWRA, Vol. 25, No. 2, pp. 421-432.
observed runoff (mm) 5. Mishra, S.K. and V.P., Singh, 2003. Soil Conservation
Service Curve Number (SCS-CN) Methodology, Kluwer
Fig. 3. Observed versus simulated runoff using distributed CN Academic Publishers, Dordrecht, The Netherlands,
technique with Ia=0.2 ISBN 1-4020-1132-6.

Figure 3 shows a graph of observed versus 6. Mishra, S.K., Jain, M.K., and Singh, V.P. 2004.
Evaluation of the SCS-CN-based model incorporating
simulated runoff using distributed CN technique for
antecedent moisture, J. Water Resources Management
Ia=0.2S. It is clearly seen that the data points are very (WARM), (18): 567-589.
close and clustered around the 1:1 line. Hence it can be
inferred that for the Tarafeni watershed distributed CN 7. Mishra, S.K., Jain, M.K., Bhunya, P.K. and Singh, V.P.
technique considering initial abstraction as 0.2S is a 2005.Field applicability of the SCS-CN-inspired
Mishra-Singh general model and its variants,’ J. Water
better predictor of runoff using SCS CN technique.
Resources Management, 19(3): 37-62.
CONCLUSIONS 8. Narayana, V. V. D. 1993. Soil and water conservation
research in India, Indian Council of Agril. Research,
In Indian watersheds, usually composite CN Krishi Anusandhan Bhawan, Pusa, New Delhi.
technique is used with initial abstraction as 0.1S for
black clay soil and 0.3S for rest of the soils (Narayana, 9. Nash J E; Sutcliffe J V. 1970. River flow forecasting
1993), But from the above investigation, it is found that through conceptual models, Part-1: a discussion of
principles, J. Hydrol., Vol. 10, No. 3, pp. 282-290.
these techniques yield lower runoff values compared
to the observed value. The pertinent observations from 10. NRSA. 1995. Integrated mission for sustainable
the study is that there is a definite increase in runoff development. technical guidelines, National Remote
value estimated by distributed CN technique over Sensing Agency, Dept. of Space, Balanagar, Hyderabad,
composited and the amount of increase is more for the pp. 86-87.

37
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

11. Pandey, A. and Dabral, P.P. 2004. Estimation of runoff watershed to landuse changes: A remote sensing and
for hilly catchment using satellite data and GIS. J. GIS approach. International Journal of Remote
Indian Soc. Remote Sensing 32 (2): 235-240. Sensing, 22 (11), 2095-2108.
12. Pandey, A. and Sahu, A.K. 2004. Estimation of runoff 16. Stuebe, M. M. and Douglas M. J., 1990, Runoff volume
using IRS-1 B LISS-II data. Indian J. Soil Cons. 32 (1): estimation using GIS technique, Water Resources
58-60. Bulletin, American Water Resources Association, 26(4),
611-620.
13. Pandey, A., Chowdary, V.M., Mal, B. C. and Dabral, P.
P.2005. Estimation of surface water potential of 17. Thomann, R. V. 1982. Verification of water quality
agricultural watershed using geographic information models, J. Environ. Engg. Div., 108 (5), 923-940.
system. Asian J. Geoinformatics. 5 (4): 29-36.
18. SCS (Soil Conservation Services), 1985, National
14. Sharma, D. and Kumar, V., 2002, Application of SCS Engineering Hand book, section 4: Hydrology
model with GIS data base for estimation of runoff in an (Washington, D.C., Soil Conservation Services, USDA).
arid watershed, Journal of Soil and Water
19. Wilcox B P; Rawls W J; Brakensiek D L; and Weight J R.
Conservation, 30 (2) , 141-145.
1990. Predicting runoff from rangeland catchments: a
15. Sharma, T., Satya Kiran, P.V., Singh, T.P., Trivedi, A.V. comparison of two models, Water Resour. Res., 26, 2401-
and Navalgund, R.R., 2001, Hydrologic response of a 2410.

38
J. Indian Water Resour. Soc.of
Journal Vol.Indian
30 No.Water
1, January, 2010
Resources
Society Vol. 30 No. 1, January, 2010
SEDIMENT RUNOFF MODELING USING ARTIFICIAL NEURAL NETWORKS

Archana Sarkar1, M. Mohan Raju2 and Anil Kumar2

ABSTRACT

The magnitude of sediments transported by rivers is a major concern for the water resources
planning and management. The methods available for sediment estimation are largely empirical,
with sediment rating curves being the most widely used. In this study, Artificial Neural Network
(ANN) technique has been applied to model the sediment-discharge relationship of a river. Daily
data of sediment concentration and discharge of Pranhita River (a sub-basin of Godavari River)
in India have been used. A comparison has been made between the results obtained using ANNs
and sediment rating curves. The sediment load estimations in the river obtained by ANNs have
been found to be significantly superior to the corresponding classical sediment rating curve
ones.

INTRODUCTION fitting methods are unable to model the non-linearity in


the relationship. On the other hand, the application of
The sediment outflow from a catchment is induced physics-based distributed process computer simulation
by processes of detachment, transportation and offers another possible method of sediment prediction.
deposition of soil materials by rainfall and runoff. The But the application of these complex software programs
assessment of the volume of sediments being is often problematic, due to the use of idealized
transported by a river is required in wide spectrum of sedimentation components, or the need for massive
problems such as the design of reservoirs and dams; amounts of detailed spatial and temporal environmental
hydroelectric power generation and water supply; data, which are not available. Simpler approaches are
transport of sediment and pollutants in rivers, lakes and therefore required in the form of ‘black-box’ modeling
estuaries; determination of the effects of watershed techniques. Neurocomputing provides one possible
management; and environmental impact assessment. answer to the problematic task of sediment transfer
Keeping this in view, in the present study, runoff- prediction. In recent years, artificial neural networks
sediment modeling has been carried out for Pranhita (ANNs) which are simplified mathematical
River, a major tributary of Gopdavari River. Pranhita representation of the functioning of the human brain
sub-basin system, which conveys the combined waters have been widely used in runoff and sediment yield
of Penganga, Wardha and Wainganga influences the modeling. Three layered feed forward ANNs have been
Godavari river system to the maximum possible extent shown to be a powerful tool for input-output mapping
(with 34% drainage area i.e., 1,09,100 km2 area) by and have been widely used in water resources
means of rainfall, runoff and sediment transportation. engineering problems (ASCE Task Committee, 2000).
For estimating the sediment concentration/yield, The application of ANN approach for modeling
there exist various models and techniques, such as sediment-discharge process is very recent, and has
sediment rating curves, erosion modeling, etc. The already produced very encouraging results. In a
models vary from a simple regression relationship to research project by Rosenbaum (2000), ANN technique
complex simulation models. As the sediment-discharge has been used to predict sediment distribution in Swedish
relationship is not linear, conventional statistical tools harbors. Baruah et al., (2001) developed neural network
used in such situations such as regression and curve models of Lake surface chlorophyll and sediment
1
National Institute of Hydrology, Roorkee-247667, Uttarakhand, content from LandsatTM imagery in order to assess
India the water quality of the lake Kasumigaura in Japan and
2
Department of Soil and Water Conservation Engineering, College of
Technology, G. B. Pant University of Agriculture and Technology, found that back propagation neural network with only
Pantnagar-263145, Uttarakhand, India. one hidden layer could model both the parameters better
Paper No. 1181

39
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

than conventional regression techniques. Jain (2001) the form:


used the ANN approach to establish an integrated stage-
discharge-sediment concentration relation for two sites C = aQb (1)
on the Mississipi River and showed that the ANN results And the log-transformed form will plot as a straight line
were much closer to the observed values than the on log-log paper:
conventional technique. Nagy et al., (2002) applied
ANN technique to estimate the natural sediment log C = log a + b log (Q) (2)
discharge in rivers in terms of sediment concentration Where, C = sediment concentration (or load), Q =
and addressed the importance of choosing an appropriate discharge, a & b are regression constants.
neural network structure and providing field data to that
network for training purpose. Sarkar et al., (2004) ARTIFICIAL NEURAL NETWORKS (ANNs)
applied ANN technique to model the sediment-discharge
relationship of Kosi River of Bihar in India and found An ANN is a computing system made up of a highly
that sediment load estimations in the river obtained by interconnected set of simple information processing
ANNs were superior to the sediment rating curve ones. elements, analogous to a neuron, called units. The
Kerem et al., (2006) estimated the river suspended neuron collects inputs from both a single and multiple
sediment using ANN algorithm and compared with the sources and produces output in accordance with a
conventional sediment rating curve and found the predetermined non-linear function. An ANN model is
superiority of the ANN application. Kisi (2007) and Rai created by interconnection of many of the neurons in a
& Mathur (2008) have reported good application known configuration. The primary elements
efficiency of ANNs in the sediment yield modeling when characterizing the neural network are the distributed
compared with the conventional modeling techniques. representation of information, local operations and non-
linear processing. Fig.1 shows the general structure of
In the present study, two techniques, namely, a three layer back propagation ANN.
sediment rating curve and artificial neural networks h1
wh11 wo11
(ANNs), have been applied for modeling the sediment-
discharge relationship for Pranhita River basin and a x1
y1
comparison of these techniques has been made.
x2 y2
Input . Output
SEDIMENT RATING CURVES . .
. : yno
. h4
xni
Sediment rating curves are widely used to estimate .
. wono,ni
the sediment concentration being transported by a river. whnh,ni

