Beruflich Dokumente
Kultur Dokumente
PROCEDURE ENHANCEMENT
Prepared by: DSS- HQ
Date: 3rd May 2018
1
Background
upon completion.
2
Table of Contents
................................................................................................................................ 2
Background .............................................................................................................. 2
1. Focus on JV development........................................................................................11
2. Consultant................................................................................................................11
3. Contractor ................................................................................................................11
1. Standardization ........................................................................................................12
5. Transparency ...........................................................................................................12
Reference ............................................................................................................... 14
3
Problem Statement
However, there are few problems has been encountered and can be further enhanced for the
benefits of industry.
1. Inconsistency of product: It has been found out that some upgraded plant has not fulfilling
the recommended minimum requirement. This has resulted in short lifespan on the STP
efficiency which later will increase the operational cost (OPEX) on the maintenance.
2. Sewerage Capital Contribution: With the variation of upgrading cost/ PE, developer has
taken opportunity in claiming more than actual construction cost. The purpose of doing this is
to avoid them for paying any amount on the difference between SCC to be paid vs cost of
upgrading.
3. Completion period: Any STP which has registered as asset number, will be monitored by
Department of Environment (DOE) on their performance. There are some cases which the
upgrading work has taken more time than their initial proposal. Even though the plant is under
upgrading, DOE will still issue a summons or letter to IWK if the plant is unable to well operated
during upgrading period., This has giving bad reputation to IWK.
4
Legislation governing upgrading STP
Sewerage Capital Contribution (SCC) Fund established under section 172 of the Water
Services Industry Act 2006 [Act 655]. The upgrading work application is usually by developer
that their development buildings other than specific buildings.
A contribution to the Fund made by any developer or person referred to in subsection 172(2)
Table 1: First Schedule: WATER SERVICES INDUSTRY ACT 2006; Water Services Industry (Sewerage Capital
Contribution Fund) Regulations 2011 (Industry, 2006)
5
Developer is entitled to apply off-set from the of SCC by upgrading the sewerage facilities
(STP/ NWS). The provision of entitlement as stipulated in “Garis Panduan Permohonan Offset
Under Suruhanjaya Perkhidmatan Air Negara (SPAN), governance of the Sewage Treatment
Plant (STP) upgrading is subjected to application made by developer via appointed consultant.
Applicants is compulsory to visit the respective plant together with the presence of
representative from IWK-OPS, IWK-CA, developer, consultants and others related parties.
The purpose of the visitation is to determine the scope of work related with the upgrading work
proposal.
Upon completion of the detail design, it will then to be tabled in Jawatankuasa Penilaian Kecil
(JAKPEN) at SPAN regional office. The approved scope of work will then to be endorsed by
certifying agencies (CA-office) located at the state of upgrading work to be proposed.
http://www.span.gov.my/files/KWSMP/Guidelines%20for%20Upgrading%20of%20Public%2
0Sewerage%20System%20Procedure%20for%20Developer%20(Applicant).pdf (SPAN,
2016b)
http://www.span.gov.my/files/KWSMP/Guidelines%20for%20Application%20of%20Sewerag
e%20Capital%20Contribution%20(SCC)%20Offset%20%20for%20Developer%20(Applicant
The following diagrams extracted from respective guidelines shows the relationship of
6
Figure 1: Upgrading work application flowchart
7
Upon completion of upgrading work, applicant has to submit the off-set application for the work
that they had carried out. The diagrams as follows:
8
Current procedure
PDC1
PDC2
PDC3/4/5
PDC6
PDC7
9
Proposed Enhancement/ implementation option
PDC1
PDC2
PDC3/4/5
PDC6
PDC7
10
Developer need to pay the SCC amount upon PDC2 approval
1. If loading reached dPE: IWK will study the needs of upgrading work either major upgrading
The LoC will be issued based on completion of sewer work connected to the STP. This will
ensure there is no pending work prior to completion of STP.
IWK is the service solution in sewerage infrastructure in Malaysia. IWK has capacity on
providing consultancy, constructing and providing overall services in sewerage. There are
some options that can be considered in implementing the mechanism:
1. Focus on JV development
As current practice, for development area which involving few developer company, there is
third parties which has been appointed by developer to coordinate the construction of STP. It
is an opportunity that the role is taken by IWK in providing overall solution for the sewerage
facility to the development. IWK in this position can either be as Project Management
Consultant (PMC), consultant or contractor for the project. This can ensure the overall process
and requirement as required by SL.
2. Consultant
IWK can consider on providing consultancy services for the developer. As the main duty of
the consultant is to ensure the proposal of upgrading will be commenced and completed within
stipulated of time. They has also to ensure all the procedure has been taken into consideration
seriously.
3. Contractor
IWK can also becoming the design and build contractor to the developer. All necessary
incorporated work element will be refined by IWK for better product output.
11
Benefits from implementation
or characteristics for activities or their results so that they can be repeated.” IWK can promote
the standardization to the STP in fulfilling national initiative.
2. Hassle Free: Developer has no need to face any difficulty in aspect of STP upgrading. The
Letter of clearance (LoC) can be obtained within time upon completion of sewer work.
3. Reduce handling cost: Considering that all associates work related with STP upgrading has
been fully transferred to IWK, handling cost shall be reduced. Based on (Winch, 1989), the
key factors in generating transaction costs are hounded rationality, in the face of uncertainty
and complexity; and opportunism in the context of small numbers relationships.
4. Optimization: Some STP does not need to upgrade but the optimization may imply.
Optimization in design is the ability to include parameters characterizing the design of the plant
as decision variables. In this way, it is possible to determine design parameter values leading
to optimal switching (Perkins and Walsh, 1996).
5. Transparency: IWK is the appointed company in providing services for sewerage facilities.
The SCC funds is mainly to be used in uplifting image of STP. As reputable sewerage service
provider, it’s the company aim to ensure the facilities maintained by IWK is beneficial to
industry.
6. Avoid Offset of SCC Funds: Developer has no control on the SCC funds amount. This is
because they have paid the SCC at any situation. The existing off-set procedure may obsolete.
12
Potential of implementation
From the overall assessment and discussion, the upgrading initiative is reliable and may be
proceeded for implementation. However, there are certain limitation that need to further
1. Refine BG Upgrading Procedure & Scope: There some needs to establish proper procedure
3. Costing: To establish cost element per items. Furthermore, the proposed cost shall be lower
from existing price by others contractor/ system supplier. Costing breakdown may be prepared
by certified quantity surveyor. By doing this, it will embark the stern of IWK in implementation.
4. Refine catchment strategy: PSS unit may need to re-look on the existing catchment
strategy. The connection to existing STP requirement may need to robust for adopting the way
forward of strategy.
13
Reference
https://www.gov.uk/government/publications/standardisation/standardisation.
10.1080/01446198900000032.
14