ITA/AITES

ITA/AITES – Training Course


TUNNEL ENGINEERING

GROUND REINFORCING FOR TUNNELLING


THE EXAMPLE OF STEEL PIPE UMBRELLA
Prepared by “D. Peila”

Istanbul - 2005

4th of May 2005 1/56


1 Index
Introduction

2
Chapter 1: Classification of ground reinforcement tecniques

3
Chapter 2: Steel pipe umbrella

4
Chapter 3: Design approach

5 References

Ground reinforcing for tunnelling


The example of steel pipe umbrella 2/56
1 Introduction
Difficult geotechnical conditions
Self supporting time and free span are too short and
2 not compatible with an industrial activity

3 Solutions

- To reduce the size of the excavation sections


4 - To improve the rock mass quality or reinforce it
- To pre-support the excavation
5 - To apply a pressure to the tunnel face

Ground reinforcing for tunnelling


The example of steel pipe umbrella 3/56
1 Introduction

USE OF GROUND REINFORCEMENT


2 To adeguate the free span and
the self supporting time to the
Traditional excavation industrial needs which require to
enlarge the excavation section
3

4 To Cross “geo” problems


TBM excavation which were encountered with a
non suitable TBM
5

Ground reinforcing for tunnelling


The example of steel pipe umbrella 4/56
1 Introduction

2
Tunnel ground reinforcement methods can be
classified on the basis of
3

4 Construction method Action

Ground reinforcing for tunnelling


The example of steel pipe umbrella 5/56
1 Chapter 1

2 Construction method

improvement
3
reinforcement

4 presupport

drainage
5

Ground reinforcing for tunnelling


The example of steel pipe umbrella 6/56
1 Chapter 1
IMPROVEMENT
2 Methods which improve (from the engineering point of
view) the mechanical or hydraulic properties of the rock
mass: injecting fluids or freezing the fluids already present
3 in the ground

4
Injection (at low pressure)
5 Jet grouting
Freezing

Ground reinforcing for tunnelling


The example of steel pipe umbrella 7/56
1 Chapter 1
Systematic jet-grouting
2

5 Montà d’Alba tunnel (Italy)


(courtesy of Geodata S.p.A)

Ground reinforcing for tunnelling


The example of steel pipe umbrella 8/56
1 Chapter 1
Injection around the tunnel
2

Milan Metro (Italy)


5 .

Ground reinforcing for tunnelling


The example of steel pipe umbrella 9/56
1 Chapter 1

REINFORCEMENT
2 Methods which use the insertion, inside the rock mass, of
structural elements with one prevalent dimention

3 They apply shear stresses to


the rock mass on the contact
surface
4
Bolts
5 Micropiles
Cable bolting

Ground reinforcing for tunnelling


The example of steel pipe umbrella 10/56
1 Chapter 1

Radial bolting from a pilot bore


2

5 Serena Tunnel (Italy)

Ground reinforcing for tunnelling


The example of steel pipe umbrella 11/56
1 Chapter 1
Tunnel face bolting
2

5
Tunnel face reinforcement schemes
Highspeed railway between Bologna and Florence (Italy)

Ground reinforcing for tunnelling


The example of steel pipe umbrella 12/56
1 Chapter 1
Tunnel face bolting

5
Tunnel face reinforcement schemes
Highspeed railway between Bologna and Florence (Italy)

Ground reinforcing for tunnelling


The example of steel pipe umbrella 13/56
1 Chapter 1
Tunnel face bolting

5
Brossure CAVET

Ground reinforcing for tunnelling


The example of steel pipe umbrella 14/56
1 Chapter 1

Pre-support
2 Methods which use the insertion, in the rock mass, of
structural elements ahead the tunnel face with the
purpose to create a pre-support before the excavation
3

4
Mechanical precut
Pretunnel
5 Steel pipe umbrella
Arch of microtunnels
(1/2)

Ground reinforcing for tunnelling


The example of steel pipe umbrella 15/56
1 Chapter 1
If improvement techniques are used to create a reinforced
2 zone around the tunnel and ahead the tunnel face
The global action must be considered as the most important and
therefore this intervention must be classified as a pre-support
3

4
Jet-grouting arch with or without reinforcement
Consolidation of the tunnel profile: injected and reinforced
5 with glass fiber elements
Injection around the tunnel (2/2)