A sediment rating curve is a relation between the hnh


sediment concentration and river discharge. Sediment Input layer Hidden layer Output layer
rating curves may be plotted showing average sediment i =1, 2, 3……ni j=1, 2, 3 …….nh k=1, 2, 3…….no
concentration or load as a function of discharge averaged
Fig 1. Structure of a multi-layer feed forward artificial
over daily, monthly, or other time periods. Rating curves neural network model.
are developed on the premise that a stable relationship
between concentration and discharge can be developed The main principle of neural computing is the
which, although exhibiting scatter, will allow the mean decomposition of the input-output relationship into series
sediment yield to be determined on the basis of the of linearly separable steps using hidden layers (Haykin,
discharge history. A problem inherent in the rating curve 1994). Generally there are four distinct steps in
technique is the high degree of scatter, which may be developing an ANN-based solution. The first step is
reduced but not eliminated. Concentration does not the data transformation or scaling. The second step is
necessarily increase as a function of discharge the network architecture definition, where the number
(Ferugson 1986). of hidden layers, the number of neurons in each layer,
and the connectivity between the neurons are set. In
Mathematically, a rating curve may be constructed the third step, a learning algorithm is used to train the
by log-transforming all data and using a linear least network to respond correctly to a given set of inputs.
square regression to determine the line of best fit. The Lastly, comes the validation step in which the
log-log relationship between load and discharge is of performance of the trained ANN model is tested through

40
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

some selected statistical criteria. The theory of ANN years (June 1, 2000 – May 31, 2004) constituting a total
has not been described here and can be found in many of 1461 patterns. Out of this, 730 patterns were used
books such as Haykin (1994). for training, 365 patterns for testing and 366 patterns
for validation.
STUDY AREA, DATA AVAILABILITY AND
SELECTION OF INPUT/OUTPUT VARIABLES The first step in developing any model is to identify
the input and output variables. The output from the
In the present study the runoff-sediment modeling models is the sediment concentration at time step t; Ct.
has been carried out for Pranhita sub-basin system, It has been shown by many authors that the current
which conveys the combined waters of Penganga, sediment concentration can be mapped better by
Wardha and Wainganga. The hydrological data for the considering, in addition to the current value of discharge,
study has been collected at Tekra site on Pranhita river the sediment and discharge at the previous times.
(Fig. 2). After the Tekra site, Pranhita river joins the Therefore, in addition to Qt, i.e., discharge at time step
main Godavari in Andhra Pradesh. t, other variables such as Qt-1, Qt-2, and Ct-1, Ct-2, were
The daily data of sediment concentration and also considered in the input.
discharge were available at the Tekra site for four water

Fig. 2 Pranhita river system and hydrological study location (Tekra site)

41
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

RATING CURVE ANALYSIS Q = Discharge in the River Pranhia at Tekra in


Cumec at time t
Based on the sediment rating curve technique given
by equation (1), the sediment rating equation between DESIGN AND TRAINING OF ANN MODELS
sediment load and discharge for Pranhita River at Tekra
site for the training period is Various combinations of input data considered for
training of ANN in the present study are given in Table
C = (4.94E-04)Q0.770 (3) 1. However, the input-output variables of ANN-1 have
been used for the conventional sediment rating curve
Where, C = Sediment concentration in the River analysis.
Pranhia at Tekra in gm/l at time t

Table 1: Various ANN Runoff-Sediment Models

ANN Architecture Output Input Variables


Model Variable
ANN-1 [1 – 2 – 1] Ct Qt
ANN-2 [3 – 3 – 1] Ct Qt, Qt-1, Ct-1
ANN-3 [5 – 4 – 1] Ct Qt, Qt-1, Qt-2, Ct-1, Ct-2
ANN-4 [7 – 6 – 1] Ct Qt, Qt-1, Qt-2, Qt-3, Ct-1, Ct-2, Ct-3
ANN-5 [9 – 7 – 1] Ct Qt, Qt-1, Qt-2, Qt-3, Qt-4, Ct-1, Ct-2, Ct-3, Ct-4
ANN-6 [1 – 2 – 5 – 1] Ct Qt
ANN-7 [3 – 3 – 5 – 1] Ct Qt, Qt-1, Ct-1
ANN-8 [5 – 4 – 5 – 1] Ct Qt, Qt-1, Qt-2, Ct-1, Ct-2
ANN-9 [7 – 6 – 5 – 1] Ct Qt, Qt-1, Qt-2, Qt-3, Ct-1, Ct-2, Ct-3
ANN-10 [9 – 7 – 5 – 1] Ct Qt, Qt-1, Qt-2, Qt-3, Qt-4, Ct-1, Ct-2, Ct-3, Ct-4

Where, C=Sediment Concentration at Tekra in g/l, the maximum value of respective variable reducing the
Q=Discharge at Tekra in cumecs, t represents the time data in the range 0 to 1 to avoid any saturation effect
step in days that may be caused by the use of sigmoid function. All
interconnecting links between nodes of successive layers
A back-propagation ANN (BPANN) with the were assigned random values called weights. A constant
generalized delta rule as the training algorithm has been value of 0.15 and 0.8 respectively has been considered
employed in this study. The ANN package Neural for learning rate  and momentum term  selected after
Power (NP), 2003, downloaded from the Internet has hit and trials. The range tried for learning rate  and
been used for the ANN model development. The momentum term  were 0.10-0.40 and 0.7-0.9
structure for all simulation models is three and four layer respectively. The quick propagation (QP) learning
BPANN which utilizes a non-linear sigmoid activation algorithm has been adopted for training of all the ANN
function uniformly between the layers. Nodes in the models. QP is a heuristic modification of the standard
input layer are equal to number of input variables, nodes back propagation and is very fast. The network weights
in hidden layer are varied from the default value by the were updated after presenting each pattern from the
NP package for various number of input nodes above learning data set, rather than once per iteration. The
to approximately double of input nodes (Zhu et al., 1994) criteria selected to avoid over training was generalization
and the nodes in the output layer is one as the models of ANN through cross-validation (Haykin, 1994). For
provide single output. According to Hsu et al. (1995), this purpose, the data were divided into training, testing
three-layer feed forward ANNs can be used to model and validation sets. Training data (730 patterns) were
real-world functional relationships that may be of used for estimation of weights of the ANN model and
unknown or poorly defined form and complexity. testing data (365 patterns) for evaluation of the
Therefore, three-layer networks were tried in this study. performance of ANN model during training. Training
However, four layer ANN models were also tried for was stopped when the error for the testing dataset
comparison purpose. started increasing i.e., when R started decreasing for
The modeling of ANN initiated with the the testing dataset as the software does not calculate
normalization (re-scaling) of all inputs and output with RMSE automatically during testing/validation phase. In

42
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

this way, the training and testing datasets have been 0.075g/l) for all the ANN models except ANN-1 and
used to assess the performance of various candidate ANN-9 models, during training. However, RMSE is
model structures, and thereby choose the best one. The lowest for ANN8 (0.151g/l) during testing and for ANN9
particular ANN model with the best performing (0.162g/l) during validation. Whereas, RMSE of the
parameter values was chosen and the generalized rating curve model is very high, i.e., 0.472g/l, 0.359g/l
performance of the resulting network has been measured and 0.424g/l during training, testing and validation
on the validation data set (366 patterns) to which it has respectively.
never before been exposed. The performance of all
the ANN models have been tested through three It can be seen from Table 2 that the correlation (R)
statistical criterion, viz, root mean square error (RMSE), values are high (more than 0.90) for all the ANN models
correlation coefficient (R) and Coefficient of during all the three phases. The performance of ANN-
Determination (DC). 9 model is the best in R statistic with R values of 0.959
and 0.954 during testing and validation respectively. The
RESULTS AND DISCUSSION performance of the rating curve model is the worst when
compared with the ANN models. The R values for rating
The comparative performance of various ANN curve model are 0.923, 0.870 and 0.867 during training,
models and rating curve analysis in terms of RMSE, R testing and validation respectively. These values are
and DC are given in Table 2. It can be seen from Table even lower than the worst ANN model, i.e., ANN-1
2 that the RMSE values are generally low (less than model.

