Beruflich Dokumente
Kultur Dokumente
Translated from the German edition: Statik und Konstruktion der Spritzbetonbauweise. Geotechnik in
Forschung und Praxis, WBI-PRINT 5, VGE-Verlag Glückauf GmbH, Essen 2002, ISBN 3-7739-1305-2
From the contents:
‚ Full-face heading
Preface
The selected case histories from the years 1985 to 2001 include
crown headings with open and closed invert, sidewall adit head-
ings, full-face headings and headings under the protection of pipe
umbrellas and jet grouting columns.
Walter Wittke
Contents Page
1. Introduction 1
2.1 Shotcrete 4
2.1.5 Deformability 15
2.1.6 Rebound 17
2.3 Anchors 30
2.4.1 Spiles 37
2.5.1 Mapping 48
2.5.2 Monitoring 54
3.1.1 Introduction 67
Contents Page
3.1.2 Structure 68
3.1.7 Conclusions 93
3.2.1 Introduction 94
3.2.2 Structure 94
Contents Page
Contents Page
Inhalt Page
Contents Page
Contents Page
8. References 404
1. Introduction
Advancing crown headings with open and closed invert are treated
in the Chapters 3 and 4. In each chapter three case histories are
presented.
Two case histories for headings under the protection of jet grout-
ing columns are dealt with in Chapter 7.
- conclusions.
2.1 Shotcrete
Requirements
Bonding agents
Admixtures
Aggregates
Additives
Composition
According to ÖBV (1998), the mixes for dry-mix and wet-mix shot-
crete are subdivided into:
- Dry mix (TM),
- moist mix, storable (FM-L),
- moist mix for immediate application (FM-S),
- wet mix (NM).
Dry-mix method
For the dry-mix method, TM, FM-L and FM-S mixes can be used. The
mix is conveyed intermittently to the spray nozzle via compressed
air using a piston or rotary engine (thin stream transport). At
the nozzle, it is wetted with water and sprayed onto the surface
of application at a speed of 20 m/s to 30 m/s.
Wet-mix method
With the wet-mix method, the wet mix (NM) is conveyed by the
spraying machine to the spray nozzle either by compressed air
(thin stream transport) or hydraulically using piston pumps (thick
stream transport).
idly developing loads from water pressure and/or rock pressure are
to be expected.
2.1.5 Deformability
2.1.6 Rebound
The rebound further depends, among other things, on the water ce-
ment ratio, the aggregates and the cement type (Maidl, 1992).
Steel sets are made with different profiles. Examples are shown in
Fig. 2.9. One distinguishes between plain girders and lattice
girders.
For the same bending stiffness, lattice girders have less weight
per meter of girder length than plain girders. They are therefore
easier to handle. Lattice girders are distinguished into 3-
stringer girders (Fig. 2.15) and 4-stringer girders. Fig. 2.16
shows the specifications for 3-stringer lattice girders in which
the rods are welded to the stiffening elements from the inside.
The rods of the Pantex 3-stringer and 4-stringer PS-girders are
welded to the stiffening elements from the outside (Fig. 2.17,
2.18 and 2.19).
For the same height, plain girders like GI, TH and other profiles
have a far greater normal and bending stiffness than lattice gird-
ers (Fig. 2.20). The normal stiffness of lattice girders is inde-
pendent of their height, if the cross sectional area of the
stringer rods As remains constant. In Fig. 2.20, As = 12.4 cm2 was
assumed for the stringer rods (d1 = 20 mm, d2 = 28 mm, see Fig.
2.16).
In tunneling according to the NATM, steel sets are only rarely in-
stalled as a closed ring after each round. Therefore, immediately
after their installation, they only have very little bearing ca-
pacity.
exceeds the one of the steel sets. After 24 hours, the normal
stiffness of the shotcrete membrane amounts to 17 times of that of
the lattice girders and 4 to 8 times the one of the GI profiles.
The steel sets covered with shotcrete can also be accounted for as
part of the reinforcement for the dimensioning of the shotcrete
membrane (e. g. stringer rods of lattice girders). This requires
however that the steel sets are completely covered with shotcrete.
Especially if plain girders are used, however, the bond is reduced
due to spray shadows. Therefore, in general steel sets are conser-
vatively disregarded as reinforcement and in finite element analy-
ses, the steel sets are generally not modeled.
- Lattice girders bond better with the shotcrete and lead gener-
ally to tighter shotcrete membranes than plain girders.
2.3 Anchors
Among the form-locked anchors are the mortar anchors (e. g. SN-
anchors, IBO-rods), the resin anchors and the friction pipe an-
chors (e. g. Swellex anchors, split-set anchors). A friction-
locked bond with the rock mass results for the expansion shell
bolt.
In the case of the mortar anchor and the resin anchor, the bond
between the anchor rod and the rock is effected by a setting agent
(cement mortar or synthetic resin mortar) over a specific length
of the borehole (Fig. 2.23). If the bond extends over the full
length of the borehole, the terms full bond anchor or fully ce-
mented anchor are used as well. Among the full bond anchors are
also the friction pipe anchors, the anchor rod of which consists
of a pipe folded in the longitudinal axis (Swellex-anchor) resp.
slit open (split-set-anchor). In the borehole, this pipe is braced
against the rock mass by pressing it against the borehole wall.
Expansion shell bolts are rock bolts in the case of which the bot-
tom end of the anchor rod is braced against the borehole wall us-
ing wedge-shaped or conical elements (expansion elements) (DIN
21521, Fig. 2.22d).
Anchor manufacturers offer anchor rods made from steel and glass
fiber reinforced synthetics with different strengths and cross-
sections (plain section, pipe cross-section). The advantages of
glass fiber anchors over steel anchors lie mainly in the fact that
they can be cut as well as bent. Glass fiber anchors are therefore
often installed at locations where they have to be removed in the
course of further excavation, e. g. for the support of the inner
walls during sidewall adit heading or for the support of the tun-
nel face. Disadvantages of glass fiber anchors are the facts that
they can carry only very small shear forces and that the transfer
of point loads into the anchor at the anchor head is difficult to
enable with the anchor design.
Special anchor head designs have been developed for the use of
non-prestressed anchors in squeezing rock. If a certain anchor
load is reached, these anchor heads yield, thus avoiding over-
stressing of the anchors. Since these anchor types are special-
purpose designs adjusted to the individual case, they will not be
dealt with here in more detail.
The admissible anchor force is the maximum force the rock bolt is
permitted to be subjected to (maximum tensile force, maximum bond
force or limit creep force) divided by a factor of safety. The
maximum tensile force of the anchor rod is calculated according to
For glass fiber anchors, attention must be paid to the fact that
the failure load of the anchor rods is generally far higher than
the failure load of the anchor head parts.
Rock bolts must carry tensile and possibly shear forces. Failure
of the anchors due to overstressing may occur. The failure mode of
bond anchors depends on whether they are placed in rock or in
soil. In rock, generally the anchor rod breaks before the bond
fails. In soil, failure of the mortar over the bond length occurs
first.
T0
cA = (2.1)
A
2.4.1 Spiles
Fig. 2.28: Driven steel pipe spiles (Tunnel Deesener Wald, new
railway line Cologne – Rhine/Main)
possible also the surrounding rock mass itself are grouted with
cement suspension from out of the pipes in order to improve the
support effect of the pipe umbrella. To this end, the pipes are
provided with injection valves at a spacing of 0.5 to 1 m (Fig.
2.32). The pipes are subsequently closed with a cover and filled
with suspension or mortar.
The boreholes for the pipe umbrella are arranged over a certain
portion of the circumference of the excavation profile at a spac-
ing of 30 to 50 cm. They are drilled ascending at an angle of ap-
prox. 5° with respect to the tunnel axis. The pipes of two pipe
umbrellas should overlap by at least 3 m in the longitudinal tun-
nel direction (Fig. 2.29 and 2.30).
2.5.1 Mapping
2.5.2 Monitoring
General
On the other hand, just as the mapping, they form one of the foun-
dations for adapting the support measures to the local ground con-
ditions. Finally, the interpretation of already existing measure-
ment results can and should be used to verify and, if indicated,
optimize the dimensioning of the temporary and permanent lining.
Stability analyses on the basis of measurement results furthermore
- Positional surveying,
- leveling,
- convergency measurements,
- extensometer measurements,
- inclinometer measurements,
- stress measurements,
- vibration measurements,
hind the tunnel face. The measuring points are steel bolts ce-
mented into the rock. Simple homing boards or triple prisms are
mounted onto these bolts. The zero reading is carried out before
the next round.
With the tachymeter, not only the vertical but also the horizontal
displacement components parallel and perpendicular to the tunnel
axis are measured. The measuring points are surveyed three-
dimensionally from bench marks by determining the direction, dis-
tance and inclination from the bench mark to the measuring point
for different points in time. The measurement data given in polar
coordinates are converted to Cartesian coordinates. From the dif-
Convergency measurements
ing marks are recorded one after the other (German Rail, Guideline
853, DB 1999).
Stress measurements
Vibration measurements
3.1.1 Introduction
3.1.2 Structure
vert was only slightly rounded out. For the transition from the
sidewalls to the invert, a radius of R = 2.66 m was selected (Fig.
3.3).
Fig. 3.4 shows the vertical section through the tunnel axis in the
area of tunnel cross-sections TC3 and TC3A as a development. The
maximum overburden height amounts to approx. 50 m.
The ground along the alignment of the Glockenberg tunnel was ex-
plored using core drillings and test pits. One borehole was
equipped as an observation well (Fig. 3.4).
The joints contain many more rock bridges than the bedding- and
foliation parallel discontinuities. Their degree of separation is
correspondingly smaller.
The observation well was set up in the area in which the highest
groundwater level was expected due to the location on the slope.
The measurements showed that the groundwater is encountered here
approx. 1 m above the tunnel roof (see Fig. 3.4).
In model A, the bedding (B) and the foliation (F) are assumed dip-
ping each at 45° perpendicular to the tunnel axis in opposite di-
rections. In addition, a vertical joint set (J) striking parallel
to the tunnel is taken into account. In model B the foliation is
assumed dipping at 30° while the bedding dips at 60° in the oppo-
site direction. Here as well an additional vertical joint set ex-
ists. Model C includes a vertical bedding striking parallel to the
tunnel and a horizontal foliation. Instead of the vertical bedding
planes, vertical joints are assumed in model D.
