Beruflich Dokumente
Kultur Dokumente
1
The plan
Future state map
Any detailed process-level maps or layouts
that are necessary
A yearly value-stream plan
2
An example of Value-stream Loops
Production 90/60/30 day
Forecasts
Control Daily order
customer
Michigan
Steel Co.
Supplier Loop
1x
daily
Stamping
Weld + Assy.
L
L
R Shipping
R
Takt = 60 sec
Loop C/T = 55 sec.
C/O = 0 Pacemaker Loop
Uptime = 100%
2 shifts
3
Loop 2: Stamping loop
Objective:
establish p
pullll ssystem
stem with
ith stamped
stamped-parts
parts supermarket
s permarket
(eliminate stamping schedule)
reduce stamping batch sizes to 300 (LH) and 160
(RH)
reduce stamping changeover time to less than 10
minutes
Goals:
only I day of stamped-bracket inventory in
supermarket
batch sizes of 300 & 160 pieces between changeovers
4
Use Option A to complete the future map
Production
Control customer
Michigan
Steel Co.
5
Tip to pick a starting point
Where the process is well-understood by
your people
Where the likehood of success is high (to
build momentum)
Where you can predict big bang for the buck
6
signatures
Date: Jan. 27, 2005
Plant union Engineer
Facility Manager: Roger Adams Yearly Value-stream Plan Manager
V.S. Manager Joe Chen
V.S. Value-stream Goal 2005 Monthly schedule Person in Related Reviewing
loop objectives (measurabl charge individuals Schedule
e) & dept.
1 2 3 4 5 6 7 8 9 1 1 1 Who? Date
0 1 2
1 Conti.
Conti Flow Zero WIP
Kaizen to 165 s. 165 time
Eliminate weld C/O 30s C/O
Uptime weld #2 100%
Finish good pull 2 days
Materials routs FG+pull
Product family
Product family
= success = Limited success = unsuccessful
7
Who’s responsibility?
Question: Who is responsible for the cost,
quality, and on-time delivery of this product
from start to finish?
Answer: Well, materials handling is
responsible for moving parts, the stamping
dept.
p is responsible
p for meeting
g his schedule,
the welding Dept. manager meeting his/her
schedule…..
In short, no one is responsible.