Ground reinforcing for tunnelling


The example of steel pipe umbrella 16/56
1 Chapter 1
Steel pipe umbrella
2

Ground reinforcing for tunnelling


The example of steel pipe umbrella 17/56
1 Chapter 1

4
Steel pipe umbrella
5 Jet grouting columns on the face

Ground reinforcing for tunnelling


The example of steel pipe umbrella 18/56
1 Chapter 1
jet-grouting arch

Ground reinforcing for tunnelling


The example of steel pipe umbrella 19/56
1 Chapter 1
Forepoling

Ground reinforcing for tunnelling


The example of steel pipe umbrella 20/56
1 Chapter 1

precut
2

4 Precut and face reinforcement

Ground reinforcing for tunnelling


The example of steel pipe umbrella 21/56
1 Chapter 1

DRAINAGE
2

Technologies which purpose is to take away water from


3 the rock mass in a controlled way

Ground reinforcing for tunnelling


The example of steel pipe umbrella 22/56
1 Chapter 1
Action
2
Methods which modify the convergence-confinement curve

3 Methods which modify the radial displacement at the face

Methods which guarantee the stability of the free span

4 Methods which guarantee the local stability of the face

5
Methods which guarantee the stability of local volumes

Methods which control water inflow

Ground reinforcing for tunnelling


The example of steel pipe umbrella 23/56
1 Chapter 1
Global view of the position of reinforcement around a tunnel

5 Courtesy Geodata S.p.A. Torino,Italy

Ground reinforcing for tunnelling


The example of steel pipe umbrella 24/56
1 Chapter 1
Methods which modify the convergence-confinement curve

2
pressure
P0

5
displacement

Ground reinforcing for tunnelling


The example of steel pipe umbrella 25/56
1 Chapter 1

2 Methods which modify the radial displacement at the face


pressure P0

3
linea di reazioneLINE
REACTION dei sostegni
OF THE SUPPORTS

4
REDUCTION OF THE DISPLACEMENT AT THE TUNNEL FACE

5 u0 * u
0

displacement

Ground reinforcing for tunnelling


The example of steel pipe umbrella 26/56
1 Chapter 1

2 Methods which guarantee the stability of the free span and of the face

3
Face stabilization

4 Free span stabilization


free span

5 lining

Ground reinforcing for tunnelling


The example of steel pipe umbrella 27/56
1 Chapter 2

Steel pipe umbrella


2
Steel pipe umbrella is a pre-reinforcement technique
which is obtained by installing steel pipes ahead of the
3 tunnel face.

The steel pipes usually have a dip of 5°-10° (with


4 reference to the horizontal) in a way as to form an
umbrella with a truncated cone shape and which allows
the overlapping of two adjacent umbrellas.
5

Ground reinforcing for tunnelling


The example of steel pipe umbrella 28/56
1 Chapter 2
Steel pipe umbrella

4
It is possible to cover advance lengths of 12-13m, of which 9-10m are
5 actual excavation, account being taken of the necessary overlap
between two sets of steel pipes to guarantee the stability of the face.

Ground reinforcing for tunnelling


The example of steel pipe umbrella 29/56
1 Chapter 2
Steel pipe umbrella
2
DO NOT MODIFY

3
the convergence-confimement curve

4 the position of the reaction line of the supports

5
Guarantee the stability of the tunnel free span

Ground reinforcing for tunnelling


The example of steel pipe umbrella 30/56
1 Chapter 2

Steel pipe umbrella. Example of application


2

Ground reinforcing for tunnelling


The example of steel pipe umbrella 31/56
1 Chapter 2

Ground reinforcing for tunnelling


The example of steel pipe umbrella 32/56
1 Chapter 2

Steel pipe
2

3
head
4
bench

5 Steel arches and shotcrete

Ground reinforcing for tunnelling


The example of steel pipe umbrella 33/56
1 Chapter 2
Example of Steel pipe umbrella in a morenic debris

Ground reinforcing for tunnelling


The example of steel pipe umbrella 34/56
1 Chapter 2

2
ur (mm) Without face reinforcement
TUNNEL FACE
REINFORCEMENT
3 With face reinforcement Reduces the radial
displacement of the tunnel
boundaries near the face

5 distanza
Distancedal fronte
from the di scavo
face [m](m)

Ground reinforcing for tunnelling


The example of steel pipe umbrella 35/56
1 Chapter 2
Steel pipe umbrella
with TBM tunnelling
2

Ground reinforcing for tunnelling


The example of steel pipe umbrella 36/56
1 Chapter 2
Steel pipe umbrella
with TBM tunnelling
2