The setup of the ground layers is the same for all analysis cross-
sections. The rock mass is encountered below a 5 m thick surface
soil layer. In some analyses a fault zone in one of the positions
shown in Fig. 3.8 is modeled discretely.
The parameters assumed in the stability analyses for the soil and
the fault zone correspond to the specifications established during
For the reference case, Young's modulus of the rock mass was as-
sumed conservatively as E = 1000 MN/m2. In comparative analyses a
value of 1500 MN/m2 was specified. Poisson's ratio was assumed as
0.33 (Fig. 3.9).
iterative calculation. Fig. 3.12 and 3.13 show the principal nor-
mal stresses, the areas where the shear strength on the disconti-
nuities is exceeded and the displacements of the excavation pro-
file computed for the bench excavation with the anchors taken into
account. The computed roof subsidence amounts to approx. 40 mm,
the maximum heave of the invert to approx. 65 mm (Fig. 3.13).
Fig. 3.14 shows the bending moments and normal thrust in the shot-
crete membrane calculated for the 5th computation step. For a
safety factor of 1.35, the design results in a statically required
reinforcement of up to 4.0 cm2/m. If the lattice girders are taken
into account, this reinforcement is covered by the planned rein-
forcement (see Fig. 3.6).
In Fig. 3.15 the tensile anchor forces computed for the truss ele-
ments for the 7th computation step are shown. They reach a maximum
value of approx. 130 kN.
1
adm FA = ⋅ βS ⋅ AS = 140 kN (3.1)
η
Fig. 3.16 to 3.19 show the results of an analysis based on the pa-
rameters given in Fig. 3.9 and 3.10, structural model B and in ad-
dition a 5 m thick fault zone dipping at 70° close to the left
side of the tunnel (see Fig. 3.8, position L). For these unfavor-
able assumptions the stability of the construction stage after the
bench excavation (5th computation step, see Fig. 3.11) can only be
proved in the analysis, if in the area of the left half of the
tunnel 10 to 15 m long IBO-bolts (see Chapter 2.3.1) reaching be-
hind the fault zone into the undisturbed rock mass are simulated
by truss elements.
Fig. 3.18 shows the bending moments and normal thrust in the shot-
crete membrane determined for the 5th computation step. Compared to
the corresponding case without a fault zone, greater maximum bend-
ing moments and smaller maximum normal thrusts occur in the shot-
crete (see Fig. 3.14 and 3.18). For a safety factor of 1.35, the
design results in a statically required reinforcement of up to
6.2 cm2/m. If the lattice girders are taken into account, this re-
inforcement is covered by the planned reinforcement as well.
In Fig. 3.19 the tensile anchor forces computed for the truss ele-
ments in the 7th computation step are given. Only the anchors run-
ning through the fault zone are loaded. The maximum computed an-
chor force amounts to 150 kN, which is only slightly more than the
admissible anchor load according to (3.1) of the planned IBO-rods
(∅ 25 mm) of 140 kN.
The results of the geotechnical mapping of the tunnel face and the
displacements measured during the crown heading allowed in consid-
eration of the results of the stability analyses the tunnel to be
driven with excavation classes 4, 5 and 6A (see Fig. 3.6). Excava-
tion class 7A was not carried out. Further, it was possible to ex-
cavate the crown over the entire tunnel length without simultane-
ously trailing bench.
3.1.7 Conclusions
3.2.1 Introduction
3.2.2 Structure
The Gäubahn Tunnel consists of two parallel ca. 300 m long tunnel
tubes with two lanes each (Fig. 3.22). Approx. 270 m of each tun-
nel tube were driven by underground construction ascending from
the eastern portal. The precuts in the portal areas were con-
structed by the cut-and-cover method (Fig. 3.22 and 3.23).
Fig. 3.24 shows the 11.5 m wide and 8.85 m high standard profile
of a tunnel tube. The excavated cross-section amounts to approx.
93 m2. The shotcrete membrane has a concrete grade of B25 and a
thickness of 25 to 30 cm. The interior lining consists of water-
tight grade B35 concrete with a thickness of 45 cm.
The roof and the invert are shallowly rounded with radii of curva-
ture of R = 8.15 m and R = 10.45 m, respectively. At the sidewalls
the radius of curvature amounts to R = 5.45 m. The transitions
from the sidewalls to the roof and to the invert, respectively,
were designed with comparatively small radii of R = 3.06 m and
R = 2.65 m, respectively (Fig. 3.24).
Below the ground surface a few meters thick overlying strata are
present (Fig. 3.23). They consist mostly of rock weathered into
sand and silt, respectively, and partially relocated.
The joints are generally steeply dipping and deviate only little
from the direction perpendicular to the bedding (here: the verti-
cal direction). In general they extend over many meters horizon-
tally. At least in some areas the joints are slightly opened ac-
cording to the exploration results.
The tunnel was excavated using a tunnel excavator and, in some ar-
eas, also by smooth blasting. Measurements carried out on build-
ings showed that the vibration velocities remained far under the
reference values for the admissible structural vibrations given in
DIN 4150, part 3 (DIN 4150-3, 1999).
In the tender documents ranges for the soil and rock mechanical
parameters are given. The stability analyses for the design of the
shotcrete support are based on the most unfavorable values (Fig.
3.28).
The intact rock strength of the sand- and siltstones was assumed
infinitely high as a simplification. The rock matrix was assigned
elastic stress-deformation behavior. This simplification is justi-
fied, because the strength on the discontinuities is markedly
smaller than the intact rock strength. Two discontinuity sets were
taken into account in the analyses. The horizontal bedding and a
vertical joint set striking parallel to the tunnel axis with an
unfavorable effect on tunnel stability.
Fig. 3.31 shows the displacements due to the crown excavation (3rd
– 1st computation step) calculated for the excavation contour and
the ground surface. The roof subsidence amounts to approx. 18 mm,
the invert heave is approx. 8 mm and the maximum subsidence at the
ground surface results to approx. 11 mm.
After the bench and invert excavation in the 5th computation step
the displacements increase only slightly. For this construction
stage as well, no reinforcement is statically required for a fac-
tor of safety of 1.35.
- leveling on structures,
In both tunnel tubes the crown heading was far ahead of the bench
and invert excavation. Fig. 3.33 shows exemplarily the ground sur-
face subsidence due to the crown heading in the area of the under-
crossing of the Gäubahn and the buildings adjacent to the Rudolf-
Sophien institution. In the area of the undercrossing of the
buildings adjacent to the Rudolf-Sophien institution the crown
heading was carried out with an open invert and small round
lengths of 0.8 to 1.2 m following excavation class 4A-1 (see Fig.
3.26). The subsidence measured here ranges from 7 to 19 mm. In the
area of the undercrossing of the Gäubahn the heading was changed
over to a crown heading with closed invert under the protection of
an advancing support using composite piles and spiles (see Fig.
3.27). The subsidence could thus be limited to 2 to 8 mm. This
small subsidence did at no point affect the railway traffic.
3.2.7 Conclusions
With a crown heading with open invert and small round lengths (ex-
cavation class 4A-1, see Fig. 3.26) it was possible to achieve
small surface subsidence < 2 cm during tunneling in the alternat-
ing sequence of sandstone and siltstone horizons of the Stuben-
sandstone formation in the region of Stuttgart.
3.3.1 Introduction
3.3.2 Structure
The ground along the alignment of the Hellenberg Tunnel was ex-
plored by test pits and core drillings. The boreholes were
equipped as observation wells (Fig. 3.34 and 3.37).
In the course of the exploration the drill cores and the test pits
were geotechnically mapped. Further, television probing and labo-
ratory and in-situ tests were carried out.
The crown was excavated over the entire tunnel length without a
trailing bench excavation (unlimited length of section D in Fig.
3.38). In the area of the southern portal a crown heading with a
temporary support of the invert was carried out over a length of
approx. 80 m (excavation class 7A-K1, Fig. 3.40). At the northern
portal a temporary support of the invert was only constructed in
the beginning of excavation (excavation class 6A-K1, Fig. 3.40).
In the remaining area a crown heading with open invert was carried
out (excavation classes 6A-1 and 6A-2, Fig. 3.40).
During the tunnel face mapping the appearance, the extent and the
orientation of the discontinuities were determined as well.
Fig. 3.43 shows the bench at the southern portal. The photograph
gives an impression of the strongly weathered rock in this area
and of the discontinuity fabric.
Fig. 3.44 shows the computation section, the FE-mesh, the ground
profile and the parameters taken as a basis for the stability
analyses (Wittke et al., 1999). The tunnel cross-section is lo-
cated in the strongly to slightly weathered Variegated Schist. The
overburden is 18 m high. Below the tunnel's invert the rock is un-
weathered.
computation step) and the bench (3rd computation step) was simu-
lated, each time with simultaneous installation of the shotcrete
membrane. In the 4th computation step the invert was excavated and
supported using shotcrete.
For the case ϕJ = 25° the stability of the construction stage due
to the bench excavation can be proven in the analysis. The hori-
zontal and vertical displacements computed at the bench support
feet converge in the course of the viscoplastic iterative analysis
(see Fig. 3.46). The horizontal and vertical components of the
viscoplastic displacements of the bench support feet amount to
δ Hvp = 15.6 mm and δ Vvp = 9.2 mm.
Fig. 3.47 shows the sequence of the heading. Following the crown
heading (1), the bench was excavated up to chainage approx. 80 m
at a round length of 2.0 m. The invert trailed with a round length
of 3.6 m and was supported after each round (2). In this area the
strongly weathered rock mass extends into the tunnel cross-section
(Fig. 3.47), and a crown invert support was installed.
In the northern portal area the bench was excavated again with im-
mediately trailing invert over a short tunnel section (4 in Fig.
3.47). The round lengths were the same as in the southern portal
area.
3.3.9 Conclusions
4.1.1 Introduction
4.1.2 Structure
During the design phase for the new by-pass road an extensive pro-
gram for the exploration of the subsoil and groundwater conditions
was carried out. This program includes core drillings, the inves-
tigation of soil, rock and water samples, water level observa-
tions, combined extensometer and inclinometer measurements as well
as in-situ stress measurements.
