Beruflich Dokumente
Kultur Dokumente
321400
UNIT PAVING
Contents
UNIT PAVING
PART 1 GENERAL
1.2 SUMMARY
1.2.1 This section covers the following works as required by the contract:
1.3.1 Works shall be performed in strict accordance with the stipulations of the
British Standard Specifications (BS) or other approved International
Standards and Sound Practice.
BS No.
1.3.2 In the event of conflict between various codes and standards, the most
stringent conditions shall apply.
1.4 SUBMITTALS
1.4.1 Submit the following in accordance with Conditions of the Contract and
Division-1 Specification Sections:
1.5.1 Tests: Use standard test with manufacturer to determine if mortar and
grout materials will obtain optimum adhesion with, and shall be
1.5.2 2 blocks shall be drawn from each group of 1000 blocks for sampling. All
samples shall be clearly marked at the time of sampling in such a way
that the designated section or part thereof and the consignment
represented by the sample are clearly defined. These blocks shall be
tested for dimensional accuracy, compressive strength, abrasion and
water absorption.
1.5.3 The results of the abroad mentioned tests should comply with the
following results:
1.5.4 Should any of the test blocks not comply with the required tests for
dimensional accuracy, it shall be left to the discretion of the Engineer
whether the whole consignment from which these blocks are selected
shall be deemed not to comply with the specifications.
1.5.6 This area will be used to determine acceptability of the surcharge of the
sand layer, joint size, and lines, laying patterns, colors and texture of the
job.
1.5.9 This area shall be the standard from which the work shall be judged.
1.5.11 Unload pavers at job site in such a manner that no damage occurs to
product.
1.5.13 Pallets shall be stored complete and unopened until time of use so that
the Company label indicating the style and color within the pallet can
be clearly viewed and open pallets should be re-covered at the end of
each workday.
PART 2 PRODUCTS
2.1.2 Units shall be cured for a period of 14 days, and shall not be incorporated
into the works until they are at least 28 days old.
2.2 MANUFACTURERS
2.3.1 Inter Locking Concrete Paving Blocks: Shall be precast (60 mm thick for
sidewalks and 80 mm thick for heavy duty blocks. Solid interlocking
paving units made from normal weight aggregates in sizes and shapes as
indicated on drawings. Concrete shall be a well compacted mixture at a
ratio of 1:2:4 by weight cement: sand: gravel respectively.
i) The blocks should have a chamfer all around the perimeter of the
wearing service of the block of weight 527 mm.
2.3.2 Color: The colors of the concrete paving blocks shall be as indicated on
Drawings or instructed by Engineer and shall be maintained at uniformity
acceptable to the Engineer. The paving blocks should be fully-integrated
colored section. Pigments shall comply with BS No. 1014.
2.4.2 Setting bed or sub-base of the unit pavers shall be according to the
following:
2.4.4 Plain Concrete: Setting bed shall be plain concrete complying with Type
C, Table 4, in Section 03300.
2.5.3 When concrete pavers are subject to vehicular traffic, the sands shall be
as hard as possible.
2.5.4 Grading of sand samples for the bedding course and shall be done
according to ASTM C 136.
2.5.5 The bedding sand shall conform to the grading requirements of ASTM C
33.
2.5.6 Joint Sand: Joint sand requires a range of particle sizes to assist in
interlock the largest particle size should be no larger than the smallest
joint width.
2.5.8 These are expressed in the table as ASTM C 144 or CSA A 179.
2.5.9 Lime stone screenings and stone dust should never be used.
2.5.10 Joint sand (unlike the bedding) needs to be dry when it is swept and
vibrated into the joints.
2.6.1 Mortar bed shall be for units installed over plain concrete or crushed
stones setting bed.
PART 3 EXECUTION
3.1.1 Examine surfaces receiving pavers, in the presence of the “installer”, for
compliance with requirements for installation tolerances and other
conditions affecting performance of the unit pavers.
3.1.4 Verify that the base materials, thickness, compaction density, surface
tolerances and elevations conform to the plans and specifications.
3.1.6 Mix unit pavers from several pallets to produce uniform blend of color
and texture.
3.1.7 Cut units with a power-driven masonry saw to provide clean, sharp,
unchipped edges. Cut to provide pattern indicated, hammer or chisel
cutting is not acceptable.