Ground reinforcing for tunnelling


The example of steel pipe umbrella 37/56
1 Chapter 2
Steel pipe umbrella with TBM tunnelling
2

Ground reinforcing for tunnelling


The example of steel pipe umbrella 38/56
1 Chapter 2
CONSTRUCTION ASPECTS

Ground reinforcing for tunnelling


The example of steel pipe umbrella 39/56
1 Chapter 2
CONSTRUCTION ASPECTS

2 In the case of drilling with the D. T. H. hammer, the


valves may be those currently used for the traditional
manchettes. The presence of a non-return valve fitted
3 to the outside of the reinforcing pipe does not generate
any problems since the pipe is simply pushed inside the
hole that has been made.
4 In the case of cased rotopercussion drilling the valves
must necessarily be located in the thickness of the pipe
to prevent them to be damaged during drilling.
5

Ground reinforcing for tunnelling


The example of steel pipe umbrella 40/56
1 Chapter 2
CONSTRUCTION ASPECTS
The injection techniques used are basically the following
2 two:
the packer method by means of which each single valve is pressurized;

4 -the total injection method: each pipe is injected using a packer placed at
the top of the pipe.

Ground reinforcing for tunnelling


The example of steel pipe umbrella 41/56
1 Chapter 2
CONSTRUCTION ASPECTS

2 The injection of stabilizing mixes surrounding the


steel pipe depends on the type of soil :
1) in uniform cohesionless soils this injection is of crucial
importance : it prevents the soil caving between adjacent
3 pipe;
2) in morenic soils with large blocks or boulders
embedded in a more or less closed matrix, the purpose of
4 the injection is to fill any voids in the matrix, insofar as the
soil is generally self-supporting between one pipe and the
next;
5 3) in soils or rocks when the matrix is sufficiently closed
and therefore the rock mass has a certain cohesion, the
injection may not even be necessary.

Ground reinforcing for tunnelling


The example of steel pipe umbrella 42/56
1 Chapter 2
EQUIPMENT

2
The execution of the umbrella arch required the
developments of special equipments capable of
3 performing all the consolidation of each umbrella in the
shortest possible time.
For this reason, equipments capable of operating in
4 confined space, quickly setting-up in the required
drilling position and also capable of assuring a very
high production rate have been designed.
5

Ground reinforcing for tunnelling


The example of steel pipe umbrella 43/56
1 Chapter 2

Ground reinforcing for tunnelling


The example of steel pipe umbrella 44/56
1 Chapter 3
DESIGN APPROACH

2 The design of the intervention with steel pipe umbrella is


particularly complex due to:
•the high number of involved parameters;
•the impossibility of correctly considering the influence of all the
parameters through empirical methods (basically based on
3 experience acquired on similar grounds);
•the inadequacy of analytical methods to simulate tunnel face
effect;
•the computational costs and complexity of three-dimensional

4 numerical method applications;


•the difficulties of interpreting the effect of the overlapping of the
umbrellas and their connection to the steel sets, of the stiffness of
steel sets in comparison to the vertical loads and of the influence
of the mechanical characteristics of the ground at the excavation
5 face;
•the influence of the position of the excavation face on the stress
state induced inside the metallic elements (i.e. residual length of
the pipe in the ground).

Ground reinforcing for tunnelling


The example of steel pipe umbrella 45/56
1 Chapter 3
DESIGN APPROACH
2

Ground reinforcing for tunnelling


The example of steel pipe umbrella 46/56
1 Chapter 3
DESIGN APPROACH
2 Stability is checked by calculating the stresses due to
bending and shear arising in the pipes from the loads
(transmitted by the ground), and taking into account only
3 the steel section of the pipes as resisting section (a
reductive factor is applied to account for the pipe
perforations).
4 The pipes are considered as almost horizontal fixed end
beams

5 The hole spacing must be chosen according to the


ground properties: grain size, permeability etc.;

Ground reinforcing for tunnelling


The example of steel pipe umbrella 47/56
1 Chapter 3
DESIGN APPROACH
2 It can be safely supposed that the loads acting on the
umbrella are transmitted to the steel arches.