The structural model for the Lias α, the Rät and the Knollenmer-
gel, illustrated in Fig. 4.5, was developed within the scope of
The soil mechanical parameters derived for the layers close to the
surface are based on the results of laboratory investigations on
samples taken from core drillings located in the area of the tun-
nel. Due to the grain-size distributions and moisture contents as
well as data gained from experience a mean modulus of deformation
of E = 25 MN/m2 as well as mean effective shear parameters of
ϕ' = 20° and c' = 10 kN/m2 are assumed (Table 4.1).
than the shear strength of the intact rock. For the shear strength
of the bedding planes a friction angle of ϕB = 20° and a cohesion
of cB = 0 are assumed. For the joints of sets J1 and J2 an angle of
friction of ϕJ = 30° and a cohesion of cJ = 40 kN/m2 are estimated
(Table 4.1). A tensile strength normal to the discontinuities is
not taken into account.
With regards to the rock mechanical properties the Rät and the re-
duction zone of the Knollenmergel are combined to a uniform layer.
On the basis of experience for the modulus of deformation a value
of E = 150 MN/m2 is assumed (Table 4.1). In laboratory tests on
rock samples unconfined compressive strengths ranging from σu = 0.3
MN/m² to 5.0 MN/m2 were determined. Though these values are quite
low, here also the strength on the discontinuities is decisive.
The shear parameters of the discontinuities in the Rät and the
slickensides at the reduction zone of the Knollenmergel, respec-
tively, are estimated to be ϕD = 17.5° and cD = 10 kN/m2 (Table
4.1). A tensile strength normal to the discontinuities here also
is not accounted for.
cated somewhat above the invert of the tunnel. In the central sec-
tion of the tunnel it is levelled at the middle of the height of
the cross-section of the tunnel (Fig. 4.2).
In Fig. 4.6 the finite element mesh used for the three-dimensional
analyses is illustrated (Hauck et al., 1998). The dimensions of
the computation section are 100 m x 100 m x 40 m. The computation
section is subdivided into 9074 isoparametric elements with 12720
nodes. The computation section is modeling the area of the Para-
diesplatz, which is located approx. 120 m south of the portal "Un-
terer Grund" (Fig. 4.1 and 4.2). The setup of the finite element
mesh enables the modeling of the stages of excavation, of the
shotcrete membrane as well as of the subsoil profile and the rail-
way trench. The analyses were carried out assuming an elastic-
viscoplastic stress-strain behaviour for the ground. For the mud-
stones of the Lias α with single layers of limestones and lime-
sandstones as mentioned above a transversally isotropic stress-
strain behaviour in the elastic domain as well as increased hori-
zontal in-situ stresses were simulated. The soil and rock mechani-
cal parameters as well as the three-dimensional finite element
mesh are shown in Table 4.1 and Fig. 4.6.
In the two first steps of the analysis the in-situ state of stress
due to dead weight and the additional horizontal stresses in the
Lias α were calculated. For the simulation of the increased hori-
zontal stresses ΔσH the nodes located at the boundary plane with
the coordinate x = 100 m were displaced in x-direction. These dis-
placements lead to horizontal stresses, which correspond to the
stress ΔσH existing in the Lias α (Fig. 4.6). In the first step of
analysis the whole computation section was horizontally loaded by
these displacements. The unit weight γ was accounted for, however,
only for the Lias α. In the second step of the analysis the soil
layer underneath the surface as well as the Rät and the Knollen-
mergel, in which increased horizontal stresses are not existing,
were substituted by materials, which have the same mechanical pa-
rameters as before, which however are not weightless any longer (γ
> 0). Since the new materials were installed stress-free into the
already deformed corresponding elements (Wittke, 2000) and because
in the second step of the analysis the horizontal displacements of
the boundary x = 100 m were not changed, the soil underneath the
surface, the Rät and the Knollenmergel are loaded only by the dead
weight and not subjected to increased horizontal stresses.
The distance from the excavation of the bench and the invert to
the crown was chosen to at least 50 m. The round lengths for the
crown's excavation were chosen between 80 cm and 1.2 m. For the
excavation of the bench and the invert round lengths ranges from
1.6 to 3.0 m (Fig. 4.11). Thus during the crown's excavation as
well as the excavation of the bench and the invert an early clo-
sure of the shotcrete membrane was realized. This measure has
proven to limit the subsidence especially during the undercrossing
of the buildings and the railway to a low level.
Due to the low overburden and the high frequency of the disconti-
nuities near the ground surface in the area of the two portals
grouted spiles were used as advancing support. The intensively
jointed mudstones located immediately above the Oolithenbank (Fig.
4.4) turned out to be caving to a major degree. In case of a unfa-
vorable location of this rock layer at the tunnel roof, therefore,
also in greater distance to the portals the installation of
grouted spiles were required.
In the area of the railway trench the excavation of the crown was
carried out underneath the protection of a total of ten advancing
pipe umbrellas (Fig. 4.11, 4.12 and 4.14). The steel pipes in each
case were installed from niches and have a diameter of 140 mm and
a length of 14.50 m. The overlap between two successive pipe um-
brellas was selected to 3 m. The lengths of the niches, which were
expanded continuously up to a maximum depth of 75 cm, is 6.5 m
(Fig. 4.11). Before the excavation of the bench and the invert in
the area of the niches was carried out, the niches were filled
with shotcrete.
The average completion time for a pipe umbrella was 5 days. During
the corresponding interruption of the crown heading the bench and
the invert excavation was carried out which was started after the
installation of the first pipe umbrella because of their higher
rate of advance. In this way an optimum rate of advance could be
achieved (Hauck et al., 1998).
For the time interval between the excavation and the installation
of the shotcrete membrane the bearing behaviour of the steel pipe
umbrella in the longitudinal direction of the tunnel is activated.
In other words the space between the tunnel face and the load
bearing shotcrete support in this stage is bridged by the pipes.
As a consequence caving and loosening of the rock mass in this
area as well as resulting subsidence are largely avoided.
measuring cross-sections (MC2, MC5, MC9 and MC11, Fig. 4.2) with
vertical combined extensometer and inclinometer measuring equip-
ments on both sides of the tunnel (Fig. 4.6) were installed.
The following excavation of the bench and the invert of the tunnel
has lead to an increase of the horizontal displacements from 50 up
to 100 % (Fig. 4.15b).
4.1.8 Conclusions
4.2.1 Introduction
The two-lane road tunnel "Elite" was headed in Ramat Gan, a city
in the Tel Aviv area. The tunnel was started from a underground
parking lot located adjacent to the 260 m high Gate Tower (Fig.
4.17), the highest building in the Middle East. The tunnel under-
4.2.2 Structure
The axis of the approx. 110 m long Elite Tunnel runs firstly along
a circular arc with a radius of approx. 120 m and then changes
into a straight line (Fig. 4.18).
In Fig. 4.21 the drill logs of four boreholes are projected onto a
longitudinal section through the tunnel axis. According to these
borehole logs, fill or clayey sands and clays exist down to a
depth of 2 m. Below, medium dense to dense calcareously bonded,
partially cemented sands with a fraction of gravel are encountered
(Fig. 4.22). In these slightly cohesive sands, termed "Kurkar",
locally cohesionless fine sands are intercalated, as mentioned
above.
formly graded sand with fines. On the basis of the blow counts per
30 cm of penetration depth determined with the SPTs ranging be-
tween N30 = 16 and N30 = 46, the Kurkar and the uniformly graded
sand can be classified as medium dense to very dense (D = 0.5 to
0.7) according to DIN 4094, appendix 1 (1990). An estimate of the
bulk moduli according to DIN 4094, appendix 1 (1990) on the basis
of the determined values for N30 leads to moduli ranging from ap-
prox. 40 to approx. 100 MN/m2.
4.2.4 Design
To protect the work space and to relieve the area of the temporary
tunnel face, the tunnel is planned to be excavated under the pro-
tection of pipe umbrellas consisting of 12 m long steel pipes with
a diameter of ca 17 cm (Fig. 4.25 and 4.26). The pipes are spaced
at approx. 40 cm and have a wall thickness of 7 mm. Four rebars
are entered into each pipe to increase the section modulus. Fur-
ther, the pipes are filled with B25 concrete (Fig. 4.26). The
steel pipes overlap by 3 m (Fig. 4.25). As mentioned above, the
pipe umbrellas are designed to bridge the work space and should
therefore be able to carry the entire load resulting from overbur-
den and traffic. Their design is therefore based on these loads
(see Chapter 4.2.5).
Fig. 4.27 shows the computation section, the FE-mesh, the boundary
conditions, the ground profile and the parameters the analyses
were based on. The computation section consists of a 48 m wide, 45
m high and 1 m thick slice. The FE-mesh was divided into 630 iso-
parametric elements with a total of 3958 nodes.
The ground was subdivided into two soil layers. Down to a depth of
8.5 m a medium dense sand was assumed with a Young's modulus of
E = 100 MN/m2 and a Poisson's ratio of ν = 0.35, corresponding to a
bulk modulus of Es = 160 MN/m2. Below that, a dense sand with
E = 250 MN/m2 and ν = 0.35 corresponding to Es = 400 MN/m2 was
specified. To be on the safe side, no cohesion was assumed for
any of the two sands (c' = 0). An angle of friction of ϕ' = 30°
Since the ground profile and the cross-section of the tunnel are
symmetrical to the tunnel axis, only one half of the tunnel cross-
section was modeled (Fig. 4.27).
Fig. 4.29 shows the displacements of the ground surface and the
tunnel contour (crown) computed for the 2nd computation step rela-
tive to the 1st computation step. The largest displacements result
at the roof with 25 mm and at the ground surface with a maximum of
22 mm. These values change only marginally in the 3rd computation
step.
Fig. 4.30 depicts the bending moments and normal thrust in the
shotcrete membrane determined for the 2nd and 3rd computation step.
Because of the small radius in the case of the crown heading the
ηt ⋅ pt + η γ ⋅ γ ⋅ H o
η = ≈ 1.45 (4.2)
pt + γ ⋅ H o
These can be covered by steel fabric mats Q295 on the inside and
on the outside and by supplementary reinforcement within the upper
sidewall area (Fig. 4.31). In the bench and invert area, the in-
side steel fabric mat Q295 can be omitted. Fig. 4.32 shows the de-
sign and the reinforcement of the shotcrete membrane in the area
of the crown's foot.
Fig. 4.33 shows the computation section, the FE-mesh, the boundary
conditions, the ground profile and the parameters these analyses
were based upon. The computation section is 40 m wide, 40 m high
and 62 m long. The FE-mesh was divided into 5848 isoparametric
elements with a total of 14945 nodes.