Table 2: Comparative Performance of Various ANN models and Rating Curve

ANN Network Training Testing Validation


Model Architecture RMSE R DC RMSE R DC RMSE R DC
(g/l) (g/l) (g/l)
ANN1 [1-2-1] 0.075 0.978 0.957 0.228 0.907 0.743 0.284 0.912 0.667
ANN2 [3-3-1] 0.067 0.983 0.966 0.170 0.951 0.856 0.217 0.946 0.805
ANN3 [5-4-1] 0.063 0.985 0.969 0.174 0.949 0.850 0.223 0.945 0.794
ANN4 [7-6-1] 0.060 0.986 0.973 0.168 0.953 0.860 0.217 0.943 0.806
ANN5 [9-7-1] 0.064 0.985 0.969 0.173 0.944 0.852 0.210 0.940 0.819
ANN6 [1-2-5-1] 0.071 0.980 0.962 0.229 0.903 0.740 0.284 0.919 0.675
ANN7 [3-3-5-1] 0.070 0.981 0.963 0.159 0.955 0.874 0.198 0.949 0.837
ANN8 [5-4-5-1] 0.067 0.984 0.966 0.151 0.953 0.887 0.217 0.920 0.805
ANN9 [7-6-5-1] 0.076 0.978 0.957 0.187 0.959 0.904 0.162 0.954 0.891
ANN10 [9-7-5-1] 0.056 0.987 0.974 0.169 0.950 0.859 0.210 0.948 0.818
SRC -- 0.472 0.923 0.680 0.359 0.870 0.870 0.424 0.867 0.668

In the coefficient of determination (DC) statistic, sediment-discharge relation of the Pranhita River at the
all the ANN models except ANN-1 perform well. In gauging site Tekra. The performance of the rating curve
DC statistic also, ANN-9 model performs the best during model is average in the R criteria but drastically poor in
testing and validation phases. The performance of rating other two criteria. It is because the estimated sediment
curve model in DC statistic has gone down drastically series (from sediment rating curve model) follows a
with DC values as low as 0.68, 0.87 and 0.668 during good general trend as that of the observed sediment
training, testing and validation respectively. series which gives high R values, but there is a significant
difference in the numeric values of observed and
It can be seen that ANN-9 model is the best estimated sediment concentration due to which the
performing model in two statistical and hydrological RMSE and DC values are very poor. The performance
criteria during testing and validation phase. ANN( model of the corresponding ANN model with only discharge
also has low RMSE values of 0.076, 0.187 and 0.162 as input, i.e. ANN-1 is also better as compared with
during training, testing and validation respectively. A the sediment rating curve technique.
model which performs better in the validation phase is
the best model as it is the most generalized model. The temporal variation of the observed sediment
Therefore, ANN-9 model is the model representing concentration and the estimate using the conventional

43
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

technique and ANN (ANN-9) for the training, testing significant mismatch with the observed curve, especially
as well as validation period is plotted in Fig 3. It is seen during the validation phase which conforms to the low
from the graph that ANN estimates very closely follow coefficient of determination of rating curve technique.
S e d i m e n t c o n c e n t r a t i o n ( g /l )

the observed curve, whereas conventional approach has

14
Obs erv ed
12 Es tiamte d (A N N )
10 Es timate d (SR C )

8
6
4
2
0
1 101 201 301 401 501 601 701
-2
T im e (d ay s )
S e d i m e n t c o n c e n t r a t i o n ( g /l )

(a) Training

5
Observed
4.5 Est imated (A N N )
4 Est imated (SR C )
3.5
3
2.5
2
1.5
1
0.5
0
-0.5 1 101 201 301
T im e (d ays )
S e d i m e n t c o n c e n t r a t i o n ( g /l )

(b) Testing

3.5
Observed
Est imated (A N N )
3
Est imated (SR C )
2.5

1.5

0.5

0
1 101 201 301
-0.5 T im e (d ays )

(c) Validation
Fig. 3. Comparative performance of observed, estimated (ANN) and estimated (rating curve) sediment concentration series

44
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

CONCLUSIONS Imagery”, Proc. 22nd Asian Conf. on Remote Sensing,


5-9 November 2001, Singapore.
In the presented study ANN technique has been
3. Ferugson, R.I. 1986, “River Loads Underestimated by
utilized for modeling the sediment-discharge process in
Rating Curves”, Water Resources Research, Vol. 22(1),
a river. The primary aim of the presented study is to pp.74-76.
illustrate the capability of ANN technique for modeling
sediment load in rivers. To achieve the objectives, a 4. Haykin, S. 1994, “Neural Networks - a Comprehensive
Foundation. Macmillan”, New York.
case study has been done utilizing four years of daily
data of the Tekra gauging site of Pranhita river (a sub- 5. Hsu, K., Gupta, H.V., & Sorooshian, S. 1995, “Artificial
basin of Godavari River) in India for analysis. Based Neural Network Modelling of the Rainfall-Runoff
on the selected performance evaluation criteria, ANN- process”, Water Resources Research, vol. 31(10),
pp.2517-2530.
9, i.e., four layered back propagation ANN model with
7 input variables, 6 nodes in the first hidden layer, 5 6. Jain, S.K. 2001, “Development of Integrated Sediment
nodes in the second hidden layer and one output variable Rating Curves using ANNs”, J. of Hydraulic
represents the best model simulating the sediment- Engineering, ASCE, Vol. 127(1), pp.30-37.
discharge relationship of the Pranhita River at Tekra 7. Kerem, H., Cigizoglu, and Alp, M. 2006. Generalized
gauging site. The results of ANN have been compared regression neural network in modeling river sediment
with those of the conventional sediment rating curve yield. Advances in Engineering Software archive,
approach. ANN results have been found to be much 37(2), pp. 63-68.
closer to the observed values than the conventional 8. Kisi, O. 2007. Development of streamflow-suspended
technique. sediment rating curve using a range dependent neural
network. International Journal of Science and
The study demonstrates that ANN technique can Technology.
be successfully applied for development of reliable 9. Nagy, H.M., Watanabe, B., and Hirano, M., 2002,
relationships between sediment and discharge in a river “Prediction of Sediment load Concentration in Rivers
when other approaches cannot succeed due to the Using Artificial Neural Network Model”, J. of
uncertainty and the stochastic nature of the sediment Hydraulic Engineering, ASCE, Vol. 128(6) pp.588-595.
movement. Moreover, ANN technique has preference 10. Rawat J.S and Rawat M.S. 1994, “Accelerated erosion
over the conventional methods as ANNs can accept and denudation in the nana kosi watershed, Central
any number of effective variables as input parameters Himalaya, India, Part I: sediment load”, J. of Mountain
without omission or simplification as commonly done in Research and Development, Vol. 14(1), pp 25-38.
conventional methods. The presented ANN model is 11. Raymo M.E. and Ruddiman W.F. 1992, “Tectonic forcing
designed by using only field river data, and it has no of Late Cainozoic Climate”, Nature, Vol. 359, pp. 117-
boundary conditions in application. The only restriction 122.
is that the model cannot estimate accurately the
12. Rosenbaum, M 2000, “Harbours- Silting and
sediment load for data out of the range of training pattern
Environmental Sedimentology (H-SENSE), Final
data. Such a problem can easily be overcome by feeding Report, Dept. of Civil & Structural Engineering”, The
the training patterns with wide range data. Nottingham Trent University, Nottingham, UK. http://
hjs.geol.uib.no/HSense/
REFERENCES
13. Sarkar, A., Kumar, R., Singh, R.D., Thakur, G and Jain,
1. ASCE. Task Committee on Application of Artificial S.K. 2004, “Sediment-Discharge Modelling in a River
Neural Networks in Hydrology. 2000, “Artificial Neural using Artificial Neural Networks”, Proc. Int. Conf.
Networks in Hydrology. II: Hydrologic Applications”, ICON-HERP, Oct 26-28, 2004, IIT, Roorkee, India.
Journal of Hydrologic Engineering, ASCE, Vol.5 (2),
pp.124-137. 14. Zhu, M., Fujita, M., and Hashimoto, N. 1994,
“Application of Neural Networks to Runoff Prediction,
2. Baruah, P. J., Tamura, M., Oki, K. and Nishimura, H. “Stochastic and Statistical Method in Hydrology and
2001, “Neural Network Modelling of Lake Surface Environmental Engineering, vol. 3, K.W. Hipel et al.,
Chlorophyll and Sediment Content from LandsatTM eds., Kluwer, , The Netherlands, pp.205-216.

45
J. Indian Water Resour. Soc.of
Journal Vol.Indian
30 No.Water
1, January, 2010
Resources
Society Vol. 30 No. 1, January, 2010

SINGLE RESERVOIR OPTIMIZATION USING HYBRID GENETIC


ALGORITHM

Nitin M Mohite1 and Sandeep Narulkar2

ABSTRACT

In this paper a hybrid genetic algorithm approach is proposed wherein the GA acts as a
base level search algorithm that generates the initial values for solving the problem with a con-
strained optimization algorithm. The adaptation of the hybrid approach has eliminated the prob-
lems associated with the GA as well as the constrained optimization. The hybrid method proves to
be superior to the pure GA in finding a good solution quickly. The problem is applied to a single
reservoir planning problem for Parbati-Kalisindh-Chambal Interlinking Project in India.

