Beruflich Dokumente
Kultur Dokumente
Bill Quinn
12 August 2010
Intro
where to spend the limited amount of P&E budget that they have. At my facility this is a
constant battle as we have numerous areas to cover with aging equipment and very little
money to spend. Therefore, in order to get funding one must make a very thorough and
convincing argument as to where the money will best be spent. One of these areas is the
Electrical Test cell for Electrical Harnesses in our component repair area.
The Electrical Test cell has been an area of neglect for many years within our
shop and is drastic need of some change. The current process for testing electrical
harnesses is extremely slow and cumbersome and is a constant bottleneck in the engine
overhaul process. In order to improve the process we must consider investing money into
Procedure
In order to get the data that I needed I first spoke with the people in the Electrical
Test cell and surveyed them in regards to the amount of time it takes them to process
parts through the area and what kind of scrap rates they were seeing. The reason that I did
this was so that I could you validate the actual data once I had pulled it. The first set of
data that I needed was our vouchered (charged) labor data for the testing of each cable
that came through the shop. I pulled this data by going to our SFE system and performing
a data dump of all of the labor times for that specific area of the shop within the last 12
months. From there I went to our scrap data base and pulled all of the scrap data for
cables within the same timeframe in order to find out the qty of scrap and the reasons
why.
The chart below shows the qty of Harnesses that we have scrapped for each
particular scrap cause and the percent of scrap that each of those causes represent. As you
can see the two leading causes for scrap are due to the harness being chafed or having its
resistance out of limits. This data allowed me to narrow my focus upon the vital few Xs
when trying to figure out which repair or process changes would yield the best results.
100
50
80
40
Percent
60
Count
30
20 40
10 20
0 0
i ts d d
re d pe de we
co f l im sco un rro d d
d /s to d o rk d gro d , fu t ure rce d
e u te w f r , e r c
a 0% ed
e d
Pe
a te er s
Defect d / sc
ra
p
ta n ce
o
D ete
ra
i re db
y
C ha
f
e rra
tic
, g ro
v
ke n/ F to
rn
10 E ro F ra
ye
le
d/ rota Ot h
af e si s qu it ed Br
o Ho
Ch Re Re rcu ug
Ci G o
Count 12 11 5 5 4 3 3 2 2 1 1 1 1 1 2
Percent 22 20 9 9 7 6 6 4 4 2 2 2 2 2 4
Cum % 22 43 52 61 69 74 80 83 87 89 91 93 94 96 100
The next chart is a copy of a pivot chart that was created using the vouchered
labor data. It shows the total labor hrs, the qty of each harness that routed through test
and the average labor hours per harness. From there I calculated the average labor per
cable for each shop visit for both our CFM56-7 and –5 engines. The variables in this data
The results of both of these sets of data helped me determine that the scrap cost
per shop visit was $1,400 for Chaffing and $1,275 for Resistance out of limits. The
average labor cost per SV equates to roughly $630. The introduction of a new testing rig
would take the labor cost per SV down to $90 for a potential savings of $540 per SV. In
order to determine the value of new repairs we estimated that we would be able to cut our
scrap rates by 40%. This would result in a savings of $560 for Chaffing and $510 for
At first glance the data would lead you to believe that new repairs would be the
most beneficial use of our money, yet after pulling several harnesses from our scrap hold
area we determined that nearly 75% of the harnesses that had scrapped for resistance out
of limits had scrapped due to the incorrect use of our current harness testing machine.
The problem largely lends itself to the age of the machine and its relative lack of
sophistication. With this data in mind we discussed the test faults that we were finding
with the vendor of our potential testing rig and discovered that the accuracy of the new
machine would completely eliminate scrap causes that were a result of our old machine.
This changed the savings associated to the new testing machine to $1496 per shop visit.
Conclusions
As a result of the data and the work with the shop floor it was determined that the
most beneficial use of our money would be to purchase a new testing rig and work has
begun to allocate the funding. Furthermore, as a result of the time savings and relative
TAT (turn around time) reduction associated with the use of the new tool we have begun
working with our sister shops to become their repair source for Electrical Harnesses. The
This project just goes to show how data and process analysis can bring many