The tunnel face was assumed inclined at 80°. The tunnel face an-
chors were considered by a cohesion in the respective area (Fig.
4.33). Five cases were investigated: c' = 0 (no tunnel face
anchors), c' = 25 kN/m2, c' = 50 kN/m2, c' = 75 kN/m2 and
c' = 100 kN/m2, corresponding to an anchor arrangement with a
raster spacing between 1 m x 1 m and 2.1 m x 2.1 m.
It should be pointed out that with these analyses as well the tun-
neling-induced displacements of the soil are underestimated, since
the support exerted by the shotcrete membrane is overestimated
with the computation sequence outlined in Fig. 4.34. For a realis-
tic computation of the displacements, one of the two procedures
for the simulation of a three-dimensional tunnel heading described
in Wittke (2000) (step-by-step method or iterative method) would
be necessary. The analyses, however, had the only purpose of as-
sessing the stability of the temporary tunnel face.
The criterion for the proof of stability of the tunnel face is the
convergency of the nodal displacements in the course of the visco-
plastic iterative analysis. Fig. 4.37 shows the development of the
The beam on two supports and the beam fixed at both ends are con-
sidered as statical systems for the design of the pipe umbrella.
For the reasons given above, the maximum span of the beam is as-
sumed as 2 m. For the fixed beam, 0.5 m each on both ends of the
beam are added to the length and assumed to be fixed. From the su-
perposition of the traffic load and the overburden pressure, tak-
ing into account the spacing of the pipes (L = 418 mm), the load-
ing of the beam results to q = 65.7 kN/m (Fig. 4.38).
4.2.6 Construction
Differing from the design the pipes only had a length of 10.4 m.
Since the overlap of the pipe umbrellas amounts to 3 m, it was
possible to excavate for 7.4 m under one umbrella before the pipes
for the next umbrella had to be installed (Fig. 4.41).
plates welded to the pipes (Fig. 4.42a). In the area of pipe um-
brellas 3 to 14 cemented rebars (spiles) were installed between
the steel pipes (Fig. 4.42b). The drillings for the spiles served
at the same time to explore the ground in advance. In the area of
the last two pipe umbrellas, additional steel pipes, filled with
B25 concrete but not reinforced, were installed (Fig. 4.42c).
Fig. 4.42: Support of the gaps between the pipes in case of lo-
cally occurring dry, loose sand or fill: a) Pipe um-
brellas 1 and 2; b) pipe umbrellas 3 to 14;
c) pipe umbrellas 15 and 16
port core was carried out (see Fig. 4.41). Further pictures from
crown heading construction are shown in Fig. 4.45 to 4.47.
The excavation of bench and invert was only started after the
crown of the entire tunnel had been excavated (see Fig. 4.41).
4.2.7 Monitoring
Fig. 4.48 further shows the ground surface subsidence measured af-
ter completion of the crown heading. It amounts to approx. 20 mm
in the area of the northern portal and to approx. 40 to 60 mm in
the remaining tunnel section.
The subsidence that has occurred at the ground surface before the
shotcrete support is installed amounts to approx. 20 mm in the ex-
ample of Fig. 4.48. By adding this subsidence to the calculated
subsidence of approx. 22 mm (see Fig. 4.29) and to the estimated
deflection of the pipe umbrella of approx. 3 mm (see Fig. 4.40), a
total subsidence of approx. 45 mm can be derived from the analysis
results which agrees well with the measured subsidence (see Fig.
4.48).
4.2.8 Conclusions
4.3.1 Introduction
In the early 1990's the Stuttgart city railway line U9 was im-
proved up to Botnang terminal. As a part of this project the
"Herder Street" and "Lindpaintner Street" stops were connected by
a 550 m long, double-tracked tunnel (Fig. 4.49a). The tunnel un-
dercrosses the Botnang saddle in a wide turn as well as the
Gäubahn and some built-up areas (Fig. 4.49).
4.3.2 Structure
- Fill,
- Gypsum Keuper.
The flanks of the Botnang saddle are covered with talus material,
the thickness of which usually amounts to 1 to 2 m. Up to 4 m of
thickness are reached in shallowly dipping terrain where the talus
material changes into residual loam. The latter consists of soft
to stiff silts containing heavily varying amounts of solid and
hard rock fragments. In the area of the Botnang Tunnel portal an
inclinometer was installed already before the start of construc-
tion. The measurements gave no indication of slope movements.
The thickness of the layers varies between 10 and 100 cm. The bed-
ding parallel discontinuities are occasionally marked by soft or
firm clay layers, on which the banks tend to separation.
The soil and rock mechanical parameters listed in Table 4.2 are
based on the results of borehole expansion tests using the bore-
hole jack model "Stuttgart", on laboratory tests on samples taken
from the exploration boreholes as well as on experience gained
from other projects located in comparable ground conditions. The
stability analyses (see Chapter 4.3.5) were based on these parame-
ters.
Lehrberg layers,
E = 300 MN/m2 ϕ = 30°
Untere Bunte Mergel,
ν = 0.3 c' = 130 kN/m2
Dunkel Mergel
Schilfsandstone, E = 150 MN/m2 ϕ = 35°
portal areas ν = 0.3 c' = 30 kN/m2
Bedding B:
2
E = 500-1000 MN/m ϕS = 40°, cS = 50 kN/m2
Schilfsandstone
ν = 0.2 Joints J:
ϕK = 40°, cK = 50 kN/m2
4.3.4 Design
Fig. 4.51 shows the standard profile divided into crown, bench and
invert and the excavation and support measures planned for the
standard excavation procedure. The excavation class was designated
as 7A according to the recommendations of the working group "Tun-
neling" of the German Geotechnical Society (DGGT, 1995: Table 1).
The support should be closed at the invert no more than 2.4 m be-
hind the invert excavation and no more than some 16 m behind the
excavation at the roof (Fig. 4.2, phase I in the left portion).
The reinforced shotcrete should be placed at the invert with a
thickness of 20 to 25 cm (Fig. 4.51).
Fig. 4.52 (phase II, right portion) and 4.53 show the excavation
and support measures planned for the later lowering of the invert
in the area with enlarged cross-section.
The support of the tunnel face and the advancing support should be
constructed as for the standard heading.
profile and the parameters are shown. The computation section con-
sists of a 63.9 m high, 45.7 m wide and 1 m thick slice of rock
mass. The FE-mesh was divided into 1104 isoparametric elements
with a total of 1320 nodes.
For the nodes on the lower boundary plane (z = 0) and on the lat-
eral boundary planes (x = 0 and x = 45.7 m), sliding supports were
introduced as boundary conditions (Fig. 4.54). For the two planes
perpendicular to the tunnel axis (y = 0, y = 1 m), equal displace-
ments were assumed as boundary conditions for nodes with equal x-
Fig. 4.55 and 4.56 show the six computation steps used to simulate
the excavation and the support during tunneling according to the
design (reference case). In the 1st computation step, the state of
stress and deformation resulting from the dead weight of the
ground (in-situ state) is determined. In the 2nd computation step
the excavation of the crown and its support using shotcrete are
simulated. The 3rd computation step comprises the excavation and
shotcrete support of bench I. In the 4th computation step excava-
tion of the invert I and the closing of the temporary support at
the invert are simulated. Since the first two construction stages
(computation steps 2 and 3) were simulated with an open invert,
this analysis sequence accounts for a late closing of the invert
as specified in the design with a distance of approx. 16 m to the
tunnel face (see Fig. 4.52). The connection of the temporary in-
vert support to the sidewall was simulated at first without any
curvature corresponding to the design (Fig. 4.55 and 4.56).
In the 5th and 6th computation step, the excavation of bench II and
the excavation of invert II with simultaneous installation of the
shotcrete support also at the invert are simulated.
Fig. 4.58 depicts the displacements computed for the 6th computa-
tion step and thus the displacements in the stage after the exca-
vation of the total cross-section. The analysis results in com-
paratively large vertical displacements of 12 cm at the roof and
7.4 cm on the ground surface.
Fig. 4.59 shows the stress resultants computed for the stage after
the excavation and support of invert I (4th computation step) and
of the total cross-section (invert II, 6th computation step). In
the 4th computation step (excavation of invert I) extremely high
bending moments result in the area of the connections of the tem-
porary invert support to the sidewalls (Fig. 4.59a). For this
loading, the shotcrete membrane cannot be reasonably designed. In
the 6th computation step as well, comparatively large bending mo-
ments occur in the area of the sidewalls (Fig. 4.59b). The design
of the shotcrete membrane for a concrete grade of B25, a shotcrete
The results of this analysis show first, that the computed dis-
placements decrease considerably due to the simulation of an early
closing of the invert and of the anchoring (see Fig. 4.58 and
4.63). The subsidence of the ground surface amounts to only 27 mm
as opposed to 74 mm in the reference case. The horizontal dis-
placements of the sidewalls decrease from 70 mm in the reference
case to 18 mm.
In Fig. 4.65a the tensile anchor forces determined in the 5th com-
putation step (see Fig. 4.62) are given. Values of up to 100 kN
(10 t) per anchor are computed.
4.3.6 Construction
Fig. 4.66 shows the excavation and support measures carried out
within the area of the enlarged cross-section during the heading
(Beiche and Kagerer, 1993).
The rounds were carried out with lengths of ≤ 80 cm. The temporary
crown invert was supported in the beginning at a distance of 9 to
14 m to the tunnel face. In the area of the undercrossing of the
4.3.7 Monitoring
4.3.8 Conclusions
A crown, bench and invert heading with closed support at the in-
vert and a following lowering of the invert was chosen. With an
early closing of the invert the tunneling-induced subsidence could
be limited to admissible values. It was possible to reduce the
loading at the transitions from the sidewalls to the temporary in-
vert decisively by rounding the temporary crown invert. The load-
ing of the high sidewalls after the enlargement of the cross-
section could be clearly reduced by a systematic anchoring (see
Fig. 4.65).