Keywords : Optimization of single reservoir; Genetic algorithms, Hybrid methods

INTRODUCTION reservoir system operation and compared the


performance of the GA approach with that of DP. Both
The water resources planning and management the works showed the significant potential of GA in
problems, particularly the reservoir design and operation water resources system optimization, and clearly
problems are quite complex and dimensionally large. demonstrated the advantage of GA over standard DP
Simulation and optimization techniques play an important in terms of computational requirement. Oliveira and
role in providing a good insight in solving these problems. Loucks (1997) used a GA model to evaluate operating
Numerous researchers have solved the problems of rules for multi reservoir systems, demonstrating that GA
optimum reservoir system planning and operation during can be used to identify effective operating policies.
past five decades using Simulation, Linear Programming
(LP), Dynamic Programming (DP), Nonlinear The breakthrough research work on GA applications
Programming (NLP) etc. along with variants and to reservoir planning and operation problems was
combination of these techniques. An exhaustive and presented by Wardlaw and Sharif (1999). They
extremely useful state-of-the-art review of simulation evaluated GA technique through the solution of the
and optimization methods applied to reservoir systems classic 4 reservoir problem and the 10 reservoir problem
planning and operation problems can be seen in the with extended time horizons explaining various aspects
works of Yeh (1985), Simonovic (1992), Wurbs (1993), of the applicability of the technique. They evaluated
and Labadie (2004) etc. In the recent era various several combinations of GA parameters viz. the binary
evolutionary search algorithms i.e. the Genetic coded and real coded representation, selection,
Algorithms (GA), Ant Colony Optimization (ACO), crossover and mutation etc. Sharif and Wardlaw (2000)
Particle Swarm Optimization (PSO) etc. have taken applied the technique to a multiple reservoir systems
the fore seat. for a case study in Indonesia by considering the existing
development situation in the basin and two future water
The Genetic Algorithm is a global stochastic search resources development scenarios. Results of GA were
technique based on the Darwinian Survival-of-the- compared with those obtained from discrete differential
Fittest principle (Holland 1975). GA models have been dynamic programming. They concluded that genetic
applied successfully to a wide range of reservoir design algorithm results are closer to the optimum.
and optimization problems of moderate size. East and
Hall (1994) and Fahmy et al. (1994) applied GA to the Many other works reported in the literature including
Hilton and Culver (2000) comparing Additive Penalty
1
Research Scholar, Dept of Civil & Applied Mechanics S.G.S.I.T.S, Method (APM) and Multiplicative Penalty Method
Indore
2
Professor, Dept. of Civil & Applied Mechanics S.G.S.I.T.S, Indore
(MPM) for constraint handling in non linear problems
Paper No. 1216 with GA technique, Ahmed and Sarma (2005) comparing

46
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

GA and Stochastic Dynamic Programming (SDP) to simulation of the system, which is a computationally
derive optimal operating policy, Nageshkumar et al. expensive process. The net result is that GA optimization
(2006) stating a GA model for obtaining an optimal is time consuming (Van Zyl et al., 2004). Similar
operating policy and optimal crop water allocation from conclusions were drawn by Chun et al. (2008).
an irrigation reservoir, Jothipraksh and Ganesh Shanti
(2006 and 2009) demonstrating application of GA to The limitations and disadvantages of the GA
multipurpose reservoir system, Momtahen and Dariane techniques can be alleviated through the use of Hybrid
(2007) comparing Real Coded Genetic Algorithm with Genetic Algorithm (HGA). The basic concept of HGA
that of conventional model involving explicit stochastic is coupling of two models, the GA and a constrained or
optimization (ESO) and implicit stochastic optimization an unconstrained nonlinear optimization model. A large
(ISO) approach, Kangrang and Chaleeraktrakoon number of such hybrid algorithms have been reported
(2007) discussing a problem of deriving optimal viz. a combination of GA and Sequential Quadratic
operating rule curves by using genetic algorithms Programming SQP (Marco, 1996, 1998), GA and
connected simulation models, Chouhan and Shrivastava Generalized Reduced Gradient (GRG) (Yen, 2005), GA
(2008) applying preference based approach using GA coupled with Chaos Optimization Algorithm (COA)
based model for optimal operation of a reservoir system (Chun, 2008). These combinations have made the
maximizing irrigation in the command area for two complex optimization problems simpler and easily
seasons and inter reservoir transfers in one of the applicable. Kapelan (2002) narrates following
seasons, Hashemi et al. (2008) showing the applicability advantages of HGA over GA as follows:
of GA model in MATLAB environment for operation 1. Increased computational efficiency typically
of a multipurpose reservoir in stochastic frame work manifested as reduced CPU search time necessary
etc. can be considered to be the benchmark works in to find an optimal solution, or to reach some pre-
the reservoir system planning and operation. Recent specified objective function value.
work of Dariane and Momtahen (2009) demonstrating 2. The optimal objective function value found by HGA
an application of direct search genetic algorithm (DSGS) is better or similar to the one found by GA, indicating
for multi- reservoir system operation can also be better (or similar) model fit. The variation of best
considered as important from the view point of large fitnesses from multiple HGA runs is usually smaller
scale reservoir system problems. than the variation of best fitnesses determined from
Despite the fact that the GA Technique is one of multiple GA runs.
the most suitable technique for direct search and as an 3. More accurate (less uncertain) calibration
optimization model, its applicability to large scale parameter values are typically determined with
problems has certain limitations as pointed out by many HGA than GA.
researchers. Kapelan (2002) has thoroughly The applications of HGA to water resources
summarized the advantages and limitations of GA. He problems are of recent origin except a few studies.
mainly points out that despite the GA Technique having Marco Franchini (1996) and Marco Franchini et al.
good capability of an efficient exploration of large, (1998) applied HGA for calibration of conceptual rainfall
complex, multi-modal search spaces with a less chance runoff modeling. Hsiao and Chang (2002) solved an
to get trapped into the local optimum, their use in terms optimum pumping problem with the use of HGA.
of CPU time is usually very expensive. He further adds Kapelan (2002) applied the HGA to a pipe network
that there is no guarantee that the global optimum will calibration problem. Van Zyl et al., (2004) applied GA
be found, even though good solutions are usually found. and two popular search methodologies the Hooke and
Moreover, in the constrained problems if a penalty Jeeves and Fibonacci methods to solve the problem of
function is not chosen carefully, it may significantly affect water distribution system network problem. Espinoza
GA search performance. He also noticed that GA et al (2005) have developed new Self Adaptive Hybrid
suffers from the slow finishing problem. Premature Genetic Algorithm (SAHGA) to solve optimal ground
convergence is another GA disadvantage. One of the water remediation problem. They compared the results
greatest drawbacks of GAs is that they require a high with simple genetic algorithm and Non Adaptive Hybrid
number of function evaluations to achieve convergence. Genetic Algorithm (NAHGA). They concluded that the
Each function evaluation entails a full extended-period selection of the local search algorithm to be combined

47
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

with the simple genetic algorithm is critical to algorithm


performance. In the present study the GA is applied first to produce
the proper starting point. Then Quadratic Programming
Reis et al. (2005) have applied hybrid genetic (QP) technique is used through optimization tool box in
algorithm (GA-LP) technique for multi-reservoir MATLAB Environment. The MATLAB software is
operation planning problem. The results were compared extremely useful and user friendly mathematical tool to
with the stochastic dual dynamic programming (SDDP). solve various problems. In early seventies MATLAB
Reis et al. (2006) have applied hybrid genetic algorithm software was written to solve the problem in the field
method using genetic (GA) and linear programming (LP) of matrices, linear algebra and numerical analysis in
to determine operational decisions for a reservoir system Stanford and New Mexico University. The important
over the optimization period. Ebrahimi et al. (2007) used feature of this software is a matrix that doesn’t need to
the G.A approach and four combined models of G.A specify its dimensions. So the solution of the problem is
and wavelet transforms to optimize the operation of as easy as writing them. There are several different
the Vanyard dam reservoir. Chung et al. (2008) proposed toolboxes available in MATLAB. One of the toolbox is
a novel Chaos Genetic Algorithm (CGA) and applied it for the applications of the Genetic Algorithms. The
to optimal operation of hydropower station reservoir invocation of the GA is through GA tool which accepts
system in China. They combined chaos optimization the objective functions and the constraints in the form
algorithm (COA) and genetic algorithm (GA) to of various matrices. The GA tool also specifies a wide
overcome premature local optimum and increase the range of parameters to be chosen with the GA
convergence speed of genetic algorithm. Li and Wei application and also the convergence criteria. The
(2008) developed a GA – Simulated Annealing Method genetic algorithm terminates when one of the following
for operation planning of a multiple reservoir system. exit conditions are met: (1) No improvement in the search
The objective was to maximize generation output from direction (2) no improvement in the solution for more
the 3-reservoir systems over each 12-month operating than pre defined maximum number of iterations
periods. The developed algorithm was stated to be faster (generations) (3) maximum time in seconds the genetic
and better in comparison to GA. Yuan et al. (2008) have algorithm runs before stopping. The GA results are then
proposed a new real value encoding self-adaptive chaotic considered as an initial starting point for QP. The QP
genetic algorithm to solve hydrogenation scheduling toolbox is accessible form: Start/Toolboxes/
problem. The new crossover operation with probability Optimization/Optimization tool (optimtool). More details
distribution function and a self-adaptive chaotic mutation of the use of these functions can be found in MATLAB
operator combined chaotic dynamic character with User’s guide (2007b). A flow diagram of the HGA
artificial neural network theory are used. The result method is given in Fig. 1
shows that the model gives better quality solution.
(GA Toolbox using GA and QUADPROG options
THE MODEL of MATLAB 7.0).
Though Hybrid GA model is considered to perform The proposed model is applied to a reservoir
better than the GA model, proper selection of the search/ planning model. The reservoir is a component of an
optimization algorithm to supplement GA is still a inter basin water transfer system in west central India.
question. In most of the applications the local search The details of the system and the model etc. are as
part of the algorithm is problem specific. However, the follows.
reservoir planning and operation problems pose a
constrained optimization problem and one should use a MODEL FORMULATION
constrained optimization model for the search of the
optimum solution. The best constrained non linear model The objective of the model is to optimize the capacity
is the Quadratic Programming (QP) model if the of a single reservoir that serves multiple purposes such
objective function is strictly quadratic and the constraints as Municipal and Industrial water supply, Irrigation and
are linear. The convergence of the QP to a satisfactory Transfer of water to other reservoir. The present
local optimum shall be fast and improved if this model objective is to minimize the capacity of a reservoir while
is coupled with a GA model which provides a good initial maximizing the other objectives. The objective function
point for the QP model. is:

48
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

Initial Population
Generation no (G=1) TB = Relative weight indicating the benefit coefficient
Specification of
Parameters of unit volume of water transfer in Millions/MCM
TRt = Monthly transfer of water from the reservoir to
Evaluation of other reservoir in period t in MCM
Objective function
(Fitness function)
TTt = Monthly transfer target of water from the reservoir
to other reservoir in period t in MCM
Selection

The objective function is subjected to following


Crossover
constraints
Mutation
The reservoir continuity equation
Elitism
The continuity equation for reservoir storage at the
end of time t , S t 1 is calculated as
If any:
1. Meet specific value
for objective function
Start QP:
Use GA final solution as
(1  at ) S t 1  (1  at ) S t  I t  IRt  TRt  SPt  Lt (2)
2. Meet stall generation QP required initial point
limits
Where
Solve the problem with
QP
S t = Reservoir storage at the beginning of time period t
Converge to
I t = Inflow in the reservoir in time period t
desired
solution? SPt = Spillage in time period t
Lt = the fixed evaporation loss at site = et * Ao , et is
Final solution
the evaporation rate in period t , Ao = water surface area
Fig.1 Flow chart of hybrid genetic algorithm
at the top of the dead storage level, at  aet / 2, and
a is the surface area per unit active storage.
Minimize
Y Y
The S t , Irrt , Tt , S t are in units of Million cubic meter
A * (C p ) 2  B * (Cc ) 2   Birr * ( IRt  IDt ) 2   TB * (TRt  TTt ) 2
t 1 t 1 (1) (x106 m3) and et is in units of millimeters (mm). The
method of computation of evaporation is as per the
Where procedure stated in Loucks et al. (1981).
u = Total no of years of planning
Bounds on Capacity Constraints
T = Total No. of time steps used for planning in each
year The reservoir capacity is constrained by upper
Y = Total No. of time steps in the time horizon (= u x T) bound
A = Relative weight indicating the unit cost of capacity C p  C pu (3)
of reservoir.
C p = Live storage capacity of the reservoir in MCM C pu = The upper bound on the capacity in MCM
B = Relative weight indicating the unit cost of capacity C c  C cu (4)
of canal.
C c = The canal Capacity in Cumec. C cu = The upper bound on the Canal capacity in Cumec.
Birr = Relative weight indicating the benefit coefficient
of unit volume of water supplied to irrigation in Millions/ Reservoir capacity constraint
MCM S t 1  C p  0 (3)
IRt = Monthly irrigation released at the reservoir in
period t in MCM The storage in the reservoir under consideration in
any time period t cannot exceed the live storage
IDt = Monthly target irrigation demand at the reservoir
capacity.
in period t in MCM

49
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

Canal capacity constraint transfer targets are shown in Table 2 and 3 respectively.
The target annual irrigation yield was at 124 million cubic
The water released from reservoir for irrigation and meters (MCM) and municipal requirement at 3 MCM.
transfer form the reservoir during t time cannot exceed An inflow record of 20 years was used to demonstrate
the canal capacity. the application. The transfer targets were varied from
the NWDA specified values and are specified as D1,
 * ( IRt  TR t )  C c (4) D2, D3 and are mentioned in Table 3. As per the priorities
for water demand satisfaction set by the NWDA the
t  1, 2,.., T ;  = factor of conversion of MCM to highest priority municipal and industrial demand was
cumec (m3/s) fulfilled in all the seasons by subtracting it from the
natural inflows. The irrigation demands as well as the
THE CASE STUDY transfer demands were weighed according to the
expected benefits. The upper bound on the reservoir
The model formulated above is applied to the
capacities were varied from the NWDA specified
Patanpur reservoir, which is first proposed reservoir in
values and many trial runs were taken to generate
Parbati-Kalisindh-Chambal (P-K-C) link project of the
minimum capacity of the reservoir fulfilling the monthly
most ambitious river interlinking project envisaged by
irrigation targets. The upper bound on the canal capacity
the Government of India. The reservoir is a multipurpose
was also varied in similar manner.
reservoir having municipal and industrial water supply,
irrigation and water transfers to other reservoir for the For model computations, the MATLAB software
purpose of inter-basin water transfer as the objectives. was used since it is easy to use and can accommodate
The proposed reservoir is located between the North large scale optimization problems. The GA component
latitude 230 42’ and 240 2’and East longitudes of 770 9’ of the model had many options due to various GA
and 770 15’. The climate of the area is subtropical and Parameters viz. the population size, number of
semi-arid. The maximum and minimum annual rainfall generations, the crossover and mutation probabilities etc.
in the basin varies from 356 mm to 1270 mm. The In general a population size of 500 and a generation
proposed active storage capacity of the reservoir is 110 number of about 1000 was sufficient for a good degree
MCM and catchment area 5312 Km2. In the present of optimum result as an initial value for QP algorithm.
study the main objective is to optimize the live storage The crossover probabilities were taken in the range of
capacity of the reservoir and the link canal capacity 0.7 to 1 and the mutation probabilities are taken in a
maximizing the fulfillment of the objectives of the inter- range .001 to 0.3. Better results are obtained at a
basin transfer. crossover probability at 0.75 and the mutation probability
at 0.002. Further the problem was solved through QP
MODEL APPLICATION
using optimization toolbox in the MATLAB Environment.
The model formulated above was applied to the
RESULTS AND DISCUSSION
Patanpur reservoir which is one of the reservoirs of
Parbati-Kalisindh-Chambal (P-K-C) link project. The The results of application of the Hybrid Model
present values of cost parameter of dams and canals proposed in the present study for various target transfer
and annual benefit of irrigation and transfer of water values are presented in Table 4. It is observed that in all
have been computed form the available data (Pre- 20 years the M & I demands along with the irrigation
Feasibility Report, 2004). The unit cost of structure was targets are fulfilled. In comparison to the planned
calculated by dividing its design project cost by the design capacity of the reservoir and canal, based on simulation
capacity as per NWDA. The rate of annual interest studies carried out by NWDA for a given set of
was taken as 5% of the respective capital cost. The hydrologic record, present model generated better
annual operation and maintenance cost is assumed to values. With an increase in the target transfer values,
be 10% of the total cost of project. The cost parameter the canal capacities are increased in proportion to the
(including all costs i.e. Construction cost + Operation highest volume of transfer chosen in a specific month.
and Maintenance cost) of the reservoir, canal and the The reliability of the transfer target met is around 80%
benefit parameters of irrigation and transfers shown in for all the cases. Also there is an increase in the net
Table 1. The water demands in various reservoirs and benefits from the proposed system.

50
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

CONCLUSIONS evolutionary algorithm is good for solving complex


problems, its application to a large dimensional
The present study demonstrates a successful constrained problem has some limitations. The worth
application of hybrid GA approach for solving a problem of quadratic programming method to purely quadratic
of optimal planning for a single reservoir. The GA model formulations such as presented in the study, has been
applied to the problem terminated to suboptimal solutions established since early stages of research in optimization.
in all the solutions employing various combinations of But with the use of a hybrid approach, the computational
the GA parameters viz. the population size, number of efficiency of the QP has increased considerably. The
generations, the crossover and mutation probabilities etc. results obtained in the present study indicate that there
The direct application of the quadratic programming to is a scope of optimization of the proposed capacities of
the same formulation though generated similar results the reservoirs in the Inter basin Transfer Project to
as the hybrid model; the starting point to be chosen was achieve better water management as well as better
a tricky aspect. Moreover, the number of iterations environmental conditions. In the present study the
required was more in such cases. A major conclusion optimization has been achieved through trials of different
was thus drawn that though, GA model as an operating policies.