3.1.8 Lay pavers units in the pattern directed and approved by Engineer.
3.2.1 The sub grade and sub-base shall be prepared in accordance with this
specification and to the Consultants approval.
3.2.2 The laying course shall consist of sharp sand to BS882 with a particle size
of 4 mm containing not more than 3% silt and/or clay by weight. The
sand shall be obtained from a single source, allowed to drain before use,
and shall be covered with suitable sheeting to minimize moisture
changes. Permissible sulphate and chloride contents shall not exceed
0.4% and 0.06% respectively (expressed only as SO3 and C1 by weight).
3.2.4 The profile of the laying course shall be similar to that of the finished
surface. The maximum deviation from the design levels shall be + 10mm.
The edge restraints to the paved area shall be laid in advance of the
laying course and all obstacles within the area, such as manhole covers,
shall be constructed to the correct finished levels.
3.2.5 The paving blocks/slabs shall be laid on the sand-laying course in such a
manner as not to disturb the blocks already laid. Each block/slab shall
be placed firmly against its neighbour so that they fit closely together.
3.2.7 Where blocks/slabs do not fit at the edge, restraints or other obstructions
such as manholes or upstands the gaps shall be filled using cut
blocks/slabs. Blocks/slabs shall only be cut using a saw - no guillotine
cutters shall be allowed on this site. Any damaged or broken
blocks/slabs shall not be laid. Any blocks/slabs damaged during
compaction shall be replaced at the discretion of the Consultant.
3.2.8 Due allowance shall be made in the final levels of the base for the
compaction of the laying course above, which occurs when paving
blocks are being vibrated. The amount of surcharge required for the
laying course shall be determined by site trials prior to the
commencement of the actual surfacing and shall be repeated when the
source of sand supply or a change of weather conditions occurs.
a) After each 20 sq m or such area that has been agreed with the
Consultant, has been laid the blocks shall be compacted to the
required levels using a plate vibrator.
b) The plate vibrator shall have a plate area of 0.20 to 0.35 sq.m. and
have a compaction force of 12-24 kN and a frequency of
approximately 75-100Hz.
3.2.10 Accuracy: On completion, the finished surface level shall be within 5mm
of the design level and the maximum deviation within the compacted
surface, measured by a 3m straight edge, shall not exceed 5mm. The
level of any two adjacent blocks/slabs shall not differ by more than 2mm.
Any areas of paving which do not comply with these tolerances shall be
removed, and sand-laying course lifted and relaid and the paving
blocks/slabs relaid to the correct levels.
3.2.11 Protection of Paving: All paving shall be protected from trafficking and
saturation until all materials are fully cured.
3.3.3 Clean sub-base to remove dirt, dust, debris and loose particles.
3.3.5 Install pavers in full mortar bed and dowel to substrate conforming to the
requirements below.
f) Pound pavers into place with heavy rubber mallet to obtain full
contact and adhesion with setting bed. Do not disturb pavers after
setting. Remove and relay pavers that must be adjusted.
g) Tolerances:
i) Expansion and Control Joints: Provide 9.5mm wide sealant filled joints
in compliance with relevant Specification section. Provide sealant
filled expansion joints over all cracks and joints in concrete sub-slabs,
over all changes in backing materials, where stone abuts a
restraining surface such as walls, columns, planters, and dissimilar
walking surfaces, all to Consultants approval.
j) Grout joints as soon as possible after initial set of setting bed. Force
grout into joints, taking care not to smear grout on adjoining exposed
stone surfaces. After grout initially sets tool joints slightly concave.
Cure grout by maintaining in damp condition for 7 days except as
otherwise indicated by latex additive manufacturer. Pointing shall be
flush unless otherwise specified.
3.3.6 Repair and Cleaning: Remove and replace loose, chipped or broken
pavers. Clean exposed surfaces using materials and methods
recommended by paver manufacturer. Remove and replace work that
cannot be successfully cleaned.
3.3.7 Sealant: Paving surface to be treated with two coats of premium, no-
sheen, natural look, water based penetrating sealer/impregnator,
applied in accordance with the manufacturers printed instructions, and
shall be Aquamix Sealers Choice 15 or equal and approved.