5.1.1 Introduction
Fig. 5.1: Road tunnel Hahnerberger Straße, site plan and ex-
ploration
5.1.2 Structure
The approx. 130 m long tunnel must provide room in each direction
for two main driving lanes and one exit or approach lane, respec-
tively (Fig. 5.2 and 5.3). The widths of the required clearances
range between 13.5 m and 16.2 m. The height of the clearances
amounts to 4.90 m. The tunnel has a total width of approx. 37 m
and a total height of approx. 12 m (Fig. 5.3). To illustrate these
very large dimensions, the cross-section of a double-tracked tun-
nel for the new high-speed railway lines of German Rail (Deutsche
Bahn AG) is shown in Fig. 5.3.
5.1.3 Exploration
The bedding planes are partially filled with clay and mixed-
grained soils at a thickness of up to 10 to 40 cm. This leads to a
greater deformability perpendicular to the bedding than parallel
to it. After Wittke (1990), transversely isotropic deformation be-
havior can be assumed in the elastic stress domain for an alter-
nating sequence of this kind. This kind of anisotropy can be de-
scribed by 5 independent elastic constants: Two Young's moduli E1
and E2, one shear modulus G2 and two Poisson's ratios ν1 and ν2
(Fig. 5.4).
The modulus E1 relevant for loading parallel to the bedding was de-
rived from the results of the pressuremeter tests and from experi-
1 1
E2 = = ≈ 400 MN/m 2 (5.1)
α β 0.9 0.1
+ +
EIR EBF 1000 70
The shear modulus G2, relevant for shear loading parallel to the
bedding and thus strongly dependent on the mechanical properties
of the bedding plane filling, was estimated at G2 = 325 MN/m2.
Laboratory tests resulted in very high values for the shear pa-
rameters of the intact rock. The failure behavior of the rock is
thus essentially determined by the shear strength along the dis-
continuities, which was modeled by the Mohr-Coulomb failure crite-
rion. For the shear strength parallel to the bedding, the bedding
plane filling is relevant. On the basis of the grain-size distri-
bution and water content and of experience, a friction angle of
ϕB = 25° and no cohesion were assumed (Fig. 5.4).
Unlike the bedding planes, the joints are mostly undulating and
contain sandy, rusty coatings. Close to the surface, however, they
are also partially filled with clayey, sandy silt. It is essential
for the assessment of their shear strength that they mostly only
extend through one layer and thus extend considerably less far
than the bedding. Therefore, a cohesion of cJ ≈ 0 to 0.02 MN/m2 and
a friction angle of ϕJ ≈ 30 to 35° were assumed for the joints (J1
to J3) (Fig. 5.4).
The adit was driven by means of smooth and true to profile blast-
ing. To keep the blasting-induced vibrations low, the round
lengths and the charges per ignition step were limited. Especially
close to the buildings, the excavation profile had to be subdi-
vided for the same reasons (I and II in Fig. 5.5). This experience
could be used for the further planning and tendering of the tun-
nel.
The first step was the excavation and support of a sidewall adit
in the northern tube. The cross-section of the sidewall adit was
again subdivided by a crown heading with trailing invert (Fig. 5.8
and 5.9). As illustrated in Fig. 5.8, the outside sidewall was
supported by a lattice girder and a 30 cm thick shotcrete membrane
as well as by SN-anchors. The side of the sidewall adit facing the
tunnel tube, on the other hand, was supported by only 15 cm of
shotcrete. Glass fiber anchors were further installed on this
side. This part of the support was removed again in the further
course of the works.
In the third step, the crown of the northern tube was excavated
and supported in sections (Fig. 5.10 and 5.11). The lattice gird-
ers and the reinforcement of the shotcrete membrane were connected
The excavation of the bench and the invert constituted the last
steps of the excavation sequence of the northern tube (Fig. 5.12
and 5.13). The invert was supported by 30 cm of shotcrete. Lattice
girders and an invert anchoring could be dispensed with.
Fig. 5.12: Bench and invert excavation with closed invert sup-
port
Since the rock mass is anisotropic and the bedding is neither ori-
ented perpendicularly nor parallel to the tunnel axis (see Fig.
5.4 and 5.14), displacements in x- and y-direction already occur
due to the dead weight of the rock mass. Therefore the nodes on
the vertical boundary planes of the computation section must not
be fixed perpendicularly to the respective boundary plane.
For the two planes normal to the tunnel axis equal displacements
were assumed as boundary conditions for opposite nodes with equal
x- and z-coordinates (Wittke, 2000).
The stability analyses were carried out with the program system
FEST03 (Wittke, 2000) in 4 computation steps: In the 1st computa-
tion step, the stresses and deformations in the rock mass result-
ing from the dead weight of the rock (in-situ state) are deter-
mined. In the 2nd computation step, the central adit as well as the
northern sidewall adit are simulated to be excavated and sup-
ported. The 3rd computation step further accounts for the installa-
tion of the reinforced concrete buttress in the central adit and
the crown excavation in the northern tunnel tube. Then, in the 4th
computation step, the stresses and deformations occurring after
the complete excavation and support of the northern tunnel tube
are computed.
In the 4th computation step the loads resulting from the overburden
weight are diverted around the entire excavation. Above and below
the tunnel unloaded areas develop, whereas stress concentrations
occur in the rock mass beside the northern tunnel tube as well as
above and below the central buttress (Fig. 5.15b and 5.16).
case, in which arching was possible in the rock mass above the
tunnel, shows that the normal thrust increases considerably (Fig.
5.21). Also for this case, however, it was possible to dimension
the shotcrete membrane taking into account the inside and outside
steel fabric mats Q221.
5.1.7 Monitoring
5.1.8 Conclusions
- smooth blasting.
5.2.1 Introduction
5.2.2 Structure
Fig. 5.28 shows the geometry of the standard profile and of the
sidewall adits. The double-tracked tunnel was constructed with a
mouth-shaped profile with a width of 15.2 m and a height of 12.4
m. In the vault area a radius of curvature of R = 7.28 m was se-
lected. The transition from the sidewalls to the invert was con-
structed with a radius of R = 4.43 m. For statical reasons the in-
vert was deeply rounded with R = 11.63 m. The inside walls of the
sidewall adits had a radius of curvature of R = 8.0 m. The roof
and the invert of the sidewall adits were rounded with small radii
of R = 0.4 m (Fig. 5.28).
For 63 samples from the clayey and silty surface layers as well as
from the decomposed rock the unconfined compressive strength was
determined. The unconfined compressive strength of the clay and
silt of the surface layers scatters over the relatively wide range
of 50 to 1900 kN/m2. The results of the tests on decomposed rock,
however, are in the range of 100 to 500 kN/m2. The strength of the
slightly to strongly weathered or decomposed slate is substan-
tially determined by the low strengths on the discontinuities (see
Chapter 5.2.6).
Between the northern portal and the eastern boundary of the middle
horst block, the groundwater table follows the course of the
ground surface at a depth of approx. 5 to 10 m (Fig. 5.27). In the
area of the central sunken block of the Limburg rift, the ground-
water table is located at a depth of about 25 to 45 m at the level
of the two receiving streams, the Elbach and the Lahn. To the east
of the central sunken block, at the Greifenberg horst, the ground-
water table rises again to approx. 5 to 10 m below the ground sur-
face (Fig. 5.27). The seasonal variations in the water table can
amount to several meters. The groundwater table shown in the lon-
gitudinal section (Fig. 5.27) is based on the highest groundwater
levels measured in the boreholes equipped as observation wells.
The groundwater is assumed to flow roughly from northeast to
southwest.
The water permeability of the Devonian rock and the Tertiary lay-
ers is estimated at 10-7 to 10-5 m/s.
In the areas of the Greifenberg horst and the middle horst block,
in which the tunnel cross-section is located in slightly weathered
slate, a crown excavation with closed invert was planned according
to excavation classes 5A-K, 6A-K or 7A-K, depending on the degree
of weathering. In the other much longer sections the tunnel is lo-
cated in soil or in decomposed slate. Here, a sidewall adit exca-
vation was planned according to excavation classes 4A-U, 5A-U, 6A-
U or 7A-U (see DGGT, 1995: Table 1).
Fig. 5.30 shows the sequence of excavation and the support for ex-
cavation class 7A-U-0, which was carried out for the most part.
Excavation class 7A-U-0 is characterized by short round lengths
for crown and bench (A = 0.6 m to 0.8 m), tunnel face support with
plain shotcrete (t ≥ 7 cm), advance support with spiles and early
closing of the invert (C ≤ 3.2 m). The tunnel profile is supported
by a reinforced shotcrete membrane with two layers of steel fabric
mats Q285 and by steel sets spaced at ea = 0.6 to 0.8 m. A system-
atic anchoring of the sidewall adits with SN-anchors was planned
on the outside and as required also on the inside.
The rock mass and the soil could be excavated mechanically using a
tunnel excavator.
The problems with the tunnel face stability that had occurred dur-
ing the sidewall adit excavation north in the decomposed slate of
the middle horst block (see Fig. 5.27) were attributed to the low
shear strengths on the discontinuities of the strongly weathered
to decomposed slate. The foliation and bedding parallel disconti-
nuities F the orientations of which were measured during tunnel
face mapping, strike approximately perpendicularly to the tunnel
axis and dip mostly steeply with dip angles between 40° and 70°
towards the tunnel face. In addition, two joint sets J1 and J2 ex-
ist, which strike in parallel and perpendicularly to the tunnel
axis and dip steeply as well (Fig. 5.39).
The heading of a sidewall adit with crown, bench and invert exca-
vation was simulated in 10 computation steps, which are outlined
in Fig. 5.41. In the 11th computation step the seepage forces due
to the water seeping through the rock mass were applied (Fig.
5.41), which had been determined in a three-dimensional seepage
flow analysis using the program system HYD03 (Wittke 2000). This
seepage flow analysis results in the distribution of piezometric
heads h, from which the seepage forces can be calculated. The
analysis was based on an undisturbed groundwater table located
16 m above the roof of the sidewall adit. Fig. 5.42 shows the lo-
cation of the groundwater table lowered due to the tunnel excava-
tion, the computed equipotential lines (h = const.), as well as,
qualitatively, the direction and magnitude of the seepage forces FS
oriented perpendicularly to the equipotential lines.
5.2.8 Conclusions
5.3.1 Introduction
The high demands and the difficult ground conditions made it nec-
essary to drain the rock in advance and to construct the tunnel in
this area in partial excavations with additional tunnel face sup-
port measures.
5.3.2 Structure
Fig. 5.46 shows the 15.7 m wide and 12.6 m high standard profile
with the geometry of the sidewall adits. The excavated cross-
section amounts to approx. 150 m2.
