Ian Heptinstall
UK
Capital & Construction Projects
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 2
Construction & Capital Projects
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 3
82 years worth of continuous
improvement
Empire 1 World
State Trade
Building Centre
1931 2013
102 floors 104 floors
381m 415m
209,000 m2 270,000 m2
410 days to build 3112 days to build
$350-600M to build $3900M to build
$2,000-3,000/m2 $14,000/m2
Values are in $ 2013
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 4
The Empire State Building, New York
1929-1931
■ Early, rapid, competence-
Empire based selection of the team
State ■ “ECI” – Early Contractor
Building Involvement
1931 ■ Overarching team goal:
Open 1 May 1931
102 floors
381m
■ Off-site manufacture &
209,000 m2 modularisation
410 days to build ■ Design for construction
$350-600M to build
$2,000-3,000/m2 ■ “Total Value Design”
Values are in $ 2013
■ Focus on FLOW
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 5
How to make projects flow
■ Use CCPM
- It works, is proven, and can easily be applied
■ BUT
- CCPM assumes there is a collaborative project team
- And that there are no substantial obstacles to collaboration
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 6
7
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 7
Procurement:
The Main Barrier to Collaboration
■ The common forms of contract used on capital and construction
projects are inherently un-collaborative in nature
■ Fixed Prices, GMP, and associated penalties for breach
- I can win, you can lose
- Very high risk to suppliers
- Add to the overall cost
- Waste time because they take longer to agree, and for change to be managed
- Incentivises conservatism and behind-the-scenes cost cutting
■ Reimbursable or basic cost-plus
- Incentivises suppliers to increase billings
- Penalises suppliers who uncover savings and improvements
■ Adding a “Partnership Charter” over the top of other contract terms
adds a potential conflict
- This can be made to work, with luck and senior-level support
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 8
Overcoming the Procurement Barrier
to Collaboration
■ Use a Project Alliance contract
- Also known as IPD – Integrated Project Delivery
■ A project alliance involves…
- A multi-party contract, that exists only for a single project
- Early selection and involvement
- An integrated team – “best for project” work allocation
- Collective sharing of risks & opportunities
- “Fault” and “Blame” are irrelevant
- Unanimous decision making
- Aligned commercial interests
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 9
The Project Alliance
(Integrated Project Delivery – IPD)
Client Client
Advisors
Project Alliance (IPD)
Main
Member Team Member
1 4
Contractor Member Member
2 3
Sub-
Sub-
Sub-
contractors
contractors
contractors Sub-
Sub-
Sub-
contractors
contractors
contractors
Shared risk/reward Traditional Contracts
Sub-sub-
Sub-
Sub- Sub-sub-
Sub-
Sub-
contractors
contractors
contractors contractors
contractors
contractors
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 10
1
• “Straight-
through” cash.
Cost • No mark-up
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 11
Using CFV Payments – The “Fix-7” Project
VF 2 VF 2
Contin.y
NP
VF 1
VF 1 Safety … 30%
T
FF 2
FF 1 Shutdown … 25%
Construct FF 2
OE
Schedule … 15%
Salaries FF 1
Cost … 20%
Equipment Behaviour … 10%
TVC
& Materials
3rd Parties
Design &
Engineer Not to scale!
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 12
Performance Fee Breakdown
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 13
Example Variable Fees
Customer Experience
Quality
Operating Cost
Behaviours
Aesthetics
Life-cycle cost
Income/Profit/ROI Efficiency
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 14
CFV Payment: Cost + Fixed + Variable
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 15
6
Alliance/IPD
scheme (Design-Bid-Build) capability (Bid-Design-
• Select lowest/fastest bid Build)
• A chain selected one at a • Select best available team
time • A team selected together
• Conflicting commercials • Aligned commercials
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 16
A Project Alliance (IPD) gives us
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 18
Critical Success Factors
A Project Alliance/IPD is necessary…but not sufficient
Higher Higher
client Supplier
ROI Profit
Project is
faster,
lower cost,
& better
RESULTS
DRIVER
Plan &
S manage
Collaborativ using CCPM
e 3: Exploit: Ensure the collaborative
Project Project team delivers great results
Alliance Team
Contracting 2: Foundation: Teamwork built on common goals and
1: Enable: Remove all obstacles to project team collaboration
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 20
Ian Heptinstall
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 21