Table 1 Cost and benefit Parameter values of Patanpur Table 2 Water demands and transfer targets for Patanpur
reservoir reservoirs (MCM)
Parameters Patanpur Month Water Supply Irrigation
June 0.25 8.68
Cost of Dam 7.594
July 0.25 19.84
Cost of canal 27.4
August 0.25 13.64
Benefits from Irrigation 5.06
September 0.25 8.68
Benefits from Transfer 1.478
October 0.25 6.2
November 0.25 8.68
The cost and benefits of all the variables are in December 0.25 13.64
Million Rs. / MCM. MCM indicates Million Cubic January 0.25 18.6
February 0.25 17.36
Meters and Rs. Specify the Indian Rupee. The cost of
March 0.25 3.72
canal is in Million Rs. / cumec. Cumec indicates Cubic April 0.25 2.48
Meter per Second. May 0.25 2.48
Annual 3 124

Table 3 Transfer targets for Patanpur reservoirs (MCM)

Month NWDA D1 D2 D3
June 6 6 6 6
July 67 80 100 100
August 131 400 450 475
September 24 250 230 205
October 57 5 5 5
November 4 5 5 5
December 4 5 5 5
January 4 1 1 1
February 4 1 1 1
March 4 1 1 1
April 4 1 1 1
May 4 1 1 1
Total 313 756 806 806

51
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

Table 4 Summary of results of optimization for Patanpur reservoir


Reservoir Storage Patanpur % Reduction
Capacity (MCM)
Adopted in planning 110
NWDA Policy 110 0
D1 101.5 7.73
D2 97 11.81
D3 97 11.81
Canal capacity (cumec)
Adopted in planning 199.32 % Reduction
NWDA Policy 59.5475 70.12467
D1 171.9895 13.71187
D2 192.8895 3.226219
D3 203.3395 -2.01661
Total Transfer From Patanpur for 20 Years (MCM)
Maximum Value Actual Reliability of
Transfers Target Met
NWDA Policy 6260 5253.951 83.9
D1 15120 12019.6 79.41
D2 16120 12625.99 83.5
D3 16120 12675.44 83.84
Net Benefit from Proposed System (Mill. Rs.)
NWDA Policy 17748.35 % Increase
D1 24738.09 39.38
D2 25076.21 41.28
D3 24862.63 40.08

REFERENCES 6. Ebrahimi, L., Barani, G. A., and Ebrahimi, H. 2007.


Optimization of reservoir operation using combined
1. Ahamed, J.A., and Sarma, 2005. Genetic algorithms for genetic algorithm and wavelet transform methods.
optimal operating policy of a multi-purpose reservoir. American J. of Agricultural and Biological sciences, 2
J. Water Resor. Manage., 19(2), 145-161. (3), 153-158.
2. Chauhan, S., and Shrivastava, R.K., 2008. Optimal 7. Espinoza, F.P., Minsker, B. and Goldberg, D. 2005.
operation of multipurpose reservoir using genetic Adaptive hybrid genetic algorithm for groundwater
algorithms. J. of Indian Water Resources Society., 28(4), remediation design. J. Water Resour. Plan. Manage.
9-17. ASCE 131(1), 14-24.
3. Chun, C. T., Wang, W. C., Mei, W.D., and Chau, K. W. 8. Fahmy, H.S. King, J.P, Wentzel, M.W. and Seton J.A. 1994.
2008. Optimizing hydropower reservoir operation Economic optimization of river management using
using genetic algorithm and chaos. J. Water Resources genetic algorithms. Paper no. 943034, ASCE Int.
Manage., 22 (7), 895-909. Summer meeting, Am. Soc. Of Agricultural Engrs., St.
4. Dariane, A., and Momtahen, S. 2009. Optimization of Joseph, Mich.
multireservoir systems operation using modified direct 9. Hashemi, M. S., Barani, G.A., and Ebrahimi, H. 2008.
search genetic algorithm. J. Water Resour. Plan. Optimization of reservoir operation by genetic
Manage. ASCE 135(3), 141-148. algorithm considering inflow probabilities (Case
5. East, V., and Hall, M.J. 1994. Water resources system study: The Jiroft Dam Reservoir). J. of Applied Sciences
optimization using genetic algorithms.” Proc., 1st Int. 8(11), 2173-2177.
Conf. on Hydroinformatics, Baikema, Rotteram, 10. Hilton, A.B. and Culver, T.B. 2000. Constraint handling
Netherlands, 220-231. for genetic algorithm in optimal remediation design. J.
Water Resour. Plan. Manage. ASCE 126(3), 128-137.

52
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

11. Holland, J.H. 1975. Adaptation in natural and artificial 24. Preliminary study of Parbati-Kalisindh Link 2004.
systems. MIT Press, Cambridge, Mass. National Water Development Agency, New Delhi, F.R.
12. Jothipraksah and Ganesh Shanti 2006. Single P/9/04 vol., I & II.
reservoir operation using genetic algorithm.” J. Water 25. Reis, F.R., Walters, G.A., Savic, D. and Chaudhry,
Resources Manage. 20 (6), 917-929. F.H.2005 .Multi-reservoir operation planning using
13. Jothipraksah and Ganesh Shanti 2009. Comparison of hybrid genetic algorithm and linear programming (GA-
policies derived from stochastic dynamic programming LP): an alternative stochastic approach. J. Water
and genetic algorithm models. J. Water Resources Resources Manage. 19 (6), 831-848.
Manage. 23 (8), 1563-1580. 26. Reis, L. F. R., Bessler, F. T., Walters, G.A. and Savic, D.
2006. Water supply reservoir operation by combined
14. Kangrang, A. and Chaleeraktrakoon, C. 2007. Genetic
genetic algorithm-linear programming (GA-LP)
algorithm connected simulation with smoothing
approach. J. Water Resources Manage. 20 (2), 227-
function for searching rule curves. American J. of
255.
Applied Sciences. 4(2), 73-79
15. Kapelan, Z. 2002. Calibration of water distribution 27. Simonovic, S. P. 1992. Reservoir system analysis:
system hydraulic models. Ph D Thesis Closing gap between theory and practice. J. Water.
Resour. Plan. Manage. ASCE 118(3), 262-280.
16. School of Engineering and science, University of Exeter,
28. Sharif, M., and Wardlaw, R. 2000. Evaluation of genetic
Exeter, UK
algorithms for optimal reservoir system operation. J.
17. Labadie, J. W., 2004. Optimal operation of Water Resour. Plan.Manage. ASCE 15(2), 25-33.
multireservoir systems: state-of –the-art- Review. J.
29. Van, Z., Savic, D.A., and Walters, G. 2004. Operational
Water Resour. Plan. Manage. ASCE 130(2), 93-111.
optimization of water distribution systems using hybrid
18. Li, X., and Wei, X. 2008. An improved genetic algorithm- genetic algorithm. J. Water Resour. Plan.Manage. ASCE
simulated annealing hybrid algorithm for the 130(2), 160-170.
optimization of multiple reservoirs. J. Water Resources
Manage. 22 (8), 1031-1049. 30. Wardlaw, R., and Sharif, M. 1999. Multireservoir system
optimization using genetic algorithm: case study. J.
19. Momtahen, Sh., and Dariane, A.B. 2007. Direct search Water Resour. Plan.Manage. ASCE 14(4), 255-263.
approaches using genetic algorithms for optimization
of water reservoir operating policies. . J. Water. Resour. 31. Wurbs, R. A. 1993. Reservoir-system simulation and
Plan. Manage. ASCE 133 (3), 202-209. optimization models. J. Water
32. Resour. Plan. Manage. ASCE 119(4), 455-472.
20. Nagesh Kumar, D., K. Srinivasa Raju, and Ashok, B.
2006. Optimal reservoir operation for irrigation of 33. Yeh, W. W.G. 1985. Reservoir management and operation
multiple crop using genetic algorithms. J. Water. Resour. models: A state-of-the-art review. J. Water Resour. Res.,
Plan. Manage. ASCE 132 (2), 123-129. 21(12), 1797-1818.
21. Marco, F. 1996. Use of a genetic algorithm combined 34. Yen, M. T., Frank, T.C., Tsai, A.M., and Yeh W. G. 2005.
with a local search method for the automatic calibration Optimization of water distribution and water quality
of conceptual rainfall-runoff model. Hydrological by hybrid genetic algorithm. J. Water Resour. Plan.
Science Journal, 41 (1), 21-39. Manage. ASCE 131(6), 431-440.
22. Marco, F. Galeati, G. and Berra, S. 1998. Global 35. Yuan Xiaohui., Yongchuan, Z. and Yanbin, Y.2008.
optimization techniques for the calibration of Improved self-adaptive chaotic genetic algorithm for
conceptual rainfall-runoff models. Hydrological hydrogenation scheduling. J. J. Water Resour. Plan.
Science Journal, 43 (3), 443-458. Manage. ASCE 134(4), 319-325.
23. Oliveira, R., and Loucks, D.P. 1997. Operating rules for
multireservoir systems. Water Resour. Res., 33 (4), 839-
852.

53
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

REVIEWERS OF IWRS JOURNAL FOR THE YEAR - 2008 - 2009

A timely and critical review of the manuscripts that are submitted is very important for publication of the journal. Such
a review also provides useful and necessary feedback to the author. The Editor and Joint Editor of IWRS Journal are thankful
to the following experts who have reviewed the various manuscripts that were submitted for possible publication in the IWRS
Journal during the year 2008-2009.