The sidewall adits were subdivided into crown and bench for the
heading. The remaining cross-section (core) was subdivided into
crown, bench and invert (Fig. 5.46).
Fig. 5.47 shows the starting wall of the northern heading at the
northern portal.
To the south of the Taunus ridge upthrust, in the middle and the
southern part of the tunnel, the rock mass is mostly unweathered.
Individual steep bedding-parallel fault zones here exist (Fig.
5.45b).
In the course of the final design for the tunnel driven by side-
wall adit excavation three-dimensional stability analyses were
carried out with the program system FEST03 (Wittke, 2000).
To calibrate the analysis model and to verify the soil and rock
mechanical parameters the analyses were to be based upon, the ver-
tical and horizontal ground displacements measured at measuring
cross-section MC 2 (Fig. 5.51) during the sidewall adit heading
were back-analyzed first. MC 2 (analysis cross-section AC 1) is
located at km 141+580 approx. 20 m in front of the undercrossing
of freeway A3 (Fig. 5.51). To record the vertical and horizontal
displacements resulting from the heading, leveling points were set
up at the ground surface and 3 multiple extensometers as well as 2
inclinometers were installed beside and above the tunnel. Zero
readings were taken sufficiently ahead of the excavation. The ar-
According to the assumed symmetry the two sidewall adits are simu-
lated as being excavated parallel in time in the analyses. In re-
ality the western sidewall adit heading ran ahead of the eastern
one by 10 to 20 m (g in Fig. 5.49). The influence of the simpli-
fied simulation in the analysis on the final result is small, how-
ever.
The tunnel face support using shotcrete is not taken into account.
decisive and taken as a basis for the design of the shotcrete mem-
brane.
larger than the minimum reinforcement only ensue in the roof (sec-
tions 1 and 2, Fig. 5.60).
5.45b; Wittke and Pierau, 2000; Wittke and Sternath, 2000). For
this purpose three-dimensional FE-analyses were carried out for
the computation section shown in Fig. 5.61 with the program system
FEST03 (Wittke, 2000).
Fig. 5.62: Crown heading with closed invert and tunnel face an-
choring: a) Stress resultants in the shotcrete mem-
brane; b) required reinforcement
The analysis results show that the stability of the crown heading
can be proved if the tunnel face is supported by advance anchoring
and the support is closed soon at the invert. As in the analyses
described before, the tunnel face anchors were accounted for by a
support of the tunnel face with p = 0.04 MN/m2 (see Fig. 5.61). It
can be proven that the subsidence due to the heading can be kept
small in this way. The computed loading of the shotcrete membrane
of the crown due to bending and normal thrust (Fig. 5.62a) reveals
a high bending compression loading at the transition to the tempo-
rary invert. The reason for this is the small radius of curvature
of the shotcrete membrane of only 2 m. For reasons inherent to the
construction process it is often attempted to keep the radius of
curvature as small as possible. For statical reasons, on the other
hand, the radius of curvature should not be less than 2 m. Supple-
mentary reinforcement cannot be dispensed with in this case, how-
ever, although the membrane is rounded according to this require-
ment (Fig. 5.62b).
5.3.6 Construction
Fig. 5.65: Tunnel face support of the sidewall adit, crown and
bench
Fig. 5.66 depicts the support measures during the sidewall adit
heading in cross- and longitudinal section. It shows that excava-
tion class 7A-U-1 was modified as follows with respect to the
original design (see Fig. 5.49):
Pipe umbrellas (see Fig. 5.50) were only carried out in the core
area of the tunnel's cross-section during the undercrossing of the
freeway A3.
Fig. 5.68 depicts the support measures carried out during the
crown heading in cross- and longitudinal section. The round
lengths and the excavation sequence are shown in the longitudinal
section as well.
5.3.7 Conclusions
A sidewall adit heading with short round lengths was carried out.
To stabilize the tunnel face the rock had to be drained in advance
and the tunnel face had to be supported by shotcrete and anchors.
The results of three-dimensional FE-analyses showed that addi-
tional measures were required to support the work space at the
tunnel face, such as e. g. the support of the temporary crown in-
vert of the two sidewall adits and the installation of spiles. Be-
cause of the extensive support measures a very low heading per-
formance could only be achieved.
6. Full-face heading
6.1.1 Introduction
The present Chapter describes the tunnel section of lot 601 driven
by underground construction, with an emphasis on the undercrossing
of the runway of the airport. In this section the absolute and
6.1.2 Structure
The course of the alignment and the ground profile are shown in
Fig. 6.2. Following lot 92, the alignment descends in the direc-
tion of Bernhausen up to the area in front of the runway.
Two single-tracked tunnel tubes are planned for the mined tunnel
section (lot 601), only one of which has been built for the time
being, however. The tunnel tube was constructed with a circular
profile, among other reasons also in order to be able to design
the shotcrete membrane for the full water pressure. The 30 to 35
cm thick shotcrete membrane was made from alkali-free dry-mix
shotcrete with a low water permeability using spray cement as a
bonding agent (see Chapter 2.1.2). The excavated diameter is ap-
In the area of the airport runway the tunnel roof is located ap-
prox. 21 m below the ground surface (Fig. 6.4). Stuttgart Airport
Co. (Flughafen Stuttgart GmbH, FSG) demanded that the tunneling-
induced subsidence in this area has to be limited to 15 mm and the
differential subsidence at the ground surface to 1 o/oo.
The ground profile in the area of the mined tunnel of lot 601 is
similar to the one in the area of the Österfeld Tunnel (see Chap-
ter 4.1). The stratigraphic sequence includes the layers of the
Knollenmergel, the Rät, the Lias α and the Quarternary (see Fig.
4.4).
formation (Fig. 6.2 and 6.4). In the area of the airport runway it
lies completely within the layers consisting predominantly of mud-
stone. Adjacent to the cut-and-cover tunnel sections, i. e. in the
areas with descending or climbing alignment, the tunnel crosses
through the alternating sequence of mudstone and banks of lime-
sandstone (Fig. 6.2). Fig. 6.5 is a photograph of the temporary
tunnel face, in which the lowest banks of lime-sandstone of the
alternating sequence, which are also referred to as "main sand-
stone", are clearly recognizable.
Fig. 6.7 shows the structural model (see Chapter 2.5.1) derived
for the ground in the area of the tunnel section driven by under-
ground construction. The discontinuity fabric is characterized by
an orthogonal system of horizontal bedding parallel discontinui-
ties and steep to vertically dipping joints. Unlike to the banks
of lime-sandstone, the bedding parallel discontinuities and joints
in the mudstone layers are mostly closed or filled with clay and
only vaguely recognizable. In the mudstones of the Rät and the
Knollenmergel slickensides exist, dipping at 20 to 40° and strik-
ing in all directions (see Chapter 4.1.3).
The soil and rock mechanical parameters given in Table 6.1 were
specified on the basis of the results of laboratory and in-situ
tests as well as experience gained from projects in comparable
ground conditions (see Chapter 4.1). For the rock layers of the
Lias α formation encountered in the area of the mined tunnel, a
transversely isotropic elastic stress-strain behavior, described
by 5 independent elastic constants (Wittke, 2000), was assumed for
loading below the strength. A further characteristic of the Lias α
layers are the low shear strengths on the bedding parallel discon-
tinuities and the joints.
stresses of ΔσH = 0.5 to 1.7 MN/m2 were derived from the results of
these stress measurements.
The mined tunnel section of lot 601 is thus located almost over
its entire length completely underneath the groundwater table. The
maximum height of the water table above the tunnel's invert is
reached in the area of the airport runway with approx. 26 to 27 m
(see Fig. 6.4).
Fig. 6.8: Advance construction (lot 92), site plan with draw-
down cone
Especially the soft valley deposits in the runway area (see Fig.
6.6) are very sensitive to settlements. Especially here, but also
in other areas, a lowering of the groundwater table as a conse-
quence of the tunnel heading would lead to subsidence due to loss
of the hydrostatic uplift. The FSG therefore demanded that no
groundwater lowering must occur during the underground tunneling.
tions. The program system used for this purpose was developed by
WBI (Erichsen, 1994). It is described in detail in Wittke (2000).
The assumptions made and the results of the analyses are described
and explained in detail in Wittke (2000) as well, and also in Wit-
tke-Gattermann and Wittke (1997). The permeability of the layers
consisting predominantly of mudstone (see Chapter 6.1.3), in which
the tunnel is located in the area of the undercrossing of the air-
port runway, as well as the permeability of the shotcrete membrane
of the tunnel were varied in the analyses.
The grouting boreholes were sealed against the borehole head with
fabric packers (geotextiles) filled with cement based suspension.
During the grouting works the heading had to be interrupted for
approx. 2 weeks each time.
Fig. 6.16 and 6.17 show the stress resultants in the shotcrete
membrane determined in this analysis. The representation of the
maximum stress resultants along the tunnel in Fig. 6.16 illus-
trates that the loading of the shotcrete membrane continuously de-
velops with increasing distance from the tunnel face, until the
maximum values are reached at a distance of approx. twice the tun-
nel's diameter. This cross-section is designated the dimensioning
section, because the stress resultants determined here have to be
considered decisive for the design of the shotcrete membrane (see
Chapter 5.3).
The load case water pressure acting on the shotcrete membrane was
investigated in separate two-dimensional FE-analyses. Because the
water pressure builds up only at a certain distance from the tun-
nel face, it suffices to superpose the stress resultants ensueing
from the rock mass pressure and the water pressure and to design
the shotcrete membrane on the basis of the stress resultants thus
obtained.
6.1.7 Monitoring
Mudstone with
single layers of ΔσH = 1.5 MN/m2 ΔσH = 1.0 MN/m2
lime-sandstone
The low modulus of ESC = 2000 MN/m2 accounts for the deformability
development as well as the creep properties of the shotcrete. Be-
cause of the short round lengths and the early closing of the sup-
port ring, the shotcrete is loaded in the present case at a very
young age, in which it still possesses a low strength and a high
deformability as well as a high creep potential (see Chapter 2.1).
The value of ESC = 15000 MN/m2 used in the design analyses there-
fore represents a conservative assumption, by which the loading of
the shotcrete membrane is overestimated.
Fig. 6.23 shows the comparison between the measured and the com-
puted values of the displacements of the tunnel contour and the
tangential stresses in the shotcrete.
ured tangential stresses are markedly higher in the roof than the
tangential stresses shown for in the shotcrete membrane of the ur-
ban railway tunnel.