3.3.8 Protection of Paving: The Contractor shall include in his rates for paving
or adequately protecting all surfaces to the satisfaction of the
Consultant until Substantial Completion of the whole of the Works.
3.4 SIDEWALKS
3.5.2 Do not use units with chips, cracks, voids, discoloration and other defects
that might be visible or cause staining in finished work.
3.5.3 Mix pavers from several pallets or cubes as they are placed to produce
uniform blend of color and texture.
3.5.4 Units shall be thoroughly soaked in clean water for at least one hour prior
to setting and shall be applied to setting beds while damp but without
free water on the back of tile.
3.5.5 Where necessary cut paving units nearly and accurately with masonry
saw to fine neat junctions with edging and adjoining finishes.
3.5.7 Lines and levels of finished surfaces shall be smooth and even to prevent
ponding.
3.6.1 The laying course shall consist of sharp sand to BS882 with a particle size
of 4 mm containing not more than 3% silt and/or clay by weight. The
sand shall be obtained from a single source, allowed to drain before use,
and shall be covered with suitable sheeting to minimize moisture
3.6.2 Sand Infill: Dune sand to be used for filling the joints (max. 3mm wide)
between the precast concrete blocks/pavers as per Consultants
approval.
3.7 WORKMANSHIP
3.7.2 The sub grade and sub-base shall be prepared in accordance with this
specification and to the Consultants approval.
3.7.3 The laying course shall consist of sharp sand to BS882 with a particle size
of 4 mm containing not more than 3% silt and/or clay by weight. The
sand shall be obtained from a single source, allowed to drain before use,
and shall be covered with suitable sheeting to minimize moisture
changes. Permissible sulphate and chloride contents shall not exceed
0.4% and 0.06% respectively (expressed only as SO3 and C1 by weight).
3.7.4 The laying course shall be laid to compacted thickness of 50mm unless
otherwise specified plus a surcharge necessary to provide the specified
final bed thickness after vibration of the block paving. During laying the
sand shall be carefully screeded to a smooth surface to receive the
paving blocks. No compaction of the sand layer and no traffic including
pedestrian is to be permitted before the blocks are laid.
3.7.5 The profile of the laying course shall be similar to that of the finished
surface. The maximum deviation from the design levels shall be + 10mm.
The edge restraints to the paved area shall be laid in advance of the
laying course and all obstacles within the area, such as manhole covers,
shall be constructed to the correct finished levels.
3.7.6 The paving blocks/slabs shall be laid on the sand laying course in such a
manner as not to disturb the blocks already laid. Each block/slab shall be
placed firmly against its neighbor so that they fit closely together.
3.7.8 Where blocks/slabs do not fit at the edge, restraints or other obstructions
such as manholes or upstands the gaps shall be filled using cut
blocks/slabs. Blocks/slabs shall only be cut using a saw - no guillotine
cutters shall be allowed on this site. Any damaged or broken
blocks/slabs shall not be laid. Any blocks/slabs damaged during
compaction shall be replaced at the discretion of the Consultant.
3.7.9 Due allowance shall be made in the final levels of the base for the
compaction of the laying course above, which occurs when paving
blocks are being vibrated. The amount of surcharge required for the
laying course shall be determined by site trials prior to the
commencement of the actual surfacing and shall be repeated when the
source of sand supply or a change of weather conditions occurs.
a) After each 20 sq m or such area that has been agreed with the
Consultant, has been laid the blocks shall be compacted to the
required levels using a plate vibrator.
The plate vibrator shall have a plate area of 0.20 to 0.35 sq.m. and
have a compaction force of 12-24 kN and a frequency of
approximately 75-100Hz.
3.7.11 Accuracy:
a) Sub grade - 25 mm
b) Sub-base - 20 mm
c) Pavement surface ± 6 mm
e) The level of any two adjacent units shall not differ by more than 2
mm. Any area of paving which do not comply with these tolerances
shall be removed.
3.8.5 Curing: Protect and cure finished concrete paving, complying with
applicable requirements of Division 3 Sections 03310. Use approved
curing and sealing compound or moist-curing methods.
3.9 CLEANING
3.9.1 After grouting has sufficiently set or hardened, tile surface shall be
cleaned and traces of cement or dust accumulations and foreign matter
shall be completely removed. Wash and scrub clean.
END OF SECTION