Dr. A.A.Kazmi, Deptt. of Civil Engg., IIT Roorkee Dr. M.L.Kansal, Deptt. of WRD&M, IIT, Roorkee
Dr. A.K.Rastogi, DEC, IIT Bombay Prof. M.Perumal, Deptt. of Hydrology, IIT, Roorkee
Dr. A.K.Lohani, Sci. NIH Roorkee Prof. M.P.Sharma, AHEC, IIT Roorkee
Dr. A.K.Vashisht, GBPUT, Pantnagar Dr. N.C.Ghosh, Sci. NIH Roorkee
Dr. Anupama Sharma, Sci. NIH Roorkee Dr. N..K.Gontia, Junagadh Agri. University, Junagarh
Ms. Archana Sarkar, Sci. NIH Roorkee Dr. N. Panighahi, NIH, Roorkee
Dr. Ashok Mishra, Deptt. of Agril. & Food Engg., IIT, Kharagpur Dr. Nayan Sharma, Head, Deptt. of WRD&M, IIT Roorkee
Dr. Ashish Pandey, Deptt. of WRD&M, IIT Roorkee Dr. Omkar Singh, NIH, Roorkee
Dr. Arnab Bandyopadhyay.NIH, Guwahati Dr. P.K.Gupta, SAC, Ahamadabad
Prof. B.C.Mal HOD, Deptt. of Agril. & Food Engg., IIT, Karagpur Dr. Pramod Kumar, Deptt. of Civil Engg., IIT Roorkee
Dr. D.C.Singal, Deptt. of Hydrology, IIT, Roorkee. Dr. P.K.Bhunya, Sci. NIH Roorkee
Prof. Deepak Khare, Deptt. of WRD&M, IIT, Roorkee Dr. P.K.Garg, Civil Engg. Deptt., IIT Roorkee
Mr. Deepak Jhajaria, Deptt. of Hydrology, IIT Roorkee Dr. P.P.Dabral, Deptt. of Agril. Engg., NERIST, Nirjuli
Mr. Dilip Durbudhe, Deptt. of Hydrology, IIT Roorkee Prof. R.K.Nema, College of Agri. Engg., JNKVV, Jabalpur
Prof. G.S.Rajput, College of Agri. Engg., JNKVV, Jabalpur Dr. R.D.Garg, Deptt. of Civil Engg., IIT Roorkee
Prof. G.C.Mishra, Deptt. of WRD&M, IIT, Roorkee Dr. Ravi Galkati Deptt. of Agril. Engg., NERIST, Nirjuli
Dr. Himanshu Joshi, Deptt. of Hydrology, IIT Roorkee Dr. Rakesh Kumar, NIH, Roorkee
Dr. J.V.Tyagi, Sci. NIH Roorkee Dr. R.P.Pandey, Sci. El, NIH Roorkee
Prof. K.L. Mishra, College of Agril. Engg., JNKVV, Jabalpur Er. R.K.Jain, CWC, New Delhi
Prof. K.C.Patra, HOD, Deptt. of Civil Engg., NIT Rourkela Dr. Surjeet Singh, NIH, Roorkee
Dr. K.D.Sharma, NRAA, New Delhi Dr. Sanjay K.Jain, NIH, Roorkee
Prof. K.N.Tiwari, Deptt. of Agril. & Food Engg., IIT, Kharagpur Dr. S.K.Mishra, Deptt. of WRD&M, IIT Roorkee
Dr. K.P.Tripathi, CSWCRTI Dr. S.K. Tripathi, Professor , Deptt. of WRD&M, IIT, Roorkee.
Dr. M.J.Kaladhorkar, CSWCRTI, Karnal Dr. S.R.Bhakar, Deptt. of SAWE, CTAE, Udaipur
Dr. M K Jain, Deptt. of Hydrology, Roorkee. Dr. S. Moulik, Deptt. of Agril. & Food Engg., IIT, Kharagpur
Dr. M.P.Tripathi, IGAU, Raipur Dr. S.K.Jain , Deptt. of WRD&M, IIT, Roorkee
Prof. M.K.Hardha, College of Agri. Engg., JNKVV, Jabalpur Dr. U. C. Kothayari, Deptt. of Civil Engineering, IIT Roorkee.
Dr. M.K.Goel, Sci. NIH Roorkee Prof. V.K.Pandey, Agril. Engg., IGAU, Raipur
Dr. Virendra K. Chaubey, Sci. NIH Roorkee
Dr. Vijay Kumar, Sci, NIH Roorkee

54
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

Journal of
Indian Water Resources Society

Volume 30 Number 1 January, 2010

CONTENTS

Page

1. Protection of Bridge Abutments from Scour 1


V. K. Sarda

2. Rainfall Pattern in Northern Kerala 10


P. A. Lisha, P. K. Pradeep Kumar and K. V. Jayakumar

3. Sustainable Management of the Water Stressed 21


Aquifers in Sabarmati Basin Gujarat, India
R. C. Jain And A. K. Sinha

4. Runoff Estimation by Distributed Curve Number Technique 31


Using Remote Sensing And GIS
Susanta Kumar Jena, Kamlesh Narayan Tiwari and Ashish Pandey

5. Sediment Runoff Modeling using Artificial Neural Networks 39


Archana Sarkar, M. Mohan Raju and Anil Kumar

6. Single Reservoir Optimization using Hybrid Genetic Algorithm 46


Nitin M Mohite and Sandeep Narulkar

55
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

ISSN O970-6984
Journal of
Indian Water Resources Society
Volume 30 Number 1 January, 2010

President

Er. A. K Bajaj
EDITORIAL
Chairman, CWC, New Delhi Dear Friends,

These days, one frequently hears about climate


change in a wide range of forums: conferences,
Editor seminars, meetings, newspapers, television, etc.
Any weather event which may have slight deviation
Prof. Sharad Kumar Jain from the general trend is attributed to climate
Deptt. of WRD & M change. Thus, climate change is blamed for an intense rainfall event and
IIT, Roorkee - 247 667 so is drought in an area. Hot weather is certainly the result of global
warming but big snow storms are also due to changes in climate. Certainly
this way of thinking is not correct and we need to address the issue with
Joint Editor a rational approach that is based upon proven theory and is in conformity
with the observed data.
Dr. Ashish Pandey
Assistant Professor Climate change is also the subject of a large number of conferences
Deptt. of WRD & M wherein this topic is being discussed from different perspectives. Although
IIT, Roorkee - 247 667 much noise is being generated in some of these events, hopefully there
Er. Avinash Agarwal will be many useful ideas and outcomes. These conferences also provide
an opportunity for interactions between people from academics, research
institutes, government organization, and political leaders. Such
interactions should eventually lead to water management that is based
IWRS as a body accepts no resoponsibility for on sound scientific principles and is sustainable.
the statements made by the individuals/authors.
The National Action Plan on climate change launched by the Government
of India in the year 2008 has proposed comprehensive steps to tackle
Further. views expressed by authors need not this problem through eight national missions. National Water Mission is
necessary be the views of the organisation to one of these. Besides, water sector has important role to play in other
missions: Enhanced Energy Efficiency, Sustainable Habitat, Sustaining
which they belong.
the Himalayan Ecosystem, Sustainable Agriculture, and Green India. A
good aspect of these missions is that many programs and activities in
the water sector in India which should have been initiated two-three decades
Reprints of any portion of this publication may be earlier are proposed under these. In that sense, whether the climate change
made, provided that reference thereto is quoted. takes place or not, proposed actions will be good for the nation. The
action plan was launched with much fanfare but typical to the Indian way
of working, the actual progress so far is not very encouraging. One can
This Journal is for private circulation only. only hope that there will be actions on the ground which will change (for
good) the way water is managed in this country.

Principal Office at : The topic of climate change was also under focus due to some alarming
statements in the Fourth Assessment Report of IPCC which had predicted
that the Himalayan glaciers will disappear by the year 2035. This error
Deptt. of Water Resources
was an aberration in the report which continues to be a valuable source of
Development & Management information for scientists and policy makers.
Indian Institute of Technology Roorkee
ROORKEE - 247 667
Uttarakhand, India (SKJain)

56
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010
Registered with the Registrar News Paper of India, under Registration of Books Act. 1867 No. 61811/95