6.1.9 Conclusions
6.2.1 Introduction
The two tunnel tubes were driven mainly by the full-face excava-
tion method within a construction time of approx. 10 month. With
four tunnel faces, maximum performances of approx. 30 m/d were at-
tained.
6.2.2 Structure
Two tunnel tubes, eastern tube and western tube each 2700 m in
length were constructed (Fig. 6.27). The spacing of axis of both
tubes ranges between approx. 23 m at the northern portal and ap-
prox. 30 m at the southern portal. Each tube comprises two traffic
lanes each 3.75 m wide and two emergency sidewalks (Fig. 6.28).
The excavated cross-section of the tunnel ranges between 80 m2 and
100 m2 (Fig. 6.28 and 6.29). The alignment dips continuously to-
wards the southern portal with 1.1 %. The maximum overburden
amounts to approx. 190 m (Fig. 6.26).
6.28 and 6.29). In the tunnel sections with closed invert between
the interior lining and the shotcrete membrane a separation foil
was installed at the invert (Fig. 6.28). Thus, in this area be-
tween interior lining and shotcrete membrane no tensile and shear
forces can be transferred.
Both tubes were carried out as fully drained road tunnels. The
seepage water was drained off by two lateral drainage pipes in the
area of the lower sidewalls and the gradient of the tunnel of
1.1 % (Fig. 6.28 and 6.29). Flushing shafts for the washing of the
drainage ducts are provided at distances of 50 to 80 m on both
sides of the lanes.
Fig. 6.30 shows the northern portal of the Berg Bock tunnel.
Fig. 6.31: View of the working face in the Lower Triassic sand-
stone
The layers of the Lower Triassic sandstone and the base sediments
consist of an alternating sequence of sandstone and mudstone. The
widely persistent bedding parallel discontinuities are mostly
horizontal in the Lower Triassic sandstone (Fig. 6.31) and pre-
dominantly steeply inclined in the base sediments. The joints nor-
mal to the bedding usually end at the bedding parallel discontinu-
ties.
In the area of the northern portal (Fig. 6.26), the following sup-
porting measures were carried out:
The round lengths ranged between 0.75 and 1.0 m. A heading per-
formance of approx. 1 m/d was achieved in the area of the com-
pletely weathered granite.
Heading schedule
Both tunnel tubes were excavated within some 10 months each, cor-
responding to an average heading performance of approx. 9 m per
day and tube.
Fig. 6.34 shows exemplarily the heading progress over time for the
eastern tube (see Fig. 6.27). The western tube was excavated in
parallel with the eastern tube by so-called opposite heading. The
eastern tube was successfully cut through on January 19, 2001. The
cut-through of the western tube and thus the heading of the entire
tunnel was celebrated on February 2, 2001.
In Fig. 6.37 the computation steps are outlined. In the 1st compu-
tation step, the state of stress and deformation resulting from
Fig. 6.38 shows the principal normal stresses in the rock mass
around the excavation after the full-face excavation and the in-
stallation of the shotcrete support at the end of the 3rd computa-
tion step. The stress redistribution that occurred with the exca-
vation as well as the areas of exceeded strength can be recog-
nized. Although these areas extend around the entire circumference
of the excavation, a pronounced arching is apparent. Due to the
low deformability of the rock mass (E = 15000 MN/m2, see Fig.
6.35), the shotcrete membrane is only marginally loaded by the
rock mass and thus takes on a slightly stabilizing and assisting
function only.
The excavation of the shoulders (4th and 5th computation step) does
not lead to significant changes relative to the 3rd computation
step.
Unlike the stability analysis for the design of the shotcrete sup-
port, the decomposed granite and weathered granite (see Fig. 6.35)
were not modeled here, since these layers are insignificant for
For the design of the interior lining it is assumed that the shot-
crete will be decomposed in the course of time and lose its bear-
ing capacity. The assumed parameters for the decomposed shotcrete
are given in Fig. 6.42. Since the interior lining is only sub-
jected to significant loads after having reached its final
strength, the calculation value for Young's modulus of 34000 MN/m2
commonly used for concrete of grade B35 is assumed (DIN 1045,
1988).
Vault
In the portal zones, in the weathered rock mass, in the base sedi-
ments and in the Lower Triassic sandstone a reinforcement was
statically required, however.
Shoulders
For the shoulders, the load combination dead weight and rock mass
pressure results in a required shear reinforcement of 7.7 cm2/m2
for analysis cross-section AC 2 (Fig. 6.46). The proof of limita-
tion of crack width according to DIN 1045 (1988) leads to a re-
quired reinforcement for the shoulders of 12.88 cm2/m in both, lon-
gitudinal and transverse direction. This amount of reinforcement
is covered by top and bottom rebars Ø 10 mm spaced at s = 10 cm,
to be placed in longitudinal and transverse direction. To cover
the required shear reinforcement, steel fabric mats were bent to
stirrup cages (Fig. 6.48). The shoulders were reinforced over the
entire tunnel length.
6.2.7 Monitoring
The heading of the Berg Bock Tunnel was accompanied by a geotech-
nical monitoring program.
In the longitudinal section of Fig. 6.49 the range of the roof
subsidence measured after the heading of the entire tunnel was
completed is exemplarily shown.
The largest subsidence was measured in the portal areas with val-
ues between 10 and 50 mm. In those tunnel sections where the
cross-section is located in granite or porphyrite, a roof subsi-
dence between 2 and 5 mm was measured. In the base sediments and
in the Lower Triassic sandstone the roof subsidence ranges from 5
to 15 mm.
6.2.8 Conclusions
Due to the low deformability and the high strength of the rock
mass, the ground was able to carry approx. 90 % of the overburden
load, and the means of support only had a slightly assisting func-
tion. On this basis it was possible to optimize the heading con-
ception and to excavate both tunnel tubes in a very short time.
With the construction of the interior lining using plain concrete
over approx. 50 % of the total tunnel length, the costs for the
interior lining could be kept low as well.
7.1.1 Introduction
7.1.2 Structure
Two tunnel tubes with two lanes and a width of approx. 11 m each
were excavated over a length of approx. 1000 m (Fig. 7.1 and 7.2).
The overburden of the tunnel tubes amounts to approx. 6 to 8 m
(Fig. 7.2). Approximately in the middle of this section the tun-
nels undercross the ICE/IC (Intercity Express/Intercity) line Co-
logne-Koblenz of German Rail as well as a city railway tunnel. The
latter is located at the construction pit Moltke square (Fig.
7.1).
The transitions from the sidewalls to the temporary invert and the
permanent invert, respectively, were constructed with relatively
small radii (Fig. 7.4). This leads to bending moments and shear
forces in the shotcrete membrane in these areas. As shown below,
at a radius of 1.2 m supplementary reinforcement is required at
The tunnels were headed in the mostly sandy and gravelly soil lay-
ers of the gravel deposits of the lower terraces typical for the
Rhine valley in the area of Bonn. Below the tunnel invert silt
lenses are sporadically embedded in the sand and gravel layers
which will be termed gravel sand in the following (Fig. 7.5).
Fig. 7.6 shows the grading ranges of the encountered gravel sand
and the silt, together with the parameters derived from the sub-
soil exploration results.
The sequence of excavation and the support measures for the head-
ing of the two two-lane tunnels are shown in Fig. 7.7 and 7.8 in
cross- and longitudinal section.
exceeds the angle of friction of the gravel sand (see Fig. 7.6),
the tunnel face was not stable if the apparent cohesion was not
taken into account. Since the latter quickly vanishes with the
soil drying up, only small sections could be excavated in one
step. These sections were immediately sealed with reinforced shot-
crete.
lapses are avoided, and the safety of the tunneling staff is thus
ensured as well.
Fig. 7.10: Load transfer by the jet grouting vault and the
shotcrete membrane: a) Cross-section; b) longitudi-
nal section
Fig. 7.12: Tunnel face with support core and niche for the con-
struction of the jet grouting columns
The nozzle rotates with the rod which is slowly pulled out of the
borehole. In this way a column develops due to the mixing of the
suspension with the ground. After hardening of the cement, this
column possesses a high strength in comparison with the undis-
turbed soil. The surplus mixture of suspension and soil exits as
backflow through the annular gap between borehole and rod. Fig.
7.13 shows the jet grout drill carriage in operation.
In the area where the tunnel tube is divided into three sections,
the side tubes were excavated first under the protection of jet
grouting columns and supported. The central tube was only exca-
vated after the interior lining had been installed in both side
tubes. A crown excavation with trailing bench and invert was car-
ried out here. The shotcrete membrane of the central tube hereby
is supported by the interior linings of both side tubes (Fig.
7.16).
Fig. 7.19 shows the computation section, the FE-mesh, the boundary
conditions, the ground profile and the parameters this analysis
was based upon. The computation section consists of a 25 m wide,
30.5 m high and 1 m thick slice of the ground. The FE-mesh was
subdivided into 669 three-dimensional isoparametric elements with
a total of 797 nodes.
The parameters chosen for the undisturbed soil and the soil stabi-
lized with jet grouting columns were determined on the basis of
the exploration results by the parties concerned during technical
discussions. They are shown in Fig. 7.19.
Young's modulus assumed for the shotcrete was varied in the sta-
bility analyses. In the following the computation sequence and the
results of an analysis are presented, in which a modulus of
E = 7500 MN/m2 was selected for the shotcrete (Fig. 7.19). This
relatively small value reflects the development of strength and
deformability and the creep properties of the shotcrete (see Chap-
ter 2.1). In the case presented here the shotcrete is loaded at a
very young age due to the early closing of the shotcrete support
approx. 6 to 8 m behind the crown excavation (see Fig. 7.8).
After the preceding stress relief of the soil in the area of the
invert excavation in the 7th computation step, the drawdown of the
groundwater table to the invert level and the excavation and shot-
crete support of the invert are simulated in the 8th computation
step.
In Fig. 7.22 the nodal displacements computed for the 8th computa-
tion step related to the in-situ state (1st computation step) are
shown in horizontal sections above the tunnel roof. The subsidence
of the ground surface above the tunnel roof amounts to 33 mm.
Fig. 7.25 shows the design of the support in the area of the
bench's foot.