3 It is important:

-to check that the steel arches and the pipes are in good
4 contact

-to guarantee that the steel arches do not have


movements (need of a good foundation).
5

Ground reinforcing for tunnelling


The example of steel pipe umbrella 48/56
1 Chapter 3
DESIGN APPROACH

5
Enlarged foot and underpinning of the steel arch

Ground reinforcing for tunnelling


The example of steel pipe umbrella 49/56
1 Chapter 3
DESIGN APPROACH
2
Steel pipe
ombrello di infilaggi

centina
Steel arch Tunnel face
fronte di scavo
3
d s g
4 q
a)
L=(d+s+g)
5 q
b)
L=(d+s+g)

Ground reinforcing for tunnelling


The example of steel pipe umbrella 50/56
1 Chapter 3
DESIGN APPROACH
2 The steel pipe is considered as almost horizontal fixed
end beams anchored in the ground after a distance g
(which is difficult to be defined).
3
It is also possible to consider a not perfect fixed end and
use the following equations for the evaluation of the
4 bending moments
(− ) 1
[
M max = − ⋅ I ⋅ q ⋅ L2
] M (+ )
max =
1 1

 8 16 ⋅ I +
1
⋅ I 2
 ⋅ [
q ⋅ L2
]
8  128 

5 If the steel pipe is modeled as a beam on two supports,


(I=0) the bending moments are bigger

Ground reinforcing for tunnelling


The example of steel pipe umbrella 51/56
1 Chapter 3

2 DESIGN APPROACH

3 Pipe bending moments


Steel arches maximum loads
ARE INFLUENCED BY
4
stiffness of the ground ahead the face, of the steel arches, of the pipes

Ground reinforcing for tunnelling


The example of steel pipe umbrella 52/56
1 Chapter 3

Ground reinforcing for tunnelling


The example of steel pipe umbrella 53/56
1 Conclusions and references
THE USE OF GROUND REINFORCEMENTS
2 REQUIRE

DESIGN VERSATILITY
3
Consider and

4
compare all the
To make the
technologies
design using
Compare the various which are
modern
options taking into availoable
procedure
account the long and
5 Use 3D models
shoret term stability

Ground reinforcing for tunnelling


The example of steel pipe umbrella 54/56
1 Conclusions and references
The conventional excavation full face

2 in difficult “geo” conditions


ADVANTAGES Cannot be done without
face reinforcement

3
⇒High level of mechanization
⇒High flexibility to adapt the reinforcement ahead the tunnel
4 face at the geological conditions encountered during excavation
⇒Good control of boundaries displacement and face extrusion
⇒Good control of the subsidences
5
⇒Possibility of casting the invert, near the face

Ground reinforcing for tunnelling


The example of steel pipe umbrella 55/56
ITA/AITES

Clause de non-responsabilité pour les rapports des groupes de travail de l'AITES


L’Association Internationale des Travaux en Souterrain (AITES) publie ce rapport, conformément à ses Statuts, pour faciliter les échanges d’informations afin :
d’encourager l’utilisation du sous-sol au profit du grand public, de l’environnement et du développement durable;
de promouvoir les progrès dans la planification, le projet, la construction, l’entretien, la réhabilitation et la sécurité des tunnels et de l’espace souterrain en
rassemblant et confrontant les informations, ainsi qu’en étudiant les questions qui s’y rapportent.
Cependant, l’AITES décline toute responsabilité en ce qui concerne les informations publiées dans ce rapport.
Ces informations :
sont exclusivement de nature générale et ne visent pas la situation particulière d’une personne physique ou morale;
ne sont pas nécessairement complètes, exhaustives, exactes ou à jour ;
proviennent parfois de sources extérieures sue lesquelles les services de l’AITES n’ont aucun contrôle et pour lesquelles l’AITES décline toute responsabilité ;
ne constituent pas un avis professionnel or juridique (si vous avez besoin d’avis spécifiques, consultez toujours un professionnel dûment qualifié).

Disclaimer for the reports of ITA working groups


The International Tunnelling Association (ITA) publishes this report to, in accordance with its statutes, facilitate the exchange of information, in order:
to encourage planning of the subsurface for the benefit of the public, environment and sustainable development
to promote advances in planning, design, construction, maintenance and safety of tunnels and underground space, by bringing together information thereon and
by studying questions related thereto.
However ITA accepts no responsibility or liability whatsoever with regard to the material published in this report.
This material is:
information of a general nature only, which is not intended to address the specific circumstances of any particular individual or entity;
not necessarily comprehensive, complete, accurate or up to date;
sometimes collected from external sources over which ITA services have no control and for which ITA assumes no responsibility;
not professional or legal advice (if you need specific advice, you should always consult a suitably qualified professional).
56/56