INDIAN WATER RESOURCES SOCIETY


PAST PRESIDENTS
Sri R. Ghosh, Former Chairman, CWC New Delhi 1980-82,1990-92
Sri Pritam Singh, Former Chairman, CWC New Delhi 1982-84
Sri J. F. Mistry, Former Secretary, Gujarat Irrigation Departmem, 1984-86
Dr. Mahesh Verma, Former Professors, Head, WRDTC, UOR, Roorkee, 1986-88
Dr. M. A. Chitale, Former Secretary, MOWR, GDI, New Delhi, 1988-90
Sri A. B. Joshi, Former Chairman, CWC New Delhi 1993-95
Dr. M. S. Reddy, Former Secretary, MOWR, GOI, New Delhi, 1995-97, 1997-99
SriZ. Hasan, Former Secretary, MOWR, GOI, New Delhi, 1999-2001
Sri A. K. Goswami, Former Secretary, MOWR, GOI, New Delhi, 2001-05
Er. M. Gopalakrishnan,Secretary General, ICID (2004 - till date) New Delhi, 2005-2009
EXECUTIVE COMMITTEE
Members Co-opted Members
President - Er. A.K.Bajaj Dr. Z. Ahmad
Executive Vice-President (HQ) - Dr. Ram Pal Singh Prof. Brijesh Chandra
Er. A.S.Dhingra Prof. Gopal Chauhan
Vice President (Executive Office) - Er. R.C.Jha Er. M. L.Garg
Vice President - Er. S.K.Kumar Er. S.S.Doifode
Er. V. K.Kanjilia
Secretary - Dr. R.P.Pandey Dr. Arun Goel
Sri R. N.Kalra
Joint Secretary - Mr O.P.Khanda Sri. Som Dutt Gupta Er. R. K.Khanna
Treasurer - Dr. R.D.Garg Er. Madhu Chandra Jain Er. M.S. Menon
Joint Treasurer - Mr. Amrinder Kumar Er. N.K.Jain Prof. S. K.Mazumder
Editor - Dr. S. K. Jain Dr. R. N. Khare Er. Jagdish Mohan
Joint Editor - Dr. Ashish Pandey Prof. D.T.Shete Dr. R. D.Singh
Er. Ravindra K.Sinha Prof. C.P.Sinha
Ms. Jaya Sood

ACTIVE LOCAL CENTRES


Centre Chairman Convenor
Ahmednagar Sri M.S.Mundhe Sri A. S. Garudkar
Bangalore Sri D. Satya Murty Sri Rajan Nair
Bhopal Sri M.M.Mahodaya Sri B. O. Joshi
Chennai Sri G. Ganapathi Subramanian Sri R. Subramanian
Delhi Er. R. C. Jha Sri R. K. Khanna
Gandhi Nagar Sri J. B.Patel Sri D. H. Patel
Guwahati Er. P. Naog
Hissar Dr. D. K. Kataria Dr. Pratap Singh
Indore Er.A. K. Sojatia Dr. R. K. Srivastava
Jaipur Sri S. K. Jain
Kolkata Sri P K. Bose Dr. Kalyan Bhar
Lucknow Sri Jagdish Mohan Sri J. M. Gupta
Meerut Er. S. K. Kumar Mr. Vijendra Kumar Tyagi
Mysore Sri M. N. Narse Gowda Sri N. Srinivas Murthy
Nagpur Er. S. S Doifode Sri S. G. Deshpande
Patna Prof. C. P. Sinha Ms. Arti Sinha
Pune Sri S. G. Shirke Sri R.K. Suryawanshi
Roorkee Er. P. K. Bhargav
Shimla Er. C. P. Mahajan Er. C. M. Walia

Printed &. Published by Dr. R. P. Pandey, Secretary, IWRS on behalf of the Indian Water Resources Society.
Department of Water Resources Development & Management, Indian Institute of Technology, Roorkee-247 667, (UK)
India Telephone : Office PBX (01332-276220, 286690)
Printed at : Jain Printing Press, Main Bazar, Roorkee, Ph. : 262722, 269999
Secretary : E-mail : secretaryiwrs@gmail.com
Editor : E-mail : editor.iwrs@gmail.com
Notional Price for Individual Members Rs. 10/-
57
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

ISSN O970-6984

Journal of
Indian Water
Resources Society

Volume 30 Number 1 January, 2010

58
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

Journal Article :
Rao, S. S., 1979. Flood Control Regulation of Reservoirs. Journal of Indian Water Resources Society, 1 1(2), 19-26.

Chapter in Book or Paper in a Proceedings :


Singhal, S. P. and Kasliwal, R., 1991. Calibration of Conceptual Catchment Models , in Applied Water Resources Planning,
P. V. Narasimha (Editor). Tata McGraw Hill Publishing Co. New Delhi.

References to unpublished work should not be listed. Papers approved for publication can be listed. In doubt, see recent
of IWRS journal to locate appropriate Styles.

Tables :
Tables should be carefully prepared and should be used to replace text, not duplicate it. They should be numbered
consecutively and should have a brief descrptive title. Use a separate page for each table, and include all tables after the
References section.

Figures :
Use a separate page for each figure. Each figure should have a title and be numbered. The figure will be placed in the
paper as soon as possible after it is first mentioned in the text. The authors shoudl take care to provide good quality figures that
can be sent directly for printing or that can be reduced to fit into journal’s one-column ot two-column format. The original figures
should be sent with the final manuscript. Figures should not be larger than twice paper size. Please send only black & white
figures. No colour figures would be accepted.

Appendices :
All appendices must have a title (for example Appendix 1 : Description of the Model). The Appendices are to be placed
after the References section.

Mathematical Symbols :
Avoid using the mathematical symbols that are difficult to read. If the length of an equation is likely to exceed one-
column width (8 cm), break the equation appropriately. Try not to make the paper too mathematical.
Please visit www.iwrs.org.in for membership application form and previous issues of the IWRS Journal

JOURNAL RECEIPT FORM


JOURNAL RECEIPT FORM
Dear Fellows/Members,
It is to bring to your notice that many copies of Journals are coming back to us undelivered because the address of
the recipient has changed. This is causing heavy finalcial loss on account of postage charges and yet the journal does not
reach to the members. Therefore, you are requested to fill up the following response form and send the same to Secretary,
IWRS, Water Resources Development and Management, Indian Institute of Technology, Roorkee - 247 667 or E-mail
at secretaryiwrs@gmail.com
1. Name (Capital) ........................................................................................................................................................................................
2. Life Membership/Fellowship No. .......................................................................................................................................................
3. Would you like to continue to receive the Journal Yes / No
4. Postel Address ............................................................................................................................................................................
............................................................................................................................................................................
............................................................................................................................................................................
............................................................................................................................................................................

Signature of Member/Fellow

59
J. Indian Water Resour. Soc. Vol. 30 No. 1, January, 2010

JOURNAL OF INDIAN WATER RESOURCES SOCIETY


GUIDELINES FOR AUTHORS
GENERAL INFORMATION

The Indian Water Resources Society (IWRS) is a multi-disciplinary organization dedicated to the advancement of the
science and technology of water resources development and management. The IWRS Journal publishes original papers on
scientific, engineering and socio-economic aspect that are clear, concise and presented in a style readily understood by an
international audience. Before publication, the papers are reviewed by the Editor/ reviewers. Detailed instructions for preparing
manuscripts are included in the following. A review of previous issues will be helpful in organizing the manuscript.

The text of the paper should be well organized and presented in a logical manner. The appropriate use of subheadings,
especially in long sections, enhances the readability and quality of paper. Repetition of data given in tables and figures should be
avoided. The paper should be written so that it will be of interest to persons in the wide variety of disciplines represented by
IWRS’s membership. Complex sentences and the excessive use of highly technical jargon are prime offenders in detracting the
readers. The articles should have well-defined objectives, discussions, applications and conclusions that are easily understood.
The papers not complying w these guidelines will be returned to the authors for improvement or publication elsewhere.

The acceptance or rejection of a paper is based on appraisal by the reviewers who examine the paper for its originality,
relevance, adequacy and conciseness of the presentation. Depending on the results of reviewer, a manuscript may be returned to
the authors for revision. If the authors suitably revise the manuscript, it is accepted for publication. If the review comments are
extensive, the authors should include a reply to the reviewer, in addition to making changes to the manuscript.

Submit two copies of the manuscript typed double spaced on A4 size paper, with 2.5 cm margin on all sides along with
clear and legible figures and tables to the Editor, Indian Water Resources Society, Water Resources Development & Management
Department, Indian Institute of Technology, Roorkee-247 667. Uttarakhand. (Add line numbers in the text of your manuscript).
The references and abstract must also be double-spaced. Include a CD-ROM with text, tables, and figures. Single-spaced
manuscripts, those clumsily typed, or those with inadequate marginal space or unreadable illustrations and tables will be re-
turned. Retain the original manuscript and illustrations and send the same to IWRS when your manuscript is approved for
publication.

PREPARATION OF MANUSCRIPT

Title page :
The title should be short, informative and should clearly reflect the content of the paper. The title should not exceed 15
words in length. Terms like Preliminary Investigations, Contributions to, Studies on etc., should be avoided.

The title page should also include the name(s) of the author(s); The affiliation and mailing address of each author; The
e-mail address, telephone and fax numbers of the corresponding author.

Abstract :

The abstract should be concise, and complete in itself, without reference to the text of the paper. It should state the
general problem and objective(s), summarize the results, and state general implications. The abstract should be in single para-
graph of not more than 200 words. Five to Six keywords supplied by the author should appear on a line following the abstract.

References :

Cite references to published literature in the text sorted by author(s) and year, for example, Prasad (1994). Avoid using a
numbering system. List all references in alphabetical order in the Reference section. Give the complete title of the reference and the
source. Please follow the sample styles shown below

Books :
Gupta, S.K., 1999. Engineering Hydrology. Tata Mc Graw-Hill Publishers, New Delhi.

Continued on Inside Back Cover

60

Das könnte Ihnen auch gefallen