7.1.6 Monitoring
Fig. 7.26 shows the maximum values of the ground surface subsi-
dence measured during the heading between the two construction
pits Moltke square and Van-Groote square. The largest subsidence
of approx. 6.5 cm occurred close to the construction pit Moltke
square in an area where the tunnel tubes were headed by sidewall
adit excavation without jet grouting columns. In the other areas
the maximum subsidence of the ground surface ranged between ap-
prox. 15 mm and approx. 45 mm (Fig. 7.26). The maximum ground sur-
face subsidence of 33 mm computed for analysis cross-section 2 is
in good agreement with the measured values (see Fig. 7.22 and
7.26).
7.1.7 Conclusions
The tunnel was excavated by the NATM under the protection of ad-
vancing jet grouting columns. With this measure a part of the
overburden load could be transferred in lateral and longitudinal
tunnel direction (see Fig. 7.10). Thus the green shotcrete in the
tunnel face area and the tunnel face itself was less strongly
loaded. Furthermore, with the jet grouting columns, the subsidence
was limited, collapses were avoided, and the safety of the tunnel-
ing staff was thus ensured as well. The tunnel was excavated with
a steeply inclined stepped tunnel face, short round lengths and a
fast closing of the invert support (see Fig. 7.8). To guarantee
the stability of the tunnel face, an immediate tunnel face support
in sections using reinforced shotcrete was necessary.
7.2.1 Introduction
Between July 1990 and April 1991 the "Killesberg-Messe" city rail-
way tunnel was constructed in Stuttgart, Germany. A 64 m long sec-
tion of the tunnel alignment is located immediately adjacent to
the State Academy of Art and Design (Academy of Art, Fig. 7.27 and
7.28). In addition, the tunnel was driven through a quarry fill in
this area. To keep the subsidence due to tunneling small, the tun-
nel was headed in this section under the protection of an advance
support constructed by jet grouting columns (EN 12716, 2001).
7.2.2 Structure
At the portal (km 0+500) the city railway tunnel cuts into talus
material and the upper layers of the Gypsum Keuper (Estherien lay-
ers). Starting at km 0+650 the Schilfsandstone enters into the
tunnel profile from the roof. From km 0+700 to the end of the tun-
nel at km 0+860 the roof and the upper part of the sidewalls are
located in the quarry fill. The lower part of the sidewalls and
the tunnel invert cut into the Schilfsandstone. The boundary to
the Gypsum Keuper is located in this area at the level of the tun-
nel invert or slightly below (Fig. 7.28).
The ground conditions were mainly derived from the results of core
drillings. In addition, test pits were excavated and dynamic prob-
ing were carried out. The evaluation of old aerial photographs and
seismic measurements served to localize the quarry edges. In front
of the Academy of Art a test shaft 4 m in diameter was sunk. Here
samples for soil mechanical laboratory tests were taken and plate
loading tests were carried out to determine the deformability.
The Gypsum Keuper layers in the tunnel invert area belong to the
White and Grey Estherien layers. Anhydrite or gypsum deposits were
not encountered in the course of the ground exploration down to
approx. one tunnel diameter below the invert. Swelling phenomena
due to the tunneling were therefore not to be expected in the
ground. No leaching cavities were drilled into either in the area
specified above.
talus
7 0,40 21,5 25 25 - - - -
material
quarry
6 0,25 19 30 0 - - - -
fill
Schilf-
2000 0,20 25 40 3000 40 30 40 0
sandstone
Gypsum
100 0,33 23 30 50 30 20 30 20
Keuper
Between km 0+556 and km 0+808 the city railway tunnel was driven
as a crown heading with trailing bench and invert excavation (Fig.
7.32a).
Crown and bench were excavated with a stepped tunnel face and a
support core in the crown area and with round lengths of 2.4 to
3.3 m. To ensure the stability of the temporary tunnel face, it
was supported in sections with reinforced shotcrete. The invert
was excavated 11 to 15 m behind the bench. The distance between
the crown face and the closing of the support at the invert
amounted to between 16 and 22 m, depending on the ground condi-
tions encountered (Fig. 7.32b).
The drillings were directed with a 6 degree outward slant with re-
spect to the tunnel axis. Thus, at the end of the enlarged excava-
tion section there was enough clearance to construct the columns
for the following section (Fig. 7.34b).
Fig. 7.34: Advancing grouting of the quarry fill and jet grout-
ing columns: a) Cross-section; b) longitudinal sec-
tion
The nature of the ground in the area of the jet grouting columns
to be constructed required particular measures. To prevent the ce-
7 sections
Per section
64 m
Boreholes number 14 - 25 152
Drilling/sleeve pipe m 283 1950
Grouted volume m3 52 361
Cement t 14 99
Covered volume of soil m3 325 2280
Achieved grouting volume % 16 16
then halfway between two columns each, and finally in the gaps be-
tween two adjacent columns. This way a vault supported by the
Schilfsandstone was constructed made up of intersecting or, in the
area more widely fanned out, touching columns. The operational pa-
rameters of the jet grouting and the amount of work done are given
in Tables 7.4 and 7.5 (Beiche et al., 1991).
7 vaults
Per segment
64 m
Columns number 28 - 44 268
Drilling m 308 - 561 3280
Grout m3 103 723
Cement kg 91000 637000
Fig. 7.35 shows the construction equipment SR 510 used for the
Killesberg-Messe city railway tunnel in operation. The boreholes
for the grouting of the quarry fill were drilled with the same
equipment (Beiche et al., 1991).
Days 10 20 30 40 50 60 70
The grouting of the quarry fill and the construction of the jet
grouting columns had to be worked into the heading scheme. Since
the columns could not be constructed in parallel with the heading,
the established heading operation in ten-days periods was gener-
ally changed over for the area with jet grouting columns to a con-
tinuous operation on demand for reasons of time (Beiche et al.,
1991).
For the design of the shotcrete support and the interior lining
two-dimensional FE-analyses were carried out using the program
system FEST03 (Wittke, 2000). Eight analysis cross-sections were
investigated in total, differing with respect to
Fig. 7.36 shows the computation section, the FE-mesh, the boundary
conditions, the ground profile and the parameters for this analy-
sis cross-section.
Fig. 7.38 shows the seven computation steps simulating the in-situ
state and the construction stages, which are the installation of
the jet grouting vault, crown, bench and invert excavation, in-
stallation of the interior lining and rise of the groundwater ta-
ble to roof level.
Fig. 7.39 to 7.41 show the analysis results for the 4th computation
step (crown and bench excavation).
Above the left half of the tunnel in the area of the vertical
quarry wall the major principal normal stress deviates from the
vertical. The vertical stresses are lower in the fill and higher
in the Schilfsandstone than the overburden weight. This result is
due to the different Young's moduli of the Schilfsandstone and the
fill. The quarry fill is thus "hung" on the edge already in the
stage before the tunnel excavation and the construction of the jet
grouting vault. This effect should be less pronounced in reality
than in the analysis, since the fill was placed in layers rather
than in one step as simulated in the analysis.
The computed roof subsidence amounts to approx. 2.5 cm. Heave oc-
curs at the bench base (Fig. 7.39b).
An arch develops in the jet grouting vault above the crown. Due to
its bond with the shotcrete membrane the latter is strongly loaded
as well and stress concentrations result in the area of the bench
base. To illustrate the load transfer described above, the hori-
zontal and vertical stresses are shown in sections in Fig. 7.40.
Stress concentrations in vertical as well as in horizontal direc-
tion are apparent at the base of the bench and of the jet grouting
vault. The loading of the shotcrete membrane exceeds the one of
the jet grouting vault. This is due to Young's modulus of the
shotcrete being markedly higher than the one of the jet grouting
columns (see Fig. 7.36).
Fig. 7.41 shows the computed bending moments and normal thrust in
the shotcrete membrane. Large bending moments together with a com-
paratively small normal compressive thrust occur in the roof and
the lower sidewall areas.
These results change only slightly with the invert excavation and
the immediate closing of the support (5th computation step).
The design of the interior lining was based on the following load
cases:
7.2.6 Monitoring
7.2.7 Conclusions
The tunnel was driven by crown heading with trailing bench and in-
vert excavation. It was constructed with a steep tunnel face,
short round lengths and a fast invert support closing (see Fig.
The FE-analyses carried out have been an important tool for the
design, the statics and the specification of the excavation and
support measures. The comparison of the FE-analysis results with
the measured displacements in the ground showed good agreement
(see Fig. 7.43).
8. References
Beiche, H.; Erichsen, C.; Kagerer, W.; Schilcher, E.; Wooge, M.:
Praktische Lösungen bei der vorauseilenden Schirminjektion unter
Einsatz von Hochdruckinjektionen (HDI). Taschenbuch für den Tun-
nelbau 1992. Verlag Glückauf, Essen, 173 - 211, 1991.
Deuse, T.; Mann, K.; Rüßmann, F.: New spray cement for processing
naturally moist aggregates for the dry spraying method. Tunnel
6/1998, 37 - 41, 1998.
DIN 4226, Part 1: Zuschlag für Beton; Zuschlag mit dichtem Gefüge;
Begriffe, Bezeichnungen und Anforderungen, 1983.
DIN 4226, Part 2: Zuschlag für Beton; Zuschlag mit porigem Gefüge
(Leichtzuschlag); Begriffe, Bezeichnungen, Anforderungen, 1983.
DIN 21521, Part 1: Gebirgsanker für den Bergbau und den Tunnelbau;
Begriffe, 1990.
DIN 21521, Part 2: Gebirgsanker für den Bergbau und den Tunnelbau;
Allgemeine Anforderungen für Gebirgsanker aus Stahl, Prüfungen,
Prüfverfahren, 1993.
Eber, A.; Betzle, M.; Baumann, T.: Untersuchungen zum Einsatz von
Gitterträgern im Tunnelbau. Bauingenieur 60, 137 - 141, 1985.
Maidl, B.: Handbuch für Spritzbeton. Verlag Ernst & Sohn, Berlin,
1992.
Wittke, W.: Rock Mechanics - Theory and Applications with Case Hi-
stories. Springer Verlag, Berlin, Heidelberg, New York, Tokyo,
1990.
Wittke, W.; Pierau, B.; Erichsen, C.: Der Einsatz von Hochdruckin-
jektionen zur Baugrundverbesserung und für den Tunnelbau im Lok-
kergestein. 15. Veder Kolloquium. Graz, 155 - 182, 2000.